Anda di halaman 1dari 87

FEMA Benefit-Cost Analysis Re-engineering (BCAR)

Project Cost Guidance Methodology Report

Version 4.5 May 2009

Table of Contents
Purpose..................................................................................................................................................... 1 Introduction: Problem Statement .............................................................................................................. 1 Recommendations: Proposed Methodology to Address Problem Statement ............................................. 2 Section 1: Cost Estimating Methodology Programming and User Overview............................................. 4 Step 1: Developing an Estimate of Pre-Construction Costs ....................................................................... 8 Step 2: Developing an Estimate of Construction Costs ............................................................................. 8 Step 3: Developing an Estimate of Ancillary Costs.................................................................................... 9 Step 4: Developing an Estimate of Annual Maintenance Costs ............................................................... 10 Step 5: Adjusting Your Estimate to Account for Project Timing .............................................................. 10 Step 6: Review and Confirmation of the Estimate .................................................................................. 12 Section 2 Provide Specific Guidance...................................................................................................... 14 Section 3 Benefit-Cost Analysis Handout Tool ....................................................................................... 15 Conclusions: Reasons for Selection of Proposed Methodology ................................................................ 16 APPENDIX A: Mitigation Strategy Flow Charts.......................................................................................... 17 APPENDIX B: Sample Estimates................................................................................................................ 34 APPENDIX C: Cost Estimating Storyboard................................................................................................ 67 Sample BCA Tool Cost Estimating Screenshot .......................................................................................... 68 APPENDIX D: Scope Builder Checklists ..................................................................................................... 69

Tables
Table 1. Proposed Hazard Mitigation Project Types ................................................................................. 2 Table 2. Recommended Proxy Values ...................................................................................................... 9 i

ii

Purpose
This Benefit-Cost Analysis Re-engineering (BCAR) report is provided for use by the Federal Emergency Management Agency (FEMA) Technical Advisory Group (TAG) to review and approve the recommended methodology to provide project cost guidance for the FEMA benefit-cost analysis (BCA) modules. The methodology report is part of a larger effort to re-engineer the FEMA BCA methods, modules, guidance, and training to improve the BCA process.

Introduction: Problem Statement


The BCA modules were developed to calculate project benefits and project costs as part of the effort to evaluate the cost-effectiveness of proposed hazard mitigation projects. However, since project benefits are more difficult to determine than project costs, the FEMA BCA modules and guidance devote most of their efforts to estimating and documenting project benefits. As a result, there is little guidance provided on how to properly and completely estimate and document project costs used in the BCA modules. For this reason, many applicants submit BCAs with project costs that are incomplete, inaccurate, or poorly documented. In response to this problem, FEMA Headquarters has requested that additional guidance be provided to assist applicants with the preparation of complete and well-documented project costs as part of the BCAR initiative. Specifically, additional guidance was requested on the following five project cost estimate issues: 1. What hard construction and ancillary costs related to a variety of mitigation project types are acceptable? 2. Should contingencies and allowances for change orders be accounted for in project cost estimates? 3. What are the acceptable sources of data for the mitigation project cost estimates? 4. What is an appropriate level of detail to be included in a mitigation project cost estimate? 5. Can we provide helpful hints and defined values to help the grant applicant develop complete and accurate cost estimates? At present, the inclusion of contingencies and allowances for change orders is not being considered by the mitigation directorate; these items are more relevant to FEMAs Public Assistance Program, and are not applicable to the majority of mitigation projects being considered. Specifically, the URS BCA team has been asked to address 16 specific mitigation project cases comprised of five hazards (flood, wind, earthquake, landslide, and wildfire) and two to five project types per hazard, including structural and non-structural mitigation alternatives, as shown in Table 1. While the estimating methodology is applicable to additional hazards and project types, sample scope items, 1

estimating flowcharts, and sample estimates are only provided for the 16 specific mitigation project cases shown in Table 1. Any project types that do not fit into the 16 defined types shall be defined as other.
Table 1. Proposed Hazard Mitigation Project Types

Hazard Flood

Mitigation Project Type Acquisition Elevation Relocation Wet and dry floodproofing/floodwalls Drainage structures (culverts, storm drains, etc.) A combination of strengthening load path members and connections and adding shutters/impact-resistant glazing Tornado safe rooms Strengthen structural elements Anchor/brace non-structural elements Retaining structures (gabions, piles, mechanically stabilized earth systems, etc.) Toe erosion armoring Surface/subsurface drainage improvements Bio-engineered surface erosion protection Vegetation control (including fire breaks around critical facilities/roads) Fire-resistant roofing Fire suppression

Wind Earthquake Landslide

Fire

Recommendations: Proposed Methodology to Address Problem Statement


To address the problem of inadequate project cost estimates as well as the project cost estimate issues raised by the BCAR initiative, the URS BCA team proposes the following methodology to provide expanded cost estimating guidance: Our efforts focused on three main areas: 1. Guidance on how to develop a complete estimate is presented in the 16 hazard/mitigation project type flow charts and sample estimates provided in Appendices A and B. These flow charts and sample estimates are further supported by definitions and references contained in the help area of the BCAR tool. 2. An overall estimating approach that walks the users through a six step process designed to help account for construction and non-construction related costs associated with a mitigation project. This process is defined and outlined in the storyboard presented in Appendix C. 2

3. A Scope Builder Checklist is designed for reference by Applicants/subapplicants prior to their use of the BCA cost estimating tool. This Handout will provide guidance to assist in the preparation of an effective scope of work and will assist the preparer in the identification and collection of the cost information needed to use the BCA module. The Checklists are provided in Appendix D.

Section 1: Cost Estimating Methodology Programming and User Overview


The critical part of developing an accurate cost estimate is having a defined scope of work that itemizes the specific work elements (tasks) that will be accomplished as part of the mitigation project. Once these specific work elements are defined they can be translated into work element descriptions for which quantities and unit prices can be estimated. The flow charts, sample estimates, and scope builder tables provided in Appendices A, B, and D offer guidance and suggestions as to typical work elements associated with the various mitigation measures. Those resources are not intended to be all inclusive, and each mitigation project may have different and unique elements that must be included in the scope of work and cost estimate. An estimate can be developed in a variety of ways, but most estimates fall into the following categories: 1. Published unit price information for defined work elements can be obtained from commercial estimating sources such as RS Means and Marshall & Swift. This information is copyrighted and users typically purchase the right to use their information. Note that these published cost sources are regularly updated and if the estimate is prepared using old unit price information, the estimate should be updated to reflect current pricing. 2. Historical Costs for completing the similar projects can be obtained from local contractors, building officials, State hazard mitigation officers, and project owners. Note that these historical costs should be escalated to ensure current pricing. 3. Contractor Bids or estimates for completing a specific scope of work or project are typically completed at the time of the bid and account for inflation over the course of the project. The accuracy of each of these estimates will vary according to the level of detail in the scope of work and work elements to be estimated. Preliminary estimates are applicable for initial project screening or scoping, but detailed costs estimates should be used when submitting project applications for funding approvals. The cost estimating portion of the BCA methodology shall use a step by step process of simple inquiries, dynamic help screens, and input boxes to walk users through the six steps associated with developing a complete cost estimate for their mitigation project. This six-step process outlined below follows the users selection of a hazard and mitigation strategy and consists of: 1. Developing an estimate of pre-construction or non-construction costs 2. Developing an estimate of construction costs 3. Developing an estimate of ancillary costs 4. Developing an estimate of annual maintenance costs 4

5. Adjusting the estimate to account for project timing and currency of the data used in the estimate 6. Reviewing and confirming the cost estimate At any time during this process users can input a previously completed estimate, an explanation of their estimating approach, and their estimate file (spreadsheet). Each step in that process is explained and illustrated in the following paragraphs. Prior to entering the cost estimation portion of the BCAR tool, users will have chosen a hazard mitigation strategy and defined a mitigation project type for a specific structure. The initial cost estimation screen will pre-populate the project and structure names and the mitigation option will be displayed for reference. At this point users will be asked to: verify the projects useful life in years; verify that a detailed scope of work has been developed; and answer whether or not a detailed cost estimate has already been developed for the project.

Depending on the answers to the above questions, users will be prompted to input a completed estimate, explanation/justification, and upload their file or they will be directed to the estimating tool. This process is presented in screen shot CE1 of the BCAR cost estimating storyboard shown in Appendix C. As noted in screen shots CE2 and CE3 of the storyboard, if a completed estimate is input (rather than built), users will be queried to ensure that the estimate includes applicable construction markups and that it reflects current pricing. If it does not include those items, users will be led through a process of adding them to their previously completed estimate. Once users have selected the option of developing a detailed cost estimate, they will follow the six-step process outlined above as they develop their project cost estimate.

Step 1: Developing an Estimate of Pre-Construction Costs

In this section, users will be asked to develop an estimate of all pre-construction costs associated with the mitigation project. Pre-construction costs are also called non-construction costs and may include those non-construction costs an owner incurs in the planning, permitting, and management of a mitigation project. For example, pre-construction costs for an acquisition project may include the costs for property surveys, property appraisal fees, transaction and legal fees, the cost to purchase property and improvements, and the cost of professional services needed for environmental or engineering assessments and/or managing the process. This process is presented in screen shot CE2a of the BCAR cost estimating storyboard shown in Appendix C. As noted in the two screen shots, users can enter a lump sum amount (if a completed estimate is available) or they can use the cost tool to develop their estimate by building on the pre-populated cells. In all cases, flexibility is built into the cost estimating tool to allow users to input specific work elements that are applicable to their mitigation project rather than use the default line items that were developed for each of the 16 mitigation project types. Within the cost estimating tool, the column format is consistent across all six steps. Each template has a description of the work element, followed by a box to check the source of the unit pricing used (i.e., published data, historical data, or contractor data), the quantity and unit associated with each work element, the unit cost of the work and a task cost, which is the product of the quantity and the unit cost. Additional rows can be added to introduce work elements that were not included in the default format.

Step 2: Developing an Estimate of Construction Costs

In this section, users will be asked to develop an estimate of all hard construction costs associated with the mitigation project. Hard construction costs are costs associated with the actual physical altering of the property or structure. In the acquisition example, costs associated with site demolition might include the removal of hazardous materials, general demolition activities, well and septic abandonment, utility disconnections, and utility removals. This process is presented in screen shot CE2b of the BCAR cost estimating storyboard shown in Appendix C. As noted in the two screen shots, users can enter a lump sum amount (if a completed estimate is available) or they can use the cost tool to develop their estimate by building on the pre-populated cells. In all cases, flexibility is built into the cost estimating tool to allow users to input specific work elements that are applicable to their mitigation project rather than use the default line items that were developed for each of the 16 mitigation project types. Within the cost estimating tool, the column format is consistent across all six steps. Each template has a description of the work element, followed by a box to check the source of the unit pricing used (i.e., published data, historical data, or contractor data), the quantity and unit associated with each work element, the unit cost of the work and a task cost, which is the product of the quantity and the unit cost. Additional rows can be added to introduce work elements that were not included in the default format.

