Rencana Anggaran Biaya (RAB)

Pekerjaan : PEMASANGAN JTR


Lokasi : Mutiara Gading City

PEKERJAAN SAT VOL HARGA JUMLAH KET


TIANG
Tiang Beton 11/200 daN Btg 2 3.350.000 6.700.000
Tiang Beton 12/350 daN Btg 3 3.500.000 10.500.000
SUB 17.200.000
SUTR
MATERIAL
TIC 3X70+N (CABLE PWR, NFA2X-T;3X70+1X70;0.6/1KV;OH) Mtr 165 55.000 9.075.000
CCO 70 / 70 Bh 4 15.000 60.000
A3CS 70 mm (Untuk Pentanahan) Mtr 10 18.000 180.000
Earthing Rod 16 x 2500 sqmm + Klem Btg 1 50.000 50.000
Fixed Dead Assembly Bh 10 45.000 450.000
Suspension Sys Bh 4 37.000 148.000
EMP (Electrical and Mecanical Protection) Set 1 15.000 15.000
Stainless Steel Strip Mtr 45 7.000 315.000
Link 25 x 25 Bh 45 1.000 45.000
Stopping Buckle Bh 45 1.000 45.000
SUB 10.383.000
JASA
Pasang SUTR TIC 3 x 70 + N Mtr 0,165 6.500.000 1.072.500
Pondasi Tiang TR Bh 5 350.000 1.750.000
Pasang Pentanahan TR (ERR) Set 1 150.000 150.000
Pasang Konstruksi TR 1B (Jaringan < 45 Derajat) Bh 2 100.000 200.000
Pasang Konstruksi TR 2B (Jaringan 45 - 120 Derajat) Bh 2 150.000 300.000
Pasang Konstruksi TR 10B (Jaringan Awal Percabangan / Aftak) Bh 1 120.000 120.000
Pasang Konstruksi TR 10B (Jaringan Akhir) Bh 1 175.000 175.000
SUB 3.767.500
SUB TOTAL 31.350.500