Anda di halaman 1dari 64

LAPORAN PERENCANAAN DAN PENGENDALIAN PROYEK

RENCANA ANGGARAN BIAYA (RAB)


RUMAH PRIBADI DUA LANTAI

Di Susun Oleh :

KELOMPOK 2
YUDA ADHA (170501022)
MUHAMMAD VIQRI ANANDA (180501108)
MUHAMMAD AKBAR (170501052)

PRODI TEKNIK SIPIL


FAKULTAS TEKNIK
UNIVERSITAS SAMUDRA
TAHUN AKADEMIK 2020

1
DAFTAR ISI

LEMBAR JUDUL....................................................................................................... 1
DAFTAR ISI .............................................................................................................. 2

BAB I SITUASI PROYEK .......................................................................................... 3


1.1. Luas Bangunan .............................................................................................. 3
1.2. Bentuk/Tipe Bangunan ................................................................................... 3
1.3. Bahan Yang Terpakai ..................................................................................... 3
1.4. Uraian Pekerjaan............................................................................................ 6

BAB II PERHITUNGAN VOLUME ............................................................................ 10

BAB III DAFTAR ANALISA HARGA ......................................................................... 13

BAB IV HARGA BAHAN ........................................................................................... 43

BAB V RENCANA ANGGARAN BIAYA ................................................................... 47

BAB VI REKAPITIULASI .......................................................................................... 52

BAB VII KESIMPULAN ............................................................................................. 53

LAMPIRAN

2
BAB I
SITUASI PROYEK

Bangunan yang akan didirikan merupakan rumah tinggal berlantai dua. Sebelum mendirikan sebuah
bangunan terlebih dahulu dihitung estimasi biaya pembangunannya. Hal tersebut dilakukan dengan
tujuan untuk mengetahui jumlah biaya yang harus dikeluarkan untuk pelaksanaan proyek tersebut dari
tahap design engineering, pelaksanaan pembangunan hingga ketahap penyelesaian proyek tersebut.

1.1 Luas Bangunan

Luas rumah ini adalah 325.96𝑚2 dengan luas bangunan lantai satu 170.80 𝑚2 dan luas bangunan
lantai dua 155.16 𝑚2 , sedangkan luas tanahnya 265.36 𝑚2 . Dengan luas tanah yang besar rumah ini
dilengkapi dengan taman yang terletak dihalaman depan rumah.

1.2 Bentuk/Tipe Bangunan

Bangunan ini merupakan rumah untuk tempat tinggal. Rumah ini berlantai dua dengan komposisi
sebahagian bertingkat. Rumah ini dilengkapi dengan fasilitas yang lengkap dan sehat. Terdiri dari
ruang tamu, ruang keluarga, garasi, dapur, 4 kamar tidur dan 4 kama r mandi.

1.3 Bahan Yang Terpakai

Dalam pembangunan rumah ini menggunakan bahan-bahan sebagai berikut:


● Pasir pasang
Pasir yang digunakan untuk alas pondasi adalah pasir sungai yang mempunyai butiran keras dan
terlepas dari lempung, lumpur atau zat organic lainnya. Pasir untuk mortal tidak boleh mengandung
lumpur lebih dari 5% berat kering. Apabila lebih dari 1% pasir tersebut harus dicuci sebelum
digunakan.
● Pasir urug
● Pasir beton
● Kerikil
Kerikil yang dipergunakan untuk beton struktur tidak boleh mengandung lumpur lebih dari 5% dari

3
berat kering. Apabila lebih dari 1% maka harus dicuci terlebih dahulu.
● Tanah timbun
Tanah timbun berasal darigalian pondasi.
● Semen andalas
● Semen putih
● Batu koral beton
● Batu bata merah
Mutu bata yang digunakan dari jenis kelas satu menurut SNI 10 untuk standar batu bata adalah
prisma empat persegi panjang, bersudut siku-siku dan tajam, permukaannya rata dan tidak
menampakkan adanya retak-retak yang merugikan.
● Batu kali
Batu kali yang digunakan adalah jenis batu yang keras, tidak koros,berwarna kehitaman. Batu harus
bersih dari lumpur dan kotoran lainnya.
● Seng
● Batu kelas I (seumantok)
● Batu kelas II (kamper)
● Kayu bekesting kelas III
● Kayu dolken ukuran 8/15-4m
● Kayu borneo
● Kayu rangka plafon kelas II
● Papan listplank kelas II
● Papan kayu borneo
● Plywood 9mm
● Paku kayu
● Paku seng
● Besi beton polos
● Besi/plat strip
● Kawat beton
● Minyak pelumas
● Residu
● Kabel instalasi θ 2,5 mm
● Stop kontak

4
● Saklar tunggal merek braco
● Bola lampu pijar 20 watt 220 volt merek philips
● Bola lampu TL 40 watt 220 volt merek Philips
● Klosed jongkok merek KIA
● Keran air merek hamco
● Seal tape
● Water drain
● Floor drain
● Wastafel keramik
● Pipa PVC θ kualitas awet
● Cat tembok sekualitas kuda terbang,polymix,vinilex,platon
● Cat tembok dasar
● Cat kayu mengkilap
● Cat kayu dasar sekualitas kuda terbang platon atau ftalit
● Cat menie
● Plamir
● Kaca rayban sekualitas asahi mas
● Keramik 20 x 20 cm merek roman
● Keramik 30x30 cm merek roman
● Engsel pintu merek ARCH Nylon
● Engsel jendela merek ARCH Nylon
● Kunci tanam
● Espagnolet
● Pacok pintu
● Hak angin untuk jendela
● Grendel
● Septitank
● Bak control
● Peresapan

5
1.4 Uraian Pekerjaan
Sebelum menguraikan secara rinci besarnya volume atau kubikasi pekerjaan,terlebih dahulu perlu
dibuat uraian pekerjaan rumah yang akan dibangun untuk mepermudah pekerjaan.dibawah ini
diberikan tabel uraian pekerjaan

No Uraian Pekerjaan
PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan
Luas Area 10.70 m x 24.80 m = 265.36 m2
2 Pengukuran dan Pemasangan Bowplank
Luas Area 10.70 m x 19.40 m = 207.58 m2
PEKERJAAN TANAH
1 Galian Tanah Pondasi
2 Timbunan Kembali Bekas Galian
3 Timbunan Tanah Bawah Lantai
4 Urugan Pasir Tanah Pondasi
5 Urugan Pasir Bawah Lantai
PEKERJAAN BATU, PEMASANGAN DAN PLESTERAN
1 Aanstamping Batu Gunung
2 Beton Cor 1 : 2 : 3
3 Pondasi Batu Gunung
4 Pasangan Bata
a. Pasangan bata 1 : 2
b. Pasangan bata 1 : 4
5 Plesteran
a. Plesteran 1 : 2
b. Plesteran 1 : 4

6
PEKERJAAN BETON BERTULANG
1 Pondasi Tapak
2 Balok Sloof
3 Kolom
a. Kolom utama
b. Kolom Praktis
4 Balok Lantai
5 Plat Lantai
6 Top Gevel
7 Reng Balok
8 Tangga
No Uraian Pekerjaan
PEKERJAAN LANTAI DAN PELAPIS DINDING
1 Lantai Beton Cor 1 : 3 : 5
2 Lantai Tegel
3 Lantai Tangga
4 Dinding Porselen
PEKERJAAN KAYU DAN KUSEN
1 Perkayuan Rangka Atap
a. Kuda-kuda
b. Gording
c. Balok bubungan
d. Papan Reuter
e. Ikatan Angin
2 Perkayuan Kusen
a. Pintu
b. Jendela

7
PEKERJAAN ATAP/PLAFOND
1 Plafond
a. Asbes
b. Gypsum
c. Turap Porselen
2 Listplank
3 Bubungan Seng
4 Atap seng
PEKERJAAN INSTALASI LISTRIK
1 Lampu TL 20 Watt
2 Lampu Pijar 40 Watt
3 Fitting Plafond
4 Stop Kontak
5 Saklar Tunggal
PEKERJAAN PENGECATAN
1 Pengecatan Kayu
a. Kusen, pintu dan jendela
b. Listplank
2 Pengecatan Dinding
3 Pengecatan Plafond
4 Residu Rangka Atap
5 Pengecatan Atap
PEKERJAAN KUNCI DAN PENGGANTUNG
1 Kunci Tanam Pintu
2 Engsel Pintu
3 Engsel Jendela
4 Hak Angin Jendela
5 Grendel Jendela
6 Pacok Pintu
7 Espagnolet
8 Kaca tebal 3 mm

8
PEKERJAAN INSTALASI DAN SANITASI AIR
1 Pasang Kloset Jongkok
2 Pasang Keran Air
3 Pasang Floor Drain
4 Pasang Wastafel
5 Pasang Sumur
6 Pemasangan Instalasi Air Bersih
7 Pemasangan Instalasi Air Kotor
8 Pemasangan Jaringan Kotoran
9 Septitank dan Resapan
10 Bak Kontrol
PEKERJAAN PAGAR

9
BAB II
PERHITUNGAN VOLUME

NO NAMA PEKERJAAN PANJAN LEBAR TINGGI BANYA DIA VOLUME SATUA


G K N
0 1 2 3 4 5 6 7 8
1 PEKERJAAN PERSIAPAN
Pembersihan Lapangan 10.70 24.80 265.36 m2
pemasangan Bowplank 10.70 19.40 207.58 m2

2 PEKERJAAN TANAH
A PONDASI MENERUS TYPE 1
Galian Tanah Pondasi 59.6 0.6 0.95 33.97 m3
Urugan Kembali 8.49 m3
B PONDASI MENERUS TYPE 2
Galian Tanah Pondasi 31.9 0.5 0.95 15.15 m3
Urugan Kembali 3.79 m3
C PONDASI TAPAK TYPE 1
Galian Tanah Pondasi 1.20 1.20 1.45 11.00 22.97 m3
Urugan Kembali 5.74 m3
D PONDASI TAPAK TYPE 2
Galian Tanah Pondasi 0.80 0.90 1.45 10.00 10.44 m3
Urugan Kembali 2.61 m3

3 PEKERJAAN PONDASI
- Pondasi Menerus Type 1
Lantai Kerja 59.60 0.60 0.10 3.58 m3
Pas. Batu Kali 59.60 0.40 0.50 11.92 m3
- Pondasi Menerus Type 2
Lantai Kerja 31.90 0.45 0.10 1.44 m3
Pas. Batu Kali 31.90 0.35 0.50 5.58 m3
- Pondasi Tapak Type 1
Lantai Kerja 1.20 1.20 0.10 11.00 1.58 m3
Pondasi 1.00 1.00 0.30 11.00 3.3 m3
- Pondasi Tapak Type
Lantai Kerja 1.00 0.80 0.10 10.00 0.8 m3
Pondasi 0.80 0.70 0.30 10.00 1.68 m3
Kolom Pedestal 40/30 1.10 0.40 0.30 21.00 2.77 m3

4 PEMASANGAN BATA DAN


PLESTERAN
A LANTAI 1
- Pasangan Bata
Pasangan Bata 1 : 4 90.10 3.25 292.83 m2
Pasangan Bata 1 : 2 90.10 0.70 63.07 m2
- Plesteran
Plesteran 90.10 0.015 3.95 2.00 10.68 m3
B LANTAI 2
- Pasangan Bata
Pasangan Bata 1 : 4 94.00 3.65 343.10 m2
Pasangan Bata 1 : 2 94.00 0.30 28.20 m2
-

10
Plesteran 94.00 0.015 3.95 2.00 11.14 m3

5 PEKERJAAN LANTAI
A LANTAI 1
Cor Lantai 1 : 3 : 5 170.80 0.07 11.956 m3
Pasir Urug 170.80 0.05 8.54 m3
Tanah Timbun Pilihan 170.80 0.24 40.992 m3
Granit 60 X 60 cm 170.80 170.80 m2
Dinding Keramik 25 x 40 Cm 6.00 6.00
Spesi 170.80 0.03 5.124 m3
B LANTAI 2
Cor Lantai 1 : 3 : 5 155.16 0.07 10.8612 m3
Granit 60 X 60 cm 155.16 155.16 m2
Dinding Keramik 25 x 40 Cm 6.00 6.00
Spesi 155.16 0.03 4.6548 m3

6 PEKERJAAN BETON
BERTULANG
A LANTAI 1
Pondasi Tapak Type 1 1 1 0.3 11 3.3 m3
Pondasi Tapak Type 2 0.8 0.7 0.3 10 1.68 m3
Balok Sloof 25/35 146.70 0.25 0.35 12.84 m3
Kolom Utama 40/30 3.55 0.40 0.30 11.00 4.69 m3
Kolom Praktis 13/13 Type 1 3.95 0.13 0.13 4.00 0.27 m3
Kolom Praktis 13/13 Type 2 3.95 0.13 0.13 11.00 0.73 m3
Balok Lantai 25/40 137.70 0.25 0.40 13.77 m3
Balok Latai 13/13 18.7 0.13 0.13 0.32 m3
Plat Lantai 170.80 0.12 20.50 m3
Tangga 1.1 0.27 0.16 25 1.33 m3
Plat Tangga 6.07 1.10 0.20 1.33 m3
Plat Bordes 2.20 2.20 0.20 2.00 0.97 m3
B LANTAI 2
Kolom Utama 40/30 Type 1 3.65 0.40 0.30 8.00 3.50 m3
Kolom Utama 40/30 Type 2 4.25 0.40 0.30 10.00 5.10 m3
Kolom Praktis 13/13 Type 1 3.65 0.13 0.13 5.00 0.31 m3
Kolom Praktis 13/13 Type 2 4.25 0.13 0.13 10.00 0.72 m3
Plat Dak 43.4 0.5 0.1 2.17 m3
Ring Balok 13/15 94.00 0.13 0.15 1.83 m3
Balok Latai 13/13 94.00 0.13 0.13 1.59 m3

