PERATURAN

MENTERI PEKERJAAN UMUM DAN PERUMAHAN RAKYAT


NOMOR 1 TAHUN 2022
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN PEKERJAAN BETON


CATATAN
Bobot isi pasir + 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Bucking factor pasir = 20 %

Membuat 1 m' kolom praktis beton bertulang (11cmx11cm)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.180 125,000.00 22,500.00
Tukang batu L.02 OH 0.020 150,000.00 3,000.00
Tukang Kayu L.02 OH 0.020 150,000.00 3,000.00
Tukang besi L.02 OH 0.020 150,000.00 3,000.00
Kepala Tukang L.03 OH 0.006 165,000.00 990.00
Mandor L.04 OH 0.009 175,000.00 1,575.00
JUMLAH TENAGA KERJA 34,065.00
B BAHAN
Kayu kelas III m3 0.0020 1,600,000.00 3,200.00
Paku 5 - 12 cm Kg 0.010 12,500.00 125.00
Besi beton polos Kg 3.000 13,000.00 39,000.00
Kawat beton Kg 0.450 20,900.00 9,405.00
Semen portland Kg 4.000 1,250.00 5,000.00
Pasir beton m3 0.006 225,000.00 1,350.00
Kerikil m3 0.009 275,000.00 2,475.00
JUMLAH HARGA BAHAN 60,555.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 94,620.00


E Overhead & Profit 7% x D 6,623.40
F Harga Satuan Pekerjaaan (D+E) 101,243.40