JADWAL PELAKSANAAN

PENGADAAN RENOVASI WISMA PRADANA BANK BTN

Minggu ke-
NO URAIAN BOBOT
1 2 3 4 5 6 7
BULAN JULI AGUSTUS SEPTEMBER
Tanggal 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10
hari ke - 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45
A PEKERJAAN PERSIAPAN & BONGKARAN 2,76% 2,76%
B PEKERJAAN ARSITEKTUR 55,36% 7,91% 7,91% 7,91% 7,91% 7,91% 7,91% 7,91%
C PEKERJAAN ELEKTRIKAL & ELEKTRONIKA 4,90% 1,63% 1,63% 1,63%
D PEKERJAAN MEKANIKAL & PLUMBING 7,23% 3,61% 3,61%
E PEKERJAAN FURNITURE 29,75% 4,96% 4,96% 4,96% 4,96% 4,96% 4,96%
RENCANA PROGRES MINGGUAN 10,67% 16,48% 16,48% 12,87% 14,50% 14,50% 14,50%
100,00%
KUMULATIF RENCANA PROGRES MINGGUAN 10,67% 27,15% 43,63% 56,50% 71,00% 85,50% 100,00%
REALISASI PROGRES MINGGUAN 1,55% 6,48% 4,95% 9,59% 23,53% 37,06% 22,56%
KUMULATIF REALISASI PROGRES MINGGUAN 1,55% 8,03% 12,98% 22,58% 46,14% 57,15% 85,94%
DEVIASI -9,12% -19,12% -30,65% -33,92% -24,86% -28,35% -14,06%
Jakarta, 18 Juni 2022
LAPORAN PROGRES MINGGUAN
REKAPITULASI WAKTU PELAKSANAAN 45 HARI
WAKTU TERPAKAI 45 HARI
SISA WAKTU 0 HARI
MINGGU KE VII TUJUH
PERIODE 08/09/2022 S/D 08/09/2022
PEKERJAAN SIPIL & FURNITURE
PENGADAAN RENOVASI WISMA PRADANA BANK BTN
B0B0T PRESTASI FISIK TERHADAP SETIAP PEKERJAAN
NO URAIAN PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
(%) BOBOT BOBOT BOBOT
A PEKERJAAN PERSIAPAN & BONGKARAN 2,76 1,98 0,60 2,58
B PEKERJAAN ARSITEKTUR 55,36 31,56 10,76 42,32
C PEKERJAAN ELEKTRIKAL & ELEKTRONIKA 4,90 3,20 1,06 4,27
D PEKERJAAN MEKANIKAL & PLUMBING 7,23 6,46 0,56 7,02
E PEKERJAAN FURNITURE 29,75 5,68 24,07 29,75

TOTAL 100,00 48,88% 37,06% 85,94%


BOBOT REALISASI 48,88% 37,06% 85,94%
BOBOT RENCANA 85,50% 14,50% 100,00%
DEVIASI -36,6% 22,56% -14,06%
LAPORAN PROGRES MINGGUAN
WAKTU PELAKSANAAN 45 HARI
WAKTU TERPAKAI 45 HARI
PEKERJAAN SIPIL & FURNITURE SISA WAKTU 0 HARI
PENGADAAN RENOVASI WISMA PRADANA BANK BTN MINGGU KE VII TUJUH
PERIODE 08/09/2022 S/D 14/09/2022
B0B0T PRESTASI FISIK TERHADAP SETIAP PEKERJAAN
NO URAIAN PEKERJAAN VOLUME SATUAN PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI KETERANGAN
(%) PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
A PEKERJAAN PERSIAPAN & BONGKARAN
I PEKERJAAN PERSIAPAN
1 Koordinasi keamanan proyek 1,00 ls 0,070 100 0,070 - 100 0,070
2 Pembersihan area kerja 264,00 m2 0,184 95 0,175 5 0,009 100 0,184 BELUM General Cleaning
- Sebelum & setelah pekerjaan + pembuangan puing
3 Marking lokasi 264,00 m2 0,092 100 0,092 - 100 0,092 sudah 100%
4 Air & listrik kerja 1,00 ls 0,070 - 100 0,070 100 0,070 belum dilampirkan tanda bukti
5 Mobilisasi dan demobilisasi pekerja 1,00 ls 0,348 100 0,348 - 100 0,348 sudah 100%
- Estimasi pekerja 12 orang
- Transportasi pulang pergi dari Jakarta
6 Akomodasi pekerja 1,00 ls 0,244 100 0,244 - 100 0,244 sudah 100%
- Tempat tinggal & konsumsi harian
- Estimasi pekerja 12 orang
7 Mobilisasi material 1,00 ls 0,348 95 0,331 5 0,017 100 0,348 sudah 100%
8 Dokumentasi & pelaporan 1,00 ls 0,070 - 100,00 0,070 100 0,070 belum 100% General cleaning
- Laporan harian, mingguan dan termi
9 Shop drawing & Asbuilt Drawing 1,00 ls 0,348 - 100 0,348 100 0,348 belum dilkerjakan
10 Keselamatan & kesehatan kerja (K3) 1,00 ls 0,070 - 100 0,070 100 0,070 belum dilampirkan tanda bukti
- Termasuk swab antigen pekerja & APD lengkap APD tidak dilaksanakan