7 PEKERJAAN PEMBESIAN
A LANTAI 1
Pondasi Tapak Type 1 10 11.00 133.10 kg
Pondasi Tapak Type 2 8 10.00 96.80 kg
Kolom Pedestal 40/30 1.1 10.00 13.31 kg
Balok Sloof 25/35 146.70 10.00 1775.07 kg
Kolom Utama 40/30 3.55 10.00 42.96 kg
Kolom Praktis 13/13 Type 1 3.95 4.00 9.80 kg
Kolom Praktis 13/13 Type 2 3.95 4.00 9.80 kg
Balok Lantai 25/40 137.70 10.00 1666.17 kg
Balok Latai 13/13 18.70 4.00 46.38 kg
Plat Lantai 2381.67 2.00 5763.63 kg
Tangga 82.50 99.83 kg
Plat Tangga 82.50 99.83 kg
Plat Bordes 49.00 59.29 kg

B LANTAI 2
Kolom Utama 40/30 Type 1 3.65 8.00 35.332 kg
Kolom Utama 40/30 Type 2 4.25 10.00 51.425 kg
Kolom Praktis 13/13 Type 1 3.65 5.00 11.315 kg
Kolom Praktis 13/13 Type 2 4.25 10.00 26.35 kg
Plat Dak 49.1 30.442 kg

11
Ring Balok 13/15 47.10 4.00 116.808 kg
Balok Latai 13/13 21.4 4.00 53.072 kg

8 PEKERJAAN PEMBESIAN
BEGEL
A LANTAI 1
Kolom Pedestal 40/30 0.34 0.24 7 0.23 kg
Balok Sloof 25/35 0.19 0.29 978 21.02 kg
Kolom Utama 40/30 0.34 0.24 24 0.75 kg
Kolom Praktis 13/13 Type 1 0.07 0.07 26 0.05 kg
Kolom Praktis 13/13 Type 2 0.07 0.07 26 0.05 kg
Balok Lantai 25/40 0.19 0.34 918 23.13 kg
Balok Latai 13/13 0.07 0.07 125 0.24 kg
B LANTAI 2
Kolom Utama 40/30 Type 1 0.34 0.24 3.65 0.12 kg
Kolom Utama 40/30 Type 2 0.34 0.24 4.25 0.14 kg
Kolom Praktis 13/13 Type 1 0.07 0.07 3.65 0.01 kg
Kolom Praktis 13/13 Type 2 0.07 0.07 4.25 0.01 kg
Ring Balok 13/15 0.07 0.09 47.10 0.12 kg
Balok Latai 13/13 0.07 0.07 21.40 0.04 kg

9 PEKERJAAN KAYU DAN


KUSEN
A LANTAI 1
Pintu Type 1
Kosen Pintu 8.35 0.1 0.05 2 0.0835 m3
Daun Pintu 1.4 2.2 2 6.16 m2
Pintu Type 2
Kosen Pintu 6.3 0.1 0.05 3 0.0945 m3
Daun Pintu 0.8 2.2 3 5.28 m2
- Pintu Type 3
Kosen Pintu 5.2 0.1 0.05 3 0.078 m3
Daun Pintu 0.7 2.2 3 4.62 m2
- Jendela Type !
Kosen Jendela 14.8 0.1 0.05 2 0.148 m3
Daun Jendela 4.1 2 8.2 m2
B LANTAI 2
1 Kosen Pintu Dan Jendela
- Pintu Type 1
Kosen Pintu 8.35 0.1 0.05 2 0.0835 m3
Daun Pintu 1.4 2.2 2 6.16 m2
- Pintu Type 2
Kosen Pintu 6.3 0.1 0.05 2 0.063 m3
Daun Pintu 0.8 2.2 2 3.52 m2
- Pintu Type 3
Kosen Pintu 5.2 0.1 0.05 2 0.052 m3
Daun Pintu 0.7 2.2 2 3.08 m2
- Jendela Type !
Kosen Jendela 14.8 0.1 0.05 4 0.296 m3
Daun Jendela 4.1 4 16.4 m2
2 Kayu Kuda –Kuda
Kuda - Kuda 2/4" 39.3 0.1 0.05 0.1965 m3
Gording 2/2" 258.4 0.05 0.05 0.646 m3
Balok Gantung 2/4" 3.12 0.1 0.05 0.0156 m3
Balok Angin 2/4" 9 0.1 0.05 0.045 m3
Balok Gapit 2/4" 36.2 0.1 0.05 0.181 m3
Balok Tarik 2/4" 9.6 0.1 0.05 0.048 m3
Balok Bubungan 2/3" 2.8 0.075 0.05 0.0105 m3
Balok Sokong 2/4" 54 0.1 0.05 0.27 m3

12
BAB III
DAFTAR ANALISA HARGA

A.2.2.1.1 HARGA SATUAN PEKERJAAN PERSIAPAN


Jenis Pekerjaan : Pengukuran Dan Pemasangan 1 m' Bowplank Satuan /
Unit : M'
Analisa : A. 2.2.1.4a

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.100 84,150.00 8,415.00
2 Tukang OH 0.100 107,100.00 10,710.00
3 Kepala Tukang OH 0.010 126,225.00 1,262.25
4 Mandor OH 0.005 95,625.00 478.13
Jumlah Tenaga Kerja 20,865.38
B. BAHAN
1 Kayu Balok 5/7 Kelas III m3 0.010 4,972,500.00 49,725.00
2 Paku Kayu 2 " - 3 " Kg 0.020 17,419.05 348.38
3 Kayu Papan 3/20 Kelas III m3 0.007 4,972,500.00 34,807.50
Jumlah Bahan 84,880.88
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 105,746.26
E Overhead & Profit 15% X E 15,861.94
F Harga Satuan Pekerjaan ( D + E ) 121,608.19
G Dibulatkan 121,608.00
Jenis Pekerjaan : Pembersihan 1 m2 Lapangan
Satuan / Unit : M2
Analisa : A. 2.2.1.9

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.100 84,150.00 8,415.00
2 Mandor OH 0.050 95,625.00 4,781.25
Jumlah Tenaga Kerja 13,196.25
B Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 13,196.25
C Overhead & Profit 15% X E 1,979.44
D Harga Satuan Pekerjaan ( B + C ) 15,175.69
E Dibulatkan 15,176.00

13
A.2.3.1 HARGA SATUAN PEKERJAAN TANAH

Jenis Pekerjaan : Penggalian 1m3 Tanah tanah biasa sedalam 1 m Satuan /


Unit : M3
Analisa : A.2.3.1.1

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.750 84,150.00 63,112.50
2 Mandor OH 0.025 95,625.00 2,390.63
Jumlah Tenaga Kerja 65,503.13
B. BAHAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 65,503.13
E Overhead & Profit 15% X D 9,825.47
F Harga Satuan Pekerjaan ( D + E ) 75,328.59
G Dibulatkan 75,329.00

Jenis Pekerjaan : Pengerugan 1 m3 kembali galian tanah Satuan


/ Unit : M3
Analisa : A.2.3.1.9

Pengerugan kembali 1 m3 galian dihitung dari 1/3 kali dari koefisien pekerjaan galian
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.500 84,150.00 42,075.00
2 Mandor OH 0.050 95,625.00 4,781.25
Jumlah Tenaga Kerja 46,856.25
B. BAHAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 46,856.25
E Overhead & Profit 15% X D 7,028.44
F Harga Satuan Pekerjaan ( D + E ) 53,884.69
G Dibulatkan 53,885.00

14
Jenis Pekerjaan : Pengurugan 1 m3 dengan pasir urug Satuan
/ Unit : M3
Analisa : A.2.3.1.11

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.300 84,150.00 25,245.00
2 Mandor OH 0.010 95,625.00 956.25
Jumlah Tenaga Kerja 26,201.25
B. BAHAN
1 Pasir Urug M3 1.200 205,004.55 246,005.46
Jumlah Bahan 246,005.46
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 272,206.71
E Overhead & Profit 15% X D 40,831.01
F Harga Satuan Pekerjaan ( D + E ) 313,037.71
G Dibulatkan 313,038.00

Jenis Pekerjaan : Timbunan 1 m3 Tanah Pilihan


Satuan / Unit : M3
Analisa : A.2.3.1.11a

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.300 84,150.00 25,245.00
2 Mandor OH 0.010 95,625.00 956.25
Jumlah Tenaga Kerja 26,201.25
B. BAHAN
1 Tanah Timbun Pilihan M3 1.200 87,975.00 105,570.00
Jumlah Bahan 105,570.00
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 131,771.25
E Overhead & Profit 15% X D 19,765.69
F Harga Satuan Pekerjaan ( D + E ) 151,536.94
G Dibulatkan 151,537.00

15
Jenis Pekerjaan : Timbunan 1 m3 Tanah Biasa
Satuan / Unit : M3
Analisa : A.2.3.1.11c

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.300 84,150.00 25,245.00
2 Mandor OH 0.010 95,625.00 956.25
Jumlah Tenaga Kerja 26,201.25
B. BAHAN
1 Tanah timbun biasa M3 1.200 49,725.00 59,670.00
Jumlah Bahan 59,670.00
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 85,871.25
E Overhead & Profit 15% X D 12,880.69
F Harga Satuan Pekerjaan ( D + E ) 98,751.94
G Dibulatkan 98,752.00

A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI

Jenis Pekerjaan : Pemasangan 1 m3 pondasi batu belah campuran 1 SP : 4 PP Satuan /


Unit : M3
Analisa : A.3.2.1.2

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 1.500 84,150.00 126,225.00
2 Tukang OH 0.750 107,100.00 80,325.00
3 Kepala Tukang OH 0.075 126,225.00 9,466.88
4 Mandor OH 0.075 95,625.00 7,171.88
Jumlah Tenaga Kerja 223,188.75
B. BAHAN
1 Batu Gunung/ Batu Kali M3 1.200 382,500.00 459,000.00
2 Semen Portland Kg 163.000 1,368.50 223,065.50
3 Pasir Pasang M3 0.520 205,004.55 106,602.36
Jumlah Bahan 788,667.86
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 1,011,856.61
E Overhead & Profit 15% X D 151,778.49
F Harga Satuan Pekerjaan ( D + E ) 1,163,635.11
G Dibulatkan 1,163,635.00

16
Jenis Pekerjaan : Pemasangan 1m3 batu kosong ( Anstamping ) Satuan /
Unit : M3
Analisa : A.3.2.1.9

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.780 84,150.00 65,637.00
2 Tukang OH 0.390 107,100.00 41,769.00
3 Kepala Tukang OH 0.039 126,225.00 4,922.78
4 Mandor OH 0.039 95,625.00 3,729.38
Jumlah Tenaga Kerja 116,058.15
B. BAHAN
1 Batu Gunung/ Batu Kali M3 1.200 382,500.00 459,000.00
2 Pasir Urug M3 0.432 205,004.55 88,561.96
Jumlah Bahan 547,561.96
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 663,620.11
E Overhead & Profit 15% X D 99,543.02
F Harga Satuan Pekerjaan ( D + E ) 763,163.13
G Dibulatkan 763,163.00

Jenis Pekerjaan : Pekerjaan 1m3 Pondasi Siklop 60% Beton Campuran 1 SP : 2 PB : 3 Kr Dan 40% Batu Belah Satuan / Unit
: M3
Analisa : A.3.2.1.10a

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 3.400 84,150.00 286,110.00
2 Tukang OH 0.850 107,100.00 91,035.00
3 Kepala Tukang OH 0.085 126,225.00 10,729.13
4 Mandor OH 0.170 95,625.00 16,256.25
Jumlah Tenaga Kerja 404,130.38
B. BAHAN
1 Batu Pecah 2-3 M3 0.480 324,545.45 155,781.82
2 Semen Portland Kg 194.000 1,368.50 265,489.00
3 Pasir Beton M3 0.312 205,004.55 63,961.42
4 Kerikil M3 0.468 240,975.00 112,776.30
Jumlah Bahan 598,008.54
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 1,002,138.91
E Overhead & Profit 15% X D 150,320.84
F Harga Satuan Pekerjaan ( D + E ) 1,152,459.75
G Dibulatkan 1,152,460.00

17
A.4.1.1 HARGA SATUAN PEKERJAAN BEKISTING

Jenis Pekerjaan : Membuat 1 m3 Beton Mutu F'c = 16,9 Mpa (K 200), Slump (12 ± 2) cm, W/c = 0,61 Satuan / Unit
: M3
Analisa : A.4.1.1.6

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 1.6500 84,150.00 138,847.50
2 Tukang OH 0.2750 107,100.00 29,452.50
3 Kepala Tukang OH 0.0280 126,225.00 3,534.30
4 Mandor OH 0.0830 95,625.00 7,936.88
Jumlah Tenaga Kerja 179,771.18
B. BAHAN
1 Semen Portland Kg 352.00 1,368.50 481,712.00
2 Pasir Beton Kg 731.00 146.43 107,041.66
3 Kerikil Kg 1,031.00 178.50 184,033.50
4 Air Liter 215.00 153.00 32,895.00
Jumlah Bahan 805,682.16
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 985,453.33
E Overhead & Profit 15% X D 147,818.00
F Harga Satuan Pekerjaan ( D + E ) 1,133,271.34
G Dibulatkan 1,133,271.00
Wc Faktor; Pasir; 1.400 Kg, dan Kerikil = 1.350 Kg

Jenis Pekerjaan : Pembesian 10 kg Dengan Besi Polos Satuan


/ Unit : Kg
Analisa : A.4.1.1.17

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.070 84,150.00 5,890.50
2 Tukang OH 0.070 107,100.00 7,497.00
3 Kepala Tukang OH 0.007 126,225.00 883.58
4 Mandor OH 0.040 95,625.00 3,825.00
Jumlah Tenaga Kerja 18,096.08
B. BAHAN
1 Besi Beton Polos Kg 10.500 8,983.23 94,323.86
2 Kawat Beton Kg 0.150 19,125.00 2,868.75
Jumlah Bahan 97,192.61
C. PERALATAN
Jumlah Peralatan -

