Anda di halaman 1dari 8

Waste Water Treatment Facility Delaram 2

Activity ID

Activity Name

Classic Schedule Layout


Original Duration Remaining
Duration

PS01 Waste Water Treatment Facility Delaram 2


PS01.1 Mi
Milestone

Schedule % Start
Complete

559

341

559

2.83% 13-Dec-10
08:00 A
0% 13-Dec-10 0...
100% 13-Dec-10 0...

A1000

Notice to Proceed

A1010

End Project

559

341

PS01.8 Wa
Waste Water Treamnt Facility

09-Aug-11 12:06

0%
2.41% 01-Jan-11 0...

Finish

Total
Float

Month

23-Jun-12
16:52
23-Jun-12 ...

-195

23-Jun-12 16:52, PS

-195

23-Jun-12 16:52, PS
Notice to Proceed

23-Jun-12 ...

-195

End Project

23-Jun-12 ...

-195

23-Jun-12 16:52, PS

559

341

12.77% 07-May-11 0... 23-Jun-12 ...

-195

23-Jun-12 16:52, PS

A1137

Security-Escort Project Personnel

180

331

100% 07-May-11 0... 14-Jun-12 ...

-185

Security-Escort Proj

A1130

Security-Escort Material

180

180

0% 19-Jul-11 08... 14-Jan-12 ...

-34

Security-Escort Material

A1135

Security-Escort Machinary/EQP

180

180

0% 19-Jul-11 08... 14-Jan-12 ...

A1280

Mobilization

10

10

0% 11-Aug-11 1...

21-Aug-11 ...

-183

A1290

Demobilization

PS01.8.7 G
General

PS01.8.2 Pre-Construction
P
A1070

Submit Security Plan

A1080

Review & Approve Security Plan

A1030

Submit QC Plan

A1040

Review & Approve QC Plan

A1050

-34

0% 19-Jun-12 1...

23-Jun-12 ...

-195

241

22

0% 01-Jan-11 0...

11-Aug-11 ...

-183

Security-Escort Machina
Mobilization
Demobilization
11-Aug-11 16:52, PS01.8.2 P

100% 01-Jan-11 0...

08-Jan-11 ...

Submit Security Plan

14

100% 05-Jan-11 0...

18-Jan-11 ...

Review & Approve Security Plan

100% 09-Mar-11 0...

16-Mar-11 ...

14

100% 02-Apr-11 0...

15-Apr-11 ...

Submit Safety Plan

0% 20-Jul-11 16... 28-Jul-11 ...

-183

Submit Safety Plan

A1090

Submit Mobilization Plan

0% 20-Jul-11 16... 28-Jul-11 ...

-183

Submit Mobilization Plan

A1120

Submit Area Use Plan

0% 20-Jul-11 16... 28-Jul-11 ...

-183

Submit Area Use Plan

A1025

Pre-CON Meeting

0% 28-Jul-11 16... 29-Jul-11 ...

-170

Pre-CON Meeting

A1060

Review & Approve Safety Plan

14

14

0% 28-Jul-11 16... 11-Aug-11 ...

-183

Review & Approve Safety Pla

A1100

Review/Approve MobilizationPlan

14

14

0% 28-Jul-11 16... 11-Aug-11 ...

-183

Review/Approve Mobilization

A1270

Review/Approve Area Use Plan

14

14

0% 28-Jul-11 16... 11-Aug-11 ...

-183

Review/Approve Area Use Pl

446

227

30.1% 08-May-11 0... 04-Apr-12 ...

-175
-183

PS01.8.3 D
Design

Submit QC Plan
Review & Approve QC Plan

04-Apr-12 16:52, PS0

A1140

Site Survey/Geotechnical

20

100% 08-May-11 0... 26-Aug-11 ...

A1150

Submit 35% Design

18

100% 02-Jun-11 0...

19-Jun-11 ...

Submit 35% Design

A1160

Review 35% Design

14

100% 20-Jun-11 0...

01-Jul-11 ...

Review 35% Design

A1170

Approve 35% Design

100% 02-Jul-11 08... 02-Jul-11 ...

A1180

Submit 65% Design

12

12

0% 26-Aug-11 1...

07-Sep-11 ...

-183

Submit 65% Design

A1210

Submit 90% Design

12

12

0% 07-Sep-11 1...

19-Sep-11 ...

-183

Submit 90% Design

A1190

Review 65% Design

14

14

0% 07-Sep-11 1...

21-Sep-11 ...