II PEKERJAAN BONGKARAN & PEMATANGAN LAHAN


1 Bongkar vegetasi eksisting area taman 170,00 m2 0,177 - - - - - belum dilkerjakan
2 Bongkar area kamar 200,00 m2 0,139 100 0,139 - 100 0,139 sudah 100%
3 Bongkar keramik dinding toilet eksisting 88,00 m2 0,122 100 0,122 - 100 0,122 sudah 100%
4 Bongkar dinding bata eksisting 60,00 m2 0,104 100 0,104 - 100 0,104 sudah 100%
5 Bongkar lis plafon eksisting 195,00 m1 0,068 100 0,068 - 100 0,068 sudah 100%
6 Kupas wallpaper kamar eksisting 420,00 m2 0,146 100 0,146 - 100 0,146 sudah 100%
7 Bongkar pintu jendela eksisting (pintu dipakai kembali) 2,00 unit 0,021 100 0,021 - 100 0,021 sudah 100%
8 Buang puing bongkaran keluar site 1,00 ls 0,139 90 0,125 10 0,014 100 0,139 belum 100% General cleaning

2,759 1,984 0,597 2,582


B PEKERJAAN ARSITEKTUR
I PEKERJAAN LANTAI
a Lantai 1
1 Pasangan parket kayu 50,00 m2 1,566 100 1,566 - 100 1,566 sudah 100%
- Tipe & warna menyesuaikan eksisting
2 Pasangan keramik lantai 60x60cm. Toilet 20,00 m2 0,529 100 0,529 - 100 0,529 sudah 100%
- ex. Granito
3 Rug custom uk. 300x300cm. Kamar Tidur 2,00 unit 1,113 - - - - - material on site belum dipasang
4 Rug custom uk. 200x300cm. Ruang Tamu 2,00 unit 0,974 - - - - - material on site belum dipasang
5 Lis edging vinyl SPC 4,00 m1 0,021 80 0,017 15 0,003 95 0,020 belum 100%

b Lantai 2
1 Pasangan parket kayu 50,00 m2 1,566 100 1,566 - 100 1,566 sudah 100%
- Tipe & warna menyesuaikan eksisting - - - - -
2 Pasangan keramik lantai 60x60cm. Toilet 15,00 m2 0,397 100 0,397 - 100 0,397 sudah 100%
- ex. Granito
3 Rug custom uk. 300x300cm. Kamar Tidur 2,00 unit 1,113 - - - - - material on site belum dipasang
4 Rug custom uk. 200x200cm. Ruang Tamu 2,00 unit 0,974 - - - - - material on site belum dipasang
5 Lis edging vinyl SPC 4,00 m1 0,021 80 0,017 20 0,004 100 0,021 sudah 100%

c Ruang Ka Kanwil
1 Pasangan lantai Homogenous Tile 80x80cm. Teras 28,00 m2 0,818 60 0,491 40 0,327 100 0,818 sudah 100%
- ex. Valentino Gress - Howlite Bianco
2 Pasangan carpet tile 50x50cm. Ka Kanwil 23,00 m2 0,800 - - - - - belum dilkerjakan
- ex. Tandus - Tricot Chroma 26527
3 Pasangan keramik lantai 60x60cm. Toilet 6,00 m2 0,159 80 0,127 20 0,032 100 0,159 sudah 100%
- ex. Granito - Frost White
4 Lis edging karpet stainless steel siku 4,00 m1 0,021 - - - - - belum dilkerjakan

d Pergola & Taman


1 Batu koral sikat tabur warna putih 30,00 m2 0,626 - 95 0,595 95 0,595 belum 100%
2 Stepping stone 10,50 m2 0,219 95 0,208 5 0,011 100 0,219 sudah 100%
3 Penataan taman & penanaman vegetasi 170,00 m2 0,592 - 80 0,473 80 0,473 belum 100%