18
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 115,288.69
E Per Kg Pembesian = D / 10 11,528.87
F Overhead & Profit 15% X E 1,729.33
G Harga Satuan Pekerjaan ( E + F ) 13,258.20
H Dibulatkan 13,258.00
Jenis Pekerjaan : Pembesian 10 Kg Dengan Besi Ulir
Satuan / Unit : Kg
Analisa : A.4.1.1.17a

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.070 84,150.00 5,890.50
2 Tukang OH 0.070 107,100.00 7,497.00
3 Kepala Tukang OH 0.007 126,225.00 883.58
4 Mandor OH 0.040 95,625.00 3,825.00
Jumlah Tenaga Kerja 18,096.08
B. BAHAN
1 Besi Beton Ulir Kg 10.500 10,313.05 108,287.03
2 Kawat Beton Kg 0.150 19,125.00 2,868.75
Jumlah Bahan 111,155.78
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 129,251.85
E Per Kg Pembesian = D / 10 12,925.19
F Overhead & Profit 15% X E 1,938.78
G Harga Satuan Pekerjaan ( E + F ) 14,863.96
H Dibulatkan 14,864.00

Jenis Pekerjaan : Pemasangan 1 m2 bekisting untuk pondasi Satuan /


Unit : M2
Analisa : A.4.1.1.20

No Uraia Satuan Koefisien Harga Satuan Jumlah Harga


n
A. TENAGA
1 Pekerja OH 0.520 84,150.00 43,758.00
2 Tukang OH 0.260 107,100.00 27,846.00
3 Kepala Tukang OH 0.026 126,225.00 3,281.85
4 Mandor OH 0.026 95,625.00 2,486.25
Jumlah Tenaga Kerja 77,372.10
B. BAHAN
1 Kayu Kelas IV M3 0.040 3,513,262.50 140,530.50
n
2 Paku 5 cm - 10 cm Kg 0.300 17,419.05 5,225.72
3 Minyak Bekisting Liter 0.100 13,175.00 1,317.50
Jumlah Bahan 147,073.72
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 224,445.82
E Overhead & Profit 15 X D 33,666.87
% 19
F Harga Satuan Pekerjaan ( E + F ) 258,112.69
G Harga 4 X Pemakaian 25% 64,528.17
H Dibulatkan 64,528.00
Jenis Pekerjaan : Pemasangan 1 m2 bekisting untuk sloof Satuan /
Unit : M2
Analisa : A.4.1.1.21

No Uraia Satuan Koefisien Harga Satuan Jumlah Harga


n
A. TENAGA
1 Pekerja OH 0.520 84,150.00 43,758.00
2 Tukang OH 0.260 107,100.00 27,846.00
3 Kepala Tukang OH 0.026 126,225.00 3,281.85
4 Mandor OH 0.026 95,625.00 2,486.25
Jumlah Tenaga Kerja 77,372.10
B. BAHAN
1 Kayu Kelas IV M3 0.045 3,513,262.50 158,096.81
2 Paku 5 cm - 10 cm Kg 0.300 17,419.05 5,225.72
3 Minyak Bekisting Liter 0.100 13,175.00 1,317.50
Jumlah Bahan 164,640.03
C. PERALATAN
Jumlah Peralatan -
n D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 242,012.13
E Overhead & Profit 15 X D 36,301.82
%
F Pekerjaan
Jenis Harga Satuan
: Pekerjaan
Pemasangan(1Em2
+F )
bekisting untuk kolom Satuan / 278,313.95
Unit
G : M2
Harga 4 X Pemakaian 25% 69,578.49
Analisa : A.4.1.1.22
H Dibulatkan 69,578.00
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.660 84,150.00 55,539.00
2 Tukang OH 0.330 107,100.00 35,343.00
3 Kepala Tukang OH 0.033 126,225.00 4,165.43
4 Mandor OH 0.033 95,625.00 3,155.63
Jumlah Tenaga Kerja 98,203.05
B. BAHAN
1 Kayu Kelas IV M3 0.040 3,513,262.50 140,530.50
2 Paku 5 cm - 10 cm Kg 0.400 17,419.05 6,967.62
3 Minyak Bekisting Liter 0.200 13,175.00 2,635.00
4 Balok Kayu Kelas IV M3 0.015 3,513,262.50 52,698.94
5 Plywood tebal 9 mm Lbr 0.350 122,670.45 42,934.66
6 Kayu dolken dia. 8-10 cm, L = 4 M Batang 2.000 55,250.00 110,500.00
Jumlah Bahan 356,266.72
C. PERALATAN
Jumlah Peralatan -

20
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 454,469.77
E Overhead & Profit 15% X D 68,170.46
n F Harga Satuan Pekerjaan ( E + F ) 522,640.23
G Harga 4 X Pemakaian 25% 130,660.06
H Dibulatkan 130,660.00
Jenis Pekerjaan : Pemasangan 1 m2 bekisting untuk balok Satuan /
Unit : M2
Analisa : A.4.1.1.23

No Uraia Satuan Koefisien Harga Satuan Jumlah Harga


n
A. TENAGA
1 Pekerja OH 0.6600 84,150.00 55,539.00
2 Tukang OH 0.3300 107,100.00 35,343.00
3 Kepala Tukang OH 0.0330 126,225.00 4,165.43
4 Mandor OH 0.0330 95,625.00 3,155.63
Jumlah Tenaga Kerja 98,203.05
B. BAHAN
1 Kayu Kelas IV M3 0.0400 3,513,262.50 140,530.50
2 Paku 5 cm - 10 cm Kg 0.4000 17,419.05 6,967.62
3 Minyak Bekisting Liter 0.2000 13,175.00 2,635.00
4 Balok Kayu Kelas IV M3 0.0180 3,513,262.50 63,238.73
5 Plywood tebal 9 mm Lbr 0.3500 122,670.45 42,934.66
n 6 Kayu dolken dia. 8-10 cm, L = 4 M Batang 2.0000 55,250.00 110,500.00
Jumlah Bahan 366,806.50
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 465,009.55
E Overhead & Profit 15 X D 69,751.43
%
F Harga Satuan Pekerjaan ( E + F ) 534,760.99
G Harga 4 X Pemakaian 25 133,690.25
%
H Dibulatkan 133,690.00
Jenis Pekerjaan : Pemasangan 1 m2 bekisting untuk lantai Satuan /
Unit : M2
Analisa : A.4.1.1.24

No Uraia Satuan Koefisien Harga Satuan Jumlah Harga


n
A. TENAGA
1 Pekerja OH 0.660 84,150.00 55,539.00
2 Tukang OH 0.330 107,100.00 35,343.00
3 Kepala Tukang OH 0.033 126,225.00 4,165.43
4 Mandor OH 0.033 95,625.00 3,155.63
Jumlah Tenaga Kerja 98,203.05
B. BAHAN
1 Kayu Kelas IV M3 0.040 3,513,262.50 140,530.50
2 Paku 5 cm - 10 cm Kg 0.400 17,419.05 6,967.62
3 Minyak Bekisting Liter 0.200 13,175.00 2,635.00
4 Balok Kayu Kelas IV M3 0.015 3,513,262.50 52,698.94
5 Plywood tebal 9 mm Lbr 0.350 122,670.45 42,934.6621
6 Kayu dolken dia. 8-10 cm, L = 4 M Batang 6.000 55,250.00 331,500.00
A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN

Jenis Pekerjaan : Pemasangan 1 m2 dinding bata merah ( 5x11x22 ) Cm Tebal 1 batu camp. 1 SP : 4 PP Satuan / Unit :
M2
Analisa : A.4.4.1.3

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.600 84,150.00 50,490.00
2 Tukang OH 0.200 107,100.00 21,420.00
3 Kepala Tukang OH 0.020 126,225.00 2,524.50
4 Mandor OH 0.030 95,625.00 2,868.75
Jumlah Tenaga Kerja 77,303.25
B. BAHAN
1 Bata Merah Bh 140.000 478.55 66,997.00
2 Semen Porland Kg 26.550 1,368.50 36,333.68
3 Pasir Pasang M3 0.093 205,004.55 19,065.42
Jumlah Bahan 122,396.10
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 199,699.35
E Overhead & Profit 15% X D 29,954.90
F Harga Satuan Pekerjaan ( D + E ) 229,654.25
G Dibulatkan 229,654.00

Jenis Pekerjaan : Pemasangan 1 m2 dinding bata merah ( 5x11x22 ) Cm Tebal 1/2 batu camp. 1 SP : 2 PP Satuan / Unit :
M2
Analisa : A.4.4.1.7

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.300 84,150.00 25,245.00
2 Tukang OH 0.100 107,100.00 10,710.00
3 Kepala Tukang OH 0.010 126,225.00 1,262.25
4 Mandor OH 0.015 95,625.00 1,434.38
Jumlah Tenaga Kerja 38,651.63
B. BAHAN
1 Bata Merah Bh 70.000 478.55 33,498.50
2 Semen Porland Kg 18.950 1,368.50 25,933.08
3 Pasir Pasang M3 0.038 205,004.55 7,790.17
Jumlah Bahan 67,221.75
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 105,873.37
E Overhead & Profit 15% X D 15,881.01

22
F Harga Satuan Pekerjaan ( D + E ) 121,754.38
G Dibulatkan 121,754.00
Jenis Pekerjaan : Pemasangan 1 m2 dinding bata merah ( 5x11x22 ) Cm Tebal 1/2 batu camp. 1 SP : 3 PP Satuan / Unit :
M2
Analisa : A.4.4.1.8

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.300 84,150.00 25,245.00
2 Tukang OH 0.100 107,100.00 10,710.00
3 Kepala Tukang OH 0.010 126,225.00 1,262.25
4 Mandor OH 0.015 95,625.00 1,434.38
Jumlah Tenaga Kerja 38,651.63
B. BAHAN
1 Bata Merah Bh 70.000 478.55 33,498.50
2 Semen Porland Kg 14.370 1,368.50 19,665.35
3 Pasir Pasang M3 0.040 205,004.55 8,200.18
Jumlah Bahan 61,364.03
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 100,015.65
E Overhead & Profit 15% X D 15,002.35
F Harga Satuan Pekerjaan ( D + E ) 115,018.00
G Dibulatkan 115,018.00

Jenis Pekerjaan : Pemasangan 1 m2 dinding bata merah ( 5x11x22 ) Cm Tebal 1/2 batu camp. 1 SP : 4 PP Satuan / Unit :
M2
Analisa : A.4.4.1.9

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.300 84,150.00 25,245.00
2 Tukang OH 0.100 107,100.00 10,710.00
3 Kepala Tukang OH 0.010 126,225.00 1,262.25
4 Mandor OH 0.015 95,625.00 1,434.38
Jumlah Tenaga Kerja 38,651.63
B. BAHAN
1 Bata Merah Bh 70.000 478.55 33,498.50
2 Semen Porland Kg 11.500 1,368.50 15,737.75
3 Pasir Pasang M3 0.043 205,004.55 8,815.20
Jumlah Bahan 58,051.45
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 96,703.07
E Overhead & Profit 15% X D 14,505.46
F Harga Satuan Pekerjaan ( D + E ) 111,208.53
G Dibulatkan 111,209.00

23
Jenis Pekerjaan : Pekerjaan 1 m2 plasteran 1 SP : 2 PP tebal 15 mm Satuan /
Unit : M2
Analisa : A.4.4.2.2

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.300 84,150.00 25,245.00
2 Tukang OH 0.150 107,100.00 16,065.00
3 Kepala Tukang OH 0.015 126,225.00 1,893.38
4 Mandor OH 0.015 95,625.00 1,434.38
Jumlah Tenaga Kerja 44,637.75
B. BAHAN
1 Semen Porland Kg 10.224 1,368.50 13,991.54
2 Pasir Pasang M3 0.020 205,004.55 4,100.09
Jumlah Bahan 18,091.63
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 62,729.38
E Overhead & Profit 15% X D 9,409.41
F Harga Satuan Pekerjaan ( D + E ) 72,138.79
G Dibulatkan 72,139.00

Jenis Pekerjaan : Pekerjaan 1 m2 plasteran 1 SP : 3 PP tebal 15 mm Satuan /


Unit : M2
Analisa : A.4.4.2.3

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.300 84,150.00 25,245.00
2 Tukang OH 0.150 107,100.00 16,065.00
3 Kepala Tukang OH 0.015 126,225.00 1,893.38
4 Mandor OH 0.015 95,625.00 1,434.38
Jumlah Tenaga Kerja 44,637.75
B. BAHAN
1 Semen Porland Kg 7.776 1,368.50 10,641.46
2 Pasir Pasang M3 0.023 205,004.55 4,715.10
Jumlah Bahan 15,356.56
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 59,994.31
E Overhead & Profit 15% X D 8,999.15
F Harga Satuan Pekerjaan ( D + E ) 68,993.46
G Dibulatkan 68,993.00

24
Jenis Pekerjaan : Pekerjaan 1 m2 plasteran 1 SP : 4 PP tebal 15 mm Satuan /
Unit : M2
Analisa : A.4.4.2.4

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.300 84,150.00 25,245.00
2 Tukang OH 0.150 107,100.00 16,065.00
3 Kepala Tukang OH 0.015 126,225.00 1,893.38
4 Mandor OH 0.015 95,625.00 1,434.38
Jumlah Tenaga Kerja 44,637.75
B. BAHAN
1 Semen Porland Kg 6.240 1,368.50 8,539.44
2 Pasir Pasang M3 0.024 205,004.55 4,920.11
Jumlah Bahan 13,459.55
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 58,097.30
E Overhead & Profit 15% X D 8,714.59
F Harga Satuan Pekerjaan ( D + E ) 66,811.89
G Dibulatkan 66,812.00