-159

Review 65% Design

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Summary

Page 1 of 8

Site Survey/Geotechnical

Approve 35% Design

TASK filter: All Activities

Primavera Systems, Inc

Waste Water Treatment Facility Delaram 2


Activity ID

Activity Name

Classic Schedule Layout


Original Duration Remaining
Duration

09-Aug-11 12:06
Schedule % Start
Complete

Finish

Total
Float

Month

A1240

Submit 100% Design

12

12

0% 19-Sep-11 1...

01-Oct-11 ...

-183

A1220

Review 90% Design

14

14

0% 19-Sep-11 1...

03-Oct-11 ...

-174

Review 90% Design

A1200

Approve 65% Design

0% 21-Sep-11 1...

22-Sep-11 ...

-159

Approve 65% Design

A1250

Review 100% Design

14

14

0% 01-Oct-11 1...

15-Oct-11 ...

-183

Review 100% Design

A1230

Approve 90% Design

0% 03-Oct-11 1...

04-Oct-11 ...

-174

Approve 90% Design

A1260

Approve 100% Design

0% 15-Oct-11 1...

16-Oct-11 ...

-183

Approve 100% Design

A2570

Submit As-Built Drawing

0% 27-Mar-12 1...

04-Apr-12 ...

-175

277

91

0% 02-Jul-11 08... 15-Jan-12 ...

-176

15-Jan-12 16:52, PS01.8

78

78

0% 16-Oct-11 1...

02-Jan-12 ...

-181

02-Jan-12 16:52, PS01.8

PS01.8.4 Procurement
P
PS01.8.4.1 Electrical

Submit 100% Design

Submit As-Built Drawi

A1300

Submit ELEC MAT Product Data

0% 16-Oct-11 1...

22-Oct-11 ...

-181

Submit ELEC MAT Produc

A1310

Approve ELEC MAT Product Data

14

14

0% 22-Oct-11 1...

05-Nov-11 ...

-181

Approve ELEC MAT Produ

A1320

Procure ELEC Material

20

20

0% 05-Nov-11 1... 25-Nov-11 ...

-181

Procure ELEC Material

A1330

Ship ELEC Material

20

20

0% 25-Nov-11 1... 15-Dec-11 ...

-181

Ship ELEC Material

A2650

Deliver ELEC Material at Site

18

18

0% 15-Dec-11 1...

02-Jan-12 ...

-181

Deliver ELEC Material at

71

71

0% 16-Oct-11 1...

26-Dec-11 ...

-183

26-Dec-11 16:52, PS01.8

PS01.8.4.2 Mechanical
A1340

Submit MECH MAT Product Data

0% 16-Oct-11 1...

22-Oct-11 ...

-183

Submit MECH MAT Produc

A1350

Approve MECH MAT Product Data

14

14

0% 22-Oct-11 1...

05-Nov-11 ...

-183

Approve MECH MAT Prod

A1360

Procure MECH Material

14

14

0% 05-Nov-11 1... 19-Nov-11 ...

-183

Procure MECH Material

A1370

Ship MECH Material

20

20

0% 19-Nov-11 1... 09-Dec-11 ...

-183

Ship MECH Material

A1550

Deliver MECH Material at Site

PS01.8.4.3 Civil

17

17

0% 09-Dec-11 1...

26-Dec-11 ...

-183

Deliver MECH Material a

240

54

0% 02-Jul-11 08... 09-Dec-11 ...

-166

09-Dec-11 16:52, PS01.8

A1380

Submit Civil MAT Product Data

100% 02-Jul-11 08... 07-Jul-11 ...

A1390

Approve Civil MAT Product Data

14

100% 08-Jul-11 08... 11-Jul-11 ...

A1400

Procure Civil Material

20

20

0% 16-Oct-11 1...

05-Nov-11 ...

-166

Procure Civil Material

A1410

Ship Civil Material

20

20

0% 05-Nov-11 1... 25-Nov-11 ...

-166

Ship Civil Material

A2670

Deliver Civil Material at Site

14

14

0% 25-Nov-11 1... 09-Dec-11 ...

-166

Deliver Civil Material at S

91

91

0% 16-Oct-11 1...

15-Jan-12 ...

-176

0% 16-Oct-11 1...

20-Oct-11 ...

-176

Submit WWTP Product Da

0% 20-Oct-11 1...