II PEKERJAAN DINDING, PARTISI DAN PELAPIS DINDING


a Lantai 1
1 Pengecatan dinding interior ex. Dulux 255,00 m2 0,603 90 0,543 8 0,048 98 0,591 belum 100% perapihan
2 Pengecatan dinding eksterior ex. Dulux brilliant white 90,00 m2 0,251 95 0,238 3 0,008 98 0,246 belum 100% perapihan
3 Pasangan keramik dinding. Toilet 48,00 m2 1,069 100 1,069 - 100 1,069 sudah 100%
- Keramik 30x60cm ex. Roman
4 Backdrop kasur 18,00 m2 1,566 45 0,705 50 0,783 95 1,488 sudah 100%, belum perapihan sudutan
5 Backdrop credenza 4,50 m2 0,391 45 0,176 50 0,196 95 0,372 sudah 100%, belum perapihan sudutan
6 Plint multipleks 18mm t=10cm fin. HPL ex. Taco - Steel Foil TH 611 AL 90,00 m1 0,313 30 0,094 68 0,213 98 0,307 sudah 100%, belum perapihan sudutan
masih kotor terkena cat dinding
b Lantai 2 sudutan masih tajam
1 Pengecatan dinding interior ex. Dulux 246,00 m2 0,582 90 0,524 8 0,047 98 0,570 belum 100% perapihan
2 Pengecatan dinding eksterior ex. Dulux brilliant white 156,00 m2 0,434 95 0,413 3 0,013 98 0,426 belum 100% perapihan
3 Pasangan keramik dinding. Toilet 40,00 m2 0,891 100 0,891 - 100 0,891 Nat masih terlalu kontras lebih kuning
- Keramik 30x60cm ex. Roman
4 Backdrop kasur 18,00 m2 1,566 45 0,705 55 0,861 100 1,566 sudah 100%, belum perapihan sudutan
5 Backdrop ruang makan 4,50 m2 0,391 45 0,176 55 0,215 100 0,391 sudah 100%, belum perapihan sudutan
6 Plint multipleks 18mm t=10cm fin. HPL ex. Taco - Steel Foil TH 611 AL 82,00 m1 0,285 60 0,171 40 0,114 100 0,285 sudah 100%, belum perapihan sudutan
masih kotor terkena cat dinding
B0B0T PRESTASI FISIK TERHADAP SETIAP PEKERJAAN
NO URAIAN PEKERJAAN VOLUME SATUAN PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI KETERANGAN
(%) PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
c Pendopo
1 Dinding roster beton 20x20cm 6,00 m2 0,125 100 0,125 - 100 0,125 belum 100% perapihan
2 Kisi-kisi penutup kolom 5,00 unit 0,261 100 0,261 - 100 0,261 belum 100% perapihan
3 Kisi-kisi pagar 2,00 m2 0,070 100 0,070 - 100 0,070 belum 100% perapihan
4 Backdrop pantry 6,00 m2 0,626 45 0,282 55 0,344 100 0,626 belum 100% perapihan
5 Hanger lampu gantung 1,00 ls 0,122 90 0,110 10 0,012 100 0,122 sudah 100%

d Ruang Ka Kanwil
1 Dinding bata ringan 15,00 m2 0,209 100 0,209 - 100 0,209 sudah 100%
- Bata ringan t=10cm ex. Leibel. Termasuk plesteran & acian
2 Plesteran dinding t=15mm 30,00 m2 0,198 100 0,198 - 100 0,198 sudah 100%
3 Acian dinding 30,00 m2 0,157 100 0,157 - 100 0,157 sudah 100%
4 Dinding partisi gypsum 2 muka 36,00 m2 0,438 - 100 0,438 100 0,438 sudah 100%
- Rangka metal stud 76
- Gypsumboard 12mm ex. Jayaboard. Termasuk corner bead di setiap sudutan dinding
5 Pengecatan dinding eksterior ex. Dulux brilliant white 60,00 m2 0,167 60 0,100 40 0,067 100 0,167 sudah 100%, belum perapihan
6 Pasangan keramik dinding. Toilet 16,00 m2 0,356 100 0,356 - 100 0,356 Nat masih terlalu kontras lebih kuning
- Keramik 30x60cm ex. Roman - dFoscari Beige W63454R
7 Pasangan keramik dinding mozaic. Toilet 3,00 m2 0,067 100 0,067 - 100 0,067 sudah 100%
- Keramik 30x60cm ex. Roman - dMarmo Mosaic W63750
8 Wallpaper dinding 72,00 m2 2,004 - - - - - belum dikerjakan
- ex. Goodrich WSE4923
9 Pembuatan meja beton wastafel t=8cm 0,08 m3 0,025 50 0,013 50 0,013 100 0,025 sudah 100%
10 Pasangan marmer slab Dark Emperador meja wastafel 1,00 m2 0,226 - 100 0,226 100 0,226 sudah 100%
11 Plint multipleks 18mm t=10cm fin. HPL ex. Taco - Steel Foil TH 611 AL 20,00 m1 0,070 - - - - - belum dikerjakan
12 Vertical blind warna putih t=2m ex. Onna 10,00 m2 0,348 - - - - - belum dikerjakan

d Pergola
1 Pondasi kolom setempat 12,00 unit 1,044 100 1,044 - 100 1,044 sudah 100%
2 Kolom pergola 12,00 unit 1,670 100 1,670 - 100 1,670 sudah 100%
3 Pengecatan kolom 12,00 unit 0,209 100 0,209 - 100 0,209 sudah 100%, belum perapihan