A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING

Jenis Pekerjaan : Pemasangan 1 m2 lantai granit ukuran 60 cm x 60 cm Satuan /


Unit : M2
Analisa : A.4.4.3.13a

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.24 84,150.00 20,196.00
2 Tukang OH 0.12 107,100.00 12,852.00
3 Kepala Tukang OH 0.012 126,225.00 1,514.70
4 Mandor OH 0.012 95,625.00 1,147.50
Jumlah Tenaga Kerja 35,710.20
B. BAHAN
1 Granit 60 x 60 cm Klas II Bh 3.10 71,606.06 221,978.79
2 Semen Portland Kg 9.60 1,368.50 13,137.60
3 Pasir Pasang M3 0.045 205,004.55 9,225.20
4 Semen Keramik Kg 1.50 3,944.93 5,917.39
Jumlah Bahan 250,258.98
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 285,969.18

25
E Overhead & Profit 15% X D 42,895.38
F Harga Satuan Pekerjaan ( D + E ) 328,864.56
G Dibulatkan 328,865.00
Jenis Pekerjaan : Pemasangan 1 m2 lantai keramik ukuran 25 cm x 25 cm Satuan /
Unit : M2
Analisa : A.4.4.3.36a

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.70 84,150.00 58,905.00
2 Tukang OH 0.35 107,100.00 37,485.00
3 Kepala Tukang OH 0.035 126,225.00 4,417.88
4 Mandor OH 0.035 95,625.00 3,346.88
Jumlah Tenaga Kerja 104,154.75
B. BAHAN
1 Keramik 25 x 25 Cm Bh 17.50 3,758.01 65,765.20
2 Semen Porland Kg 10.40 1,368.50 14,232.40
3 Pasir Pasang M3 0.045 205,004.55 9,225.20
4 Semen Keramik Kg 1.62 3,944.93 6,390.78
Jumlah Bahan 95,613.59
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 199,768.34
E Overhead & Profit 15% X D 29,965.25
F Harga Satuan Pekerjaan ( D + E ) 229,733.59
G Dibulatkan 229,734.00

Jenis Pekerjaan : Pemasangan 1m2 Dinding Keramik Uk.25 x 40 Cm Satuan /


Unit : M2
Analisa : A.4.4.3.54a

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.90 84,150.00 75,735.00
2 Tukang OH 0.45 107,100.00 48,195.00
3 Kepala Tukang OH 0.045 126,225.00 5,680.13
4 Mandor OH 0.045 95,625.00 4,303.13
Jumlah Tenaga Kerja 133,913.25
B. BAHAN
1 Keramik 25 x 40 Cm Bh 10.50 9,659.09 101,420.49
2 Semen Porland Kg 9.30 1,368.50 12,727.05
3 Pasir Pasang M3 0.018 205,004.55 3,690.08
4 Semen Keramik Kg 1.94 3,944.93 7,653.16
Jumlah Bahan 125,490.78
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 259,404.03
E Overhead & Profit 15% X D 38,910.60
F Harga Satuan Pekerjaan ( D + E ) 298,314.63

26
G Dibulatkan 298,315.00
A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT PLAFOON

Jenis Pekerjaan : Pemasangan 1m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm Satuan / Unit
: M2
Analisa : A.4.5.1.7a

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.100 84,150.00 8,415.00
2 Tukang OH 0.050 107,100.00 5,355.00
3 Kepala Tukang OH 0.005 126,225.00 631.13
4 Mandor OH 0.005 95,625.00 478.13
Jumlah Tenaga Kerja 14,879.25
B. BAHAN
1 Gypsum Board Lembar 0.364 67,729.55 24,653.56
2 List Profil Gypsum M' 4.000 3,863.63 15,454.53
3 Paku Skrup Kg 0.110 2,975.00 327.25
Jumlah Bahan 40,435.34
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 55,314.59
E Overhead & Profit 15% X D 8,297.19
F Harga Satuan Pekerjaan ( D + E ) 63,611.77
G Dibulatkan 63,612.00

Jenis Pekerjaan : Pemasangan 1m2 langit-langit Calsyboard ukuran (120x240x9) mm, tebal 9 mm Satuan / Unit
: M2
Analisa : A.4.5.1.7a

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.100 84,150.00 8,415.00
2 Tukang OH 0.050 107,100.00 5,355.00
3 Kepala Tukang OH 0.005 126,225.00 631.13
4 Mandor OH 0.005 95,625.00 478.13
Jumlah Tenaga Kerja 14,879.25
B. BAHAN
1 Calsyboard Lembar 0.364 67,729.55 24,653.56
2 List Profil Gypsum M' 4.000 3,863.63 15,454.53
3 Paku Skrup Kg 0.110 2,975.00 327.25
Jumlah Bahan 40,435.34
C. PERALATAN
Jumlah Peralatan -

27
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 55,314.59
E Overhead & Profit 15% X D 8,297.19
F Harga Satuan Pekerjaan ( D + E ) 63,611.77
G Dibulatkan 63,612.00
A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP

Jenis Pekerjaan : Pemasangan 1 M2 Atap Genteng Metal 25 Satuan /


Unit : M2
Analisa : A.4.5.2.32

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.200 84,150.00 16,830.00
2 Tukang OH 0.100 107,100.00 10,710.00
3 Kepala Tukang OH 0.010 126,225.00 1,262.25
4 Mandor OH 0.001 95,625.00 95.63
Jumlah Tenaga Kerja 28,897.88
B. BAHAN
1 Atap genteng metal M2 1.020 70,009.09 71,409.28
2 Paku Genteng Kg 0.200 13,522.73 2,704.55
Jumlah Bahan 74,113.82
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 103,011.70
E Overhead & Profit 15% X D 15,451.75
F Harga Satuan Pekerjaan ( D + E ) 118,463.45
G Dibulatkan 118,463.00

Jenis Pekerjaan : Pemasangan 1 M' Rabung Atap Genteng Metal 25 Satuan /


Unit : M'
Analisa : A.4.5.2.36

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.250 84,150.00 21,037.50
2 Tukang OH 0.150 107,100.00 16,065.00
3 Kepala Tukang OH 0.015 126,225.00 1,893.38
4 Mandor OH 0.013 95,625.00 1,243.13
Jumlah Tenaga Kerja 40,239.00
B. BAHAN
1 Nok/Rabung Atap Genteng M2 1.10 70,202.27 77,222.50
2 Paku Genteng Kg 0.05 13,522.73 676.14
Jumlah Bahan 77,898.64
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 118,137.64
E Overhead & Profit 15% X D 17,720.65
F Harga Satuan Pekerjaan ( D + E ) 135,858.28

28
G Dibulatkan 135,858.00
A.4.6.1 HARGA SATUAN PEKERJAAN KAYU

Jenis Pekerjaan : Pembuatan dan pemasangan 1 m3 Kusen pintu dan kusen jendela, kayu kelas I Satuan / Unit
: M3
Analisa : A.4.6.1.1

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 7.000 84,150.00 589,050.00
2 Tukang OH 21.000 107,100.00 2,249,100.00
3 Kepala Tukang OH 2.100 126,225.00 265,072.50
4 Mandor OH 0.350 95,625.00 33,468.75
Jumlah Tenaga Kerja 3,136,691.25
B. BAHAN
1 Balok Kayu Kelas I M3 1.100 8,847,875.25 9,732,662.78
2 Paku Kayu 10 Cm Kg 1.250 17,419.05 21,773.81
3 Lem Kayu Kg 1.000 37,825.00 37,825.00
Jumlah Bahan 9,792,261.59
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 12,928,952.84
E Overhead & Profit 15% X D 1,939,342.93
F Harga Satuan Pekerjaan ( D + E ) 14,868,295.76
G Dibulatkan 14,868,296.00

Jenis Pekerjaan : Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas I Satuan / Unit
: M2
Analisa : A.4.6.1.5

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 1.000 84,150.00 84,150.00
2 Tukang OH 3.000 107,100.00 321,300.00
3 Kepala Tukang OH 0.300 126,225.00 37,867.50
4 Mandor OH 0.050 95,625.00 4,781.25
Jumlah Tenaga Kerja 448,098.75
B. BAHAN
1 Papan Kayu Kelas I M3 0.040 8,847,875.25 353,915.01
2 Lem Kayu Kg 1.000 37,825.00 37,825.00
Jumlah Bahan 391,740.01
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 839,838.76
E Overhead & Profit 15% X D 125,975.81
F Harga Satuan Pekerjaan ( D + E ) 965,814.57

29
G Dibulatkan 965,815.00
Jenis Pekerjaan : Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelas I atau II Satuan / Unit
: M2
Analisa : A.4.6.1.6a

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.800 84,150.00 67,320.00
2 Tukang OH 2.400 107,100.00 257,040.00
3 Kepala Tukang OH 0.240 126,225.00 30,294.00
4 Mandor OH 0.040 95,625.00 3,825.00
Jumlah Tenaga Kerja 358,479.00
B. BAHAN
1 Papan Kayu Kelas II M3 0.024 6,502,500.00 156,060.00
2 Lem Kayu Kg 0.300 37,825.00 11,347.50
3 Kaca Bening 5 mm M2 0.640 99,166.66 63,466.66
Jumlah Bahan 230,874.16
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 589,353.16
E Overhead & Profit 15% X D 88,402.97
F Harga Satuan Pekerjaan ( D + E ) 677,756.14
G Dibulatkan 677,756.00

Jenis Pekerjaan : Pemasangan 1 m3 kontruksi kuda-kuda konvensional, kayu kelas I, II dan III Bentang 6 M Satuan / Unit
: M3
Analisa : A.4.6.1.13

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 4.000 84,150.00 336,600.00
2 Tukang OH 12.000 107,100.00 1,285,200.00
3 Kepala Tukang OH 1.200 126,225.00 151,470.00
4 Mandor OH 0.200 95,625.00 19,125.00
Jumlah Tenaga Kerja 1,792,395.00
B. BAHAN
1 Balok Kayu Klas I M3 1.100 8,847,875.25 9,732,662.78
2 Paku 12 Cm Kg 5.600 17,419.05 97,546.68
Jumlah Bahan 9,830,209.46
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 11,622,604.46
E Overhead & Profit 15% X D 1,743,390.67
F Harga Satuan Pekerjaan ( D + E ) 13,365,995.12
G Dibulatkan 13,365,995.00

30
Jenis Pekerjaan : Pemasangan 1 m3 kontruksi Kayu Kelas I Satuan
/ Unit : M3
Analisa : A.4.6.1.13a

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 4.000 84,150.00 336,600.00
2 Tukang OH 12.000 107,100.00 1,285,200.00
3 Kepala Tukang OH 1.200 126,225.00 151,470.00
4 Mandor OH 0.200 95,625.00 19,125.00
Jumlah Tenaga Kerja 1,792,395.00
B. BAHAN
1 Balok Kayu Klas I M3 1.100 8,847,875.25 9,732,662.78
2 Paku 12 Cm Kg 5.600 17,419.05 97,546.68
Jumlah Bahan 9,830,209.46
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 11,622,604.46
E Overhead & Profit 15% X D 1,743,390.67
F Harga Satuan Pekerjaan ( D + E ) 13,365,995.12
G Dibulatkan 13,365,995.00

Jenis Pekerjaan : Pemasangan 1 m3 kontruksi Kayu Kelas II Satuan


/ Unit : M3
Analisa : A.4.6.1.13b

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 4.000 84,150.00 336,600.00
2 Tukang OH 12.000 107,100.00 1,285,200.00
3 Kepala Tukang OH 1.200 126,225.00 151,470.00
4 Mandor OH 0.200 95,625.00 19,125.00
Jumlah Tenaga Kerja 1,792,395.00
B. BAHAN
1 Balok Kayu Klas II M3 1.100 6,502,500.00 7,152,750.00
2 Paku 12 Cm Kg 5.600 17,419.05 97,546.68
Jumlah Bahan 7,250,296.68
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 9,042,691.68
E Overhead & Profit 15% X D 1,356,403.75
F Harga Satuan Pekerjaan ( D + E ) 10,399,095.43
G Dibulatkan 10,399,095.00

31
Jenis Pekerjaan : Pemasangan 1 m3 kontruksi gordeng, kayu kelas II Satuan /
Unit : M3
Analisa : A.4.6.1.15a

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 6.700 84,150.00 563,805.00
2 Tukang OH 20.100 107,100.00 2,152,710.00
3 Kepala Tukang OH 2.010 126,225.00 253,712.25
4 Mandor OH 0.335 95,625.00 32,034.38
Jumlah Tenaga Kerja 3,002,261.63
B. BAHAN
1 Balok Kayu Kelas II M3 1.100 6,502,500.00 7,152,750.00
2 Paku 12 Cm Kg 3.000 17,419.05 52,257.15
Jumlah Bahan 7,205,007.15
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 10,207,268.78
E Overhead & Profit 15% X D 1,531,090.32
F Harga Satuan Pekerjaan ( D + E ) 11,738,359.09
G Dibulatkan 11,738,359.00

Jenis Pekerjaan : Pemasangan 1 m' lisplank ( 2 x 20 cm ), Kayu kelas I Atau Kelas II Satuan /
Unit : M'
Analisa : A.4.6.1.21a

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.100 84,150.00 8,415.00
2 Tukang OH 0.200 107,100.00 21,420.00
3 Kepala Tukang OH 0.020 126,225.00 2,524.50
4 Mandor OH 0.005 95,625.00 478.13
Jumlah Tenaga Kerja 32,837.63
B. BAHAN
1 Papan Kayu Klas II M3 0.0108 6,502,500.00 70,227.00
2 Paku Kayu Kg 0.100 17,419.05 1,741.91
Jumlah Bahan 71,968.91
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 104,806.53
E Overhead & Profit 15% X D 15,720.98
F Harga Satuan Pekerjaan ( D + E ) 120,527.51
G Dibulatkan 120,528.00