PS01.8.4.4 WWTP

Submit Civil MAT Product Data


Approve Civil MAT Product Da

15-Jan-12 16:52, PS01.8

A1420

Submit WWTP Product Data

A1430

Approve WWTP Product Data

14

14

03-Nov-11 ...

-176

Approve WWTP Product D

A1440

Purchase order WWT Plant

0% 03-Nov-11 1... 05-Nov-11 ...

-176

Purchase order WWT Plan

A1450

Fabricate WWT Plant at Site

45

45

0% 05-Nov-11 1... 20-Dec-11 ...

-176

Fabricate WWT Plant at S

A2690

Ship WWT Plant

12

12

0% 20-Dec-11 1...

-176

Ship WWT Plant

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Summary

Page 2 of 8

01-Jan-12 ...

TASK filter: All Activities

Primavera Systems, Inc

Waste Water Treatment Facility Delaram 2


Activity ID

Activity Name
A2700

Classic Schedule Layout


Original Duration Remaining
Duration

Deliver WWT Plant at Site

09-Aug-11 12:06
Schedule % Start
Complete

Finish

Total
Float

Month

14

14

0% 01-Jan-12 1...

15-Jan-12 ...

-176

PS01.8.5 C
Construction

217

217

0% 04-Oct-11 1...

08-May-12...

-201

08-May-12 16:52, PS

PS01.8.5.1 Facilities

122

122

0% 17-Dec-11 0...

17-Apr-12 ...

-179

17-Apr-12 08:52, PS0

54

54

0% 17-Dec-11 0...

20-Feb-12 ...

-141

0% 17-Dec-11 0...

18-Dec-11 ...

-141

Layout for Office BLDG

PS01.8.5.1.1 Office/Analyzer Building


PS01.8
A146 Layout for Office BLDG
A147 Excavation - Office BLDG

Deliver WWT Plant at Si

20-Feb-12 08:52, PS01

0% 18-Dec-11 0...

21-Dec-11 ...

-141

Excavation - Office BLDG

A148 Construct FDN - Office BLDG

10

10

0% 21-Dec-11 0...

02-Jan-12 ...

-141

Construct FDN - Office B

A149 Instal Container (CONEX)

10

10

0% 02-Jan-12 0...

14-Jan-12 ...

-141

Instal Container (CONEX

A150 Insulate Walls

0% 14-Jan-12 0...

17-Jan-12 ...

-141

Insulate Walls

A151 Heating & Colling

0% 17-Jan-12 0...

26-Jan-12 ...

-141

Heating & Colling

A152 Plumbing Works

0% 17-Jan-12 0...

26-Jan-12 ...

-141

Plumbing Works

A153 Install Sink & Floor Drain

0% 26-Jan-12 0...

30-Jan-12 ...

-141

Install Sink & Floor Drain

A154 Install Work Table

0% 30-Jan-12 0...

01-Feb-12 ...

-141

Install Work Table

A156 Install Wooden Desk

0% 30-Jan-12 0...

01-Feb-12 ...

-141

Install Wooden Desk

A157 Install Drawer MET filing CAB

0% 30-Jan-12 0...

01-Feb-12 ...

-141

Install Drawer MET filing

10

10

0% 01-Feb-12 0...

13-Feb-12 ...

-141

EXT & INT Finishing

0% 13-Feb-12 0...

20-Feb-12 ...

-141

Punchlist/Inspect -Offic

57

57

0% 20-Feb-12 0...

17-Apr-12 ...

-179

17-Apr-12 08:52, PS0

0% 20-Feb-12 0...

21-Feb-12 ...

-141

Layout for Storage Roo

A158 EXT & INT Finishing


A159 Punchlist/Inspect -Office BLDG
PS01.8.5.1.2 Storage Building
PS01.8
A160 Layout for Storage Room
A161 Excavation for Storage Room

0% 21-Feb-12 0...

25-Feb-12 ...

-141

Excavation for Storage

A162 Construct FDN-Storage Room

10

10

0% 25-Feb-12 0...

13-Mar-12 ...

-115

Construct FDN-Storag

A163 Install Conex - Storage Room

10

10

0% 13-Mar-12 0...

26-Mar-12 ...

-145

Install Conex - Storage

A165 Install MET Shelving Units

0% 26-Mar-12 0...

29-Mar-12 ...

-145

Install MET Shelving U

A164 Install LTG for Storage Room

0% 26-Mar-12 0...

31-Mar-12 ...

-145

Install LTG for Storage

A167 INT Finishing - Storage

10

10

0% 29-Mar-12 0...