III PEKERJAAN PINTU JENDELA


a Lantai 1
1 Pengecatan pintu jendela eksisting 1,00 ls 0,139 100 0,139 - 100 0,139 sudah 100%, belum perapihan
2 Perbaikan pintu jendela 1,00 ls 0,139 100 0,139 - 100 0,139 sudah 100%, belum perapihan
3 Gordyn jendela polos t=3m 24,00 m2 0,835 - - - - - belum dikerjakan
4 Vitrase polos putih t=3m 24,00 m2 0,418 - - - - - belum dikerjakan

b Lantai 2
1 Pengecatan pintu jendela eksisting 1,00 ls 0,139 100 0,139 - 100 0,139 sudah 100%, belum perapihan
2 Perbaikan pintu jendela eksisting 1,00 ls 0,139 100 0,139 - 100 0,139 sudah 100%, belum perapihan
3 Gordyn jendela polos t=3m 36,00 m2 1,253 - - - - - belum dikerjakan
4 Vitrase polos putih t=3m 36,00 m2 0,626 - - - - - belum dikerjakan

c Ruang Ka Kanwil
1 Relokasi pintu jendela eksisting 2,00 set 0,139 100 0,139 - 100 0,139 sudah 100%, belum perapihan
2 Kusen & daun pintu toilet 1,00 unit 0,278 80 0,223 20 0,056 100 0,278 sudah 100%, belum perapihan
- Kusen kayu kamper solid 5/10 fin. HPL ex. Taco TH 1202 FC
- Architrave multipleks 18mm fin. HPL ex. Taco TH 1202 FC
Daun pintu double multipleks 18mm fin. HPL ex. Taco TH 1202 FC
- Handle: Level handle solid roses ex. Dekkson - LHSR 0016 22mm SSS
- Engsel: Deluxe hinge ex. Dekson ESS DL 4x3x2mm 2BB SSS (2 unit)
- Lock case: Swing/interlatch ex. Dekkson - MTS IL DL 8258 SSS
- Cylinder: Construction key ex. Dekkson - CON CYL DC DL 62mm SN (2+3)
- Escutcheon: Ex. Dekkson - ESCN 855 SSS
- Door stopper: Magnetic ex. Dekkson - MDS 889 SN
- Door closer: DCL 525 NHO NA
- Grill aluminium 30x40cm
3 Kusen & daun jendela aluminium 3,00 unit 1,044 - - - - - Tidak dikerjakan
- Kusen aluminium 4" warna hitam ex. YKK/Alexindo
- Daun jendela aluminium + kaca bening 5mm
4 Door sign. Ka Kanwil, Toilet 2,00 unit 0,049 - - - - - belum dikerjakan
- Plat stainless steel 1mm. Lettering cutting sticker warna putih

IV PEKERJAAN PLAFOND & ATAP


a Lantai 1
1 Perbaikan plafon gypsum 30,00 m2 0,303 100 0,303 - 100 0,303 sudah 100%
- Rangka hollow galvanis 4/4 & 4/2
- Gypsumboard 9mm ex. Jayaboard
2 Pekerjaan alumunium shadowline 95,00 m1 0,331 80 0,264 20 0,066 100 0,331 sudah 100%
3 Pengecatan plafon & shadowline 160,00 m2 0,445 95 0,423 5 0,022 100 0,445 sudah 100%
- ex. Dulux brilliant white
4 Kanopi pergola kaca laminated rangka besi hollow 18,00 m2 1,503 100 1,503 - 100 1,503 sudah 100%

b Lantai 2
1 Perbaikan plafon gypsum 30,00 m2 0,303 100 0,303 - 100 0,303 sudah 100%
- Rangka hollow galvanis 4/4 & 4/2
- Gypsumboard 9mm ex. Jayaboard
2 Pekerjaan alumunium shadowline 95,00 m1 0,331 95 0,314 5 0,017 100 0,331 sudah 100%
3 Pengecatan plafon & shadowline 140,00 m2 0,390 100 0,390 - 100 0,390 sudah 100%
- ex. Dulux brilliant white
4 Perbaikan kebocoran atap 1,00 ls 0,209 95 0,198 - 95 0,198 Belum 100%, area nok blm di waterproof

c Ruang Ka Kanwil
1 Up ceiling gypsum 20,00 m2 0,313 100 0,313 - 100 0,313 sudah 100%
- Rangka hollow galvanis 4/4 & 4/2
- Gypsumboard 9mm ex. Jayaboard
2 Plafon GRC. Toilet 5,00 m2 0,061 100 0,061 - 100 0,061 belum dikerjakan
- Rangka hollow galvanis 4/4 & 4/2
- GRC 6mm ex. GRC Board
3 Pekerjaan alumunium shadowline 25,00 m1 0,087 100 0,087 - 100 0,087 sudah 100%
4 Pengecatan plafon & shadowline 25,00 m2 0,070 90 0,063 10 0,007 100 0,070 sudah 100%
- ex. Dulux brilliant white

