Anda di halaman 1dari 10

Faiz Fadhilah Wahab (4221210022)

Alif Rafli Lazuardi (4221210026)


Keyla Aptaning Batari (4221210037)
Shyreeva Djamal Putra Indrawan (4221210041)
TEKNIK SIPIL UNIVERSITAS PANCASILA Bara Jauza (4221210047)

BAB III
Desain Rangka Kuda-Kuda

NAMA PANJANG
NO. PANJANG BATANG BATANG (SKALA)
BATANG
1. ag 416,6533 cm 16 cm
2. ao 289,13665 cm 11,65 cm
3. og 300 cm 12 cm
4. af 300 cm 12 cm
5. of 80 cm 3,2 cm
6. a1 138,8844 cm 5,5 cm
7. a2 138,8844 cm 5,5 cm
8. a3 138,8844 cm 5,5 cm
9. a4 138,8844 cm 5,5 cm
10. a5 138,8844 cm 5,5 cm
11. a6 138,8844 cm 5,5 cm
12. b1 100 cm 4 cm
13. b2 100 cm 4 cm
14. b3 100 cm 4 cm
15. b4 100 cm 4 cm
16. b5 100 cm 4 cm
17. b6 100 cm 4 cm
18. d1 107,0825 cm 4,3 cm
19. d2 153,9119 cm 6,1 cm
20. d3 153,9119 cm 6,1 cm
21. d4 107,0825 cm 4,3 cm
22. t1 73,333 cm 2,9 cm
23. t2 146,666 cm 5,9 cm
24. t3 220 cm 8,8 cm
25. t4 146,666 cm 5,9 cm
26. t5 73,333 cm 2,9 cm
Faiz Fadhilah Wahab (4221210022)
Alif Rafli Lazuardi (4221210026)
Keyla Aptaning Batari (4221210037)
Shyreeva Djamal Putra Indrawan (4221210041)
TEKNIK SIPIL UNIVERSITAS PANCASILA Bara Jauza (4221210047)

1. Identifikasi data-data yang digunakan


Q atap = 5,24 kg/m2
Jarak antar kuda-kuda = 1,8 m
Panjang Batang = 1,388844 m
Beraj jenis baja = 7850 kg/m3
Berat gording = 9,54 kg/m
Berat penggantung (plafon) = 11 kg/m2
P (berat pekerja) = 90 kg
Tekanan tiup angin = 10 km/jam

2. Perhitungan Pembebanan
a. Beban Mati (BM)
i. Beban Penutup Atap (P1)
P1(Kg) = Luas bidang penutup atap yang dipikul (m2) X Berat penutup atap per
meter2 (kg/m2)
Faiz Fadhilah Wahab (4221210022)
Alif Rafli Lazuardi (4221210026)
Keyla Aptaning Batari (4221210037)
Shyreeva Djamal Putra Indrawan (4221210041)
TEKNIK SIPIL UNIVERSITAS PANCASILA Bara Jauza (4221210047)

- Luas Bidang 1 = (1/2 x AA) x (1/2 x a1)


= (1/2 x 1,8) x (1/2 x 1,388844)
= 0,624798 m2
- Luas Bidang 2 = (1/2 x CC) x (1/2 x a1)
= (1/2 x 1,8) x (1/2 x 1,388844)
= 0,624798 m2
- Luas Bidang 3 = (1/2 x CC) x (1/2 x a2)
= (1/2 x 1,8) x (1/2 x 1,388844)
= 0,624798 m2
- Luas Bidang 4 = (1/2 x EE) x (1/2 x a2)
= (1/2 x 1,8) x (1/2 x 1,388844)
= 0,624798 m2
- Luas Bidang 5 = (1/2 x EE) x (1/2 x a3)
= (1/2 x 1,8) x (1/2 x 1,388844)
= 0,624798 m2
- Luas Bidang 6 = (1/2 x GG) x (1/2 x a3)
= (1/2 x 1,8) x (1/2 x 1,388844)
= 0,624798 m2

Titik A = Luas Bidang 1 x Berat penutup atap per meter2


= 0,624798 m2 x 5,24kg/m2
= 3,27394152 kg
Titik B =0
Titik C = Luas Bidang 2 + Luas Bidang 3 x Berat penutup atap per meter2
= 0,624798 m2 + 0,624798 m2 x 5,24 kg/m2
= 6,54788304 kg
Titik D =0
Titik E = Luas Bidang 4 + Luas Bidang 5 x Berat Penutup atap per meter2
= 0,624798 m2 + 0,624798 m2 x 5,24 kg/m2
= 6,54788304 kg
Titik F =0
Titik G = (1/2 x GG) x (1/2 x a3) x Berat Penutup atap per meter2
= (1/2 x 1,8) x (1/2 x 1,388844) x 5,24 kg/m2
= 3,27394152 kg
Faiz Fadhilah Wahab (4221210022)
Alif Rafli Lazuardi (4221210026)
Keyla Aptaning Batari (4221210037)
Shyreeva Djamal Putra Indrawan (4221210041)
TEKNIK SIPIL UNIVERSITAS PANCASILA Bara Jauza (4221210047)

ii. Berat Kuda – Kuda (P2)