10-Apr-12 ...

-143

INT Finishing - Storag

A166 EXT Finishing - Storage

0% 29-Mar-12 0...

12-Apr-12 ...

-114

EXT Finishing - Storag

A168 Punchlist/Inspect-Storage BLDG

0% 12-Apr-12 0...

17-Apr-12 ...

-145

Punchlist/Inspect-Stor

56

56

0% 20-Feb-12 0...

16-Apr-12 ...

-178

16-Apr-12 08:52, PS0

A169 Layout for Chemical Feed

0% 20-Feb-12 0...

21-Feb-12 ...

-135

Layout for Chemical Fe

A170 Excavation - Chemical Feed

0% 21-Feb-12 0...

25-Feb-12 ...

-135

Excavation - Chemical

A171 Construct FDN -Checmical Feed

10

10

0% 25-Feb-12 0...

13-Mar-12 ...

-110

Construct FDN -Checm

A172 CMU Walls - Chemical Feed

10

10

0% 13-Mar-12 0...

26-Mar-12 ...

-140

CMU Walls - Chemica

PS01.8.5.1.3 Chemical Feed/Storage Building


PS01.8

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Summary

Page 3 of 8

TASK filter: All Activities

Primavera Systems, Inc

Waste Water Treatment Facility Delaram 2


Activity ID

Activity Name

Classic Schedule Layout


Original Duration Remaining
Duration

09-Aug-11 12:06
Schedule % Start
Complete

Finish

Total
Float

Month

A173 Install Doors - Chemical Feed

0% 26-Mar-12 0...

31-Mar-12 ...

-140

Install Doors - Chemic

A176 Metal Roofing - Chemical Feed

0% 31-Mar-12 0...

05-Apr-12 ...

-139

Metal Roofing - Chem

A175 INT Plaster - Chemical Feed

0% 31-Mar-12 0...

07-Apr-12 ...

-140

INT Plaster - Chemica

A174 EXT Stucco - Chemical Feed

0% 31-Mar-12 0...

11-Apr-12 ...

-113

EXT Stucco - Chemic

A177 Punchlist/Inspection

0% 11-Apr-12 0...

16-Apr-12 ...

-144

Punchlist/Inspection

55

55

0% 20-Feb-12 0...

15-Apr-12 ...

-177

0% 20-Feb-12 0...

25-Feb-12 ...

-134

Layout & Excavation

A179 Construct FDN - ELEC BLDG

10

10

0% 25-Feb-12 0...

13-Mar-12 ...

-109

Construct FDN - ELEC

A180 Construct CMU - ELEC BLDG

10

10

0% 13-Mar-12 0...

26-Mar-12 ...

-139

Construct CMU - ELEC

A181 Install Doors - ELEC BLDG

0% 26-Mar-12 0...

29-Mar-12 ...

-139

Install Doors - ELEC B

A182 Metal Roofing - ELEC BLDG

0% 29-Mar-12 0...

04-Apr-12 ...

-139

Metal Roofing - ELEC

A184 INT Finishing - ELEC BLDG

0% 29-Mar-12 0...

05-Apr-12 ...

-139

INT Finishing - ELEC

A183 EXT Finishing - ELEC BLDG

0% 29-Mar-12 0...

10-Apr-12 ...

-112

EXT Finishing - ELEC

A185 Punchlist/Inspect - ELEC BLDG

0% 10-Apr-12 0...

15-Apr-12 ...

-143

Punchlist/Inspect - EL

217

217

0% 04-Oct-11 1...

08-May-12...

-201

08-May-12 16:52, PS

30

30

0% 26-Dec-11 1...

30-Jan-12 ...

-120

30-Jan-12 16:52, PS01.

0% 26-Dec-11 1...

27-Dec-11 ...

-148

Layout - W Distribution S

PS01.8.5.1.4 Process & Electrical Panel Building


PS01.8
A178 Layout & Excavation

PS01.8.5.2 Site Development/Improvement


PS01.8.5.2.1 Water Distribution System
PS01.8
A186 Layout - W Distribution SYS
A187 Excavation - W Distribution SYS

15-Apr-12 08:52, PS0

0% 27-Dec-11 1...

31-Dec-11 ...

-120

Excavation - W Distributi

10

10

0% 31-Dec-11 1...

11-Jan-12 ...

-120

Lay Water Pipes

A189 Backfill Water Pipes

0% 11-Jan-12 1...

14-Jan-12 ...