Step 3: Developing an Estimate of Ancillary Costs

Once users input a detailed construction cost estimate, they will be queried to ensure that all general construction and ancillary costs have been accounted for. Specifically, users will be asked if their unit prices/costs have accounted for any of the following cost elements: A/E Costs associated with project design and construction administration General Contractor costs for general requirements and general conditions General Contractor costs for overhead and profit Project management costs associated with executing the project Permit fees, testing costs, and plan approval fees Mobilization and Demobilization costs Depending upon the answer to each of the above questions, users will be asked to include those costs in their estimate. This can be accomplished in two ways. First, users can revisit their pre-construction and construction costs and add a line item for the ancillary costs not previously included. Alternatively, they can use industry standard proxy values as shown below in Table 2. These specific value ranges are referenced using RS Means construction cost data as a resource. However, other national cost data sources have similar values.
Table 2. Recommended Proxy Values

Cost Element Mobilization and Demobilization Construction General Conditions and Requirements (i.e., costs associated with a general contractors field supervision costs and job site costs, such as temporary services and utilities, safety and security measures, quality control, and administrative submittals) General Contractor Overhead Costs, Insurance Costs and Payment/Performance Bond Costs, and Profit

3% of the hard construction cost 10% of the hard construction cost

Proxy Value

Architectural and Engineering Services to cover the cost of basic design and inspection services normally associated with a construction project, such as preliminary engineering analysis, preliminary design, final design, and construction inspection.

10-20% of the hard construction cost 10% of the hard construction cost

Project Management costs to cover the applicant costs to manage the project during the evaluation, design, permitting, coordination, and construction phases

4% of the hard construction cost

This process is presented in the BCA Tool screen shot shown in Appendix C. As noted in the screen shots, the users can select a proxy value that will be included in the mitigation project estimate.

Step 4: Developing an Estimate of Annual Maintenance Costs

The cost of maintaining mitigation measures is often not accounted for in mitigation cost estimates. If maintenance is required for the proper and effective implementation of the mitigation measure, it should be included in the cost estimate. In this section, the users will be asked to develop an estimate of the annual maintenance costs necessary for the proper and effective implementation of the mitigation project and to identify the number of years maintenance will be required (which is typically the project useful life). The software will then calculate the present worth of the annual maintenance costs and add that value to the project cost. This process is presented in screen shot CE3 of the BCAR cost estimating storyboard shown in Appendix C.

Step 5: Adjusting Your Estimate to Account for Project Timing

In this section, the users will be asked if the estimate reflects current prices. Price currency is a function of two separate issues. First, was the estimate prepared using current pricing data and second, was the estimate escalated to the midpoint of construction to account for anticipated inflation in labor, materials, and equipment over the term of the construction project. With regard to the current pricing question, historical data must be escalated to todays values and published data may vary based on the date of the published source. With regard to the issue of inflation over the course of a project, the issue is the length of time between when the estimate was developed and the start/completion of construction. Estimates are typically escalated to the midpoint of construction to account for the inflation that will occur over the project lifecycle (design, bidding, and construction). As noted in screen CE3 of the storyboard (Appendix C), users will be asked if their estimate reflects current prices and if not, they will be asked to input information on the type of construction project, the cost basis year, the construction start year and the construction end year. The software will calculate the escalation according to the methodology described in the following paragraphs. The escalation is based on a computed 5-year annual building construction escalation rate for each FEMA Region based on Engineering News Record Building Cost Index for cities within each region. The 5-year average annual escalation used in this step is based on index values from December 2002 to December 2007. The recommended escalation factors are provided in the following table.

10

FEMA Region(s) 1 2 3 4 and 10 5 6 and 9 7 8

2002 - 2007 Average Annual Escalation Rate 6.4% 3.9% 5.0% 4.3% 4.4% 4.9% 5.4% 5.2%

We recommend that the escalation factors be used to escalate cost data from the date of its source to the anticipated mid-point of construction of the proposed project. Escalation can be calculated using the formula: EC = PC*(1+E)N Where EC = Escalated cost PC = Present cost E = Escalation rate N = Estimated number of years from data date of date source to midpoint of construction Project schedules must indicate reasonable periods for project design, bid and contract award and construction. Cost data should be escalated to the estimated mid-point of construction. The mid-point of construction is calculated as the time for design, bid and contract award plus one-half the construction period. Based on the precision of the data, including proposed project schedules, we recommend that times to mid-point of construction be rounded upward to the next full year for escalation purposes Project schedules should be developed by experienced project and construction professionals. However, a general guide to estimating project timelines as a function of project construction cost is provided on the following table.
Design & Construction Monthly Expenditure Ramp-up and closeRate Assumptions out time Design Fee < $50,000 $ 15,000 2 Months Fee > $50,000 $ 35,000 4 Months Construction Estimate <$500,000 2 Months $ 125,000 $500,000 to $1 Million 3 Months $ 200,000 $1 to $5 million 4 Months $ 350,000 > $5 million $ 500,000 6 Months

11

Example 1: A proposed drainage mitigation project located in FEMA Region 3 is identical to a project completed by the applicant in 2005. The proposed project is scheduled for completion by the end of 2010. The project cost in 2005 was $300,000 plus $30,000 design and construction inspection fees. Estimated Schedule: Design fee approx. $30,000 Design time = ($30,000/$15,000 per month) + 2 months = 4 months Construction cost = $300,000 Construction time = ($300,000/125,000) + 2 months = 4.4 months Time to mid-point of construction = 4 months design + (4.4 months construction/2) = 6.2 months. Round up to 1 year from start of design. Escalated Project Cost Estimated project start data January 2009 Escalation period = (Estimated start date + Time to midpoint of construction) Data source year (2009 + 1) 2005 = 5 years EC = ($330,000)*(1+0.05) 5 EC = $421,173

Example 2: The $1,750,000 construction cost estimate for a proposed relocation in FEMA Region 6 is based on 2008 published construction cost data. The estimated design and construction inspection fee is $175,000. The project is expected to be completed in 2011. Estimated Schedule Design fee $175,000 Design time = ($175,000/$35,000 per month) + 4 months = 9 months Construction cost = $1,750,000 Construction time = ($1,750,000/$350,000 per month) + 4 months = 9 months Time to midpoint of construction = 9 months design + (9 months construction/2) = 13.5 months. Use 2 years from start of design. Escalated Project Cost Estimated project start January 2009 Escalation period = (Estimated start date + Time to midpoint of construction) Data source year (2009 + 2) 2008 = 3 years EC = (1,925,000)*(1+0.049)3 EC = $2,222,067

Step 6: Review and Confirmation of the Estimate

Finally, users will be required to certify that their cost estimate is complete and includes all costs associated with the mitigation project scope of work. Queries should require the users to be instructed to: Compare each item in the cost estimate with the scope of work to make certain that all work necessary to complete the project has been included 12

Review the unit and quantity of each item to confirm accuracy of the total costs Assure that items that have been presented as lump sums are appropriate and cannot be readily broken into units, and Accept the following certification language by checking a box and entering the preparers name: Information provided in this section has been reviewed and found to be complete. The information represents a full and complete description of the components of the project scope of work and associated costs.

13

Section 2 Provide Specific Guidance


The flow charts provided in Appendix A lead the estimator through specific steps in developing a cost estimate that is consistent with the scope of work, transparent, and contains only the appropriate lump sum items. To assist the estimator in developing a complete and comprehensive cost estimate, the following specific guidance will be provided within the cost portion of the BCAR effort. Estimating process flow charts: Appendix A provides 16 cost estimation process flow charts that detail the general steps required in developing reliable estimates, and offer specific suggestions for each hazard and mitigation combination identified in Table 1. These estimating process flow charts are designed to be referenced in Step 1 of the cost estimating process, and provide users with a road map for developing a valid cost estimate. See Figures 1-16 in Appendix A. Sample estimate template: A sample cost estimate will be prepared for each of the 16 hazard mitigation project types covered in Table 1. These estimates are designed to be referenced during each step of the cost estimating process, providing the users with a typical approach to developing a valid cost estimate. It is important to note that these estimates are only samples, and each mitigation project may have different descriptions of the items of work, different quantities, different units, and different unit costs based on each projects specific scope of work. Estimating helpful hints: Dynamic help features will be available to guide the users through the software and define terms and processes associated with each step in the process. Examples of these helpful hints are shown in the layout of the main cost estimation screen shown in Appendix A.

14

Section 3 Benefit-Cost Analysis Handout Tool


The Benefit Cost Analysis (BCA) Handout is designed for reference by Applicants and subapplicants prior to their use of the BCA tool. This Handout will provide guidance to assist in the preparation of an effective scope of work and will assist the preparer in the identification and collection of the cost information needed to use the BCA module. This handout will consist of the following elements and will be developed once the software is beta tested: 1. Overview of the BCA Tool 2. Scope Builder checklists for each of the 16 mitigation project types covered in the estimating module. These checklists will provide an itemized breakdown of the primary work tasks and subtasks and are provided in Appendix D. (To be finalized after the tool structure is completed.) 3. Estimating Flow Charts for each of the 16 mitigation project types as provided in Appendix A 4. Sample Cost Estimates for each of the 16 mitigation project types as provided in Appendix B

15

Conclusions: Reasons for Selection of Proposed Methodology


In conclusion, the URS BCA team recommends the proposed methodology because it provides a simple, straightforward approach to supplying comprehensive cost estimate guidance for a wide range of hazard mitigation projects. The proposed methodology does not require recreating, linking, or updating any existing cost estimating tools or products. Instead, users will be referred to those tools/products where applicable, and would be expected to learn tools or purchase products to address shortcomings in their project cost estimates, as illustrated in the flow charts. This will simplify programming, reduce development costs, and avoid licensing issues with firms that have proprietary estimating products. Specifically, the proposed methodology addresses the five project cost estimate issues identified earlier as follows: Provides guidance on what hard construction and ancillary costs should be included for a variety of mitigation project types Does not include contingencies or allowances for change orders Reinforces to the users that historical cost data is as useful as standard cost estimating references Provides guidance on an appropriate level of detail to be included in a mitigation project cost estimate Provides helpful hints, reference values, and sample cost estimates to guide the user through the cost estimating process

16

APPENDIX A: Mitigation Strategy Flow Charts

17

Flood

A-1 Cost Estimate Process Flood-Proofing

Flood-Proofing

Step 1 Preconstruction Cost Non-construction costs for planning, permitting, and managing mitigation projects Typical Preconstruction Activities (listed below) o Site Topographic Survey o Feasibility Studies o Materials Evaluations

Step 6 Review and Confirm Estimate

Step 5 Adjust Estimate For Project Timing & Data Currency

Step 2 Construction Costs (Develop hard costs to execute the project) Identify All Work Elements o Flood Proofing Wet Flood Proofing Dry Flood Proofing Identify Cost Data Sources o Published vs. Historical o Current Bids Develop Cost Estimate o Itemize cost elements using appropriate units of measurement o Limit lump sums to less than 20% of Task line items

Step 4 Estimate Annual Maintenance Costs

Step 3 Ancillary Costs (Add General Costs Not Included In Task Estimate) Mobilization & demobilization 3% Construction general conditions/requirements 10% General Contractor overhead & profit 20% A/E services for preparation of bid documents 10%