P2(kg) = Luas penampang (m2) X Berat jenis (kg/m2) x Panjang (m)
Panjang (m) = ½ Panjang seluruh batang yang ada pada titik simpul

Titik A = (1/2 x a1) + (1/2 x b1) x Bj Baja x Panjang


= (1/2 x 1.388844) + (1/2 x 1) x 7850 x 0,004274 x 2
= 34,245322 kg
Titik B = (1/2 x b1) + (1/2 x t1) + (1/2 x b2) x Bj Baja x Panjang
= (1/2 x 1) + (1/2 x 0,7333) + (1/2 x 1) x 7850 x 0,004274 x 2
= 34,41755 kg
Faiz Fadhilah Wahab (4221210022)
Alif Rafli Lazuardi (4221210026)
Keyla Aptaning Batari (4221210037)
Shyreeva Djamal Putra Indrawan (4221210041)
TEKNIK SIPIL UNIVERSITAS PANCASILA Bara Jauza (4221210047)

Titik C = (1/2 x a1) + (1/2 x t1) + (1/2 x a2) + (1/2 x d1) x Bj Baja x Panjang
= (1/2 x 1.388844) + (1/2 x 0,7333) + (1/2 x 1,388844) + (1/2 x
1,070825) x 7850 x 0,004274 x 2
= 37,68264 kg
Titik D = (1/2 x b2) + (1/2 x t2) + (1/2 x b3) + (1/2 x d1) x Bj Baja x Panjang
= (1/2 x 1) + (1/2 x 1,46666) + (1/2 x 1) + (1/2 x 1,070825) x 7850 x
0,004274 x 2
= 37,66047 kg
Titik E = (1/2 x a2) + (1/2 x t2) + (1/2 x d2) + (1/2 x a3) x Bj Baja x Panjang
= (1/2 x 1,388844) + (1/2 x 1,46666) + (1/2 x 1,539119) + (1/2 x
1,388844) x 7850 x 0,004274 x 2
= 48,79428 kg
Titik F = (1/2 x b3) + (1/2 x d2) + (1/2 x t3) x Bj Baja x Panjang
= (1/2 x 1) + (1/2 x 1,539119) + (1/2 x 2,2) x 7850 x 0,004274 x 2
= 35,42046 kg
Titik G = (1/2 x a3) + (1/2 x t3) x Bj Baja x Panjang
= (1/2 x 1.388844) + (1/2 x 2,2) x 7850 x 0,004274 x 2
= 47,69697 kg

iii. Berat Gording (P3)


P3 (kg) = (jumlah gording pada area pikul x berat gording per meter (kg/m) x
jara antar kuda-kuda (m)) /2
Faiz Fadhilah Wahab (4221210022)
Alif Rafli Lazuardi (4221210026)
Keyla Aptaning Batari (4221210037)
Shyreeva Djamal Putra Indrawan (4221210041)
TEKNIK SIPIL UNIVERSITAS PANCASILA Bara Jauza (4221210047)

Titik A = (1 x 9,54 x (1/2 x 1,8)) / 2


= 4,293 kg
Titik B =0
Titik C = (1 x 9,54 x (1/2 x 1,8)) / 2
= 4,293 kg
Titik D =0
Titik E = (1 x 9,54 x (1/2 x 1,8)) / 2
= 4,293 kg
Titik F =0
Titik G = (1 x 9,54 x (1/2 x 1,8)) / 2
= 4,293 kg
iv. Berat Plafond (P4)
P4 (kg) = Berat Plafond x Luas Bidang (m)
Faiz Fadhilah Wahab (4221210022)
Alif Rafli Lazuardi (4221210026)
Keyla Aptaning Batari (4221210037)
Shyreeva Djamal Putra Indrawan (4221210041)
TEKNIK SIPIL UNIVERSITAS PANCASILA Bara Jauza (4221210047)

- Luas Bidang 1 = (1/2 x AA) x (1/2 x b1)


= (1/2 x 1,8) x (1/2 x 1)
= 0,45 m2
- Luas Bidang 2 = (1/2 x CC) x (1/2 x b1)
= (1/2 x 1,8) x (1/2 x 1)
= 0,45 m2
- Luas Bidang 3 = (1/2 x CC) x (1/2 x b2)
= (1/2 x 1,8) x (1/2 x 1)
= 0,45 m2
- Luas Bidang 4 = (1/2 x EE) x (1/2 x b2)
= (1/2 x 1,8) x (1/2 x 1)
= 0,45 m2
- Luas Bidang 5 = (1/2 x EE) x (1/2 x b3)
= (1/2 x 1,8) x (1/2 x 1)
= 0,45 m2
- Luas Bidang 6 = (1/2 x GG) x (1/2 x b3)
= (1/2 x 1,8) x (1/2 x 1)
= 0,45 m2