-120

Backfill Water Pipes

A190 Install Water Tank

0% 14-Jan-12 1...

17-Jan-12 ...

-120

Install Water Tank

A191 Booster Pump Station

0% 14-Jan-12 1...

19-Jan-12 ...

-120

Booster Pump Station

A192 Construct Metal Canopy

0% 19-Jan-12 1...

24-Jan-12 ...

-120

Construct Metal Canopy

A193 Inspection - W Distribution SYS

0% 24-Jan-12 1...

30-Jan-12 ...

-120

Inspection - W Distributi

PS01.8.5.2.2 Sanitary Sewer System


PS01.8

43

43

0% 30-Jan-12 1...

13-Mar-12 ...

-145

13-Mar-12 16:52, PS0

A194 Layout - SAN Sewer SYS

0% 30-Jan-12 1...

31-Jan-12 ...

-120

Layout - SAN Sewer SY

A195 Excavation - SAN Sewer SYS

0% 31-Jan-12 1...

04-Feb-12 ...

-120

Excavation - SAN Sewe

A196 Lay Sewer Pipes

0% 04-Feb-12 1...

13-Feb-12 ...

-120

Lay Sewer Pipes

A188 Lay Water Pipes

A197 CONS Sewer Manholes

10

10

0% 13-Feb-12 1...

26-Feb-12 ...

-94

CONS Sewer Manhole

A198 Connect SAN SewerSYS with WWTP

0% 26-Feb-12 1...

06-Mar-12 ...

-117

Connect SAN SewerSY

A199 Punchlist/Inspect - SAN SYS

0% 06-Mar-12 1...

13-Mar-12 ...

-117

48

48

0% 27-Dec-11 1...

13-Feb-12 ...

-194

PS01.8.5.2.3 Lift Station


PS01.8
Actual Work

Critical Remaining Work

Remaining Work

Milestone

Summary

Page 4 of 8

Punchlist/Inspect - SAN
13-Feb-12 16:52, PS01

TASK filter: All Activities

Primavera Systems, Inc

Waste Water Treatment Facility Delaram 2


Activity ID

Activity Name

Classic Schedule Layout


Original Duration Remaining
Duration

09-Aug-11 12:06
Schedule % Start
Complete

Finish

Total
Float

Month

A200 Layout for Lift Station

0% 27-Dec-11 1...

28-Dec-11 ...

-148

Layout for Lift Station

A201 Excavation for Lift Station

0% 28-Dec-11 1...

01-Jan-12 ...

-148

Excavation for Lift Station

20

20

0% 01-Jan-12 1...

05-Feb-12 ...

-135

Construct Lift Station

A203 Install Submersible Pump No. 1

0% 05-Feb-12 1...

07-Feb-12 ...

-158

Install Submersible Pum

A204 Install Submersible Pump No. 2

0% 05-Feb-12 1...

07-Feb-12 ...

-158

Install Submersible Pum

A205 Punchlist/Inspet - Lift STA

0% 07-Feb-12 1...

13-Feb-12 ...

-158

Punchlist/Inspet - Lift ST

PS01.8.5.2.4 Sewage Off Loading System


PS01.8

43

43

0% 13-Feb-12 1...

27-Mar-12 ...

-198

27-Mar-12 16:52, PS0

A206 Formwork for Sewage Off SYS

0% 13-Feb-12 1...

22-Feb-12 ...

-158

Formwork for Sewage O

A207 Rebar for Sewage Off SYS

0% 22-Feb-12 1...

03-Mar-12 ...

-158

Rebar for Sewage Off S

A208 Pour Concrete for Sewage Off

0% 03-Mar-12 1...

12-Mar-12 ...

-131

Pour Concrete for Sew

A209 Curing -Sewage Off Loading SYS

0% 12-Mar-12 1...

20-Mar-12 ...

-162

Curing -Sewage Off Lo


Punchlist/Inspect - Sew

A202 Construct Lift Station

A210 Punchlist/Inspect - Sewage Off

0% 20-Mar-12 1...

27-Mar-12 ...

-162

59

59

0% 15-Jan-12 1...

27-Mar-12 ...

-142

W10 Layout for WWT Plant

0% 15-Jan-12 1...

16-Jan-12 ...

-142

Layout for WWT Plant

W10 Excavation for WWTP

0% 16-Jan-12 1...

18-Jan-12 ...

-142

Excavation for WWTP

W10 Form Work for FND - WWTP

0% 18-Jan-12 1...

21-Jan-12 ...