32
A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI DAN KACA

Jenis Pekerjaan : Pemasangan 1 Bh Kunci Tanam Biasa


Satuan / Unit : Bh
Analisa : A.4.6.2.2

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.01 84,150.00 841.50
2 Tukang OH 0.50 107,100.00 53,550.00
3 Kepala Tukang OH 0.050 126,225.00 6,311.25
4 Mandor OH 0.005 95,625.00 478.13
Jumlah Tenaga Kerja 61,180.88
B. BAHAN
1 Kunci Tanam Biasa Bh 1.00 200,000.00 200,000.00
Jumlah Bahan 200,000.00
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 261,180.88
E Overhead & Profit 15% X D 39,177.13
F Harga Satuan Pekerjaan ( D + E ) 300,358.01
G Dibulatkan 300,358.00

Jenis Pekerjaan : Pemasangan 1 Bh Kunci Tanam 2 Daun Satuan


/ Unit : Bh
Analisa : A.4.6.2.2 (1)

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.01 84,150.00 841.50
2 Tukang OH 0.50 107,100.00 53,550.00
3 Kepala Tukang OH 0.050 126,225.00 6,311.25
4 Mandor OH 0.005 95,625.00 478.13
Jumlah Tenaga Kerja 61,180.88
B. BAHAN
1 Kunci Tanam 2 Daun Bh 1.00 220,000.00 220,000.00
Jumlah Bahan 220,000.00
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 281,180.88
E Overhead & Profit 15% X D 42,177.13
F Harga Satuan Pekerjaan ( D + E ) 323,358.01
G Dibulatkan 323,358.00

33
Jenis Pekerjaan : Pemasangan 1 Bh Engsel Pintu
Satuan / Unit : Bh
Analisa : A.4.6.2.5

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.015 84,150.00 1,262.25
2 Tukang OH 0.15 107,100.00 16,065.00
3 Kepala Tukang OH 0.015 126,225.00 1,893.38
4 Mandor OH 0.0008 95,625.00 76.50
Jumlah Tenaga Kerja 19,297.13
B. BAHAN
1 Engsel Pintu Bh 1.00 27,200.00 27,200.00
Jumlah Bahan 27,200.00
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 46,497.13
E Overhead & Profit 15% X D 6,974.57
F Harga Satuan Pekerjaan ( D + E ) 53,471.69
G Dibulatkan 53,472.00

Jenis Pekerjaan : Pemasangan 1 Bh Engsel Jendela Kupu-kupu Satuan /


Unit : Bh
Analisa : A.4.6.2.6

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.01 84,150.00 841.50
2 Tukang OH 0.10 107,100.00 10,710.00
3 Kepala Tukang OH 0.010 126,225.00 1,262.25
4 Mandor OH 0.0005 95,625.00 47.81
Jumlah Tenaga Kerja 12,861.56
B. BAHAN
1 Engsel Jendela Bh 1.00 23,800.00 23,800.00
Jumlah Bahan 23,800.00
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 36,661.56
E Overhead & Profit 15% X D 5,499.23
F Harga Satuan Pekerjaan ( D + E ) 42,160.80
G Dibulatkan 42,161.00

34
Jenis Pekerjaan : Pemasangan 1 Bh Kait Angin / Hak Angin Satuan
/ Unit : Bh
Analisa : A.4.6.2.9

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.015 84,150.00 1,262.25
2 Tukang OH 0.15 107,100.00 16,065.00
3 Kepala Tukang OH 0.015 126,225.00 1,893.38
4 Mandor OH 0.008 95,625.00 765.00
Jumlah Tenaga Kerja 19,985.63
B. BAHAN
1 Kait Jendela Bh 1.00 14,372.73 14,372.73
Jumlah Bahan 14,372.73
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 34,358.35
E Overhead & Profit 15% X D 5,153.75
F Harga Satuan Pekerjaan ( D + E ) 39,512.10
G Dibulatkan 39,512.00

Jenis Pekerjaan : Pemasangan 1 Bh Kunci Slot / Pacok Satuan


/ Unit : Bh
Analisa : A.4.6.2.11

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.02 84,150.00 1,683.00
2 Tukang OH 0.2 107,100.00 21,420.00
3 Kepala Tukang OH 0.02 126,225.00 2,524.50
4 Mandor OH 0.001 95,625.00 95.63
Jumlah Tenaga Kerja 25,723.13
B. BAHAN
1 Kunci Slot / Pacok Bh 1.00 24,534.09 24,534.09
Jumlah Bahan 24,534.09
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 50,257.22
E Overhead & Profit 15% X D 7,538.58
F Harga Satuan Pekerjaan ( D + E ) 57,795.80
G Dibulatkan 57,796.00

35
Jenis Pekerjaan : Pemasangan M2 Kaca Tebal 5 mm
Satuan / Unit : M2
Analisa : A.4.6.2.17

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.015 84,150.00 1,262.25
2 Tukang OH 0.15 107,100.00 16,065.00
3 Kepala Tukang OH 0.015 126,225.00 1,893.38
4 Mandor OH 0.0008 95,625.00 76.50
Jumlah Tenaga Kerja 19,297.13
B. BAHAN
1 Kaca T=5 mm M2 1.10 99,166.66 109,083.33
2 Sealet Kg 0.05 6,400.00 320.00
Jumlah Bahan 109,403.33
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 128,700.45
E Overhead & Profit 15% X D 19,305.07
F Harga Satuan Pekerjaan ( D + E ) 148,005.52
G Dibulatkan 148,006.00
A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

Jenis Pekerjaan : 1 m2 Pengecatan Cat Minyak ( 1 Lapis Plamur, 1 Lapis Cat Dasar, 2 Lapis Penutup ) Satuan / Unit
: M2
Analisa : A.4.7.1.4a

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.07 84,150.00 5,890.50
2 Tukang OH 0.009 107,100.00 963.90
3 Kepala Tukang OH 0.006 126,225.00 757.35
4 Mandor OH 0.003 95,625.00 286.88
Jumlah Tenaga Kerja 7,898.63
B. BAHAN
1 Plamur Kg 0.15 11,590.91 1,738.64
2 Cat Dasar Kayu Kg 0.17 43,834.50 7,451.87
3 Cat Penutup Minyak Kg 0.26 51,038.63 13,270.04
4 Kuas bh 0.01 9,659.09 96.59
5 Pengencer / Miyak Cat Ltr 0.03 21,636.37 649.09
6 Ampelas lbr 0.2 11,432.50 2,286.50
Jumlah Bahan 25,492.73
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 33,391.35
E Overhead & Profit 15% X D 5,008.70
F Harga Satuan Pekerjaan ( D + E ) 38,400.06
G Dibulatkan 38,400.00

36
Jenis Pekerjaan : Pengecatan 1 m2 Tembok Baru ( 1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup ) Satuan / Unit :
M2
Analisa : A.4.7.1.10

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.02 84,150.00 1,683.00
2 Tukang OH 0.063 107,100.00 6,747.30
3 Kepala Tukang OH 0.0063 126,225.00 795.22
4 Mandor OH 0.003 95,625.00 286.88
Jumlah Tenaga Kerja 9,512.39
B. BAHAN
1 Plamur Kg 0.10 11,590.91 1,159.09
2 Cat Dasar Tembok Kg 0.10 43,834.50 4,383.45
3 Cat Penutup Tembok Kg 0.26 29,750.00 7,735.00
Jumlah Bahan 13,277.54
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 22,789.93
E Overhead & Profit 15% X D 3,418.49
F Harga Satuan Pekerjaan ( D + E ) 26,208.42
G Dibulatkan 26,208.00

Jenis Pekerjaan : Pengecatan 1 m2 Plafoon ( 1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup ) Satuan / Unit
: M2
Analisa : A.4.7.1.10a

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.02 84,150.00 1,683.00
2 Tukang OH 0.063 107,100.00 6,747.30
3 Kepala Tukang OH 0.0063 126,225.00 795.22
4 Mandor OH 0.003 95,625.00 286.88
Jumlah Tenaga Kerja 9,512.39
B. BAHAN
1 Plamur Kg 0.10 11,590.91 1,159.09
2 Cat Dasar Kg 0.10 43,834.50 4,383.45
3 Cat Penutup Kg 0.26 29,750.00 7,735.00
Jumlah Bahan 13,277.54
C. PERALATAN
1 Perancah Hari -Sewa 1.00 15,000.00 15,000.00
Jumlah Peralatan 15,000.00
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 37,789.93
E Overhead & Profit 15% X D 5,668.49
F Harga Satuan Pekerjaan ( D + E ) 43,458.42
G Dibulatkan 43,458.00

37
A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG

Jenis Pekerjaan : Pemasangan 1 Bh Closet Duduk/Monoblock Stara TOTO Satuan /


Unit : Bh
Analisa : A.5.1.1.1a

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 3.30 84,150.00 277,695.00
2 Tukang OH 1.10 107,100.00 117,810.00
3 Kepala Tukang OH 0.01 126,225.00 1,262.25
4 Mandor OH 0.16 95,625.00 15,300.00
Jumlah Tenaga Kerja 412,067.25
B. BAHAN
1 Closet Duduk Unit 1.00 502,272.73 502,272.73
2 Perlengkapan Ls 6% x Closet 30,136.36 30,136.36
Jumlah Bahan 532,409.09
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 944,476.34
E Overhead & Profit 15% X D 141,671.45
F Harga Satuan Pekerjaan ( D + E ) 1,086,147.79
G Dibulatkan 1,086,148.00

Jenis Pekerjaan : Pemasangan 1 Bh Westafel


Satuan / Unit : Bh
Analisa : A.5.1.1.5

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 1.20 84,150.00 100,980.00
2 Tukang OH 1.45 107,100.00 155,295.00
3 Kepala Tukang OH 0.15 126,225.00 18,933.75
4 Mandor OH 0.06 95,625.00 5,737.50
Jumlah Tenaga Kerja 280,946.25
B. BAHAN
1 Westafel Unit 1.20 463,636.37 556,363.64
2 Semen Porland Kg 6.00 1,368.50 8,211.00
3 Pasir Pasang M3 0.01 205,004.55 2,050.05
4 Perlengkapan % 12.00 14,356.00 172,272.00
Jumlah Bahan 738,896.69
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 1,019,842.94
E Overhead & Profit 15% X D 152,976.44

38
F Harga Satuan Pekerjaan ( D + E ) 1,172,819.38
G Dibulatkan 1,172,819.00
Jenis Pekerjaan : Pemasangan 1 Bh Floor Drain Stanlesteel Satuan /
Unit : Bh
Analisa : A.5.1.1.14

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.01 84,150.00 841.50
2 Tukang OH 0.10 107,100.00 10,710.00
3 Kepala Tukang OH 0.01 126,225.00 1,262.25
4 Mandor OH 0.005 95,625.00 478.13
Jumlah Tenaga Kerja 13,291.88
B. BAHAN
1 Floor drain Stanlesteel Bh 1.000 24,534.09 24,534.09
Jumlah Bahan 24,534.09
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 37,825.97
E Overhead & Profit 15% X D 5,673.90
F Harga Satuan Pekerjaan ( D + E ) 43,499.86
G Dibulatkan 43,500.00

Jenis Pekerjaan : Pemasangan 1 Bh Bak Kontrol Pasangan Bata 30 x 30 Cm Tinggi 35 Cm ( Penutup Plat Beton ) Satuan / Unit :
Bh
Analisa : A.5.1.1.15.a

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 2.1600 84,150.00 181,764.00
2 Tukang OH 0.7200 107,100.00 77,112.00
3 Kepala Tukang OH 0.0720 126,225.00 9,088.20
4 Mandor OH 0.0110 95,625.00 1,051.88
Jumlah Tenaga Kerja 269,016.08
B. BAHAN
1 Bata Merah Bh 40.00 478.55 19,142.00
2 Semen Portland Kg 44.00 1,368.50 60,214.00
3 Pasir Pasang M3 0.07 205,004.55 14,350.32
4 Pasir Beton M3 0.06 205,004.55 12,300.27
5 Kerikil M3 0.07 240,975.00 16,868.25
6 Baja Profil Kg 1.60 44,972.73 71,956.36
Jumlah Bahan 194,831.20
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 463,847.28
E Overhead & Profit 15% X D 69,577.09
F Harga Satuan Pekerjaan ( D + E ) 533,424.37
G Dibulatkan 533,424.00

39
Jenis Pekerjaan : Pemasangan 1 Bh Bak Kontrol Pasangan Bata 30 x 30 Cm Tinggi 35 Cm Penutup Besi Satuan / Unit :
Bh
Analisa : A.5.1.1.15b

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 2.1600 84,150.00 181,764.00
2 Tukang OH 0.7200 107,100.00 77,112.00
3 Kepala Tukang OH 0.0720 126,225.00 9,088.20
4 Mandor OH 0.0110 95,625.00 1,051.88
Jumlah Tenaga Kerja 269,016.08
B. BAHAN
1 Bata Merah Bh 40.00 478.55 19,142.00
2 Semen Portland Kg 44.00 1,368.50 60,214.00
3 Pasir Pasang M3 0.07 205,004.55 14,350.32
4 Pasir Beton M3 0.06 205,004.55 12,300.27
5 Kerikil M3 0.07 240,975.00 16,868.25
6 Penutup Beton Bh 1.00 65,000.00 65,000.00
Jumlah Bahan 187,874.84
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 456,890.92
E Overhead & Profit 15% X D 68,533.64
F Harga Satuan Pekerjaan ( D + E ) 525,424.55
G Dibulatkan 525,425.00

Jenis Pekerjaan : Pemasangan 1 Bh Kran Air Diameter 1/2 " Atau 3/4 " Satuan /
Unit : Bh
Analisa : A.5.1.1.19

