Schedule Ammassangeng
Schedule Ammassangeng
JUMLAH 100.00
RENCANA KEMAJUAN PEKERJAAN MINGGUAN 0.93 38.39 39.39 21.28
KUMULATIF RENCANA KEMAJUAN PEKERJAAN MINGGUAN 0 0.93 39.32 78.72 100.00
REALISASI KEMAJUAN PEKERJAAN MINGGUAN 1.13 37.24 36.51 25.12
KUMULATIF REALISASI KEMAJUAN PEKERJAAN MINGGUAN 0 1.13 38.37 74.88 100.00
DEVIASI 0 0.20 - 0.95 - 3.84 -