V PEKERJAAN SANITAIR
a Lantai 1
1 Kloset duduk ex.Toto CW 823 RJ 2,00 unit 1,427 100 1,427 - 100 1,427 sudah 100%
2 Jet washer ex. Toto TX403SEV2CR 2,00 unit 0,139 100 0,139 - 100 0,139 sudah 100%
3 Paper holder ex. Toto TX720ACRB 2,00 unit 0,070 - - - - - belum dikerjakan
B0B0T PRESTASI FISIK TERHADAP SETIAP PEKERJAAN
NO URAIAN PEKERJAAN VOLUME SATUAN PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI KETERANGAN
(%) PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
4 Robe hook ex. Toto TS118WSB 2,00 unit 0,056 - - - - - belum dikerjakan
5 Wastafel ex. Toto LW819J 2,00 unit 0,696 100 0,696 - 100 0,696 sudah 100%
6 Afur & tutup wastafel ex. Toto 2,00 unit 0,139 100 0,139 - 100 0,139 sudah 100%
7 Kran wastafel ex. Toto TX116LRSN 2,00 unit 0,557 100 0,557 - 100 0,557 sudah 100%
8 Kaca cermin bevel 80x180cm 2,00 unit 0,278 - - 100 0,278 100 0,278 sudah 100%
9 Kran air wudhu ex. Toto TX133L 2,00 unit 0,063 - - - - - Tidak dikerjakan
10 Floor drain ex. Paloma FDP 2101 2,00 unit 0,070 - - 100 0,070 100 0,070 sudah 100%
11 Shower box kaca tempered 2,00 unit 0,974 100 0,974 - 100 0,974 sudah 100%
12 Shower set ex. Toto 2,00 unit 1,531 - - 100 1,531 100 1,531 sudah 100%
13 Bathtub ex. Toto 2,00 unit 1,531 100 1,531 - 100 1,531 sudah 100%
14 Kran taman 2,00 unit 0,070 - - - - - belum dikerjakan

b Lantai 2
1 Kloset duduk ex.Toto CW 823 RJ 2,00 unit 1,427 100 1,427 - 100 1,427 sudah 100%
2 Jet washer ex. Toto TX403SEV2CR 2,00 unit 0,139 100 0,139 100 0,139 200 0,278 sudah 100%
3 Paper holder ex. Toto TX720ACRB 2,00 unit 0,070 - - - - - belum dikerjakan
4 Robe hook ex. Toto TS118WSB 2,00 unit 0,056 - - - - - belum dikerjakan
5 Wastafel ex. Toto LW819J 2,00 unit 0,696 100 0,696 - 100 0,696 sudah 100%
6 Afur & tutup wastafel ex. Toto 2,00 unit 0,139 100 0,139 - 100 0,139 sudah 100%
7 Kran wastafel ex. Toto TX116LRSN 2,00 unit 0,557 100 0,557 - 100 0,557 sudah 100%
8 Kaca cermin bevel 80x180cm 2,00 unit 0,278 - - 100 0,278 100 0,278 sudah 100%
9 Kran air wudhu ex. Toto TX133L 2,00 unit 0,063 - - - - - Tidak dikerjakan
10 Floor drain ex. Paloma FDP 2101 2,00 unit 0,070 - - 100 0,070 100 0,070 sudah 100%
11 Shower box kaca tempered 2,00 unit 0,974 100 0,974 - 100 0,974 sudah 100%
12 Shower set ex. Toto 2,00 unit 1,531 - - 100 1,531 100 1,531 sudah 100%
13 Bathtub ex. Toto 2,00 unit 1,531 100 1,531 - 100 1,531 sudah 100%
belum dikerjakan
c Ruang Ka Kanwil
1 Kloset duduk ex.Toto CW 823 RJ 1,00 unit 0,713 - - 100 0,713 100 0,713 sudah 100%
2 Jet washer ex. Toto TX403SEV2CR 1,00 unit 0,070 - - 100 0,070 100 0,070 sudah 100%
3 Paper holder ex. Toto TX720ACRB 1,00 unit 0,035 - - - - - belum dikerjakan
4 Robe hook ex. Toto TS118WSB 1,00 unit 0,028 - - - - - belum dikerjakan
5 Hand dryer ex. Toto TYC322WF 1,00 unit 0,696 - - - - - belum dikerjakan
6 Kaca cermin bevel 80x180cm 1,00 unit 0,139 - - 100 0,139 100 0,139 sudah 100%
7 Wastafel ex. Toto LW819J 1,00 unit 0,348 - - 100 0,348 100 0,348 sudah 100%
8 Kran wastafel ex. Toto TX116LRSN 1,00 unit 0,278 - - 100 0,278 100 0,278 sudah 100%
9 Kran air wudhu ex. Toto TX133L 1,00 unit 0,031 - - - - - Tidak dikerjakan
10 Afur, syphon & aksesoris lainnya ex. Toto 1,00 unit 0,070 - - 100 0,070 100 0,070 sudah 100%
11 Floor drain ex. Paloma FDP 2101 1,00 unit 0,035 - - 100 0,035 100 0,035 sudah 100%

55,360 31,557 10,761 42,319


C PEKERJAAN ELEKTRIKAL & ELEKTRONIKA
I PANEL
1 Modifikasi panel elektrikal 1,00 unit 0,348 100 0,348 - 100 0,348 Sudah dikerjakan
- Termasuk penambahan, MCCB, MCB, bus bar dan komponen lainnya

