JADWAL KEGIATAN TUKANG

NO JENIS PEKERJAAN LOKASI PETUGAS PELAKSANAAN SELESAI KETERANGAN


SENIN SELASA RABU KAMIS JUMAT SABTU
1 Meninggikan dinding Kamar mandi NS-1 P. Mahmud-sori 22-Jun 23-Jun selesai
2 Pasang kloset NS-1 P. Mahmud-sori 24-Jun selesai
3 Pasang plafon dan eternit Loundry p. Hasan-P.Mahmud-Sori 25-Jun 26-Jun 27-Jun blm selesai Tinggal ngecat
4 Pasang Keramik dinding R6 P. Hasan 22-Jun 23-Jun 24-Jun 25-Jun selesai
5 Pasang Pagar kawat berduri belakang AKP P. Hasan-bahrul-ahmad 26-Jun 27-Jun blm selesai

1 Ngecat Eternit Londry P. Hasan-Sori 29-Jun selesai


2 Buat pintu masuk Londry P. Mahmud-P.Hasan-Sori 29-Jun 30-Jun 1-Jul blm selesai tinggal ngecat
3 Nyekat dinding Londry P. Mahmud-sori 2-Jul 3-Jul 4-Jul selesai
4 Melanjutkan pasang pagar duri Belakang AKP Bahrul-Ahmad 29-Jun 30-Jun selesai
5 Pasang keramik dinding R7 Bahrul-ahmad 1-Jul 2-Jul 3-Jul 4-Jul blm selesai

1 Melanjutkan pasang keramik dinding R7 P. Hasan-Bahrul-Ahmad 6-Jul 7-Jul seleai


2 Mengecat Pintu Baru Loundry P. mahmud-sori 6-Jul seleai
3 Buat Pos Satpam baru Dpn sampah P. mahmud-sori 7-Jul 8-Jul 9-Jul 10-Jul 11-Jul blm selesai
1 Lanjut buat pos satpam Dpn Sampah P. Mahmud-P.Hasan-Sori 13-Jul 14-Jul 15-Jul 16-Jul Libur Libur Blm selesai
2 Ngecat dinding 2A3 P. Bahrul-Ahmad 13-Jul 14-Jul Libur Libur selesai
3 Ngecat dinding 2A2 / 2A1 P. Bahrul-Ahmad 15-Jul 16-Jul Libur Libur selesai

1 Lanjut Buat Pos Satpam Bahrul-Ahmad 27-Jul 28-Jul 29-Jul Belum selesai
2 Ngecat pagar Luar poli Bahrul-Ahmad 30-Jul 31-Jul 1-Aug selesai

1 Lanjut Pos Satpam P. Mahmud-Hasan-sori 3-Aug 4-Aug 5-Aug Selesai


2 Melester lantai Belakang OK P. Mahmud-Hasan-sori 6-Aug 7-Aug 8-Aug Selesai
3 Ngecat dinding Tulip 1,2 Bahrul Ahmad 3-Aug 4-Aug Selesai
4 Ngecat dinding Tulip 1,1 Bahrul Ahmad 5-Aug 6-Aug Selesai
5 Ngecat dinding Tulip 2,1 Bahrul Ahmad 7-Aug 8-Aug Belum Selesai

1 Lanjut Cat dinding Tulip 2,1 Bahrul - Ahmad 10-Aug 11-Aug Selesai
2 Melester Lantai IPAL P. Mahmud-Hasan-Sori 10-Aug 11-Aug 12-Aug 13-Aug Selesai
3 Pasang Baut dinding A4 Bahrul - Ahmad 12-Aug Selesai
4 Pasang Baut dinding R9 Bahrul - Ahmad 13-Aug Selesai
5 Pasang Baut dinding R8 Bahrul - Ahmad 14-Aug 15-Aug Selesai
6 Ganti dinding Kmr, Jenazah P. Mahmud-Hasan-Sori 14-Aug 15-Aug Belum selesai

1 Buat Rak susun Rekam medis P Mahmud-sori-bahrul 17-Aug 18-Aug 19-Aug 20-Aug 21-Aug 22-Aug selesai

1 Ganti kayu usuk Kmr, Jenazah P. Mahmud-sori-bahrul 23-Aug 24-Aug 25-Aug Selesai
2 Pasang Plafon dan langit2 Kmr, Jenazah P. Mahmud-sori-bahrul 26-Aug 27-Aug 28-Aug Selesai

1 Melamir dan ngecat langit2 Kmr, Jenazah P. Mahmud-sori-bahrul 31-Aug 1-Sep


2 Buat tempat pemandian jenazah Kmr, Jenazah P. Mahmud-sori-bahrul 2-Sep 3-Sep 4-Sep 5-Sep
JADWAL KEGIATAN TUKANG

NO JENIS PEKERJAAN LOKASI PETUGAS SELESAI KETERANGAN


1 Ninggikan dinding kamar mandi NS-1 P. Mahmud-P.Hasan-Sori 11-May-15
2 Buat spool hoek NS-1 P. Mahmud-P.Hasan-Sori 13-May-15
3
4
5

1 Pasang keramik dinding R6 P. Dul-Bahrul-Ahmad 22-May-15


2 Melubangi angin2 istirahat cs Bawah Tandon P. Dul-Bahrul-Ahmad 22-May-15
3
4
5

1 Buat spool hoek NS-2 P. Mahmud-Sori-P.Hasan 1-Jun-15


2 Buat ruang studio Receiver Dpn Kant. Umum P.Dul-Anwari-Ahmad 2-Jun-15
3
4
5

1 Buat jalan naik ke kamar mandi Poli P. Mahmud-Sori 4-Jun-15


2 Masang water heater Londry & Gizi P. Hasan 6-Jun-15
3
4
5

1 Melanjut ngecat Mushollah Ahmad-Bahrul 12-Jun-15


2 Masang keramik dinding A9 P.Hasan-P.Mahmud-Sori 13-Jun-15
3
4
5

1 Melamir dan ngecat pagar Jemuran Sori-Ahmad 20-Jun-15


2
3
4
5