RAB Moveable Toilet 24-10-2022
RAB Moveable Toilet 24-10-2022
HASSCO JAKARTA
QUOTATION
Di buat oleh :
Total 46,785,055
Pembulatan 46,785,000
*Catatan:
1. Harga penawaran berlaku selama 7 hari dari tanggal pembuatan.
2. Harga penawaran belum termasuk PPN 11%
COST BREAK DOWN
Project : Pekerjaan Moveable Toilet uk 2,4 x 2,4 m
Up : Bapak Humala
Lokasi :
Kontraktor : PT. Cruzindo Utama Jaya Date, 24 Oct '2022
MATERIAL LABOUR+EQUIPMENT TOTAL
NO DESCRIPTION VOLUME
U/PRICE AMOUNT U/PRICE AMOUNT U/PRICE AMOUNT
B. Pekerjaan Dinding
1 Hollow - 75 x 75 x 2,3 mm 42.67 kg 23,500 1,002,745 5,000 213,350 28,500 1,216,095
2 Hollow - 50 x 50 x 2,3 mm 94.58 kg 23,500 2,222,630 5,000 472,900 28,500 2,695,530
3 Steel Plat - t=10 mm 16.18 kg 23,500 380,243 5,000 80,903 28,500 461,146
4 Steel Plat - t=6 mm 20.42 kg 23,500 479,792 5,000 102,083 28,500 581,875
5 Zincromate ex. Propan 173.85 kg 950 165,155 300 52,154 1,250 217,309
6 Cat finish ex. Propan 173.85 kg 1,250 217,309 300 52,154 1,550 269,463
7 Baut M12 mm x 4" 10 set 14,500 145,000 2,500 25,000 17,000 170,000
8 Baut M12 mm x 3" 14 set 12,500 175,000 2,500 35,000 15,000 210,000
C. Pekerjaan Atap
1 Hollow - 50 x 50 x 2,3 mm 82.36 kg 23,500 1,935,460 5,000 411,800 28,500 2,347,260
2 Steel Plat - t=6 mm 19.42 kg 23,500 456,370 5,000 97,100 28,500 553,470
3 Zincromate ex. Propan 101.78 kg 950 96,691 300 30,534 1,250 127,225
4 Cat finish ex. Propan 101.78 kg 1,250 127,225 300 30,534 1,550 157,759
5 Baut M12 mm x 3" 32 set 12,500 400,000 2,500 80,000 15,000 480,000
Page 4 of 5
MATERIAL LABOUR+EQUIPMENT TOTAL
NO DESCRIPTION VOLUME
U/PRICE AMOUNT U/PRICE AMOUNT U/PRICE AMOUNT
*Catatan:
1. Harga penawaran berlaku selama 7 hari dari tanggal pembuatan.
2. Harga penawaran belum termasuk PPN 11%
3. Harga Untuk Pekerjaan 1 Unit
Page 5 of 5