18

Flood

A-2 Cost Estimate Process FloodRelocation

Relocation

Step 1 Preconstruction Cost Non-construction costs for planning, design, permitting, and managing mitigation projects Typical Preconstruction Activities (listed below) o New Site Phase I Environmental Site Assessment o Site Purchas New Locations o Property Survey o Transaction Closing Fees

Step 6 Review and Confirm Estimate

Step 2 Construction Costs (Develop hard costs to execute the project) Identify All Work Elements o Site Acquisition o Transport Facility o Foundation Construction o Site Improvements and Infrastructure o Old Site Restoration Identify Cost Data Sources o Published vs. Historical o Current Bids Develop Cost Estimate o Itemize cost elements using appropriate units of measurement o Limit lump sums to less than 20% of Task line items

Step 5 Adjust Estimate For Project Timing & Data Currency

Step 4 Estimate Annual Maintenance Costs

Step 3 Ancillary Costs (Add General Costs Not Included In Task Estimate) Mobilization & demobilization 3% Construction general conditions/requirements 10% General Contractor overhead & profit 20% A/E services for preparation of bid documents 10%

19

Flood Drainage Step 1 Preconstruction Cost Non-construction costs for planning, design, permitting, and managing mitigation projects Typical Preconstruction Activities (listed below) o Hydrology Studies o Environmental Assessment o Compliance Studies

A-3 Cost Estimate Process Flood-Drainage

Step 6 Review and Confirm Estimate

Step 2 Construction Costs (Develop hard costs to execute the project) Identify All Work Elements o Site Acquisition o Demolition o Site Restoration o Site Maintenance o Professional Fees Identify Cost Data Sources o Published vs. Historical o Current Bids Develop Cost Estimate o Itemize cost elements using appropriate units of measurement o Limit lump sums to less than 20% of Task line items

Step 5 Adjust Estimate For Project Timing & Data Currency

Step 4 Estimate Annual Maintenance Costs

Step 3 Ancillary Costs (Add General Costs Not Included In Task Estimate) Mobilization & demobilization 3% Construction general conditions/requirements 10% General Contractor overhead & profit 20% A/E services for preparation of bid documents 10%

20

Flood Elevation Step 1 Preconstruction Cost Non-construction costs for planning, design, permitting, and managing mitigation projects Typical Preconstruction Activities (listed below) o Site Topographic survey o Existing Floor Elevation Certification Survey

A-4 Cost Estimate Process FloodElevation

Step 6 Review and Confirm Estimate

Step 2 Construction Costs (Develop hard costs to execute the project) Identify All Work Elements o o o o o o o o o o Elevate Facility Foundation Construction Utilities Adjustments Building Access Site Restoration Professional Fees Demolition of Existing Facility Construction of New Facility Site Restoration Professional Fees

Step 5 Adjust Estimate For Project Timing & Data Currency

Step 4 Estimate Annual Maintenance Costs

Identify Cost Data Sources o Published vs. Historical o Current Bids Develop Cost Estimate o Itemize cost elements using appropriate units of measurement o Limit lump sums to less than 20% of Task line items

Step 3 Ancillary Costs (Add General Costs Not Included In Task Estimate) Mobilization & demobilization 3% Construction general conditions/requirements 10% General Contractor overhead & profit 20% A/E services for preparation of bid documents 10%

21

Flood Acquisition Step 1 Preconstruction Cost Non-construction costs for planning, design, permitting, and managing mitigation projects Typical Preconstruction Activities (listed below) o Property Surveys o Appraisal Fees o Property Purchase o Transaction Closing Fees

A-5 Cost Estimate Process FloodAcquisition

Step 6 Review and Confirm Estimate

Step 2 Construction Costs (Develop hard costs to execute the project) Identify All Work Elements o Site Acquisition o Demolition o Site Restoration o Site Maintenance o Professional Fees Identify Cost Data Sources o Published vs. Historical o Current Bids Develop Cost Estimate o Itemize cost elements using appropriate units of measurement o Limit lump sums to less than 20% of Task line items

Step 5 Adjust Estimate For Project Timing & Data Currency

Step 4 Estimate Annual Maintenance Costs

Step 3 Ancillary Costs (Add General Costs Not Included In Task Estimate) Mobilization & demobilization 3% Construction general conditions/requirements 10% General Contractor overhead & profit 20% A/E services for preparation of bid documents 10%

22

Earthquake Anchor Non-Structural Elements Step 1 Preconstruction Cost Non-construction costs for planning, design, permitting, and managing mitigation projects Typical Preconstruction Activities (listed below) o Feasibility Studies o Relocate Materials To Temporary Storage Prior To Construction

A-6 Cost Estimate Process EarthquakeAnchor Non-Structural Elements

Step 6 Review and Confirm Estimate

Step 2 Construction Costs (Develop hard costs to execute the project) Identify All Work Elements o Mobilization and Demobilization o Anchoring Non-Structural Elements o Bracing o Service and Utility Connections o Professional Fees Identify Cost Data Sources o Published vs. Historical o Current Bids Develop Cost Estimate o Itemize cost elements using appropriate units of measurement o Limit lump sums to less than 20% of Task line items

Step 5 Adjust Estimate For Project Timing & Data Currency

Step 4 Estimate Annual Maintenance Costs

Step 3 Ancillary Costs (Add General Costs Not Included In Task Estimate) Mobilization & demobilization 3% Construction general conditions/requirements 10% General Contractor overhead & profit 20% A/E services for preparation of bid documents 10%

23

Earthquake

A-7 Cost Estimate Process EarthquakeStrengthen Structural Elements

Strengthen Structural Elements

Step 1 Preconstruction Cost Non-construction costs for planning, design,

Step 6 Review and Confirm Estimate

Step 5 Adjust Estimate For Project Timing & Data Currency Step 2 Construction Costs (Develop hard costs to execute the project) Identify All Work Elements o Work Area Preparation o Reinforce Facility o Strengthen Structural Members o Professional Fees Identify Cost Data Sources o Published vs. Historical o Current Bids Develop Cost Estimate o Itemize cost elements using appropriate units of measurement o Limit lump sums to less than 20% of Task line items

Step 4 Estimate Annual Maintenance Costs

Step 3 Ancillary Costs (Add General Costs Not Included In Task Estimate) Mobilization & demobilization 3% Construction general conditions/requirements 10% General Contractor overhead & profit 20% A/E services for preparation of bid documents 10%

24

Wildfire

A-8 Cost Estimate Process WildfireVegetative Control

Vegetative Control

Step 1 Preconstruction Cost Non-construction costs for planning, design, permitting, and managing mitigation projects Typical Preconstruction Activities (listed below) o Erosion/Environmental Study o Property Survey

Step 6 Review and Confirm Estimate

Step 5 Adjust Estimate For Project Timing & Data Currency

Step 2 Construction Costs (Develop hard costs to execute the project) Identify All Work Elements o Vegetative Control (Fuel Reduction) o Fire Breaks o Professional Fees Identify Cost Data Sources o Published vs. Historical o Current Bids Develop Cost Estimate o Itemize cost elements using appropriate units of measurement o Limit lump sums to less than 20% of Task line items

Step 4 Estimate Annual Maintenance Costs

Step 3 Ancillary Costs (Add General Costs Not Included In Task Estimate) Mobilization & demobilization 3% Construction general conditions/requirements 10% General Contractor overhead & profit 20% A/E services for preparation of bid documents 10%

25

Wildfire

A-9 Cost Estimate Process Wildfire-Fire Resistant Exterior

Fire Resistant Exterior

Step 1 Preconstruction Cost Non-construction costs for planning, design, permitting, and managing mitigation projects Typical Preconstruction Activities (listed below) o Appraisers Fees o Property Survey

Step 6 Review and Confirm Estimate

Step 5 Adjust Estimate For Project Timing & Data Currency

Step 2 Construction Costs (Develop hard costs to execute the project) Identify All Work Elements o Roofing o Walls Identify Cost Data Sources o Published vs. Historical o Current Bids Develop Cost Estimate o Itemize cost elements using appropriate units of measurement o Limit lump sums to less than 20% of Task line items

Step 4 Estimate Annual Maintenance Costs

Step 3 Ancillary Costs (Add General Costs Not Included In Task Estimate) Mobilization & demobilization 3% Construction general conditions/requirements 10% General Contractor overhead & profit 20% A/E services for preparation of bid documents 10%

26

Wildfire

A-10 Cost Estimate Process Wildfire-Fire Suppression

Fire Suppression

Step 1 Preconstruction Cost Non-construction costs for planning, design, permitting, and managing mitigation projects Typical Preconstruction Activities (listed below) o Property Acquisition o Inspection Fees o Property Survey

Step 6 Review and Confirm Estimate

Step 2 Construction Costs (Develop hard costs to execute the project) Identify All Work Elements o Enhanced Fire Suppression Capabilities o Improved Suppressant Agent Delivery Systems o Piping and Hydrant Systems o Pumping Systems o Professional Fees Identify Cost Data Sources o Published vs. Historical o Current Bids Develop Cost Estimate o Itemize cost elements using appropriate units of measurement o Limit lump sums to less than 20% of Task line items

Step 5 Adjust Estimate For Project Timing & Data Currency

Step 4 Estimate Annual Maintenance Costs

Step 3 Ancillary Costs (Add General Costs Not Included In Task Estimate) Mobilization & demobilization 3% Construction general conditions/requirements 10% General Contractor overhead & profit 20% A/E services for preparation of bid documents 10%

27

Wind

A-11 Cost Estimate Process WindStrengthen Load Path Elements/Shutters

Strengthen Load Path Elements/Shutters

Step 1 Preconstruction Cost Non-construction costs for planning, design, permitting, and managing mitigation projects Typical Preconstruction Activities (listed below) o Feasibility Study o Structural Assessment Of Existing Structural System o Feasibility Analysis Of Alternatives

Step 6 Review and Confirm Estimate

Step 5 Adjust Estimate For Project Timing & Data Currency Step 2 Construction Costs (Develop hard costs to execute the project) Identify All Work Elements o Temporary Relocation Costs o Strengthen Structural Members o Strengthen Load Path Connections o Strengthen Building Openings o Impact Resistant Glazing o Install Shutters o Reengineer Ancillary Equipment Connections o Selective Demolition o Professional Fees Identify Cost Data Sources o Published vs. Historical o Current Bids o Develop Cost Estimate o Itemize cost elements using appropriate units of measurement o Limit lump sums to less than 20% of Task line items

Step 4 Estimate Annual Maintenance Costs

Step 3 Ancillary Costs (Add General Costs Not Included In Task Estimate) Mobilization & demobilization 3% Construction general conditions/requirements 10% General Contractor overhead & profit 20% A/E services for preparation of bid documents 10%

28

Wind

A-12 Cost Estimate Process Wind-Tornado Shelter

Tornado Shelter

Step 1 Preconstruction Cost Non-construction costs for planning, design, permitting, and managing mitigation projects Typical Preconstruction Activities (listed below) o Site Acquisition o Inspection Fees o Property Survey

