RAB Kolam Renang
RAB Kolam Renang
PROYEK :
PEKERJAAN : Kolam Renang
LOKASI :YONKAV-5/DPC
UKURAN :10 m x 25 m
NO JENIS PEKERJAAN VOLUME SATUAN HARGA SATUAN
(RP)
A B C D E
I PEK PERSIAPAN
1 Pengukuran 1 LS 3,500,000.00
2 pasang patok 18 BH 100,000.00
3 mobilisasi 1 LS 18,000,000.00
4 Fortho Dokumentasi 1 unit 1,500,000.00
Jumlah I
II PEK . PONDASI DAN SLOOF
1 Galian Tanah 810 m3 72,000.00
2 Urugan Pasir Pondasi Plat, Pond.Sloof, Lantai 25 m3 110,880.00
3 Lantai Kerja Beton Tumbuk Pond.Plat 12.5 m3 994,638.00
4 Lantai Plat Beton Bertulang 50 m3 4,127,370.00
5 Dinding Plat beton Bertulang 35.00 m3 4,127,370.00
6 Plester Braven 225 m2 50,715.00
7 Sloof Beton 20/35 9.8 m3 4,127,370.00
8 Urugan Tanah Kembali Galian Pondasi 175 m3 26,460.00
9 pas.keramik 530 m2 125,000
Jumlah II
Total
JUMLAH HARGA (RP) BOBOT
3,500,000.00
1,800,000.00
18,000,000.00
1,500,000.00
24,800,000.00
58,320,000.00
2,772,000.00
12,432,975.00
206,368,500.00
144,457,950.00
11,410,875.00
40,448,226.00
4,630,500.00
66,250,000.00
547,091,026.00
571,891,026.00