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.01 84,150.00 841.50
2 Tukang OH 0.10 107,100.00 10,710.00
3 Kepala Tukang OH 0.04 126,225.00 5,049.00
4 Mandor OH 0.005 95,625.00 478.13
Jumlah Tenaga Kerja 17,078.63
B. BAHAN
1 Kran Air Bh 1.00 11,590.91 11,590.91
2 Sealtape Buah 0.025 6,181.82 154.55
Jumlah Bahan 11,745.45
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 28,824.08
E Overhead & Profit 15% X D 4,323.61
F Harga Satuan Pekerjaan ( D + E ) 33,147.69

40
G Dibulatkan 33,148.00
Jenis Pekerjaan : Pemasangan 1 m' pipa PVC tipe AW diameter 3/4 " Satuan /
Unit : M'
Analisa : A.5.1.1.26

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.036 84,150.00 3,029.40
2 Tukang OH 0.06 107,100.00 6,426.00
3 Kepala Tukang OH 0.006 126,225.00 757.35
4 Mandor OH 0.002 95,625.00 191.25
Jumlah Tenaga Kerja 10,404.00
B. BAHAN
1 PVC ¾ M 1.20 4,906.82 5,888.18
2 Perlengkapan % 35.00 58.88 2,060.86
Jumlah Bahan 7,949.05
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 18,353.05
E Overhead & Profit 15% X D 2,752.96
F Harga Satuan Pekerjaan ( D + E ) 21,106.01
G Dibulatkan 21,106.00

Jenis Pekerjaan : Pemasangan 1 m' pipa PVC tipe AW diameter 3 " Satuan /
Unit : M'
Analisa : A.5.1.1.31

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.081 84,150.00 6,816.15
2 Tukang OH 0.135 107,100.00 14,458.50
3 Kepala Tukang OH 0.0135 126,225.00 1,704.04
4 Mandor OH 0.004 95,625.00 382.50
Jumlah Tenaga Kerja 23,361.19
B. BAHAN
1 PVC 3" M 1.20 22,080.68 26,496.82
2 Perlengkapan % 35.00 264.97 9,273.89
Jumlah Bahan 35,770.70
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 59,131.89
E Overhead & Profit 15% X D 8,869.78
F Harga Satuan Pekerjaan ( D + E ) 68,001.67
G Dibulatkan 68,002.00

41
Jenis Pekerjaan : Pemasangan 1 m' pipa PVC tipe AW
diameter 4 " Satuan / Unit : M'
Analisa : A.5.1.1.32

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.081 84,150.00 6,816.15
2 Tukang OH 0.135 107,100.00 14,458.50
3 Kepala Tukang OH 0.0135 126,225.00 1,704.04
4 Mandor OH 0.004 95,625.00 382.50
Jumlah Tenaga Kerja 23,361.19
B. BAHAN
1 PVC 4" M 1.20 42,525.76 51,030.91
2 Perlengkapan % 35.00 510.31 17,860.82
Jumlah Bahan 68,891.72
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan ( A + B + C ) 92,252.91
E Overhead & Profit 15% X D 13,837.94
F Harga Satuan Pekerjaan ( D + E ) 106,090.85
G Dibulatkan 106,091.00

42
BAB IV
HARGA BAHAN

DAFTAR HARGA SATUAN UPAH DAN BAHAN


BANGUNAN
UNTUK WILAYAH KOTA LANGSA TAHUN 2019
(PEMERINTAH KOTA)
No. URAIAN SATUAN HARGA ( Rp. )
1 2 3 4
A. UPAH
1 Pekerja OH 84,150.00
2 Tukang OH 107,100.00
3 Kepala tukang OH 126,225.00
4 Mandor OH 95,625.00

B. BAHAN
1 Air Ltr 153.00
2 Asbes Quality 1 x 1 M' Lbr / M2 23,954.55
3 Atap asbes Gelombang 8 kaki Lbr 74,954.55
4 Atap genteng metal 0.25 Lbr 70,009.09
5 Atap genteng metal 0.35 Lbr 87,511.37
6 Atap seng Onduline / Bitumen Bergelombang H : 38 mm T= Lbr 160,799.13
3 mm
7 Atap Spandek M2 72,866.25
8 Baja Ringan C75,75 (Setara Taso) Kg 12,583.33
9 Baja Ringan C75,100 (Setara Taso) Kg 15,687.50
10 Baja Profil Kg 44,972.73
11 Bak Air Fiber Sudut Bh 333,000.00
12 Batu Bata Bh 478.55
13 Batu Alam Hitam Tempel Bh 63,830.75
14 Batu Kali/Batu Belah (Sungai/Gunung) M3 382,500.00
15 Batu Pecah 2 - 3 cm Kg 240.40
16 Batu Pecah 2 - 3 cm M3 324,545.45
17 Batu Pecah 3 - 5 cm M3 317,204.55
18 Batu Pecah 5 - 7 cm M3 348,306.82
19 Baut Seng Metal Bh 1,081.82
20 Besi Beton Polos Kg 8,983.23
21 Besi Beton Ulir Kg 10,313.05
22 Besi Furing Plafoon M' 10,908.33
23 Cat Dasar Tembok Kg 43,834.50
24 Cat Kayu Dasar Kg 43,834.50
25 Cat Kayu Mengkilat (setara Venilex) Kg 51,038.63
26 Cat Lapangan Olahraga (setara Propan Tennokote) Kg 199,325.00
27 Cat Menie (Besi) Kg 37,485.00
28 Cat Menie (Kayu) Kg 39,015.00
29 Cat seng ( Stara Sanco ) Kg 89,327.27

43
30 Cat Tembok (setara Paragon) Kg 29,750.00
31 Calsyboard M2 67,729.55
32 Dempul kayu Kg 23,715.00
33 Doop penguras bak dari kuningan/Pengering Bak Bh 9,090.91
34 Engsel Jendela Bh 23,800.00
35 Engsel Pintu Bh 27,200.00
36 Flor Drain Stainlesteel Bh 24,534.09
37 Granit 60 x 60 (Kelas I) M2 324,545.45
38 Granit 60 x 60 (Kelas II) M2 214,818.18
39 Granit 60 x 60 (Kelas III) M2 95,818.18
40 Gypsum Board Bermotif (Stara Jaya Board) M2 101,594.32
41 Gypsum Board Polos (Stara Jaya Board) M2 67,729.55
42 Ijuk Ikat/M3 32,725.00
43 Instalasi Titik Lampu Titik 190,500.00
44 Kaca Bening Tebal 5 mm M2 99,166.66
45 Kaca Clear Tebal 5 mm ( Corak ) M2 153,000.00
46 Kaca Ryband Tebal 5 mm M2 108,611.11
47 Kait Angin jendela Bh 14,372.73
48 Kapur Kg 9,775.00
49 Kapur Batu Kg 8,925.00
50 Kawat Beton Kg 19,125.00
51 Kawat Duri Kg 17,425.00
52 Kawat Harmonika No. 14 M2 43,180.00
53 Kayu bakau Btg 20,825.00
54 Kayu Dolken Ø 8-10 Panjang 4 m Btg 55,250.00
55 Kayu kasau 5/7 M3 2,671,762.50
56 Kayu Klas I (Seumentok,Ulim) M3 8,847,875.25
57 Kayu Klas II (Leamper/Kruing/Dll) M3 6,502,500.00
58 Kayu Klas III (Sembarang keras) M3 4,972,500.00
59 Kayu Klas IV (Sengon) M3 3,513,262.50
60 Keramik 20 x 20 Cm (Stara Platinum) Bh 2,142.00
61 Keramik 25 x 25 Cm ( Stara Ikad ) Bh 3,758.01
62 Keramik 25 x 40 Cm ( Stara Sun Flower ) Bh 9,659.09
63 Keramik 30 x 30 Cm ( Setara Ikad) Bh 5,852.25
64 Keramik 40 x 40 Cm ( Setara Ikad) Bh 10,771.20
65 Keramik 60 x 60 Cm ( Setara Platinum) Bh 30,362.85
66 Kerikil Beton M3 240,975.00
67 Kerikil Beton Kg 178.50
68 Kertas Amplas Lbr 11,432.50
69 Klip BRC Bh 13,636.36
70 Kloset Duduk Stara American Standart Bh 956,250.00
71 Kloset Duduk Stara toto Bh 502,272.73
72 Kloset Jongkok Bh 229,500.00
73 Kran Diameter 3/4" atau 1/2" Bh 11,590.91

44
74 Kuas Bh 9,659.09
75 Kunci Tanam 2 Daun Bh 220,000.00
76 Kunci Tanam Biasa Bh 200,000.00
77 Kunci Tanam Silinder Bh 161,500.00
78 Lampu LED 18 Watt ( Stara Hannconh) Bh 35,700.00
79 Lampu SL 14 Watt ( Stara Hannconh) Bh 36,000.00
80 Lampu SL 18 Watt ( Stara Hannconh) Bh 40,500.00
81 Lampu SL 23 Watt ( Stara Hannconh) Bh 42,300.00
82 Lampu SL 42 Watt ( Stara Hannconh) Bh 58,500.00
83 Lem Kg 37,825.00
84 List Eternit Kayu M' 20,863.63
85 List Gypsum 12 Cm M' 3,863.63
86 Minyak Bekisting Ltr 13,175.00
87 Minyak Cat Ltr 21,636.37
88 Minyak Pelumas Ltr 48,681.82
89 Multipleks / Playwood 3 mm Lbr 52,043.18
90 Multipleks / Playwood 4 mm Lbr 63,788.63
91 Multipleks / Playwood 6 mm Lbr 88,322.73
92 Multipleks / Playwood 9 mm Lbr 122,670.45
93 Pacok Jendela / Pintu Bh 24,534.09
94 Paku Asbes Kg 27,200.00
95 Paku Kait Bh 2,163.63
96 Paku Kayu Kg 17,419.05
97 Paku Seng Kg 30,252.27
98 Paku Seng genteng Kg 13,522.73
99 Paku Ulir Bh 2,975.00
100 Panel BRC Uk 120 / 240 Cm Panel 222,159.09
101 Panel BRC Uk 90 / 240 Cm Panel 177,727.27
102 Pasir Beton M3 205,004.55
103 Pasir Beton Kg 146.43
104 Pasir Pasang M3 205,004.55
105 Pasir Urug M3 205,004.55
106 Paving Block segi enam ( 8 Cm ) M2 121,344.30
107 Paving Block segi enam (6 Cm) M2 69,445.00
108 Pegangan Pintu Double Bh 201,898.18
109 Pipa Galvanis 3 " Btg 314,500.00
110 Pipa Galvanis Kg 14,027.65
111 Pipa PVC Ø 1'' (Kualitas Aw) M' 7,360.23
112 Pipa PVC Ø 1 1/2'' ( Kualitas Aw ) M' 10,631.43
113 Pipa PVC Ø 1/2'' ( Kualitas AW) M' 4,089.02
114 Pipa PVC Ø 12'' ( Kualitas RRJ ) M' 122,421.89
115 Pipa PVC Ø 2'' ( Kualitas Aw) M' 17,991.66
116 Pipa PVC Ø 3'' ( Kualitas AW) M' 22,080.68
117 Pipa PVC Ø 3/4'' ( Kualitas Aw) M' 4,906.82

45
118 Pipa PVC Ø 4'' ( Kualitas AW) M' 42,525.76
119 Pipa PVC Ø 6'' ( Kualitas Aw ) M' 79,616.66
120 Plamur Kg 11,590.91
121 Plint Granit 10 x 60 Cm Bh 21,481.82
122 Rabung Atap Zincalum powder coating 30 / Spandek M' 23,375.00
123 Rabung genteng metal 0.25 Lbr 70,202.27
124 Rabung genteng metal 0.35 Lbr 87,752.84
125 Rabung Seng Lbr 56,950.00
126 Rabung/Nok seng Onduline / Bitumen Bergelombang H : 38 Lbr 86,020.00
mm T= 3 mm
127 Residu Ltr 13,175.00
128 Roll Cat Bh 15,454.55
129 Sabun Bh 15,454.55
130 Saklar Ganda ( Setara Brocco) Set 23,090.91
131 Saklar Triple ( Setara Brocco) Set 28,863.64
132 Saklar tunggal ( Setara Brocco ) Set 19,000.00
133 Seal Tape Bh 6,181.82
134 Semen keramik Kg 3,944.93
135 Semen Portland @ 40 Kg Kg 1,368.50
136 Semen putih / Warna Kg 1,453.50
137 Seng Bjls 0,20 (8 kaki) Lbr 56,950.00
138 Seng Plat Bjls 0,20 ( 8 Kaki ) Lbr 62,645.00
139 Seng Plat Genteng 0,35 ( 8 Kaki ) Lbr 87,752.84
140 Seng Plat Spandex 0,35 ( 8 Kaki ) M' 23,375.00
141 Sirtu M3 240,975.00
142 Soda Api Ltr 15,454.55
143 Solar Ltr 5,525.00
144 Stop Kontak + Instalasi Titik 165,000.00
145 Talang Air PVC M' 55,250.00
146 Tanah Pupuk M3 212,500.00
147 Tanah Timbun sungai M3 165,750.00
148 Tanah Timbunan Biasa ( tanpa batu ) M3 49,725.00
149 Tanah Timbunan Pilihan M3 87,975.00
150 Tarikan Jendela Bh 16,320.00
151 Tepung Gypsum Kg 21,250.00
152 Tiang BRC Type 120 Bh 88,636.36
153 Tiang BRC Type 90 Bh 67,954.55
154 Wastafel Cuci Piring/Bak Curi Piring Logam Bh 270,454.55
155 Wastafel Cuci Tangan Bh 463,636.37
156 Walpaper 50 Cm M' 31,875.00