II PEKERJAAN PENERANGAN DAN STOP KONTAK


aLantai 1
1 Recessed downlight LED 14W 6500K ex. Philips Eridani 16,00 bh 0,223 60 0,134 40 0,089 100 0,223 Sudah dikerjakan
2 Lampu taman 8,00 bh 0,278 - 100 0,278 100 0,278 Sudah dikerjakan
3 Lampu gantung utama pendopo 1,00 bh 0,313 90 0,282 10 0,031 100 0,313 Sudah dikerjakan
4 Lampu gantung ambience pendopo & teras 7,00 bh 0,487 90 0,438 10 0,049 100 0,487 Sudah dikerjakan
5 Outbow LED 11W 6500K ex. Philips 5,00 bh 0,174 90 0,157 10 0,017 100 0,174 Sudah dikerjakan
6 Instalasi penerangan dari panel ke titik lampu 37,00 titik 0,451 100 0,451 - 100 0,451 Sudah dikerjakan
- Kabel NYM 3 x 2,5mm² ex. Supreme dalam conduit pvc 20 mm
7 Saklar Ganda ex. Panasonic White Style 11,00 bh 0,042 60 0,025 40 0,017 100 0,042 Sudah dikerjakan
8 Stop Kontak PLN ex. Panasonic White Style di dinding/plafon 19,00 bh 0,086 60 0,052 40 0,034 100 0,086 Sudah dikerjakan
9 Instalasi stop kontak PLN 19,00 titik 0,231 100 0,231 - 100 0,231 Sudah dikerjakan
- Kabel 3 x 2,5mm² ex. Supreme dalam conduit pvc 20 mm

b Lantai 2
1 Recessed downlight LED 14W 6500K ex. Philips Eridani 20,00 bh 0,278 60 0,167 40 0,111 100 0,278 Sudah dikerjakan
2 Instalasi penerangan dari panel ke titik lampu 22,00 titik 0,268 100 0,268 - - 100 0,268 Sudah dikerjakan
- Kabel NYM 3 x 2,5mm² ex. Supreme dalam conduit pvc 20 mm
3 Saklar Ganda ex. Panasonic White Style 8,00 bh 0,031 60 0,018 40 0,012 100 0,031 Sudah dikerjakan
4 Stop Kontak PLN ex. Panasonic White Style di dinding/plafon 6,00 bh 0,027 60 0,016 40 0,011 100 0,027 Sudah dikerjakan
5 Instalasi stop kontak PLN 6,00 titik 0,073 100 0,073 - 100 0,073 Sudah dikerjakan
- Kabel 3 x 2,5mm² ex. Supreme dalam conduit pvc 20 mm

c Ruang Ka Kanwil
1 Recessed downlight LED 14W 6500K ex. Philips Eridani 3,00 bh 0,042 60 0,025 40 0,017 100 0,042 Sudah dikerjakan
2 Recessed downlight LED 7.5W 6500K ex. Philips Eridani 8,00 bh 0,111 60 0,067 40 0,045 100 0,111 Sudah dikerjakan
3 Lampu outdoor wallmount bulb 12W ex. Philips 4,00 bh 0,070 60 0,042 40 0,028 100 0,070 Sudah dikerjakan
4 LED Strip 18W 3000K warm white ex. Philips 13,00 m1 0,136 - 100 0,136 100 0,136 Sudah dikerjakan
5 Instalasi penerangan dari panel ke titik lampu 17,00 titik 0,207 100 0,207 - 100 0,207 Sudah dikerjakan
- Kabel NYM 3 x 2,5mm² ex. Supreme dalam conduit pvc 20 mm
6 Saklar Ganda ex. Panasonic White Style 4,00 bh 0,015 - 100 0,015 100 0,015 Sudah dikerjakan
7 Stop Kontak PLN ex. Panasonic White Style di dinding/plafon 5,00 bh 0,023 - 100 0,023 100 0,023 Sudah dikerjakan
8 Stop Kontak PLN ex. Panasonic White Style di furniture 1,00 bh 100 100 Sudah dikerjakan
9 Stop Kontak UPS ex. Panasonic White Style di furniture 1,00 bh 100 100 Sudah dikerjakan
10 Instalasi stop kontak PLN & UPS 7,00 titik 0,085 100 0,085 - 100 0,085 Sudah dikerjakan
- Kabel 3 x 2,5mm² ex. Supreme dalam conduit pvc 20 mm
11 Test commisioning 1,00 ls 0,070 - 50 0,035 50 0,035 belum dikerjakan

III INSTALASI TELEPON


1 Instalasi telepon dari MDF ke unit telepon 1,00 titik 0,016 100 0,016 - 100 0,016 Sudah dikerjakan
- Kabel telepon ex. Supreme dalam pipa conduit PVC 20mm
- Termasuk konektor, T-dos, socket, klem & aksesoris
2 Kabel jumper 1m dari outlet telepon ke pesawat telepon 1,00 titik 0,005 90 0,004 5 0,000 95 0,004 belum dikerjakan
- Kabel telepon ex. Supreme dengan konektor RJ11
3 Outlet telpon ex. Panasonic White Style 1,00 titik 0,003 90 0,003 5 0,000 95 0,003 belum dikerjakan
4 Test commisioning 1,00 ls 0,070 - - - - - belum dikerjakan

