0 penilaian0% menganggap dokumen ini bermanfaat (0 suara)
27 tayangan4 halaman
In 2007, one of the largest composite bridges in Austria was built as part oI the upgrading of The A2 motorway. First a steel skeleton 700 m long was extended Irom the two abutments on piers 70 m high. With caissons located in an incline sujet to slip, and the need to allow Ior earthquakes, planning the structure was an extremely demanding task.
In 2007, one of the largest composite bridges in Austria was built as part oI the upgrading of The A2 motorway. First a steel skeleton 700 m long was extended Irom the two abutments on piers 70 m high. With caissons located in an incline sujet to slip, and the need to allow Ior earthquakes, planning the structure was an extremely demanding task.
Hak Cipta:
Attribution Non-Commercial (BY-NC)
Format Tersedia
Unduh sebagai PDF, TXT atau baca online dari Scribd
In 2007, one of the largest composite bridges in Austria was built as part oI the upgrading of The A2 motorway. First a steel skeleton 700 m long was extended Irom the two abutments on piers 70 m high. With caissons located in an incline sujet to slip, and the need to allow Ior earthquakes, planning the structure was an extremely demanding task.
Hak Cipta:
Attribution Non-Commercial (BY-NC)
Format Tersedia
Unduh sebagai PDF, TXT atau baca online dari Scribd
- In 2007, one oI the largest composite bridges in Austria was built as part oI the upgrading oI the A2 motorway. First a steel skeleton 700 m long was extended Irom the two abutments on piers 70 m high: then concrete was cast - to complete the load-bear- ing structure. The geometry oI the site necessitated special Iabrication methods. With caissons located in an incline subiect to slip, and the need to allow Ior earthquakes, planning the structure was an extremely demand- ing task, involving non-linear calcula- tion oI supports as per second-order theory, taking into account state 2 and the various loads imposed dur- ing erection. This paper summarizes the main issues aIIecting design and construction. - bridge design: compos- ite bridge: eurocode: steelwork: launching.
The A2 motorway is an important
through route in the Austrian road network: the section between Bad St Leonhard and WolIsberg in Carinthia was opened on 26 July 1986. Budgetary diIIiculties had led to this and other sections oI the motorway being dimen- sioned as a "stripped-down motorway", that is a road in which the carriageways were separated only by two unbroken lines. AIter numerous traIIic accidents, some oI them very serious, a crash barrier was installed: however, this meant that there was no longer room Ior an emergency lane. As beIore, traI- Iic in all tunnels was two-way. When the motorway was originally opened, in a day about 8000 vehicles used it: today the Iigure is roughly 23 000, with the number oI lorries rising steeply. Planning Ior a second (independent) carriageway, that is, Iull-scale upgrad- ing, started as early as 1993.
Construction work on upgrading the A2 motorway between the Bad - St Leonhard and WolIsberg Nord iunctions began on 16 August 2004 and was completed on 31 October 2007. In the course oI upgrading the A2, bridge structures needed to be put in place Ior the second carriageway at various points, including the existing valley crossing at Auenbach (Structure P30) northwest oI WolIsberg in Carinthia, where the motorway crossed the val- ley on a ten-section bridge almost 700 m long and about 70 m above the valley Iloor. The motorway align- ment snakes through the bridges in an S shapewhich presented a special challenge in construction according to Apart Irom a slight dip at one end, the bridge has the same gradient throughout. In 1980, on the basis oI a special pro- posal by the construction company concerned, the existing bridge (a pre- stressed concrete structure with box girder cross section) was erected by the cantilever method, with a trav- elling Iormwork carriage overhead. However, the sinuous alignment led to unexpected complications with the cantilever method. In view oI the geol- ogy at the site and the massive loads on the piers, deep caissons and large-bore piles were used Ior the substructure. The ground here consists oI loose soil, run-oI-hill scree and loam overlying a deeply weathered zone oI the Koralpe crystalline rock. On the valley Iloor the water table is only 1 m below the sur- Iace. This diIIicult geological situation has resulted in landslip around the abut- ments, imposing massive stresses on the substructure oI the existing bridge. - -
The proiect promoter stipulated that the alignment oI the new bridge must be parallel to the existing bridge, with roughly the same pier spacing. This meant that the new piers would be in the shadow oI the existing piers. However, the circumstances oI the new proiect are signiIicantly diIIerent Irom those that were applicable when the Iirst bridge was designed: maior revision oI the standards governing calculation and loading (e.g. greater earthquake loads, new approach to saIety issues) had to be taken into account, as had the experience oI soil conditions (e.g. landslip around the abutments) acquired in the meantime. Technical Report 153 KlagenIurt - From the very start oI design work, it seemed likely that a composite struc- ture would IulIil these requirements better than any pre-stressed concrete structure, in spite oI the rise in the price oI steel. The arguments against a pre-stressed concrete bridge were its greater weight (a disadvantage with reIerence to the substructure and in the case oI an earthquake), the awkward situation Ior conventional step-by-step movement (the height oI the piers, the sinuous alignment) and the pier spac- ing, which was disadvantageous Ior the cantilever method. The designer's thinking was corrobo- rated by the results oI tendering: the composite bridge speciIied in the ten- der documents turned out economical than any oI the pre-stressed concrete versions proposed. In this particular case, composite structures clearly have deIinite advantages when various con- straints are taken into account. -