Titik A = Luas Bidang 1 x Berat Plafond


= 0,45 m2 x 11 kg/m
= 4,95 kg
Titik B = Luas Bidang 2 + Luas Bidang 3 x Berat Plafond
= 0,45 m2 + 0,45 m2 x 11 kg/m
= 5,4 kg
Titik C =0
Titik D = Luas Bidang 4 + Luas bidang 5 x Berat Plafond
= 0,45 m2 + 0,45 m2 x 11 kg/m
= 5,4 kg
Titik E =0
Titik F = Luas Bidang 6 x Berat Plafond
= 0,45 m2 x 11 kg/m
= 4,95 kg
Titik G =0
Faiz Fadhilah Wahab (4221210022)
Alif Rafli Lazuardi (4221210026)
Keyla Aptaning Batari (4221210037)
Shyreeva Djamal Putra Indrawan (4221210041)
TEKNIK SIPIL UNIVERSITAS PANCASILA Bara Jauza (4221210047)

Berat
Titik Berat Peutup Berat Kuda- Berat
No Plafond Total Beban
Simpu Atap Kuda Gording
. (P4) Mati (Kg)
l (P1) (Kg) (P2) (Kg) (P3) (Kg)
(Kg)
1 A 3,27394152 34,245322 4,293 4,95 46,76226352
2 B 0 34,41755 0 5,4 39,81755
3 C 6,54788304 37,68264 4,293 0 48,52352304
4 D 0 37,66047 0 5,4 43,06047
5 E 6,54788304 48,79428 4,293 0 59,63516304
6 F 0 35,42046 0 4,95 40,37046
7 G 3,27394152 47,69697 4,293 0 55,26391152

b. Beban Hidup (BH)


P (Kg) = 90 Kg

Titik A = 90 Kg
Titik B = 0
Titik C = 90 Kg
Titik D = 0
Titik E = 90 Kg
Titik F = 0
Titik G = 90 Kg
Faiz Fadhilah Wahab (4221210022)
Alif Rafli Lazuardi (4221210026)
Keyla Aptaning Batari (4221210037)
Shyreeva Djamal Putra Indrawan (4221210041)
TEKNIK SIPIL UNIVERSITAS PANCASILA Bara Jauza (4221210047)

c. Beban Angin
Pw (Kg) = Luas Bidang Penutup Atap yang Dipikul (m2) x Tenganan Angin Per
Meter (Kg/m2)

- Luas Bidang 1 = (1/2 x AA) x (1/2 x a1)


= (1/2 x 1,8) x (1/2 x 1,388844)
= 0,624798 m2
- Luas Bidang 2 = (1/2 x CC) x (1/2 x a1)
= (1/2 x 1,8) x (1/2 x 1,388844)
= 0,624798 m2
- Luas Bidang 3 = (1/2 x CC) x (1/2 x a2)
= (1/2 x 1,8) x (1/2 x 1,388844)
= 0,624798 m2
- Luas Bidang 4 = (1/2 x EE) x (1/2 x a2)
= (1/2 x 1,8) x (1/2 x 1,388844)
= 0,624798 m2
- Luas Bidang 5 = (1/2 x EE) x (1/2 x a3)
= (1/2 x 1,8) x (1/2 x 1,388844)
= 0,624798 m2
- Luas Bidang 6 = (1/2 x GG) x (1/2 x a3)
= (1/2 x 1,8) x (1/2 x 1,388844)
= 0,624798 m2
Faiz Fadhilah Wahab (4221210022)
Alif Rafli Lazuardi (4221210026)
Keyla Aptaning Batari (4221210037)
Shyreeva Djamal Putra Indrawan (4221210041)
TEKNIK SIPIL UNIVERSITAS PANCASILA Bara Jauza (4221210047)

Titik A = Luas Bidang 1x Tekanan Tiup Angin


= 0,624798 m2 x 10
= 6,24798 kg
Titik B =0
Titik C = Luas Bidang 2 + Luas Bidang 3 x Berat penutup atap per meter2
= 0,624798 m2 + 0,624798 m2 x 10
= 12,49596 kg
Titik D =0
Titik E = Luas Bidang 4 + Luas Bidang 5 x Berat Penutup atap per meter2
= 0,624798 m2 + 0,624798 m2 x 10
= 12,49596 kg
Titik F =0
Titik G = (1/2 x GG) x (1/2 x a3) x Berat Penutup atap per meter2
= (1/2 x 1,8) x (1/2 x 1,388844) x 10
= 6,24798 kg

d. Total Beban

No Titik Beban Mati Beban Hidup Beban Angin


. Simpul (BM) (BH) (BA)
1 A 46,76226352 90 6,2478
2 B 39,81755 0 0
3 C 48,52352304 90 12,49596
4 D 43,06047 0 0
5 E 59,63516304 90 12,49596
6 F 40,37046 0 0
7 G 55,26391152 90 6,2478

Anda mungkin juga menyukai