-142

Form Work for FND - W

W10 Rebar for Foundation - WWTP

0% 21-Jan-12 1...

25-Jan-12 ...

-142

Rebar for Foundation - W

W10 Pour Concrete for FND - WWTP

0% 25-Jan-12 1...

29-Jan-12 ...

-142

Pour Concrete for FND -

W10 Curing for FND - WWTP

0% 29-Jan-12 1...

01-Feb-12 ...

-142

Curing for FND - WWTP

W10 Graveling & Compaction -WWTP

0% 01-Feb-12 1...

04-Feb-12 ...

-142

Graveling & Compaction

W10 Underground Piping - WWTP

0% 04-Feb-12 1...

07-Feb-12 ...

-142

Underground Piping - W

W10 Backfil Pipes - WWTP

0% 07-Feb-12 1...

11-Feb-12 ...

-142

Backfil Pipes - WWTP

W10 Install Inlet Bar Screen

0% 11-Feb-12 1...

13-Feb-12 ...

-142

Install Inlet Bar Screen

W11 Construct Primary Settling Zone

0% 13-Feb-12 1...

18-Feb-12 ...

-142

Construct Primary Settl

W11 Install Aerated Equalization Tank

0% 18-Feb-12 1...

20-Feb-12 ...

-142

Install Aerated Equaliza

W11 Install Equalized Sewage Pumps

0% 20-Feb-12 1...

23-Feb-12 ...

-142

Install Equalized Sewag

W11 Install Aeration SYS for Aeration tank

0% 23-Feb-12 1...

28-Feb-12 ...

-142

Install Aeration SYS for

W11 Construct Clarifier Zone

0% 28-Feb-12 1...

01-Mar-12 ...

-142

Construct Clarifier Zone

W11 Install Chlorine Contact Tank

0% 01-Mar-12 1...

04-Mar-12 ...

-142

Install Chlorine Contac

W11 Install Sludge holding tank

0% 04-Mar-12 1...

07-Mar-12 ...

-142

Install Sludge holding t

W11 Install Air blower

0% 07-Mar-12 1...

12-Mar-12 ...

-142

Install Air blower

W11 Install Post Chlorination Dosing Unit

0% 12-Mar-12 1...

15-Mar-12 ...

-142

Install Post Chlorinatio

PS01.8.5.2.5 Waste Water Treatment Plant


PS01.8

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Summary

Page 5 of 8

27-Mar-12 16:52, PS0

TASK filter: All Activities

Primavera Systems, Inc

Waste Water Treatment Facility Delaram 2


Activity ID

Activity Name

Classic Schedule Layout


Original Duration Remaining
Duration

09-Aug-11 12:06
Schedule % Start
Complete

Finish

Total
Float

Month

W11 Motor Control Center

0% 15-Mar-12 1...

18-Mar-12 ...

-142

Motor Control Center

W12 Test and Commissioning

0% 18-Mar-12 1...

22-Mar-12 ...

-142

Test and Commissioni

W12 Punchlist & Inspect WWTP

0% 22-Mar-12 1...

27-Mar-12 ...

-142

Punchlist & Inspect W

34

34

0% 27-Mar-12 1...

08-May-12...

-162

08-May-12 16:52, PS

0% 27-Mar-12 1...

28-Mar-12 ...

-162

Layout for Outfall Pipe

PS01.8.5.2.6 WWTP Outfall


PS01.8
A215 Layout for Outfall Pipes
A216 Excavation for Outfall Pipes

0% 28-Mar-12 1...

31-Mar-12 ...

-162

Excavation for Outfall

20

20

0% 31-Mar-12 1...

23-Apr-12 ...

-162

Construct & Lay Outfa

A218 Backfill Outfall Pipes

0% 23-Apr-12 1...

29-Apr-12 ...

-162

Backfill Outfall Pipes

A219 Install Iron Grating

0% 29-Apr-12 1...

02-May-12...

-162

Install Iron Grating

A220 Punchlist/Inspect Outfall Pipe

0% 02-May-12 1... 08-May-12...

-162

Punchlist/Inspect Out

31

31

0% 04-Oct-11 1...

15-Nov-11 ...

-144

15-Nov-11 08:52, PS01.8.

A217 Construct & Lay Outfall Pipes

PS01.8.5.2.7 Grading & Storm Water Management


PS01.8
A221 Demolition & Site Grading

0% 04-Oct-11 1...

12-Oct-11 ...

