Planned Cost Differs from Actual Cost Question : I have a problem.

I have a standard activity which the price is $1 / hr. I have createda project in which a activity has a planned hr of qty 1. But my planned cost comes in as '$0.83'.But when I comfirm my activity, the actual cost comes in as '$1'.Why is my planned cost differing? What is the cause of the $0.83 instead of $1. Where can icheck and change this. Answer : I guess that you use different costing (and valuation) variants. so the system mightvaluate plan and actuals differently. Question : Where and how do i control it? Answer : In the network header are two fields: one for the plan costing variant and one for theactual costing variant.You maintain the costing variants in the customizing: PS -> Costs -> Planned Costs ->AutomaticCosting in Networks -> Costing -> Define Costing Variants. Display the costing variant and jump to the valuation variant. There you find how the determines the costs. Validations in PS Question : I am trying to use validation in the Project. Can anyone tell when are the call up points 110 and 120 triggered? I want to validate one of the user defined fields in WBS

Everything is working fine when I simulate the validation. But when I enter a value in the user defined field and save the project then I do not get the error message as expected.Does anybody have an idea what could be wrong ?? Answer : Please see if you have checked the check box for Automatic validation in the relevant project profile. Question : I want to validate the customer number in one of the user fields in WBS. Theformula builder in the validation screen, it seems, does not support table fields other than fieldsfrom PRPS. Can this be done thru some user exits ?? If yes how ?? Can u guide me in this ?? Answer : To use a user exit in validations, you have to perform following steps;- copy SAP standard program GGBS002 to ZGGBS002- create a user exit in this program (such as U902, U903 etc)the user exit you defined in the above mentioned program will be visible in validations onscreen tab 'Exits'- configure your validation with 'User exit' as option WBS description doesnt appear completely in hierarchical Question : In the hierarchical reports in PS de WBS description is not showed completely. Doyou know a way to make this appear completely? Answer:-

We are on 4.6B and this is what you can do. :1) Execute report2) Expand your results, if necessary3) Click on any WBS line description4) Follow the menu path Settings/Characteristic display5) Choose lead column6) Move object short description to the value set side of the panel7) Move object long description to the lead column side of the panel Save (if you have authorization). Note you can use this procedure for any other object that may show up on the report display. I.e. navigation characteristics change the objects displayed. Anyway to put checks before setting to TECO? Question: Can anyone Pl let me know about the followings: Is there any way to put checks (in the form of tick mark etc.) before setting the system status to "TECO"- e.g. some documents are received or not etc.

Answer : You can set the system status to Technically completed TECO which can be later onwithdrawn. The necessary changes are reflected in the system status on saving the Network With the setup of user statusses (tr. OIBS), you have the ability to disable the 'TECO' as long as acertain user status 'e.g. waiting for documents' is active Links to documents stored on the Web Question : Is there a way to create a document (under a project) which refers to a URL and notto a document stored on a content server? Answer : Yes you can, but you need define in DMS customizing some points.1.- Inner "Define Data Carriers" in Define data carrier type external "DMS" a record with thisinformation: TYP = IE, Description = That you want, Check ONLINE and EX, the inside this inDefine External DMS create a record with DATACAR = INTERNET, TYP = IE, Description =That you want, Check EX.2.- Inner "Define Workstation Applications" define an application for web pages without fileformat, inside this in "Define Workstation applications in network" create records for options 1,2, 3, the path of location of your navigator in your PC or you can put "%AUTO% iexplore.exe %f". Then when you create a document in the Original field you can put the URL and in theData Carrier field put the name that you define in the customizing. How to settlement auc to asset in PS? Question : The cost of project have settled to auc (investment asset), but when the project is finished, in AM or in PS i can't settle auc to asset?Pls give me some suggestion! Any idea is appreciation! Answer : You must set technically complete for your WBS & NW before settle AUC to Assets. Updating the current Order cost plan Question : We are in 46C. Starting a project, we establish an Order cost plan. We plan the amount of work (in hours) and specify the work center for each of the activities. For material

Anda mungkin juga menyukai