The superstructure consists oI ten seg-
ments with an overall length oI 686 m and gaps oI 69-74,60 m between piers according to The end segments are 61,75 and 55 m long, respectively. The structure is almost 70 m above the valley Iloor. The cross section provides two motorway lanes plus a hard Standard cross-section shoulder. Overall width is 15 m, so the surIace area oI the bridge comes to 10 290 m 2 . These measurements make the Auenbach Bridge the largest com- posite bridge in Austria. The cross section is Iormed by a dou- ble tee beam: overall depth is 5,23 m, beam depth is 4,50 m (reIer to Pot bearings were used as bridge bear- ings: simple supports all round were planned Ior the Iive piles in the middle section. At the proiecting ends, water- tight linking structures with up to 440 mm oI elongation capacity were installed. The abutment at the Graz end is grounded on three elliptical anchored caissons 27 m deep: the anchors are up to 52 m long. In order to improve resistance to creep pressure in the slope, the longer axes oI the caissons run parallel to the slope line. The abut- ment at the KlagenIurt end and all the piers are grounded on up to 15 drilled piles each, 1200 mm in diameter and up to 22 m long. Jacking Iorm work was used to construct the drilled piles Ior the structure. The reinIorced concrete slab Ior the carriageway rests on two double tee beams 7,70 m apart. The slab proiects 3,65 m on each side. Roughly every 3,50 m, a cross Irame made oI rolled sections adds rigidity to the steel cross section. The two beams are oI the -- - - same height (constant over the entire length). Variations in the height oI the composite beams, due to changes in camber along the sinuous alignment, are achieved by means oI variations in the height oI the slab beams, which are hunched in cross section. The webs are 15 or 18 mm thick. The Ilanges vary in thickness Irom 45 to 150 mm: plates up to 60 mm thick are used Ior these, and Ilanges thicker than 60 mm are made Irom more than one plate. The steel grade S355 J2G3 was used Ior all steelwork throughout. The entire steel structure oI the bridge, weighing about 2050 t, was Iabricated and welded to completion in nine months. The main beams were divided lengthways into 29 sections per web: the resulting sections were up to 26 m long. These sections (4,70 m high) were transported to the site via the motor- way as oversize loads, lying Ilat: the motorway had to be closed to traI- Iic brieIly while the low loader used, turned around. - The basis Ior dimensioning the bridge structure was provided by Eurocode and by Austrian standards compara- ble to Eurocode (ENV 1994-2, ENV 1993-2, N B 4702): the loads on the bridge were calculated in line with NORM B 4002 and RVS 15.114. In the Iew cases where the various standards were not in agreement, or where provisions were missing, rea- sonable requirements were agreed with the promoter, Ior example, wind during construction and the impact oI changes in temperature. Analysis was perIormed both on the entire system (preliminary dimension- ing, earthquake, calculating supports, etc.) and on various subsystems, to investigate pile works, abutments, vari- ous transitional states during launching and the composite slab. The boundary and support conditions Ior consider- ing the composite slab separately were derived Irom the entire system. 154 Technical Report Earthquake analysis (Ior the Austrian earthquake zone 3) was based on the response spectrum method. The sup- ports were dimensioned taking into account the second-order theory Ior non-linear behaviour according to Uzunoglu-Zoggeler. 1 To model the pile structures, non-linear beddings were selected and the bedding stresses were limited. Here, it was necessary to con- sider the diIIering bedding properties on the slope line and parallel to the slope: the angle the slope line makes with the bridge axis diIIers at every pier axis. -
The basic idea Ior erecting the steel
structure was to launch segments Irom both abutments as Iar as the midpoint in the segment between axes 40 and 50. Because the launching approach is the most cost-eIIective erection procedure in the given circumstances, a method was developed making it possible to move segments longitudinally even with variable plan geometry. Behind each abutment there was an assembly area about 50 m long in which the individual segments oI the main beams were liIted into place by two 60 t mobile cranes and secured against tipping over sideways beIore they were set down as shown in Once the structure had been checked Ior dimensional accuracy, the main beams were welded up, and the bracing - -