-144

Demolition & Site Grading

A222 Construct Storm Drainages

18

18

0% 12-Oct-11 1...

02-Nov-11 ...

-144

Construct Storm Drainages

0% 02-Nov-11 1... 15-Nov-11 ...

-144

Punchlist/Inspect Grading/

31

31

0% 15-Nov-11 0... 22-Dec-11 ...

-144

22-Dec-11 08:52, PS01.8

A223 Punchlist/Inspect Grading/Storm


PS01.8.5.2.8 Facility Fencing & Gates
PS01.8
A224 Layout for Fencing & Gates

0% 15-Nov-11 0... 17-Nov-11 ...

-144

Layout for Fencing & Gate

16

16

0% 17-Nov-11 0... 07-Dec-11 ...

-144

Construct Fencing

A226 Construct & Install Gates

0% 07-Dec-11 0...

17-Dec-11 ...

-144

Construct & Install Gates

A227 Punchlist/Inspect Fencing/Gate

0% 17-Dec-11 0...

22-Dec-11 ...

-144

Punchlist/Inspect Fencing

A225 Construct Fencing

48

48

0% 06-Mar-12 1...

23-Apr-12 ...

-186

23-Apr-12 16:52, PS0

A228 Layout for Road Network

0% 06-Mar-12 1...

11-Mar-12 ...

-151

Layout for Road Netwo

A232 Layout for Walkways

0% 11-Mar-12 1...

13-Mar-12 ...

-151

Layout for Walkways

A229 Construct Sub-Grade

0% 11-Mar-12 1...

18-Mar-12 ...

-143

Construct Sub-Grade

A237 Layout for Parking Area

0% 13-Mar-12 1...

15-Mar-12 ...

-146

Layout for Parking Are

A233 Sub-Grade - Walkways

0% 13-Mar-12 1...

20-Mar-12 ...

-151

Sub-Grade - Walkway

A238 Sub-Grade for Parking Area

0% 15-Mar-12 1...

24-Mar-12 ...

-146

Sub-Grade for Parking

A230 Construct Sub-Base

0% 18-Mar-12 1...

29-Mar-12 ...

-113

Construct Sub-Base

A234 Sub-Base - Walkways

0% 20-Mar-12 1...

31-Mar-12 ...

-151

Sub-Base - Walkways

A239 Base Course for Parking

0% 24-Mar-12 1...

31-Mar-12 ...

-116

Base Course for Parki

A231 Construct Base-Course

0% 29-Mar-12 1...

10-Apr-12 ...

-113

Construct Base-Cours

A240 Graveling for Parking Area

0% 31-Mar-12 1...

08-Apr-12 ...

-144

Graveling for Parking

A235 Concreting for Walkways

0% 31-Mar-12 1...

10-Apr-12 ...

-120

Concreting for Walkw

PS01.8.5.2.9 Road Network, Walkways, Parking


PS01.8

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Summary

Page 6 of 8

TASK filter: All Activities

Primavera Systems, Inc

Waste Water Treatment Facility Delaram 2


Activity ID

Activity Name

Classic Schedule Layout


Original Duration Remaining
Duration

09-Aug-11 12:06
Schedule % Start
Complete

Finish

Total
Float

Month

A241 Compact Parking Area

0% 08-Apr-12 1...

11-Apr-12 ...

-144

Compact Parking Area

A242 Punchlist/Inspect Road

0% 10-Apr-12 1...

15-Apr-12 ...

-144

Punchlist/Inspect Roa

A236 Curing for Walkways

0% 10-Apr-12 1...

18-Apr-12 ...

-151

Curing for Walkways

A244 Punchlist/Inspect Parking

0% 11-Apr-12 1...

15-Apr-12 ...

-144

Punchlist/Inspect Park

A243 Punchlist/Inspect Walkways

0% 18-Apr-12 1...

23-Apr-12 ...

-151

Punchlist/Inspect Wal

72

72

0% 02-Jan-12 1...

14-Mar-12 ...

-162

14-Mar-12 16:52, PS0

A245 Excavation for ELEC SYS

0% 02-Jan-12 1...

04-Jan-12 ...

-146

Excavation for ELEC SY

A246 Backfilling and Compaction

0% 04-Jan-12 1...

07-Jan-12 ...

-146

Backfilling and Compacti

A247 Lay Electrical Conduits

0% 07-Jan-12 1...

16-Jan-12 ...

-146

Lay Electrical Conduits

A248 ELEC Cabling Inside Conduits

0% 16-Jan-12 1...