46
BAB V
RENCANA ANGGARAN BIAYA

HARGA JUMLA
NO URAIAN PEKERJAAN VOLUME SATUAN ANALISA H
SATUA HARGA
N
(Rp.) (Rp.)
I PEKERJAAN
PERSIAPAN
1 Pembersihan Lapangan 265.36 m2 A. 2.2.1.9 Rp 15,176.00 Rp 4,027,103.36
2 Pemasangan Bowplank 207.58 M A. 2.2.1.4a Rp 121,608.00 Rp 25,243,388.64
SUBTOTAL Rp 29,270,492.00
SUBTOTAL PEKERJAAN I Rp 29,270,490.00
II PEKERJAAN TANAH
1 Galian Tanah Pondasi Menerus Type 1 33.97 m3 A.2.3.1.1 Rp 75,329.00 Rp 2,559,076.79
2 Urugan Kembali Type 1 8.49 m3 A.2.3.1.9 Rp 53,885.00 Rp 457,645.31
4 Galian Tanah Pondasi Menerus Type 2 15.15 m3 A.2.3.1.1 Rp 75,329.00 Rp 1,141,422.67
5 Urugan Kembali Type 2 3.79 m3 A.2.3.1.9 Rp 53,885.00 Rp 204,123.12
6 Galian Tanah Pondasi Tapak Type 1 22.97 m3 A.2.3.1.1 Rp 75,329.00 Rp 1,730,156.47
7 Urugan Kembali Type 1 5.74 m3 A.2.3.1.9 Rp 53,885.00 Rp 309,407.67
8 Galian Tanah Pondasi Tapak Type 2 10.44 m3 A.2.3.1.1 Rp 75,329.00 Rp 786,434.76
9 Urugan Kembali Type 2 2.61 m3 A.2.3.1.9 Rp 53,885.00 Rp 140,639.85
10 Timbunan Tanah Pilihan 40.99 m3 A.2.3.1.11a Rp 151,537.00 Rp 6,211,804.70
SUBTOTAL Rp 13,540,711.34
SUBTOTAL PEKERJAAN II Rp 13,540,710.00

III PEKERJAAN PONDASI


1 Pondasi Menerus Type 1 11.92 m3 A.3.2.1.2 Rp 1,163,635.00 Rp 13,870,529.20
2 Lantai Kerja 3.58 m3 A.4.1.1.6 Rp 1,133,271.00 Rp 4,052,577.10
3 Pondasi Menerus Type 2 5.58 m3 A.3.2.1.2 Rp 1,163,635.00 Rp 6,495,992.39
4 Lantai Kerja 1.44 m3 A.4.1.1.6 Rp 1,133,271.00 Rp 1,626,810.52
5 Pondasi Tapak Type 1 3.3 m3 A.4.1.1.6 Rp 1,133,271.00 Rp 3,739,794.30
6 Lantai Kerja 1.58 m3 A.4.1.1.6 Rp 1,133,271.00 Rp 1,795,101.26
7 Pondasi Tapak Type 2 1.68 m3 A.4.1.1.6 Rp 1,133,271.00 Rp 1,903,895.28
8 Lantai Kerja 0.8 m3 A.4.1.1.6 Rp 1,133,271.00 Rp 906,616.80
9 Kolom Pedestal 40/30 2.77 m3 A.4.1.1.6 Rp 1,133,271.00 Rp 3,141,427.21
SUBTOTAL Rp 37,532,744.06
SUBTOTAL PEKERJAAN II Rp 37,532,740.00

IV PEKERJAAN BETON BERTULANG


A LANTAI 1
1 Pondasi Tapak Type 1 3.30 m3 A.4.1.1.6 Rp 1,133,271.00 Rp 3,739,794.30
2 Pondasi Tapak Type 2 1.68 m3 A.4.1.1.6 Rp 1,133,271.00 Rp 1,903,895.28
3 Balok Sloof 25/35 12.84 m3 A.4.1.1.6 Rp 1,133,271.00 Rp 14,546,949.87
4 Kolom Utama 40/30 4.69 m3 A.4.1.1.6 Rp 1,133,271.00 Rp 5,310,507.91
5 Kolom Praktis 13/13 Type 1 0.27 m3 A.4.1.1.6 Rp 1,133,271.00 Rp 302,606.02
6 Kolom Praktis 13/13 Type 2 0.73 m3 A.4.1.1.6 Rp 1,133,271.00 Rp 832,166.56
7 Balok Lantai 25/40 13.77 m3 A.4.1.1.6 Rp 1,133,271.00 Rp 15,605,141.67
8 Balok Latai 13/13 0.32 m3 A.4.1.1.6 Rp 1,133,271.00 Rp 358,147.63
9 Plat Lantai 20.50 m3 A.4.1.1.6 Rp 1,133,271.00 Rp 23,227,522.42
10 Tangga 1.33 m3 A.4.1.1.6 Rp 1,133,271.00 Rp 1,512,123.50
11 Plat Tangga 1.33 m3 A.4.1.1.6 Rp 1,133,271.00 Rp 1,512,123.50
12 Plat Bordes 0.97 m3 A.4.1.1.6 Rp 1,133,271.00 Rp 1,097,006.33
B LANTAI 2
1 Kolom Utama 40/30 Type 1 3.65 m3 A.4.1.1.6 Rp 1,133,271.00 Rp 4,136,439.15
2 Kolom Utama 40/30 Type 2 4.25 m3 A.4.1.1.6 Rp 1,133,271.00 Rp 4,816,401.75
3 Kolom Praktis 13/13 Type 1 3.65 m3 A.4.1.1.6 Rp 1,133,271.00 Rp 4,136,439.15
4 Kolom Praktis 13/13 Type 2 4.25 m3 A.4.1.1.6 Rp 1,133,271.00 Rp 4,816,401.75
13 Plat Dak 2.17 m3 A.4.1.1.6 Rp 1,133,271.00 Rp 2,459,198.07
14 Ring Balok 13/15 1.83 m3 A.4.1.1.6 Rp 1,133,271.00 Rp 2,077,285.74
15 Balok Latai 13/13 1.59 m3 A.4.1.1.6 Rp 1,133,271.00 Rp 1,800,314.31
SUBTOTAL Rp 88,546,775.33
SUBTOTAL PEKERJAAN II Rp 88,546,770.00

47
V PEKERJAAN BEKISTING
A LANTAI 1
1 Balok Sloof 25/35 12.84 m3 A.4.1.1.20a Rp 69,578.00 Rp 893,120.60
2 Kolom Utama 40/30 4.69 m3 A.4.1.1.22 Rp 130,660.00 Rp 612,272.76
3 Kolom Praktis 13/13 Type 1 0.27 m3 A.4.1.1.22 Rp 130,660.00 Rp 34,888.83
4 Kolom Praktis 13/13 Type 2 0.73 m3 A.4.1.1.22 Rp 130,660.00 Rp 95,944.29
5 Balok Lantai 25/40 13.77 m3 A.4.1.1.23 Rp 133,690.00 Rp 1,840,911.30
6 Balok Latai 13/13 0.32 m3 A.4.1.1.23 Rp 133,690.00 Rp 42,250.05
7 Plat Lantai 20.50 m3 A.4.1.1.24 Rp 129,465.00 Rp 2,653,514.64
8 Tangga 1.33 m3 A.4.1.1.24 Rp 129,465.00 Rp 172,745.15
9 Plat Tangga 1.33 m3 A.4.1.1.24 Rp 129,465.00 Rp 172,745.15
10 Plat Bordes 0.97 m3 A.4.1.1.24 Rp 129,465.00 Rp 125,322.12
B LANTAI 2
1 Kolom Utama 40/30 Type 1 3.50 m3 A.4.1.1.22 Rp 130,660.00 Rp 457,832.64
2 Kolom Utama 40/30 Type 2 5.10 m3 A.4.1.1.22 Rp 130,660.00 Rp 666,366.00
3 Kolom Praktis 13/13 Type 1 0.31 m3 A.4.1.1.22 Rp 130,660.00 Rp 40,298.81
4 Kolom Praktis 13/13 Type 2 0.72 m3 A.4.1.1.23 Rp 133,690.00 Rp 96,022.84
5 Plat Dak 2.17 m3 A.4.1.1.24 Rp 129,465.00 Rp 280,939.05
6 Ring Balok 13/15 1.83 m3 A.4.1.1.23 Rp 133,690.00 Rp 245,053.77
7 Balok Latai 13/13 1.59 m3 A.4.1.1.23 Rp 133,690.00 Rp 212,379.93
SUBTOTAL Rp 8,642,607.94
SUBTOTAL PEKERJAAN II Rp 8,642,600.00

VI PEKERJAAN
PEMBESIAN
A LANTAI 1
1 Pondasi Tapak Type 1 133.10 m1 A.4.1.1.17 Rp 13,258.00 Rp 1,764,639.80
2 Pondasi Tapak Type 2 96.80 m1 A.4.1.1.17 Rp 13,258.00 Rp 1,283,374.40
3 Kolom Pedestal 30/40 13.31 m1 A.4.1.1.17 Rp 13,258.00 Rp 176,463.98
4 Balok Sloof 25/35 1775.07 m1 A.4.1.1.17 Rp 13,258.00 Rp 23,533,878.06
5 Kolom Utama 40/30 42.96 m1 A.4.1.1.17 Rp 13,258.00 Rp 569,497.39
6 Kolom Praktis 13/13 Type 1 9.80 m1 A.4.1.1.17 Rp 13,258.00 Rp 129,875.37
7 Kolom Praktis 13/13 Type 2 9.80 m1 A.4.1.1.17 Rp 13,258.00 Rp 129,875.37
8 Balok Lantai 25/40 1666.17 m1 A.4.1.1.17 Rp 13,258.00 Rp 22,090,081.86
9 Balok Latai 13/13 46.38 m1 A.4.1.1.17 Rp 13,258.00 Rp 614,853.01
10 Plat Lantai 5763.63 m1 A.4.1.1.17 Rp 13,258.00 Rp 76,414,250.73
11 Tangga 99.83 m1 A.4.1.1.17 Rp 13,258.00 Rp 1,323,479.85
12 Plat Tangga 99.83 m1 A.4.1.1.17 Rp 13,258.00 Rp 1,323,479.85
13 Plat Bordes 59.29 m1 A.4.1.1.17 Rp 13,258.00 Rp 786,066.82
B LANTAI 2 0.00 m1
1 Kolom Utama 40/30 Type 1 35.33 m1 A.4.1.1.17 Rp 13,258.00 Rp 468,431.66
2 Kolom Utama 40/30 Type 2 51.43 m1 A.4.1.1.17 Rp 13,258.00 Rp 681,792.65
3 Kolom Praktis 13/13 Type 1 11.32 m1 A.4.1.1.17 Rp 13,258.00 Rp 150,014.27
4 Kolom Praktis 13/13 Type 2 26.35 m1 A.4.1.1.17 Rp 13,258.00 Rp 349,348.30
5 Plat Dak 30.44 m1 A.4.1.1.17 Rp 13,258.00 Rp 403,600.04
6 Ring Balok 13/15 116.81 m1 A.4.1.1.17 Rp 13,258.00 Rp 1,548,640.46
7 Balok Latai 13/13 53.07 m1 A.4.1.1.17 Rp 13,258.00 Rp 703,628.58
SUBTOTAL Rp 134,445,272.44
SUBTOTAL PEKERJAAN II Rp 134,445,270.00

VII PEKERJAAN PEMBESIAN BEGEL


A LANTAI 1
3 Kolom Pedestal 30/40 0.23 m1 A.4.1.1.17 Rp 13,258.00Rp 3,094.10
4 Balok Sloof 25/35 21.02 m1 A.4.1.1.17 Rp 13,258.00Rp 278,633.34
5 Kolom Utama 40/30 0.75 m1 A.4.1.1.17 Rp 13,258.00Rp 9,985.50
6 Kolom Praktis 13/13 Type 1 0.05 m1 A.4.1.1.17 Rp 13,258.00Rp 667.18
7 Kolom Praktis 13/13 Type 2 0.05 m1 A.4.1.1.17 Rp 13,258.00Rp 667.18
8 Balok Lantai 25/40 23.13 m1 A.4.1.1.17 Rp 13,258.00Rp 306,632.24
9 Balok Latai 13/13 0.24 m1 A.4.1.1.17 Rp 13,258.00Rp 3,158.56
B LANTAI 2 Rp -
1 Kolom Utama 40/30 Type 1 0.12 m1 A.4.1.1.17 Rp 13,258.00 Rp 1,540.02
2 Kolom Utama 40/30 Type 2 0.14 m1 A.4.1.1.17 Rp 13,258.00 Rp 1,793.17
3 Kolom Praktis 13/13 Type 1 0.01 m1 A.4.1.1.17 Rp 13,258.00 Rp 92.48
4 Kolom Praktis 13/13 Type 2 0.01 m1 A.4.1.1.17 Rp 13,258.00 Rp 107.68
6 Ring Balok 13/15 0.12 m1 A.4.1.1.17 Rp 13,258.00 Rp 1,534.28
7 Balok Latai 13/13 0.04 m1 A.4.1.1.17 Rp 13,258.00 Rp 542.19
SUBTOTAL Rp 608,447.92
SUBTOTAL PEKERJAAN II Rp 608,440.00

48
VIII PEKERJAAN
PASANGAN
A LANTAI 1
1 Pasangan Bata 1 : 4 292.83 m2 A.4.4.1.3 Rp 229,654.00 Rp 67,248,432.55
2 Pasangan Bata 1 : 2 63.07 m2 A.4.4.1.7 Rp 121,754.00 Rp 7,679,024.78
3 Plesteran 10.68 m2 A.4.4.2.2 Rp 72,139.00 Rp 770,217.28
B LANTAI 2
1 Pasangan Bata 1 : 4 343.10 m2 A.4.4.1.3 Rp 229,654.00 Rp 78,794,287.40
2 Pasangan Bata 1 : 2 28.20 m2 A.4.4.1.7 Rp 121,754.00 Rp 3,433,462.80
3 Plesteran 11.14 m2 A.4.4.2.2 Rp 72,139.00 Rp 803,556.32
SUBTOTAL Rp 158,728,981.13
SUBTOTAL PEKERJAAN II Rp 158,728,980.00