Step 6 Review and Confirm Estimate

Step 2 Construction Costs (Develop hard costs to execute the project) Identify All Work Elements o Strengthen Designated Shelter Areas o Provide Emergency Access o Retrofit Services For Emergency Use o Site Acquisition o New Construction o Site Improvements o Professional Fees Identify Cost Data Sources o Published vs. Historical o Current Bids o Develop Cost Estimate o Itemize cost elements using appropriate units of measurement o Limit lump sums to less than 20% of Task line items

Step 5 Adjust Estimate For Project Timing & Data Currency

Step 4 Estimate Annual Maintenance Costs

Step 3 Ancillary Costs (Add General Costs Not Included In Task Estimate) Mobilization & demobilization 3% Construction general conditions/requirements 10% General Contractor overhead & profit 20% A/E services for preparation of bid documents 10%

29

Landslide Slope Drainage Improvements Step 1 Preconstruction Cost Non-construction costs for planning, design, permitting, and managing mitigation projects Typical Preconstruction Activities (listed below) o Site Survey o Geotechnical Borings o Environmental Assessment and Compliance Studies

A-13 Cost Estimate Process LandslideSlope Drainage Improvements

Step 6 Review and Confirm Estimate

Step 2 Construction Costs (Develop hard costs to execute the project) Identify All Work Elements o Grading o Install Channel Lining o Outlet Structures o Dimensions o Professional Fees o Excavation o Drain Installation o Ancillary Structures o Dimensions o Professional Services Identify Cost Data Sources o Published vs. Historical o Current Bids o Develop Cost Estimate o Itemize cost elements using appropriate units of measurement o Limit lump sums to less than 20% of Task line items

Step 5 Adjust Estimate For Project Timing & Data Currency

Step 4 Estimate Annual Maintenance Costs

Step 3 Ancillary Costs (Add General Costs Not Included In Task Estimate) Mobilization & demobilization 3% Construction general conditions/requirements 10% General Contractor overhead & profit 20% A/E services for preparation of bid documents 10%

30

Landslide

A-14 Cost Estimate Process LandslideBio-Engineered Slope Stabilization

Bio-Engineered Slope Stabilization

Step 1 Preconstruction Cost Non-construction costs for planning, design, permitting, and managing mitigation projects Typical Preconstruction Activities (listed below) o Environmental Assessment and Compliance Reviews o Agricultural Assessment o Geotechnical Studies o Typographic Surveys

Step 6 Review and Confirm Estimate

Step 5 Adjust Estimate For Project Timing & Data Currency

Step 2 Construction Costs (Develop hard costs to execute the project) Identify All Work Elements o Site Grading o Bio-Engineered Slope Protection o Dimensions o Professional Fees Identify Cost Data Sources o Published vs. Historical o Current Bids Develop Cost Estimate o Itemize cost elements using appropriate units of measurement o Limit lump sums to less than 20% of Task line items

Step 4 Estimate Annual Maintenance Costs

Step 3 Ancillary Costs (Add General Costs Not Included In Task Estimate) Mobilization & demobilization 3% Construction general conditions/requirements 10% General Contractor overhead & profit 20% A/E services for preparation of bid documents 10%

31

Landslide

A-15 Cost Estimate Process Landslide-Toe Armoring

Toe Armoring

Step 1 Preconstruction Cost Non-construction costs for planning, design, permitting, and managing mitigation projects Typical Preconstruction Activities (listed below) o Hydrology/Hydraulic Studies o Environmental Assessment and Compliances Studies o Geotechnical Studies

Step 6 Review and Confirm Estimate

Step 5 Adjust Estimate For Project Timing & Data Currency

Step 2 Construction Costs (Develop hard costs to execute the project) Identify All Work Elements o Surface Water (if required) o Armoring Approach o Site Grading o Professional Fees Identify Cost Data Sources o Published vs. Historical o Current Bids Develop Cost Estimate o Itemize cost elements using appropriate units of measurement o Limit lump sums to less than 20% of Task line items

Step 4 Estimate Annual Maintenance Costs

Step 3 Ancillary Costs (Add General Costs Not Included In Task Estimate) Mobilization & demobilization 3% Construction general conditions/requirements 10% General Contractor overhead & profit 20% A/E services for preparation of bid documents 10%

32

Landslide

A-16 Cost Estimate Process LandslideRetaining Structures

Retaining Structures

Step 1 Preconstruction Cost Non-construction costs for planning, design, permitting, and managing mitigation projects Typical Preconstruction Activities (listed below) o Right of Way Study o Easement or Access Costs o Topographic Survey o Geotechnical Studies

Step 6 Review and Confirm Estimate

Step 5 Adjust Estimate For Project Timing & Data Currency

Step 4 Estimate Annual Maintenance Costs Step 2 Construction Costs (Develop hard costs to execute the project) Identify All Work Elements o Retention System o Site Grading o Slope Drainage Structures o Professional Fees Identify Cost Data Sources o Published vs. Historical o Current Bids Develop Cost Estimate o Itemize cost elements using appropriate units of measurement o Limit lump sums to less than 20% of Task line items

Step 3 Ancillary Costs (Add General Costs Not Included In Task Estimate) Mobilization & demobilization 3% Construction general conditions/requirements 10% General Contractor overhead & profit 20% A/E services for preparation of bid documents 10%

33

APPENDIX B: Sample Estimates

34

Applicant Project Title Preparer:

BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATE City of Lowland, GA Lowland Civic Center Floodproofing HAZARD: MITIGATION STRATEGY Flood Floodproofing
Quantity Unit Unit Cost $ $ Task Cost

Estimating Step

Project Phase

Description

Pre-Construction (Specify) Pre-construction subtotal Excavating, trench or continuous footing, common earth, 3/8 C.Y. excavator, 1' to 4' deep, excludes sheeting or dewatering Excavating, trench or continuous footing, common earth, trim sides and bottom for concrete pours, excludes sheeting or dewatering Structural concrete, in place, continuous strip footing, 36" wide x 12" deep, includes forms(4 uses), reinforcing steel, and finishing Curing, burlap, 12 oz., 4 uses assumed Structural concrete, in place, grade wall, 12" thick x 8' high, includes forms(4 uses), reinforcing steel, and finishing Backfill, light soil, by hand, no compaction Backfill, 6" layers, compaction in layers, hand tamp Anchor bolt, J-type, plain steel, 1/2" dia x 18" L, incl nut & washer Column base plates, structural, heavy, 100-ton project, over 150 lb each, A992 steel, shop fabricated, incl shop primer Precast wall panel, exposed aggregate, uninsulated, low rise, 8' x 8' x 4" thick, 3000 psi Precast column, small, rectangular to 12' high., 3000 psi, includes material only Waterstop, fittings, rubber, flat, dumbbell or center bulb, flat cross, 3/8" thick x 9" wide Caulking & Sealants, backer rod, polyethylene, 1/4" dia Caulking & Sealants, acrylic latex caulk, white, 1/2" x 1/2", in place Self-raising flood gate @ pedestrian entrance Self-raising flood gate @ vehicle entrance Construction Subtotal 260.00 B.C.Y. $7.55

$ $ $ $1,963

5,700.00

S.F.

$0.81

$4,617

130.00 23.00 65.00 65.00 65.00 300.00 900.00 5,700.00 600.00 60.00 1,200.00 1,200.00 1.00 1

C.Y. C.S.F. C.Y. L.C.Y. E.C.Y. Ea. Lb. S.F. L.F. Ea. L.F. L.F. Ea. Ea.

$255.00 $28.50 $375.00 $27.00 $18.50 $18.15 $2.07 $33.00 $113.00 $68.50 $1.12 $2.40 $13,250.00 $41,700.00 $-

$33,150 $656 $24,375 $1,755 $1,203 $5,445 $1,863 $188,100 $67,800 $4,110 $1,344 $2,880 $13,250 $41,700 $394,210

Construction (Specify Phases)

35

Estimating Step

Project Phase

Description Insurance and Bonds Site supervision and contract requirements

Quantity 1 1 1 1 1 1 1

Unit LS LS LS LS LS LS LS

Unit Cost 3.5% 10% 28% 0.5% 10% 2% 4% $$$-

Task Cost $13,797 $40,801 $125,666 $2,872 $183,137 $57,735 $11,547 $23,094 $92,375

Construction General 3

G.C. overhead & profit Permits and Review Fees General Construction Phase Subtotal Preparation of construction documents Applicant Cost to Manage Design

Applicant Costs

Applicant Cost to Manage Construction Applicant Cost Subtotal Maintenance

Maintenance Annual Maintenance Subtotal

$12 Months 0.42% $28,890 $$394,210 $183,137 $92,375 $$28,890 $698,613

Escalation

Escalation (to mid-point of construction) Pre-construction subtotal Construction subtotal

Estimate Review & Confirmation

General Construction Phase Subtotal Applicant Cost Subtotal Annual Maintenance Subtotal Escalation Subtotal

PROJECT TOTAL

36

Applicant Project Title Preparer:

BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATE Riverside Township, PA Township Office Building Relocation H. Waters HAZARD: Flood MITIGATION STRATEGY Relocation
Description Pre-purchase Phase I Environmental Site Assessment Quantity 1 3 1500 1 Unit Ea. Acres LF LS Unit Cost $2,500.00 $25,000 $2 $1,500 Task Cost $2,500 $75,000 $2,370 $1,500 $81,370 100,000 C.F. $0.29 $29,000

Estimating Step

Project Phase

Pre-Construction (Specify)

Site purchase - new location Property boundary survey Legal Fees Pre-construction subtotal Building demolition, small buildings or single buildings, masonry, elevated slabs, includes 20 mile haul, excludes salvage, foundation demolition or dump fees Rubbish handling, loading & trucking, chute loaded, including 2 mile haul, cost to be added to demolition cost. Dump charges, typical urban city, building construction materials, includes tipping fees only Seeding, wildflower, 0.10 lb. per M.S.F., tractor spreader A Substructure Standard Foundations Slab on Grade Basement Excavation Basement Walls

1,300 1,400 40

C.Y. Ton M.S.F.

$45.50 $90.00 $17.35 $-

$59,150 $126,000 $694

8,000 8,000 8,000 8,000 8,000 8,000 8,000 8,000 8,000 8,000 8,000 8,000 8,000 8,000 8,000 8,000 8,000 8,000 8,000 8,000 8,000 8,000 8,000 8,000 8,000 8,000 50 150

SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF Car L.F.

$2.40 $4.45 $0.24 $3.33 $$6.25 $8.56 $4.76 $0.81 $2.88 $$4.05 $2.60 $0.48 $1.26 $7.00 $4.71 $$5.26 $1.40 $0.89 $7.94 $2.40 $2.33 $9.00 $2.40 $0.13 $$2.08 $965.01 $24.71

$19,200 $35,600 $1,920 $26,640 $50,000 $68,480 $38,080 $6,480 $23,040 $32,400 $20,800 $3,840 $10,080 $56,000 $37,680 $42,080 $11,200 $7,120 $63,520 $19,200 $18,640 $72,000 $19,200 $1,040 $16,640 $48,251 $3,706

Construction (Specify Phases)

B Shell Roof Construction Exterior Walls Exterior Windows Exterior Doors Roof Coverings C Interiors Partitions Interior Doors Fittings Wall Finishes Floor Finishes Ceiling Finishes D Services

Construction(Specify Phases)

Plumbing Fixtures Domestic Water Distribution Rain Water Drainage Terminal & Package Units Sprinklers Electrical Service/Distribution Lighting and Branch Wiring Communications and Security Other Electrical Systems E Equipment & Furnishings Other Equipment Parking lot, 60 degree angle parking, 3" bituminous paving, 6" gravel base Concrete sidewalk, 4" thick, 4" gravel base, 5' wide

37

$Construction Subtotal $967,680

38

Estimating Step

Project Phase

Description Insurance and Bonds Site supervision and contract requirements

Quantity 1 1 1 1 1 1 1

Unit LS LS LS LS LS LS LS

Unit Cost 3.5% 10% 28% 0.5% 10% 2% 4% $$$-

Task Cost $33,869 $100,155 $308,477 $7,458 $449,959 $141,764 $28,353 $56,706 $226,822

Construction General 3

G.C. overhead & profit Permits and Review Fees General Construction Phase Subtotal Preparation of construction documents Applicant Cost to Manage Design

Applicant Costs

Applicant Cost to Manage Construction Applicant Cost Subtotal Maintenance

Maintenance Annual Maintenance Subtotal

$19 Months 0.42% $112,320 $81,370 $967,680 $449,959 $226,822 $$112,320 $1,838,151

Escalation

Escalation (to mid-point of construction) Pre-construction subtotal Construction subtotal

Estimate Review & Confirmation

General Construction Phase Subtotal Applicant Cost Subtotal Annual Maintenance Subtotal Escalation Subtotal

PROJECT TOTAL

39

Applicant Project Title Preparer:

BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATE Palisades County, New Jersey Dept. of Roads Hill Bench Road Stabilization N. Wetfoot HAZARD: Landslide MITIGATION STRATEGY Drainage Improvements
Description Site survey Geotechnical Borings Quantity 1 1 Unit LS LS Unit Cost $5,000.00 $27,500.00 $ $ Pre-construction subtotal Minor site demolition, patio/carport, bituminous, to 6" thick, with hand held air equipment, excludes hauling Demo guard rail, corrugated steel Demo guard rail, wood posts Rubbish handling, loading & trucking, machine loading truck, includes 2 mile haul, cost to be added to demolition cost. Rubbish handling, up to 8 C.Y. truck, loading & trucking, haul, per mile, includes 2 mile haul, cost to be added to demolition cost. Dump charges, typical urban city, reclamation station, usual charge, includes tipping fees only Excavating, trench or continuous footing, common earth, 1/2 C.Y. excavator, 1' to 4' deep, excludes sheeting or dewatering 1,000 600 75 20 S.F. L.F. Ea. C.Y. $1.29 $2.38 $5.95 $18.30 $32,500 $1,290 $1,428 $446 $366 Task Cost $5,000 $27,500

Estimating Step

Project Phase

Pre-Construction (Specify)

100 30 80

C.Y. Ton B.C.Y.

$0.81 $104.50 $5.65

$81 $3,135 $452

Construction (Specify Phases)

Excavating, trench or continuous footing, common earth, 1/2 C.Y. excavator, 4' to 6' deep, excludes sheeting or dewatering Drainage geotextiles, fabric, laid in trench, polypropylene, ideal conditions Bedding, for pipe and conduit, crushed or screened bank run gravel, excludes compaction Corrugated plastic tubing, perforated or plain, in rolls, 8" diameter, excludes excavation and backfill Piping, HDPE, butt fusion joints, 40' lengths, 24" diameter, SDR 21 Excavating, trench backfill, 1 C.Y. bucket, minimal haul, front end loader, wheel mounted, excludes dewatering Asphaltic concrete pavement, for highways and large paved areas, pavement replacement over trench, 6" thick, for paving projects 300 tons or less add for trucking

50 450 500 500 50 30

B.C.Y. S.Y. L.C.Y. L.F. L.F. L.C.Y.

$5.65 $1.90 $36.00 $10.30 $116.00 $2.17

$283 $855 $18,000 $5,150 $5,800 $65

125

S.Y.

$61.99

$7,748

40

Estimating Step

Project Phase

Description Manholes, concrete, precast, 4' I.D., 6' deep, excludes base, excavation, backfill, frame and cover Manhole steps, heavyweight cast iron, 8" x 9" Catch basins, frames and covers, cast iron, heavy traffic, 24" diameter, 400 lb., excludes footing, excavation, and backfill Fine grade, slopes, steep, gentle, finish grading Soil stabilization, geotextile fabric, woven, heavy duty, 600 lb. tensile strength Rip-rap, random, broken stone, 18" minimum thickness, machine placed for slope protection, not grouted Guide/Guard rail, corrugated steel, galvanized steel posts, install wrap around end section Guide/Guard rail, corrugated steel, galvanized steel posts, install metal guide/guard rail, double face, steel posts 6' - 3" O.C., W6x8 posts Construction Subtotal Insurance and Bonds Site supervision and contract requirements

Quantity 2 4 2 200 200 200 2 600

Unit Ea. Ea. Ea. S.Y. S.Y. S.Y. Ea. L.F.

Unit Cost $1,799.87 $38.00 $469.97 $0.20 $2.34 $84.00 $165.00 $32.50

Task Cost $3,600 $152 $940 $40 $468 $16,799 $330 $19,500 $86,928

Construction(Specify Phases)

1 1 1 1 1 1 1

LS LS LS LS LS LS

3.5% 10% 28% 0.5% 10% 2% 4% $ $ $

$3,042 $8,997 $27,711 $796 $40,546 $12,747 $2,549 $5,099 $20,396

Construction General 3

G.C. overhead & profit Permits and Review Fees General Construction Phase Subtotal Preparation of construction documents Applicant Cost to Manage Design

Applicant Costs

Applicant Cost to Manage Construction Applicant Cost Subtotal Maintenance

Maintenance Annual Maintenance Subtotal

$ 9 Months 0.33% $3,729 $32,500 $86,928 $40,546 $20,396 $ $3,729 $184,100

Escalation

Escalation (to mid-point of construction) Pre-construction subtotal Construction subtotal

Estimate Review & Confirmation

General Construction Phase Subtotal Applicant Cost Subtotal Annual Maintenance Subtotal Escalation Maintenance Subtotal

PROJECT TOTAL

41

Applicant Project Title Preparer:

BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATE Lowland, MS Elevate Town Hall Building P. Riser HAZARD: Flood MITIGATION STRATEGY Elevation
Description Quantity Unit Unit Cost $ $ Task Cost

Estimating Step

Project Phase

Pre-Construction (Specify) Pre-construction subtotal Selective demolition- wood frame, includes loading and 5 mile haul to dump Demolition, concrete slab on grade, reinforced, Footings and foundations demolition, remove concrete footing, 2' thick, 3' wide Selective demolition, timber piles, up to 14", diameter Dump charges, typical urban city, building construction materials, includes tipping fees only Bulk Asbestos Removal, remove VAT from floor by hand, incl. disp. and tools Waste Packaging, Handling & Disposal, containerize bagged material in drums, per 3 CF drum Waste Packaging, Handling & Disposal, collect and bag bulk material, by hand, 3 CF Construction (Specify Phases) Asbestos contaminated waste Packaging, Handling & Disposal, disposal charges, Decontamination Containment Area Demolition & Cleanup, fine clean exposed substrate, wet wipe substrate Excavating, grade beams Piles, concrete, precast, prestressed; 10" square, Piles, mobilization, 1 Structural concrete, in place, grade beams Structural concrete, in place, handicap access ramp, railing both sides, 5' wide, Cast-in-place concrete beam and slab, 75 PSF superimposed load Wood roof, truss, 4/12 slope, 24" O.C., 44' to 60' span Wood siding, 2"x6" studs 24"OC, insulated wall, 1" x 4" vertical T&G redwood Windows, aluminum, projecting, insulated glass, 4'-5" x 5'-3" 2,500.00 5,400.00 510.00 900.00 150.00 4,800.00 25.00 25.00 5.00 4,800.00 100.00 1,900.00 1,900.00 100.00 120.00 5,400.00 5,400.00 3,024.00 57.00 C.Y. S.F. L.F. V.L.F. Ton S.F. Ea. Ea. C.Y. S.F. B.C.Y. V.L.F. V.L.F. C.Y. L.F. S.F. S.F. S.F. Ea. $17.75 $5.95 $22.00 $9.30 $90.00 $1.83 $12.40 $11.85 $175.00 $0.88 $6.65 $19.55 $1.68 $249.00 $650.00 $17.95 $6.26 $11.30 $622.95

$ $ $ $44,375 $32,130 $11,220 $8,370 $13,500 $8,784 $310 $296 $875 $4,224 $665 $37,145 $3,192 $24,900 $78,000 $96,930 $33,794 $34,165 $35,508

42

Estimating Step

Project Phase

Description Door, aluminum & glass, with transom, narrow stile, double door, hardware, 6'-0" x 10'-0" opening Door, steel 18 gauge, hollow metal, 1 door with frame, no label, 3'-0" x 7'-0" opening Asphalt roofing, strip shingles, premium laminated, multi-layered, Class A, 4" slope, 260300 lbs/SQ Flashing, aluminum, no backing sides, .019" Gravel stop, aluminum, extruded, 4", mill finish, .050" thick Wood partition, 5/8" fire rated gypsum board face, 5/8" fire rated gypsum board base, 2x4 @ 16", 5/8" fire rated gypsum board opposite face, no insulation 1/2" fire rated gypsum board, taped & finished, painted on metal furring Door, single leaf, wood frame, 3'-0" x 7'-0" x 13/8", birch, solid core Toilet partitions, cubicles, ceiling hung, plastic laminate

Quantity 1.00 2.00 5,700.00 360.00 360.00

Unit Opng. Opng. S.F. S.F. L.F.

Unit Cost $2,221.21 $1,073.67 $2.14 $3.88 $8.85

Task Cost $2,221 $2,147 $12,181 $1,397 $3,186

2,700.00

S.F.

$4.99

$13,469

3,024.00 27.00 6.00 4,860.00 540.00 3,780.00 810.00 810.00 5,400.00 6.00 3.00 6.00 1.00 3.00 2.00 1.00

S.F. Opng. Unit S.F. S.F. S.F. S.F. S.F. S.F. Ea. Ea. Ea. Ea. Ea. Ea. Ea.

$3.85 $521.02 $874.28 $0.71 $6.26 $4.47 $22.79 $3.11 $4.71 $1,465.48 $1,055.95 $956.20 $1,006.87 $1,813.30 $1,131.71 $2,013.13

$11,644 $14,067 $5,246 $3,450 $3,381 $16,899 $18,462 $2,518 $25,433 $8,793 $3,168 $5,737 $1,007 $5,440 $2,263 $2,013

Construction(Specify Phases)

Painting, interior on plaster and drywall, walls & ceilings, roller work, primer & 2 coats Ceramic tile, thin set, 4-1/4" x 4-1/4" Carpet tile, nylon, fusion bonded, 18" x 18" or 24" x 24", 35 oz Terrazzo, maximum Vinyl, composition tile, maximum Acoustic ceilings, 3/4" mineral fiber, 12" x 12" tile, concealed 2" bar & channel grid, suspended support Water closet, vitreous china, bowl only with flush valve, wall hung Urinal, vitreous china, wall hung Lavatory w/trim, vanity top, PE on CI, 19" x 16" oval Kitchen sink w/trim, countertop, PE on CI, 24" x 21", single bowl Service sink w/trim, PE on CI, corner floor, 28" x 28", w/rim guard Water cooler, electric, wall hung, 8.2 GPH Water cooler, electric, wall hung, wheelchair type, 7.5 GPH

43

Estimating Step

Project Phase

Construction (Specify Phases)

Description Gas fired water heater, commercial, 100< F rise, 95 MBH input, 86 GPH Roof drain, CI, soil, single hub, 4" diam, 10' high Roof drain, CI, soil, single hub, 4" diam, for each additional foot add Rooftop, single zone, air conditioner, offices, 10,000 SF, 31.67 ton Wet pipe sprinkler systems, steel, light hazard, 1 floor, 10,000 SF Service installation, includes breakers, metering, 20' conduit & wire, 3 phase, 4 wire, 120/208 V, 400 A Feeder installation 600 V, including RGS conduit and XHHW wire, 400 A Switchgear installation, incl switchboard, panels & circuit breaker, 400 A Receptacles incl plate, box, conduit, wire, 16.5 per 1000 SF, 2.0 watts per SF Wall switches, 1.0 per 1000 SF Miscellaneous power, 1.2 watts Central air conditioning power, 6 watts Fluorescent fixtures recess mounted in ceiling, 2 watt per SF, 40 FC, 10 fixtures per 1000 SF Communication and alarm systems, includes outlets, boxes, conduit and wire, fire detection systems, 25 detectors Generator sets, w/battery, charger, muffler and transfer switch, gas/gasoline operated, 3 phase, 4 wire, 277/480 V, 15 kW Directory boards, plastic, glass covered, 36" x 48" Detection Systems, heat detector, smoke detector, ceiling type, excl. wires & conduit Emergency light units, nickel cadmium battery operated, twin sealed beam light, 25 W, 6 V each Bituminous roadway, two lanes, 3-1/2" thick pavement, 3" thick gravel base, 24' wide Parking lot, 90 degree angle parking, 3" bituminous paving, 6" gravel base Bituminous sidewalk, 1" thick paving, 4" gravel base, 5' width Septic system, 2000 gal tank, 6' high precast pit, 2@6'-6" diameter, 50 feet from building

Quantity 2.00 3.00 95.00 5,400.00 5,400.00 1.00 50.00 1.00 5,292.00 5,400.00 5,400.00 5,076.00 5,400.00 1.00

Unit Ea. Ea. Ea. S.F. S.F. Ea. L.F. Ea. S.F. S.F. S.F. S.F. S.F. Ea.

Unit Cost $5,601.54 $1,502.62 $27.81 $7.94 $2.40 $6,623.60 $94.48 $7,251.83 $3.14 $0.25 $0.29 $0.91 $4.52 $3,073.06

Task Cost $11,203 $4,508 $2,642 $42,885 $12,960 $6,624 $4,724 $7,252 $16,619 $1,350 $1,566 $4,619 $24,408 $3,073

1.00 1.00 8.00 8.00 100.00 25.00 200.00 1.00

kW Ea. Ea. Ea. L.F. Car L.F. Ea.

$689.36 $1,375.27 $171.03 $769.77 $91.00 $965.00 $7.00 $10,628.46

$689 $1,375 $1,368 $6,158 $9,100 $24,125 $1,400 $10,628

Construction (Specify Phases)

$ $ $
Construction Subtotal Insurance and Bonds Site supervision and contract requirements 1 1 1 1 1 1 LS LS LS LS LS LS 3.5% 10% 28% 0.5% 10% 2% $ $ $ Annual Maintenance Subtotal $ 14 Months 0.36% $ $831,785 $386,419 $194,913 $ $ 61,056 $1,474,173 $ 61,056 Escalation (to midpoint of construction) Pre-construction subtotal Construction subtotal General Construction Phase Subtotal Applicant Cost Subtotal Annual Maintenance Subtotal Escalation Subtotal $831,785 $29,112 $86,090 $265,156 $6,061 $386,419 $121,820 $24,364

Construction General 3

G.C. overhead & profit Permits and Review Fees General Construction Phase Subtotal Preparation of construction documents Applicant Cost to Manage Design Maintenance

Applicant Costs

Maintenance

Escalation

Estimate Review & Confirmation

PROJECT TOTAL

44

Applicant Project Title Preparer:

BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATE Shaking Heights, CA Fire Department Heavy Equipment Storage Stabilization 0 HAZARD: MITIGATION STRATEGY Earthquake Anchor Non-structural Component
Quantity 160 Unit Hrs. Unit Cost $28.75 $ $ $ Pre-construction subtotal Walls and partitions demolition, brick wall, 4" thick Rubbish handling, 100' haul, load, haul to chute and dumping into chute, cost to be added to demolition cost. Dump charges, typical urban city, building construction materials, includes tipping fees only Rubbish handling, up to 8 C.Y. truck, loading & trucking, haul, per mile, includes 2 mile haul, cost to be added to demolition cost. Channel framing, structural steel, field fabricated, C4x5.4, incl cutting & welding Acoustical slotted concrete masonry unit (CMU), partition, 2000 psi, 4" thick, NRC .65 type A-1, includes mortar, excludes scaffolding, horizontal reinforcing, vertical reinforcing and grout Concrete masonry unit (CMU), high strength, hollow, 5000 psi, 4" x 8" x 16", includes mortar and horizontal joint reinforcing every other course, excludes scaffolding, grout and vertical reinforcing #3 and #4 reinforcing steel bars, placed vertically, ASTM A615 Construction Subtotal Insurance and Bonds Site supervision and contract requirements 1 1 1 1 1 1 1 LS LS LS LS LS LS LS 3.5% 10% 28% 0.5% 10% 2% 4% $ $ $ Annual Maintenance Subtotal $ 9 Months 0.41% $748 $4,600 $13,886 $6,474 $3,258 $ $748 $28,966 Escalation (to mid-point of construction) Pre-construction subtotal Construction subtotal 280 5 7 50 160 S.F. C.Y. Ton C.Y. L.F. $2.13 $46.00 $90.00 $0.83 $34.49 $4,600 $596 $230 $630 $42 $5,518 Task Cost $4,600

Estimating Step

Project Phase

Description Remove equipment from storage shelves and remove shelves to storage

Pre-Construction (Specify)

Construction (Specify Phases)

280

S.F.

$10.40

$2,912

280

S.F.

$7.35

$2,058

1,000

Lb.

$1.90 $

$1,900

$13,886 $486 $1,437 $4,427 $124 $6,474 $2,036 $407 $814 $3,258

Construction General 3

G.C. overhead & profit Permits and Review Fees General Construction Phase Subtotal Preparation of construction documents Applicant Cost to Manage Design

Applicant Costs

Applicant Cost to Manage Construction Applicant Cost Subtotal Maintenance

Maintenance

Escalation

Estimate Review & Confirmation

General Construction Phase Subtotal Applicant Cost Subtotal Annual Maintenance Subtotal Escalation Subtotal

PROJECT TOTAL

45

Applicant Project Title Preparer:

BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATE Shaking Dunes, SC Earthquake Retrofit of Public Work Building J. E. Orler HAZARD: Earthquake MITIGATION STRATEGY Strengthen Structural Elements
Project Phase Description Quantity Unit Unit Cost $ $ Task Cost

Estimating Step

Pre-Construction (Specify) Pre-construction subtotal Office systems furniture, cubicle, selective demolition Ceiling demolition, suspended ceiling, mineral fiber, on suspension system, remove Walls and partitions demolition, drywall, nailed Walls and partitions demolition, metal or wood studs, finish two sides, plywood Rubbish handling, 100' haul, load, haul to chute and dumping into chute, cost to be added to demolition cost. 14,400 4,080 5,000 300 75 S.F. S.F. S.F. S.F. C.Y. $0.25 $0.64 $0.38 $2.60 $46.00

$ $ $ $3,600 $2,611 $1,900 $780 $3,450

Construction (Specify Phases)

Rubbish handling, dumpster, 30 C.Y., 10 ton capacity, weekly rental, includes one dump per week, cost to be added to demolition cost. Temporary floor protection, exterior plywood, 2 uses, 1/2" thick Steel plate, structural, for connections & stiffeners, 1/2" T, shop fabricated, incl shop primer Welding, structural steel, in field, cleaning & welding plates/bars/rods to existing beams/columns/trusses Gypsum wallboard, on walls, standard, w/compound skim coat (level 5 finish), 1/2" thick Suspended Acoustic Ceiling Tiles, fiberglass boards, film faced, 2' x 2' or 2' x 4' x 5/8" thick Paints & Coatings, walls & ceilings, interior, concrete, drywall or plaster, oil base, 2 coats, smooth finish, roller Flooring demolition, remove temporary floor protection Systems furniture, replace secretarial work station, minimum Systems furniture, replace management work station, minimum Systems furniture, replace executive work station, minimum Construction Subtotal

1 10,800 600 750 5,300 4,080 10,000 10,800 3 10 2

Week S.F. S.F. L.F. S.F. S.F. S.F. S.F. Ea. Ea. Ea.

