CCO (Contract Change Order)

PEKERJAAN : Penyediaan Sarana Pengairan di Instalasi Benih Tanaman Pangan Ogomolos Kec. Mepanga Kab. Parigi Moutong

LOKASI : Desa Ogomolos Kec. Mepanga Kab. Parigi Moutong


TAHUN ANGGARAN : 2021

KONTRAK PEKERJAAN TAMBAH PEKERJAAN KURANG KONTRAK ADDENDUM


No. URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH HARGA JUMLAH HARGA HARGA SATUAN JUMLAH HARGA HARGA SATUAN JUMLAH HARGA
VOL VOL VOL VOL
(Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.)
1 4 3 3 3 3
PEKERJAAN PERSIAPAN
1 Pekerjaan Pembersihan LS 1.00 1,000,000.00 1,000,000.00 1.00 1,000,000.00 1,000,000.00
2 Papan Nama Kegiatan LS 1.00 100,000.00 100,000.00 1.00 100,000.00 100,000.00
3 K3 LS 1.00 3,000,000.00 3,000,000.00 1.00 3,000,000.00 3,000,000.00
PEKERJAAN SALURAN 521 m
1 Pekerjaan Galian Tanah M3 464.58 51,396.27 23,877,679.12 198.36 51,396.27 10,194,964.12 266.22 51,396.27 13,682,715.00
2 Pekerjaan Urugan Pasir Bawah Pasangan M3 47.07 158,180.00 7,445,532.60 28.52 158,180.00 4,511,293.60 18.55 158,180.00 2,934,239.00
3 Pekerjaan Pasangan Batu 1PC 5PP M3 227.17 697,720.80 158,501,234.14 126.53 697,720.80 88,282,205.86 353.70 697,720.80 246,783,440.00
4 Pekerjaan Plesteran 1PC 3PP M2 1,540.00 65,752.67 101,259,111.80 663.92 65,752.67 43,654,707.66 876.08 65,752.67 57,604,404.14
5 Pekerjaan Acian M2 1,540.00 34,325.50 52,861,270.00 812.57 34,325.50 27,891,973.33 727.43 34,325.50 24,969,296.67
6 Timbunan Setempat/Urugan Kembali M3 156.10 30,125.70 4,702,621.77 67.36 30,125.70 2,029,267.15 88.74 30,125.70 2,673,354.62
PEKERJAAN GORONG-GORONG 0.00
1 Pekerjaan Galian Tanah M3 0.72 51,396.27 37,005.31 - 0.72 51,396.27 37,005.31
2 Pekerjaan Beton 1PC 3 PP 5 KR M3 0.36 739,046.00 266,056.56 - 0.36 739,046.00 266,056.56
3 Gorong-gorong dia. 60 cm M 4.00 498,620.00 1,994,480.00 - 4.00 498,620.00 1,994,480.00
Pekerjaan Akhir - 0.00
1 Pelaporan LS 1.00 1,000,000.00 1,000,000.00 - 1.00 1,000,000.00 1,000,000.00
2 As Build Drawing LS 1.00 1,000,000.00 1,000,000.00 - 1.00 1,000,000.00 1,000,000.00
A. BIAYA KONTRUKSI 357,044,991.30 88,282,205.86 88,282,205.86 357,044,991.30
B. PAJAK PENAMBAHAN NILAI (PPN) 10% 35,704,499.13 8,828,220.59 8,828,220.59 35,704,499.13
C. JUMLAH 392,749,490.43 97,110,426.45 97,110,426.45 392,749,490.43

Disetujui Oleh Diperiksa Dibuat Oleh


KUASA PENGGUNA ANGGARAN CV. LIMA DIMENSI CV. PUTRI SAFIRA

Ir. SALEH GUNAWAN BUDJANG, MT TUSIONO TRI PAMBUDI,ST ANDI AMALIA


NIP. 19651103 199203 2 007 SITE ENGINEER DIREKTUR