IX PEKERJAAN LANTAI
A LANTAI 1
1 Cor Lantai 1 : 3 : 5 11.956 m3 A.4.1.1.6 Rp 1,133,271.00 Rp 13,549,388.08
2 Pasir Urug 8.54 m3 A.2.3.1.9 Rp 313,038.00 Rp 2,673,344.52
3 Granit 60 X 60 cm 170.80 m2 A.4.4.3.13a Rp 328,865.00 Rp 56,170,142.00
4 Dinding Keramik 25 x 40 Cm 6.00 m2 A.4.4.3.54a Rp 298,315.00 Rp 1,789,890.00
5 Spesi 5.124 m3 A.4.4.2.2 Rp 72,139.00 Rp 369,640.24
B LANTAI 2
1 Cor Lantai 1 : 3 : 5 10.86 m3 A.4.1.1.6 Rp 1,133,271.00 Rp 12,308,682.99
2 Granit 60 X 60 cm 155.16 m2 A.4.4.3.13a Rp 328,865.00 Rp 51,026,693.40
3 Dinding Keramik 25 x 40 Cm 6.00 m2 A.4.4.3.54a Rp 298,315.00 Rp 1,789,890.00
4 Spesi 4.65 m3 A.4.4.2.2 Rp 72,139.00 Rp 335,792.62
SUBTOTAL Rp 140,013,463.83
SUBTOTAL PEKERJAAN II Rp 140,013,460.00

X PEKERJAAN KAYU DAN KUSEN


A LANTAI 1
1 Kosen Pintu Dan Jendela
a Pintu Type 1
Kosen Pintu 0.0835 m3 A.4.6.1.1 Rp 14,868,296.00 Rp 1,241,502.72
Daun Pintu 6.16 m2 A.4.6.1.6a Rp 677,756.00 Rp 4,174,976.96
b Pintu Type 2
Kosen Pintu 0.0945 m3 A.4.6.1.1 Rp 14,868,296.00 Rp 1,405,053.97
Daun Pintu 5.28 m2 A.4.6.1.6a Rp 677,756.00 Rp 3,578,551.68
c Pintu Type 3
Kosen Pintu 0.078 m3 A.4.6.1.1 Rp 14,868,296.00 Rp 1,159,727.09
Daun Pintu 4.62 m2 A.4.6.1.6a Rp 677,756.00 Rp 3,131,232.72
d Jendela Type !
Kosen Jendela 0.148 m3 A.4.6.1.1 Rp 14,868,296.00 Rp 2,200,507.81
Daun Jendela 8.2 m2 A.4.6.1.6a Rp 677,756.00 Rp 5,557,599.20
B LANTAI 2
1 Kosen Pintu Dan Jendela
a Pintu Type 1
Kosen Pintu 0.0835 m3 A.4.6.1.1 Rp 14,868,296.00 Rp 1,241,502.72
Daun Pintu 6.16 m2 A.4.6.1.6a Rp 677,756.00 Rp 4,174,976.96
b Pintu Type 2
Kosen Pintu 0.063 m3 A.4.6.1.1 Rp 14,868,296.00 Rp 936,702.65
Daun Pintu 3.52 m2 A.4.6.1.6a Rp 677,756.00 Rp 2,385,701.12
c Pintu Type 3
Kosen Pintu 0.052 m3 A.4.6.1.1 Rp 14,868,296.00 Rp 773,151.39
Daun Pintu 3.08 m2 A.4.6.1.6a Rp 677,756.00 Rp 2,087,488.48
d Jendela Type 1
Kosen Jendela 0.296 m3 A.4.6.1.1 Rp 14,868,296.00 Rp 4,401,015.62
Daun Jendela 16.4 m2 A.4.6.1.6a Rp 677,756.00 Rp 11,115,198.40
2 Kayu Kuda -Kuda
Kuda - Kuda 2/4" 0.1965 m2 A.4.6.1.13a Rp 13,365,995.00 Rp 2,626,418.02
Gording 2/2" 0.646 m2 A.4.6.1.13a Rp 13,365,995.00 Rp 8,634,432.77
Balok Gantung 2/4" 0.0156 m2 A.4.6.1.13a Rp 13,365,995.00 Rp 208,509.52
Balok Angin 2/4" 0.045 m2 A.4.6.1.13a Rp 13,365,995.00 Rp 601,469.78
Balok Gapit 2/4" 0.181 m2 A.4.6.1.13a Rp 13,365,995.00 Rp 2,419,245.10
Balok Tarik 2/4" 0.048 m2 A.4.6.1.13a Rp 13,365,995.00 Rp 641,567.76
Balok Bubungan 2/3" 0.0105 m2 A.4.6.1.13a Rp 13,365,995.00 Rp 140,342.95
Balok Sokong 2/4" 0.27 m2 A.4.6.1.13a Rp 13,365,995.00 Rp 3,608,818.65
SUBTOTAL Rp 45,996,541.87
SUBTOTAL PEKERJAAN II Rp 45,996,540.00

49
XI PEKERJAAN ATAP DAN PLAFOND
1 Atap Genteng Metal 226.69 m2 A.4.5.2.32 Rp 118,463.00 Rp 26,854,377.47
2 Rabung Atap Genteng Metal 29.36 m2 A.4.5.2.36 Rp 135,858.00 Rp 3,988,790.88
A Lantai 1
1 Plafond Gypsum 170.80 m2 A.4.5.1.7a Rp 63,612.00 Rp 10,864,929.60
B Lantai 2
1 Plafond Gypsum 155.16 m2 A.4.5.1.7a Rp 63,612.00 Rp 9,870,037.92
SUBTOTAL Rp 51,578,135.87
SUBTOTAL PEKERJAAN II Rp 51,578,130.00

XII PEKERJAAN INSTALASI LISTRIK


A Lantai 1
1 Lampu LED 18 Watt 10 Bh Rp 148,500.00 Rp 1,485,000.00
2 Lampu LED 14 Watt 21 Bh Rp 148,500.00 Rp 3,118,500.00
3 Stop 21 Bh Rp 128,500.00 Rp 2,698,500.00
Kontak
4 Saklar Tunggal 5 Bh Rp 125,000.00 Rp 625,000.00
5 Saklar 6 Bh Rp 125,000.00 Rp 750,000.00
Ganda
6 Kabel 20 M Rp 135,800.00 Rp 2,716,000.00
7 Box Sekring 1 Bh Rp 810,000.00 Rp 810,000.00
B Lantai 2
1 Lampu LED 18 Watt 9 Bh Rp 148,500.00 Rp 1,336,500.00
2 Lampu LED 14 Watt 27 Bh Rp 148,500.00 Rp 4,009,500.00
3 Stop 22 Bh Rp 128,500.00 Rp 2,827,000.00
Kontak
4 Saklar Tunggal 5 Bh Rp 125,000.00 Rp 625,000.00
5 Saklar 6 Bh Rp 125,000.00 Rp 750,000.00
Ganda
6 Kabel 20 M Rp 135,800.00 Rp 2,716,000.00
SUBTOTAL Rp 24,467,000.00
SUBTOTAL PEKERJAAN II Rp 24,467,000.00

XIII PEKERJAAN KUNCI DAN PENGGANTUNG


1 Kunci Tanam Pintu 18 Bh A.4.6.2.2 Rp 300,358.00 Rp 5,406,444.00
2 Engsel Pintu 66 Bh A.4.6.2.5 Rp 53,472.00 Rp 3,529,152.00
3 Kunci Pacok Jendela 20 Bh A.4.6.2.11 Rp 57,796.00 Rp 1,155,920.00
4 Engsel Jendela 40 Bh A.4.6.2.6 Rp 42,161.00 Rp 1,686,440.00
5 Hak angin Jendela 40 Bh A.4.6.2.9 Rp 39,512.00 Rp 1,580,480.00
6 Pekerjaan Kaca Jendela Dan ventilasi 12.6 m2 A.4.6.2.17 Rp 148,006.00 Rp 1,864,875.60
SUBTOTAL Rp 15,223,311.60
SUBTOTAL PEKERJAAN II Rp 15,223,310.00

XIV PEKERJAAN SANITASI DAN INSTALASI AIR


A Air Kotor
1 Pipa PVC 27 M A.5.1.1.31 Rp 68,002.00 Rp 1,836,054.00
3"
2 Resapan 1 Bh Rp 7,237,461.79 Rp 7,237,461.79
3 SapticTank 1 Bh Rp 442,217.00 Rp 442,217.00
4 Bak Kontrol 2 Bh A.5.1.1.15b Rp 525,425.00 Rp 1,050,850.00
B Air Bersih
1 Pipa PVC 3/4" 39 M A.5.1.1.26 Rp 21,106.00 Rp 823,134.00
2 Kran Air 12 Bh A.5.1.1.19 Rp 33,148.00 Rp 397,776.00
3 Kloset 4 Bh A.5.1.1.1a Rp 1,086,148.00 Rp 4,344,592.00
Duduk
4 Floor Drain 4 Bh A.5.1.1.14 Rp 43,500.00 Rp 174,000.00
5 Washtafel 2 Bh A.5.1.1.5 Rp 1,172,819.00 Rp 2,345,638.00
SUBTOTAL Rp 18,651,722.79
SUBTOTAL PEKERJAAN II Rp 18,651,720.00

XV PEKERJAAN
PENGECATAN
1 Pengecatan Dinding Lt 1 292.825 m2 A.4.7.1.10 Rp 26,208.00 Rp 7,674,357.60
2 Pengecatan Dinding LT 2 343.1 m2 A.4.7.1.10 Rp 26,208.00 Rp 8,991,964.80
3 Pengecatan Kosen Pintu Lt 0.256 m2 A.4.7.1.10 Rp 38,400.00 Rp 9,830.40
1
4 Pengecatan Daun Pintu Lt 1 16.06 m2 A.4.7.1.10 Rp 38,400.00 Rp 616,704.00
5 Pengecatan Kosen Pintu Lt 0.1985 m2 A.4.7.1.10 Rp 38,400.00 Rp 7,622.40
2
6 Pengecatan Daun Pintu Lt 2 12.76 m2 A.4.7.1.10 Rp 38,400.00 Rp 489,984.00
7 Pengecatan Kosen Jendela Lt 1 0.148 m2 A.4.7.1.10 Rp 38,400.00 Rp 5,683.20
8 Pengecatan Daun Jendela Lt 8.2 m2 A.4.7.1.10 Rp 38,400.00 Rp 314,880.00
1
9 Pengecatan Jendela Lt 2 0.296 m2 A.4.7.1.10 Rp 38,400.00 Rp 11,366.40
10 Pengecatan Daun Jendela Lt 16.4 m2 A.4.7.1.10 Rp 38,400.00 Rp 629,760.00
2
50
11 Pengecatan Lisplank 33.01 m2 A.4.7.1.10 Rp 38,400.00 Rp 1,267,587.84
12 Plafond Lt 1 170.80 m2 A.4.7.1.10a Rp 43,458.00 Rp 7,422,626.40
13 Plafond Lt 2 155.16 m2 A.4.7.1.10a Rp 43,458.00 Rp 6,742,943.28
SUBTOTAL Rp 34,185,310.32
SUBTOTAL PEKERJAAN II Rp 34,185,310.00

XVI PEKERJAAN FINISHING


1 Relief 84.32 M2 Rp 250,000.00 Rp 21,080,000.00
SUBTOTAL Rp 21,080,000.00
SUBTOTAL PEKERJAAN II Rp 21,080,000.00

51
BAB VI
REKAPITIULASI

PEMBUATAN RUMAH DUA LANTAI

NO. URAIAN PEKERJAAN JUMLAH TOTAL

I PEKERJAAN PERSIAPAN Rp 29,270,490.00


II PEKERJAAN TANAH Rp 13,540,710.00
III PEKERJAAN PONDASI Rp 37,532,740.00
IV PEKERJAAN BETON BERTULANG Rp 88,546,770.00
V PEKERJAAN BEKISTING Rp 8,642,600.00
VI PEKERJAAN PEMBESIAN Rp 134,445,270.00
VII PEKERJAAN PEMBESIAN BEGEL Rp 608,440.00
VIII PEKERJAAN PASANGAN Rp 158,728,980.00
IX PEKERJAAN LANTAI Rp 140,013,460.00
X PEKERJAAN KAYU DAN KUSEN Rp 45,996,540.00
XI PEKERJAAN ATAP DAN PLAFOND Rp 51,578,130.00
XII PEKERJAAN INSTALASI LISTRIK Rp 24,467,000.00
XIII PEKERJAAN KUNCI DAN PENGGANTUNG Rp 15,223,310.00
XIV PEKERJAAN SANITASI DAN INSTALASI AIR Rp 18,651,720.00
XV PEKERJAAN PENGECATAN Rp 34,185,310.00
XVI PEKERJAAN FINISHING Rp 21,080,000.00
JUMLAH Rp 822,511,470.00
PPN 10 % Rp 82,251,147.00
JUMLAH + PPN 10% Rp 904,762,617.00
DIBULATKAN Rp 904,762,000.00
Terbilang : Sembilan Ratus Empat Juta Tujuh Ratus Enam Puluh Dua Ribu Rupiah

52
BAB VII
KESIMPULAN

Rencana anggaran biaya (RAB) adalah banyaknya biaya yang di butuhkan baik upah maupun bahan dalam
sebuah pekerjaan proyek konstruksi seperti membangun gedung. Rencana anggaran biaya dibuat berdasarkan
uraian pekerjaan, RAB ini juga di hitung berdasarkan gambar kerja perencanaan karena setiap item pekerjaan
itu di hitung sesuai gambar kerja jika salah perhitungannya maka salah juga harga yanh akan di keluarkan. Maka
dari itu untuk menghitung RAB harus memiliki ketelitian yang akurat agar tidak salah.

53
LAMPIRAN

54
55
56
57
58
59
60
61
62
63
64

Anda mungkin juga menyukai