JO/ HC 109/PO 10

Sub-Center Field Operations Office

Doc. No. Rev: Page

001

Job Safety Analysis


Job name/number: Loading/Unloading of Site Office using Crane Job Location : Wafra Field Division/section: Job crew: POD
Asset Owner contact (Name and Tel.):

1 of 4 New

Date: 15/06/2001 Compiled By : HSE Officer Ali Farahan

Revised

Eng. Raj 66933178

Reviewed By: Eng: Nawal Attwa

Personal Protective Equipment: Hard hat, Eye protection (safety googles), Gloves, Ear Plug, Work boots & H2S monitors.

Other Safety/E emergency Equipment Required: Multi Gas Monitor, Fire Extinguishers & First aid Kit.

Sequence of Job Components & Tasks

Potential Hazards, Concerns

Safe Practice/Procedure

1. Pre job planning and preparation

7.Clean work site, Work Completed, final thorough check up, hand over

All necessary tools & equipment available and in good condition and functioning. Heat stress if work carried out during summer. Incorrect placing Simultaneous/conflicting operation, condition such loading/unloading, rig working near by Grinding/Welding/Lifting /Cutting old line at work site.

Ensure that appropriate permit to work is in place and work site thoroughly inspected, get familiar with other obstruction. Conduct tool box meeting and explain expected hazards and necessary precautions. All necessary tools & equipment available and in good condition and proper functioning. Correct missing item. Remove a surplus supports, pipes, trashes. Maintain allcomfortable distance from different work activities, be more attentive make aware of your work to other crew. Maintain minimum distance of 4 meters from overhead power line. Check surrounding area, ground condition, wind condition, overhead power lines. Check lifting capacity of Crane and radius of operation. Ensure Crane is placed on hard, level ground, outriggers fully extended and placed under timber mats. Ensure the Crane is having spark arrester when working in restricted area Keep hands out of pinch point while rigging, Use hand gloves. Know the weight to be lifted and its configuration, Check Weather condition , Wind speed(low, high) Emphasis more to STOP WORK if they see anything unsafe. Barricade the area of Crane operation place warning. Check rigging before lifting. Ensure lifted load is properly balanced. Stop lifting if wind is getting strong and poor visibility. Refer to load chart and radius of operation. Assign one man to give signal to crane operator. Use tagline to control suspended load. Use safety glasses, gloves. Keep other people

2.Setting Crane for the load to be lifted

Hand Injury to the rigger. Failure of slings or Dshackles.

3.Lifting the load

Lifted material falling. Hitting people or existing facility. Crane losing balance.

I have reviewed JSA at site and discussed with all workers Signature of permit user: