Membuat 1 m' kolom praktis beton bertulang (11cmx11cm)
Harga Satuan Jumlah Harga No Uraian Kode Satuan Koefisien (Rp) (Rp) A TENAGA Pekerja L.01 OH 0.180 125,000.00 22,500.00 Tukang batu L.02 OH 0.020 150,000.00 3,000.00 Tukang Kayu L.02 OH 0.020 150,000.00 3,000.00 Tukang besi L.02 OH 0.020 150,000.00 3,000.00 Kepala Tukang L.03 OH 0.006 165,000.00 990.00 Mandor L.04 OH 0.009 175,000.00 1,575.00 JUMLAH TENAGA KERJA 34,065.00 B BAHAN Kayu kelas III m3 0.0020 1,600,000.00 3,200.00 Paku 5 - 12 cm Kg 0.010 12,500.00 125.00 Besi beton polos Kg 3.000 13,000.00 39,000.00 Kawat beton Kg 0.450 20,900.00 9,405.00 Semen portland Kg 4.000 1,250.00 5,000.00 Pasir beton m3 0.006 225,000.00 1,350.00 Kerikil m3 0.009 275,000.00 2,475.00 JUMLAH HARGA BAHAN 60,555.00 C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 94,620.00
E Overhead & Profit 7% x D 6,623.40 F Harga Satuan Pekerjaaan (D+E) 101,243.40