$990.00 $0.91 $23.00 $66.00 $1.70 $1.43 $0.65 $0.81 $3,075.00 $3,500.00 $7,800.00 $

$990 $9,828 $13,800 $49,500 $9,010 $5,834 $6,500 $8,748 $9,225 $35,000 $15,600

Construction(Specify Phases)

$176,377

46

Estimating Step

Project Phase

Description Insurance and Bonds Site supervision and contract requirements

Quantity 1 1 1 0 1 1 1

Unit LS LS LS LS LS LS LS

Unit Cost 3.5% 10% 28% 0.5% 10% 2% 4% $ $ $ $

Task Cost $6,173 $18,255 $56,225 $80,653 $25,703 $5,141 $10,281 $41,125

Construction General 3

G.C. overhead & profit Permits and Review Fees General Construction Phase Subtotal Preparation of construction documents Applicant Cost to Manage Design

Applicant Costs

Applicant Cost to Manage Construction Applicant Cost Subtotal Maintenance

Maintenance Annual Maintenance Subtotal

$ 10 Months 0.36% $ $176,377 $80,653 $41,125 $ $9,202 $307,357 $9,202

Escalation

Escalation (to mid-point of construction) Pre-construction subtotal Construction subtotal

Estimate Review & Confirmation

General Construction Phase Subtotal Applicant Cost Subtotal Annual Maintenance Subtotal Escalation Subtotal

PROJECT TOTAL

47

Applicant Project Title Preparer:

BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATE Weeville, CO West Trail High School Landscaping Improvements S. Bear HAZARD: Wildfire MITIGATION STRATEGY Vegetation Control
Description Quantity Unit Unit Cost $ $ Task Cost

Estimating Step

Project Phase

Pre-Construction (Specify) Pre-construction subtotal Site clearing trees, with 335 H.P. dozer, to 24" diameter Selective clearing, brush, medium clearing, to 4" diameter, with dozer and brush rake, excludes removal offsite Grub stumps, with 335 H.P. dozer, to 36" diameter Tree pruning, 36" caliper, aerial lift equipment Ground covers, vines and climbing plants, phlox subulata, (Moss Phlox, Creeping Phlox), B&B, zone 4, 1 gallon Deciduous trees, oak, B & B, 2-1/2"-3" caliper, in prepared beds Construction (Specify Phases) Loam or topsoil, up to 200' radius, remove and stockpile on site, spread from pile to rough finish grade, by hand Lawn bed preparation, rake topsoil, site materials, adverse conditions, harley rock rake Lawn bed preparation, root raking and loading, municipal, no boulders Lawn bed preparation, spread conditioned topsoil, 6" deep, by hand Mulch, filter fabric weed barrier Mulch, stone mulch, ceramic chips, deluxe, hand spread 25 2.2 125 100 150 10 1,200 45 50 550 550 550 Ea. Acre Ea. Ea. Ea. Ea. E.C.Y. M.S.F. M.S.F. S.Y. S.Y. S.Y. $20.50 $239.00 $10.65 $608.00 $4.73 $640.00 $25.50 $205.00 $7.15 $8.45 $1.38 $15.40

$ $ $ $513 $526 $1,331 $60,800 $710 $6,400 $30,600 $9,225 $358 $4,648 $759 $8,470 $ $ $ Construction Subtotal Insurance and Bonds Site supervision and contract requirements 1 1 0 0 1 1 1 LS LS LS LS LS LS LS 3.5% 10% 28% 0.5% 10% 2% 4% $ $ $17,221 $14,156 $2,831 $5,662 $22,649 $124,338 $4,352 $12,869

Construction General 3

G.C. overhead & profit Permits and Review Fees General Construction Phase Subtotal Preparation of construction documents Applicant Cost to Manage Design

Applicant Costs

Applicant Cost to Manage Construction Applicant Cost Subtotal

48

Estimating Step

Project Phase

Description Maintenance Site maintenance, general site work maintenance, clearing brush, by hand - quarterly

Quantity

Unit

Unit Cost $

Task Cost

2,200 20

S.Y. M.S.F.

$1.28 $17.90 $

$2,816 $358

Maintenance

Site maintenance, flower bed maintenance, weed mulched bed - quarterly Annual Maintenance Subtotal

$3,174 9 Months 0.43% $ $124,338 $17,221 $22,649 $3,174 $5,517 $172,899 $5,517

Escalation

Escalation (to mid-point of construction) Pre-construction subtotal Construction subtotal

Estimate Review & Confirmation

General Construction Phase Subtotal Applicant Cost Subtotal Annual Maintenance Subtotal Escalation Subtotal

PROJECT TOTAL

49

Applicant Project Title Preparer:

BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATE Upland County, CA Library District Middle County Library Renovation C. Pasquel HAZARD: Wildfire MITIGATION STRATEGY Fire Resistant Exterior Materials
Description Quantity Unit Unit Cost $ $ Task Cost

Estimating Step

Project Phase

Pre-Construction (Specify) Pre-construction subtotal Siding demolition, wood, boards, vertical Insulation removal, rigid board Roofing and siding demolition, shingles, wood Brick veneer wall, standard face, 2x4 studs @ 16" back-up, running bond 5,000 15,000 12,000 5,400 12,000 12,000 S.F. B.F. S.F. S.F. S.F. S.F. $0.90 $0.10 $0.83 $20.75 $6.98 $2.55

$ $ $ $4,501 $1,500 $9,960 $112,059 $83,760 $30,590 $ $ Construction Subtotal Insurance and Bonds Site supervision and contract requirements 1 0 0 1 1 1 1 LS LS LS LS LS LS LS 3.5% 10% 28% 0.5% 10% 2% 4% $ $ $ Annual Maintenance Subtotal $ 12 Months 0.41% $ $242,370 $9,737 $40,337 $ $12,343 $304,788 $12,343 Escalation (to mid-point of construction) Pre-construction subtotal Construction subtotal $ $ $1,254 $9,737 $25,211 $5,042 $10,084 $40,337 $242,370 $8,483

Construction (Specify Phases)

Slate roofing, shingles, 3/16" thick, 4" min slope, 8.0 PSF Insulation, rigid, roof deck, polyisocyanurate, 2#/CF, 3.5" thick, R25

Construction General 3

G.C. overhead & profit Permits and Review Fees General Construction Phase Subtotal Preparation of construction documents Applicant Cost to Manage Design

Applicant Costs

Applicant Cost to Manage Construction Applicant Cost Subtotal Maintenance

Maintenance

Escalation

Estimate Review & Confirmation

General Construction Phase Subtotal Applicant Cost Subtotal Annual maintenance Subtotal Escalation Subtotal

PROJECT TOTAL

50

Applicant Project Title Preparer:

BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATE Sedge County, Florida Emergency Wildfire Suppression Water Storage T. Bear HAZARD: Wildfire MITIGATION STRATEGY Suppression
Description Land acquisition Quantity 1.5 Unit Acres Unit Cost $3,500.00 $ $ $ Pre-construction subtotal Clear and grub, cut & chip, light trees, to 6" diameter Stripping and stockpiling, topsoil, sandy loam, adverse conditions, 200 H.P. dozer Fine grade, fine grade for slab on grade, machine Fill, from stockpile, 130 H.P., 2-1/2 C.Y., 300' haul, spread fill, with front-end loader, excludes compaction Compaction, riding, vibrating roller, 3 passes, 6" lifts Backfill, structural, common earth, 80 H.P. dozer, 50' haul, excludes compaction 1.00 450.00 3,400.00 1,150.00 1,150.00 800.00 800.00 1.00 Acre C.Y. S.Y. L.C.Y. E.C.Y. L.C.Y. E.C.Y. Ea. $3,475.00 $1.51 $1.32 $2.60 $0.49 $1.06 $0.37 $31,400.00 $5,250 $3,475 $680 $4,488 $2,990 $564 $848 $296 $31,400 Task Cost $5,250

Estimating Step

Project Phase

Pre-Construction (Specify)

Construction (Specify Phases)

Compaction, riding, vibrating roller, 2 passes, 6" lifts Storage Tanks, vinyl coated fabric pillow type, freestanding, 50,000 gallons, excl. supporting embankment Aggregate base course, for roadways and large paved areas, alternate method to figure base course, crushed stone, compacted, 3/4", 6" deep Chain link fence, industrial, galvanized steel, 6 ga. wire, 2-1/2" posts @ 10' OC, 8' high, includes excavation Chain link fence, double swing gates, 6' high, 20' opening Construction Subtotal Insurance and Bonds Site supervision and contract requirements

270.00

E.C.Y.

$43.50

$11,745

570.00 2.00

L.F. Opng.

$44.00 $1,675.00

$25,080 $3,350 $84,915

1 1 1 1 1 1 1

LS LS LS LS LS LS

3.5% 10% 28% 0.5% 10% 2% 4%

$2,972 $8,789 $27,069 $645 $39,475 $12,439 $2,488 $4,976 $19,902

Construction General

G.C. overhead & profit Permits and Review Fees General Construction Phase Subtotal Preparation of construction documents Applicant Cost to Manage Design

Applicant Costs

Applicant Cost to Manage Construction Applicant Cost Subtotal

51

Estimating Step

Project Phase Maintenance

Description

Quantity

Unit

Unit Cost $ $

Task Cost

Maintenance

Labor for weed control: Laborer 2 days/month Annual Maintenance Subtotal Escalation (to mid-point of construction) Pre-construction subtotal Construction subtotal

192 11

Hrs. Months

$31.76 0.42%

$6,098 $6,098 $5,706 $5,250 $84,915 $39,475 $19,902 $6,098 $5,706 $161,346

Escalation

Estimate Review & Confirmation

General Construction Phase Subtotal Applicant Cost Subtotal Annual Maintenance Subtotal Escalation Subtotal

PROJECT TOTAL

52

Applicant Project Title Preparer:

BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATE Seawinds, Texas Town Hall Strengthening Norman Storm HAZARD: Wind Roof and Load Path Strengthening and MITIGATION STRATEGY Shutters
Description Quantity Unit Unit Cost $ $ Task Cost

Estimating Step

Project Phase

Pre-Construction (Specify)

Relocation costs: moving expenses Relocation costs: rental assistance Pre-construction subtotal Roof Reinforcement Light Framing, average for all light framing Labor productivity for restricted work space for crew of two carpenters Load Path Reinforcement Ceiling demolition, drywall, furred and nailed, remove Walls and partitions demolition, drywall, nailed Selective demolition, rubbish handling, dumpster, 30 C.Y., 10 ton capacity, weekly rental, includes one dump per week, cost to be added to demolition cost. Selective demolition, rubbish handling, 100' haul, load, haul to chute and dumping into chute, cost to be added to demolition cost. Timber Connectors, joist & beam hangers, galvanized, 18 gauge, for 2" x 6" to 2" x 10" joist Timber Connectors, split rings, twist straps, 18 gauge, 12" x 1-1/4" Concrete impact drilling, for anchors, 3/8" dia, in concrete or brick walls and floors, incl bit & layout, excl anchor, for each additional inch of depth, add Anchor, expansion shield, zinc, 3/8" dia x 1-1/2" L, single, in concrete, brick or stone, excl layout & drilling Gypsum wallboard, on beams, columns, or soffits, w/compound skim coat (level 5 finish), 1/2" thick Paints & Coatings, walls & ceilings, interior, concrete, drywall or plaster, oil base, 3 coats, smooth finish, roller 3,820 2,300 4 S.F. S.F. Week $1.00 $0.40 $990.00 1 3 M.B.F. Days $1,599.94 $1,009.60

$ $ $ $ $1,600 $3,029

$3,819 $925 $3,960

10 560 570 160

C.Y. Ea. Ea. Ea.

$48.50 $4.14 $7.30 $1.51

$485 $2,318 $4,162 $242

Construction (Specify Phases)

160 3,820

Ea. S.F.

$8.05 $2.24

$1,288 $8,557

3,820

S.F.

$0.88

$3,362

53

Estimating Step

Project Phase

Description Ceiling Suspension System, class A, 15/16" T bar, 2' x 4" grid Exterior Shutters, polystyrene, solid raised panel, 16" wide x 80" long Door hardware, hinges, full mortise, average frequency, steel base, USP, 6" x 6" Concrete impact drilling, for anchors, 1/4" dia, in concrete or brick walls and floors, incl bit & layout, excl anchor, for each additional inch of depth, add Anchor, expansion shield, zinc, 1/4" dia x 1-5/16" L, single, in concrete, brick or stone, excl layout & drilling

Quantity 2,300 72 144 576

Unit S.F. Pr. Pr. Ea.

Unit Cost $1.21 $129.01 $85.80 $1.20

Task Cost $2,783 $9,288 $12,355 $691

Construction(Specify Phases)

576

Ea.

