KEBUTUHAN MATERIAL PEKERJAAN JALAN

NO URAIAN SATUAN VOL KEBUTUHAN PEMBULATAN


PEKERJAAN JALAN
1 LPB (BATU BELAH) M3 118.125 118.125
2 LPB (SIRTU) M3 81 118.125
3 LANTAI KERJA K 175 M3 22.5
SPLIT 1/2 M3 12.8625 13
PASIR BETON M3 10.6875 11
SEMEN ZAK 122.25 123
4 PLASTIK COR UKURAN (1 X 50 MTR PER ROLL) ROL 9
5 WIREMASH M8 LBR 43.65079 43.65079365 44
6 RIGID BETON K 350 M3 112.5
SPLIT 1/2 M3 62.5 63
PASIR BETON M3 46.8984375 47
SEMEN ZAK 840 840

PEKERJAAN SALURAN
1 PAS BATU KALI M3 157.5
BATU BELAH M3 189 189
PASIR PASANG M3 85.68 86
SEMEN ZAK 357 357

KEBUTUHAN PEKERJAAN RIGID BETON DAN SALURAN


SEMEN 1320 ZAK
SPLIT 1/2 76 M3
PASIR BETON 58 M3
PASIR PASANG 86 M3