JANGKA WAKTU PELAKSANAAN (KURVA - S)

67 (Enam Puluh Tujuh) Hari Kalender

MASA PEMELIHARAAN 180 Hari Kalender


Tahun 2021
Mggu Mggu Mggu Mggu Mggu Mggu Mggu Mggu Mggu Mggu Mggu
BOBOT
NO. URAIAN PEKERJAAN (%) Ke Ke Ke Ke Ke Ke Ke Ke Ke Ke Ke KET
1 2 3 4 5 6 7 8 9 10 11

FINAL HAND OVER (FHO)


24 31 7 14 21 28 5 12 19 26

30 6 13 20 27 4 11 18 25 31

10000%

PROVISIONAL HAND OVER


A PEKERJAAN PERSIAPAN 6.454 0.286 0.500 0.143 0.111 0.048 1.032 1.078 0.755 1.045 1.457

B GEDUNG REKTORAT 34.375 0.322 0.477 4.859 13.343 10.986 1.993 2.395 8000%

C GEDUNG LABORATORIUM

(PHO)
6.858 0.058 0.270 0.396 1.117 3.065 1.952
6000%
D GEDUNG G 18.530 0.177 0.654 1.636 3.544 7.365 5.154

4000%
E GEDUNG E 8.493 0.448 1.365 2.629 2.493 1.558

F GEDUNG F 9.626 0.399 0.575 1.419 1.916 3.715 1.603


2000%
G GEDUNG H 15.664 0.053 1.116 1.215 2.711 5.331 5.238
0%

100.00

BOBOT RENCANA 0.52 1.87 3.54 7.72 13.90 16.25 17.06 16.37 12.08 10.69

KOMULATIF BOBOT RENCANA 0.52 2.39 5.93 13.65 27.55 43.80 60.86 77.22 89.31 100.00