24-Jan-12 ...

-146

ELEC Cabling Inside Co

A249 Construct Manholes/Handholes

14

14

0% 24-Jan-12 1...

18-Feb-12 ...

-125

Construct Manholes/Ha

PS01.8.5.2.10 Site Electrical Distribution System


PS01.8

A250 Install Manhole/Handhole Cover

0% 18-Feb-12 1...

23-Feb-12 ...

-151

Install Manhole/Handho

A251 Construct CONC Pad-Fuel Tanks

10

10

0% 18-Feb-12 1...

29-Feb-12 ...

-125

Construct CONC Pad-F

A252 Install Set of Generators

12

12

0% 18-Feb-12 1...

03-Mar-12 ...

-122

Install Set of Generator

0% 29-Feb-12 1...

06-Mar-12 ...

-151

Punchlist/Inspect ELEC

12

12

0% 29-Feb-12 1...

14-Mar-12 ...

-132

Install Fuel Storage Ta

36

36

0% 10-Mar-12 0...

14-Apr-12 ...

-177

14-Apr-12 17:00, PS0

20

20

0% 10-Mar-12 0...

08-Apr-12 ...

-112

Exterior Lighting

0% 09-Apr-12 0...

14-Apr-12 ...

-143

Punchlist/Inspect-EXT

100% 19-Dec-10 0...

20-Jul-11 ...

-183

20-Jul-11 16:41, PS01.2 DBA

100% 19-Dec-10 0...

20-Jul-11 ...

-183

Submit DBA Insurance

102

102

0% 28-Dec-11 1...

08-Apr-12 ...

-171

102

102

0% 28-Dec-11 1...

08-Apr-12 ...

-171

0% 28-Dec-11 1...

02-Jan-12 ...

-120

A254 Punchlist/Inspect ELEC SYS


A253 Install Fuel Storage Tanks
PS01.8.5.2.11 Exterior Lighting
PS01.8
A255 Exterior Lighting
A256 Punchlist/Inspect-EXT Lighting

PS01.2 DB
DBA INSURANCE
A1020

Submit DBA Insurance

PS01.12 Optional
O
Items
PS01.12.1 A
Additional Lift Stations

08-Apr-12 16:52, PS0


08-Apr-12 16:52, PS0

A2710

Layout for Lift Stations

A2720

Excavation for Lift Stations

18

18

0% 02-Jan-12 1...

23-Jan-12 ...

-120

Excavation for Lift Statio

A2730

Construct Lift Stations

20

20

0% 05-Feb-12 1...

11-Mar-12 ...

-108

Construct Lift Stations

A2740

Install Submersible Pump No. 1 & 2

0% 11-Mar-12 1...

20-Mar-12 ...

-138

Install Submersible Pu

A2750

Install Submersible Pump No. 3 & 4

0% 20-Mar-12 1...

31-Mar-12 ...

-138

Install Submersible Pu

A2760

Punchlist/Inspet - Lift STA

0% 31-Mar-12 1...

08-Apr-12 ...

-138

Punchlist/Inspet - Lift

80

80

0% 04-Apr-12 1...

23-Jun-12 ...

-195

0% 04-Apr-12 1...

12-Apr-12 ...

-175

Submit O&M Manual

0% 08-May-12 1... 10-May-12...

-162

Pre-Final Inspection

PS01.6 Clo
Close-out
A2580

Submit O&M Manual

A2590

Pre-Final Inspection

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Summary

Page 7 of 8

Layout for Lift Stations

23-Jun-12 16:52, PS

TASK filter: All Activities

Primavera Systems, Inc

Waste Water Treatment Facility Delaram 2


Activity ID

Activity Name

Classic Schedule Layout


Original Duration Remaining
Duration

A2600

Correction from Pre-Final

A2610

Final Inspection

A2620

Correction from Final Inspection

A2630

Final Hand-Over

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Summary

09-Aug-11 12:06
Schedule % Start
Complete

Finish

Total
Float

Month

15

15

0% 10-May-12 1... 28-May-12...

-162

Correction from Pre-

0% 28-May-12 1... 02-Jun-12 ...

-162

Final Inspection

15

15

0% 02-Jun-12 1...

19-Jun-12 ...

-162

Correction from Fin

0% 19-Jun-12 1...

23-Jun-12 ...

-195

Final Hand-Over

Page 8 of 8

TASK filter: All Activities

Primavera Systems, Inc

Anda mungkin juga menyukai