IV INSTALASI DATA
1 Instalasi kabel data dari server ke outlet data 1,00 titik 0,035 90 0,031 10 0,003 100 0,035 Sudah dikerjakan
- Kabel UTP CAT6 ex. Panduit TX6 dalam pipa conduit PVC 20mm
- Termasuk konektor, T-dos, socket, klem & aksesoris
2 Outlet data RJ45 ex. Panasonic White Style 1,00 ttk 0,005 45 0,002 55 0,002 100 0,005 belum dikerjakan
3 Kabel jumper 1m dari outlet data ke PC 1,00 titik 0,017 45 0,008 55 0,010 100 0,017 belum dikerjakan
B0B0T PRESTASI FISIK TERHADAP SETIAP PEKERJAAN
NO URAIAN PEKERJAAN VOLUME SATUAN PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI KETERANGAN
(%) PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
- Kabel UTP CAT6 ex. Panduit TX6 dengan konektor RJ45
4 Test commisioning 1,00 ls 0,035 - - - - - belum dikerjakan

V INSTALASI TV & SECURITY SYSTEM


1 CCTV digital IP camera ex. Samsung 2,00 unit belum dikerjakan
2 Instalasi CCTV dari NVR ke unit kamera 2,00 titik 0,070 - 100 0,070 100 0,070 Sudah dikerjakan
- Kabel UTP CAT6 ex. Panduit TX6 dalam pipa conduit PVC 20mm
3 Panic Button ex. Albox 1,00 unit 0,035 - - - - - belum dikerjakan
4 Instalasi security alarm 1,00 titik 0,016 - - - - - belum dikerjakan
- Kabel NYM 2 x 1,5mm² ex. Supreme dalam conduit pvc 20 mm
5 Instalasi TV 2,00 titik 0,031 45 0,014 55 0,017 100 0,031 Sudah dikerjakan
- Kabel Coaxial RG11 ex. Belden dalam pipa conduit PVC 20mm
- Termasuk konektor, T-dos, socket, klem & aksesoris
6 Outlet TV ex. Panasonic White Style 2,00 titik 0,006 45 0,003 55 0,003 100 0,006 Sudah dikerjakan
7 Test commisioning 1,00 ls 0,017 - - - - - belum dikerjakan

VI PEKERJAAN FIRE PROTECTION


1 Smoke detector ex. Hooseki 2,00 unit 0,104 - - - - - belum dikerjakan
2 ROR detector ex. Hooseki 1,00 unit 0,042 - - - - - belum dikerjakan
3 Instalasi dari TBFA ke detektor 3,00 titik 0,047 80 0,038 20 0,009 100 0,047 Sudah dikerjakan
- Kabel NYM 2 x 1,5mm² ex. Supreme dalam conduit pvc 20 mm
4 Fire extinguisher APAR CO2 3.2kg ex. Yamato 1,00 unit 0,244 - - - - - belum dikerjakan
5 Test commisioning 1,00 ls 0,035 - - - - - belum dikerjakan

VII PEKERJAAN ELEKTRONIKA


1 TV LED 55" wallmount 4,00 unit by owner
2 LED monitor CCTV 22" ex. Samsung 1,00 unit by owner
2 Kukas 2 pintu 4,00 unit by owner
3 Dispenser hot & cold 4,00 unit by owner
4 Water heater ex. Ariston 4,00 unit by owner

4,899 3,204 1,064 4,268


D PEKERJAAN MEKANIKAL & PLUMBING
I PEKERJAAN PEMIPAAN AIR BERSIH
1 Pipa PVC-AW Ø 1/2" ex. Rucika 85,00 m1 0,384 100 0,384 - 100 0,384 Sudah dikerjakan
2 Kuras & cuci tangki air eksisting 3,00 unit 0,104 - - - - - - belum dikerjakan
3 Fitting & alat bantu 1,00 ls 0,035 100 0,035 - 100 0,035 Sudah dikerjakan

II PEKERJAAN PEMIPAAN AIR KOTOR


1 Pipa PVC-AW Ø 100mm ex. Rucika. Air kotor & air hujan 50,00 m1 0,505 100 0,505 - 100 0,505 Sudah dikerjakan
2 Pipa PVC-AW Ø 2" ex. Rucika 65,00 m1 0,430 100 0,430 - 100 0,430 Sudah dikerjakan
3 Fitting & alat bantu 1,00 ls 0,035 100 0,035 - 100 0,035 Sudah dikerjakan

III PEKERJAAN TATA UDARA


1 AC split non inverter 1PK ex. Panasonic 6,00 unit 2,881 90 2,593 10 0,288 100 2,881 Sudah dikerjakan
- Termasuk pipa refrigerant, pipa drain, isi freon dan aksesoris lainnya
2 AC split non inverter 2PK ex. Panasonic 5,00 unit 2,749 90 2,474 10 0,275 100 2,749 Sudah dikerjakan
- Termasuk pipa refrigerant, pipa drain, isi freon dan aksesoris lainnya
3 Exhaust fan cerobong 8" ceiling mounted ex. KDK 24CDQN 1,00 unit 0,070 - - - - - belum dikerjakan
4 Test commisioning 1,00 ls 0,035 - - - - - belum dikerjakan