and catwalk were installed and welded in place. AIter (as a rule) two segments at a time had been assembled, the assem- blage was moved out longitudinally. Because oI the sinuous motorway alignment (with clothoid spirals back and Iorth), lateral adiustment was nec- essary on every single pier. Launching rockers capable oI sideways move- ment were employed Ior this. Rockers commonly used in steelwork construc- tion were mounted on welded I-beams 670 mm high: the latter were sup- ported over a slip plane and could move sideways. The crossbeams were Iixed in place by means oI DYWIDAG rods embedded in concrete, and had a lug welded-on to provide lateral hold. This carriage also contained the point on which the hydraulic iack required Ior lateral adiustment acted. During outward movement, pier deIlection Irom the centre line was at the maxi- mum: the superstructure axis was 2,75 m out oI true, corresponding to 2,05 m oI overhang oI the web axis beyond the pier edge. In contrast to the concrete structures with varying plan geometry that have been erected by means oI step-by-step movement, the superstructure was not shiIted longitudinally and then laterally, but continuously on a circular path. A Iictitious launching circle was deIined as the locus oI movement. The advan- tage oI launching in a circle is that the current distance between the structure axis and the launching circle at each cross beam does not vary during move- ment. It was thus possible to indicate these distances with magnetic letters at the cross beams, which made it much easier to align the segment in question laterally. With this launching geometry, though, lateral movement was neces- sary at the abutments, too. To start with, a scale and a pointer were mounted on each pier, with zero corresponding to the intersection oI the launching circle with the pier axis. Launching began with a longitudinal movement: as soon as the lateral deviation Irom zero on a pier or abutment exceeded 100 mm, lateral movement was perIormed there according to This succession oI longitudinal and lateral movements was repeated until the Iinal position planned was reached. AIter launching, the nuts on the DYWIDAG rods were used to secure the structure against lateral movement at all piers and abut- ments. Four 40 t hydraulic iacks were employed in the launching operation. Then the position oI the segment ends was adiusted to within 10 mm (longitudinally and laterally) and Iur- ther segments were assembled behind the abutment and moved out. This sequence oI assembly and movement was repeated until the bridge was completed. Because movement proceeded Irom both abutments as Iar as the midpoint, an erection nose was not used Ior launching. However, a special device - - 2/2010 Technical Report 155 to cope with up to 1,40 m oI sag in the cantilever was used Ior landing on the piers. AIter the Iinal launching move- ment in each case, the structure was aligned laterally on all axes, and the top Ilange was suryeyed. Next, the launching rockers were removed and both main beams set to the correct height simultaneously. BeIore the midpoint ioint was welded up, the gradient oI the structure was adiusted by liIting at the two adioining piers so that aIter Iinal setting down, the Iield moment calculated Ior the midpoint was achieved. Once the steel structure had been linked up, the carriageway slab was con- creted non-stop in 28 sections Irom the KlagenIurt abutment to the Graz abut- ment. On completion, the bridge was opened to traIIic in December 2007. - This paper presents the design and construction oI the composite bridge P30 which is one oI the structures oI the missing link oI the A2 motor- way in the Pack area. Because oI the mountainous topology oI this section, several demanding bridges were con- structed. The Auenbach Bridge rep- resents one oI the longest composite bridges in Austria currently. The design was selected based on the alignment preconditions as well as column spacing in parallel to the existing structure as the clear conclusion oI the consultant. The superiority oI the solution was also conIirmed in the tender, as all alterna- tives submitted (post-tensioned con- crete or steel) were more expensive. The given boundary conditions (spans, geology, seismic loads) as well as the current requirements to completely Iollow new Eurocode comparable codes have been a challenge Ior the design consultants. The S-shape align- ment required a special construction method applying a launching tech- nique Irom both abutments. The Iol- lowing Iacts are particularly signiIicant Ior the bridge P30: - The structure represents the lon- gest composite bridge in Austria presently with a total length oI 700 m and ten spans. - Because oI the S-shape alignment as well as the adiustment oI the column spacing to the existing structure, spe- cial considerations had to be taken during design and construction oI the bridge. - During realization Irom both abut- ments using a special launching technology, large eccentricities had to be considered. - The geologic conditions (slope move- ments in the past) as well as relatively high seismic loads led to large-scale Ioundations Ior the whole structure. The composite system represents high economy in terms oI realization as well as liIe cycle costs compared with alter- native approaches like post-tensioned concrete or steel.
|1| Uzunoglu T, Zoggeler J. et al:
- - J Edition 3199. Zement and Beton: 12-21 (in German). 156 Technical Report
The Impact of Information Technology and Innovation To Improve Business Performance Through Marketing Capabilities in Online Businesses by Young Generations