7,227 6,455 0,563 7,018

TOTAL 70,246 43,20 12,99 56,19


BOBOT REALISASI 43,20% 12,99% 56,19%
BOBOT RENCANA 85,50% 14,50% 100,00%
DEVIASI -42,30% -1,52% -43,81%
LAPORAN PROGRES MINGGUAN
WAKTU TERPAKAI 45 HARI
RENCANA ANGGARAN BIAYA PEKERJAAN FURNITURE SISA WAKTU 0 HARI
PENGADAAN RENOVASI WISMA PRADANA BANK BTN MINGGU KE VII TUJUH
PERIODE 28/07/2022 S/D 03/08/2022
B0B0T PRESTASI FISIK TERHADAP SETIAP PEKERJAAN
NO URAIAN PEKERJAAN VOLUME SATUAN PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
(%) PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
E PEKERJAAN FURNITURE
I KAMAR TIDUR LANTAI 1
1 Sofa double seater 4,00 unit 1,949 - 100 1,949 100 1,949
2 Sofa outdoor single 4,00 unit 0,974 - 100 0,974 100 0,974
3 Coffee table ruang tamu 2,00 unit 0,696 - 100 0,696 100 0,696
4 Coffee table teras 2,00 unit 0,557 - 100 0,557 100 0,557
5 Kasur king size + ranjang 2,00 unit 2,992 - 100 2,992 100 2,992
6 Nakas 4,00 unit 0,418 90 0,376 10 0,042 100 0,418
7 Credenza l=1.6m 2,00 unit 0,661 90 0,595 10 0,066 100 0,661
8 Meja kerja 2,00 unit 0,835 - - 100 0,835 100 0,835
9 Kursi kerja ex. Indachi Vouge I CR (warna hitam kaki chrome) 2,00 unit 0,522 90 0,470 10 0,052 100 0,522
10 Kabinet pantry 2,00 unit 0,418 - - 100 0,418 100 0,418
11 Kabinet wastafel bawah l=1m 2,00 unit 0,418 - - 100 0,418 100 0,418
12 Kabinet wastafel atas l=1m 2,00 unit 0,418 - - 100 0,418 100 0,418
13 Relokasi furniture eksisting 1,00 ls 0,174 90 0,157 10 0,017 100 0,174

II KAMAR TIDUR LANTAI 2


1 Sofa single seater 6,00 unit 1,461 - - 100 1,461 100 1,461
2 Kursi makan 8,00 unit 1,113 - - 100 1,113 100 1,113
3 Coffee table 2,00 unit 0,696 - - 100 0,696 100 0,696
4 Meja makan 2,00 unit 1,411 95 1,341 5 0,071 100 1,411
5 Credenza TV l=2.4m 2,00 unit 1,044 90 0,939 10 0,104 100 1,044
6 Kabinet pantry 2,00 unit 0,814 - - 100 0,814 100 0,814
7 Kasur single size + ranjang 2,00 unit 2,742 35 0,960 65 1,782 100 2,742
8 Nakas 4,00 unit 0,696 90 0,626 10 0,070 100 0,696
9 Puff 2,00 unit 0,278 - - 100 0,278 100 0,278
10 Kabinet wastafel bawah l=1m 2,00 unit 0,522 - - 100 0,522 100 0,522
11 Kabinet wastafel atas l=1m 2,00 unit 0,522 - - 100 0,522 100 0,522
12 Relokasi furniture eksisting 1,00 ls 0,244 90 0,219 10 0,024 100 0,244

III RUANG KA KANWIL


1 Meja kerja & credenza Ka Kanwil ex. High Point Huron Office Desk ODHR10 1,00 unit 0,821 - - 100 0,821 100 0,821
- Rangka multipleks fin. HPL ex. Arborite A8368M - Browny Pine + kaca bening bevel 5mm
- Kaki meja stainless steel. Termasuk fliptop aluminium
- Termasuk outlet power, data, telepon, grommet, belalai kabel & aksesoris lainnya
2 Kursi kerja Ka Kanwil ex. Indachi Vouge I CR (warna hitam kaki chrome) 1,00 unit 0,313 - - 100 0,313 100 0,313
3 Kursi hadap Ka Kanwil ex. Indachi Vouge III VCR (warna hitam kaki chrome) 2,00 unit 0,487 - - 100 0,487 100 0,487
4 Lemari Ka Kanwil 1,00 unit 0,896 - - 100 0,896 100 0,896
- Rangka multipleks fin. HPL ex. Taco TH 1202 FC
5 Coffee table 1,00 unit 0,452 - - 100 0,452 100 0,452
6 Sofa 1 seater 1,00 unit 0,278 - - 100 0,278 100 0,278
7 Sofa 2 seater 1,00 unit 0,870 - - 100 0,870 100 0,870

IV PENDOPO
1 Sofa outdoor single 5,00 unit 1,392 - - 100 1,392 100 1,392
2 Sofa outdoor double 1,00 unit 0,522 - - 100 0,522 100 0,522
3 Coffee table teras 3,00 unit 1,148 - - 100 1,148 100 1,148

29,75 5,68 24,07 29,75