$6.90 $ $ $ $ $

$3,975

Construction Subtotal Insurance and Bonds Site supervision and contract requirements Construction General 3 G.C. overhead & profit Permits and Review Fees General Construction Phase Subtotal Preparation of construction documents Applicant Cost to Manage Design Applicant Costs Applicant Cost to Manage Construction Applicant Cost Subtotal Maintenance 4 Maintenance Annual Maintenance Subtotal 5 Escalation Escalation (to mid-point of construction) Pre-construction subtotal Construction subtotal 6 Estimate Review & Confirmation General Construction Phase Subtotal Applicant Cost Subtotal Annual Maintenance Subtotal Escalation Subtotal PROJECT TOTAL $ 11 Months 0.41% $ $ $ $ $ 1 1 1 LS LS LS 10% 2% 4% 1 1 1 0 LS LS LS LS 3.5% 10% 28% 0.5% $

$62,839 $2,199 $6,504 $20,032 $28,735 $9,157 $1,831 $3,663 $14,652

$4,110 $62,839 $28,735 $14,652 $4,110 $110,335

54

Applicant Project Title Preparer:

BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATE Prairieland Texas School Board Flattop Elementary School Tornado Safe room B. Eddy HAZARD: Wind MITIGATION STRATEGY Tornado Safe Room
Description Quantity Unit Unit Cost $ $ Task Cost

Estimating Step

Project Phase

Pre-Construction (Specify) Pre-construction subtotal Strip footing, concrete, reinforced, Foundation wall, CIP, Slab on grade, 6" thick, light industrial, reinforced Concrete block (CMU) wall, regular weight, solid, double wythe, reinforced and grouted Concrete block (CMU) partition, regular weight, solid, 6" thick, no finish Exterior Door, steel 18 gauge, hollow metal, 1 door with frame, "A" label, 3'-0" x 7'-0" opening Metal door/metal frame, flush, composite, 18 ga full panel, 3'-0" x 6'-8", KD drywall frame, 4-7/8" Interior Door frames, steel channels with anchors and bar stops, 8" channel@ 11.5 lb/LF, 6' x 8' door, weighs 275 lb 180 180 900 1,200 300 2 2 1 2 1,500 900 900 900 1 900 900 2 L.F. L.F. S.F. S.F. S.F. Opng. Ea. Ea. Ea. S.F. S.F. S.F. S.F. Ea. S.F. S.F. Ea. $38.55 $60.35 $6.76 $17.80 $7.75 $1,740.00 $870.00 $655.55 $360.00 $1.75 $3.34 $1.26 $3.10 $7,250.00 $3.17 $0.76 $1,185.00

$ $ $ $6,939 $10,863 $6,084 $21,360 $2,325 $3,480 $1,740 $656 $720 $2,625 $3,006 $1,134 $2,790 $7,250 $2,853 $684 $2,370

Construction (Specify Phases)

Interior Doors, commercial, steel, flush, full panel, hollow core, 18 ga., 3'-0" x 6'-8" x 1-3/4" thick Painting, masonry or concrete, latex, brushwork, primer & 2 coats Roof, steel joists, on bearing walls Insulation, rigid, roof deck, fiberboard, high density, 3'x4' sheets, 1-1/2" thick, R3.8 Roofing, coal tar pitch, gravel, coated glass fiber base sheet, 3 plies glass fiber felt (Type IV), mopped, on nailable deck Switchgear installation, incl switchboard, panels & circuit breaker, 400 A Receptacles and wall switches, 600 SF, 10 receptacles Receptacles and wall switches, 600 SF, 2 switches Urinal, vitreous china, wall hung

55

Estimating Step

Project Phase

Description Water closets, battery mount, wall hung, side by side, first closet Water closets, battery mount, wall hung, side by side, each additional water closet, add Lavatories, battery mount, side by side, first lavatory Lavatories, battery mount, side by side, each additional lavatory, add Heat pump, thru-the-wall, supplemental electric heat, cabinet, louver, 1-1/2 ton Partitions, toilet, cubicles, ceiling hung, painted metal Partitions, toilet, cubicles, floor & ceiling anchored, incl. 52" grab bars, for handicap units, add Construction Subtotal Insurance and Bonds Site supervision and contract requirements

Quantity 1 5 1 3 2 6 2

Unit Ea. Ea. Ea. Ea. Ea. Ea. Ea.

Unit Cost $1,720.00 $1,615.00 $1,540.00 $1,245.00 $3,205.00 $705.00 $330.00 $

Task Cost $1,720 $8,075 $1,540 $,735 $6,410 $4,230 $660

Construction (Specify Phases)

$103,249 1 1 1 0 1 1 1 LS LS LS LS LS LS LS 3.5% 10% 28% 0.5% 10% 2% 4% $ $ $ $ $47,213 $15,046 $3,009 $6,018 $24,074 $3,614 $10,686 $32,914

Construction General 3

G.C. overhead & profit Permits and Review Fees General Construction Phase Subtotal Preparation of construction documents Applicant Cost to Manage Design

Applicant Costs

Applicant Cost to Manage Construction Applicant Cost Subtotal Maintenance

Maintenance Annual Maintenance Subtotal

$ 11 months 0.41% $ $103,249 $47,213 $24,074 $ $6,753 $181,289 $6,753

Escalation

Escalation (to mid-point of construction) Pre-construction subtotal Construction subtotal

Estimate Review & Confirmation

General Construction Phase Subtotal Applicant Cost Subtotal Annual maintenance Subtotal Escalation Subtotal

PROJECT TOTAL

56

Applicant Project Title Preparer:

BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATE Palisades County, New Jersey Dept. of Roads Hill Bench Road Stabilization N. Wetfoot HAZARD: Landslide MITIGATION STRATEGY Drainage Improvements
Description Site survey Geotechnical Borings Quantity 1 1 Unit LS LS Unit Cost $5,000.00 $27,500.00 $ $ Pre-construction subtotal Minor site demolition, patio/carport, bituminous, to 6" thick, with hand held air equipment, excludes hauling Demo guard rail, corrugated steel Demo guard rail, wood posts Rubbish handling, loading & trucking, machine loading truck, includes 2 mile haul, cost to be added to demolition cost. Rubbish handling, up to 8 C.Y. truck, loading & trucking, haul, per mile, includes 2 mile haul, cost to be added to demolition cost. Dump charges, typical urban city, reclamation station, usual charge, includes tipping fees only Excavating, trench or continuous footing, common earth, 1/2 C.Y. excavator, 1' to 4' deep, excludes sheeting or dewatering 1,000 600 75 20 S.F. L.F. Ea. C.Y. $1.29 $2.38 $5.95 $18.30 $32,500 $1,290 $1,428 $446 $366 Task Cost $5,000 $27,500

Estimating Step

Project Phase

Pre-Construction (Specify)

100 30 80

C.Y. Ton B.C.Y.

$0.81 $104.50 $5.65

$81 $3,135 $452

Construction (Specify Phases)

Excavating, trench or continuous footing, common earth, 1/2 C.Y. excavator, 4' to 6' deep, excludes sheeting or dewatering Drainage geotextiles, fabric, laid in trench, polypropylene, ideal conditions Bedding, for pipe and conduit, crushed or screened bank run gravel, excludes compaction Corrugated plastic tubing, perforated or plain, in rolls, 8" diameter, excludes excavation and backfill Piping, HDPE, butt fusion joints, 40' lengths, 24" diameter, SDR 21 Excavating, trench backfill, 1 C.Y. bucket, minimal haul, front end loader, wheel mounted, excludes dewatering Asphaltic concrete pavement, for highways and large paved areas, pavement replacement over trench, 6" thick, for paving projects 300 tons or less add for trucking

50 450 500 500 50 30

B.C.Y. S.Y. L.C.Y. L.F. L.F. L.C.Y.

$5.65 $1.90 $36.00 $10.30 $116.00 $2.17

$283 $855 $18,000 $5,150 $5,800 $65

125

S.Y.

$61.99

$7,748

57

Estimating Step

Project Phase

Description Manholes, concrete, precast, 4' I.D., 6' deep, excludes base, excavation, backfill, frame and cover Manhole steps, heavyweight cast iron, 8" x 9" Catch basins, frames and covers, cast iron, heavy traffic, 24" diameter, 400 lb., excludes footing, excavation, and backfill Fine grade, slopes, steep, gentle, finish grading Soil stabilization, geotextile fabric, woven, heavy duty, 600 lb. tensile strength Rip-rap, random, broken stone, 18" minimum thickness, machine placed for slope protection, not grouted Guide/Guard rail, corrugated steel, galvanized steel posts, install wrap around end section Guide/Guard rail, corrugated steel, galvanized steel posts, install metal guide/guard rail, double face, steel posts 6' - 3" O.C., W6x8 posts Construction Subtotal Insurance and Bonds Site supervision and contract requirements

Quantity 2 4 2 200 200 200 2 600

Unit Ea. Ea. Ea. S.Y. S.Y. S.Y. Ea. L.F.

Unit Cost $1,799.87 $38.00 $469.97 $0.20 $2.34 $84.00 $165.00 $32.50

Task Cost $3,600 $152 $940 $40 $468 $16,799 $330 $19,500 $86,928

Construction(Specify Phases)

1 1 1 1 1 1 1

LS LS LS LS LS LS

3.5% 10% 28% 0.5% 10% 2% 4% $ $ $

$3,042 $8,997 $27,711 $796 $40,546 $12,747 $2,549 $5,099 $20,396

Construction General 3

G.C. overhead & profit Permits and Review Fees General Construction Phase Subtotal Preparation of construction documents Applicant Cost to Manage Design

Applicant Costs

Applicant Cost to Manage Construction Applicant Cost Subtotal Maintenance

Maintenance Annual Maintenance Subtotal

$ 9 Months 0.33% $3,729 $32,500 $86,928 $40,546 $20,396 $ $3,729 $184,100

Escalation

Escalation (to mid-point of construction) Pre-construction subtotal Construction subtotal

Estimate Review & Confirmation

General Construction Phase Subtotal Applicant Cost Subtotal Annual Maintenance Subtotal Escalation Maintenance Subtotal

PROJECT TOTAL

58

Applicant Project Title Preparer:

BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATE Puma, WV Dept. of Highways Sliding Hill Road Slope Stabilization I. M. Ivy HAZARD: Landslide MITIGATION STRATEGY Bio-Engineered Slope Stabilization
Description Quantity Unit Unit Cost $ $ Task Cost

Estimating Step

Project Phase

Pre-Construction (Specify) Pre-construction subtotal Fine grade, slopes, steep, gentle, finish grading Stolens, sprigging, broadcast, 6 bushels per M.S.F., hydro planter Mulch, filter fabric weed barrier Construction (Specify Phases) Ground covers, vines and climbing plants, arctostaphylos uva-ursi, (Bearberry), container, zone 2, 3" pot Planting, trees, shrubs and ground cover, light soil, bare root seedlings, 6" to 10", includes planting only 10,800 100 10,800 40,000 40,000 S.Y. M.S.F. S.Y. Ea. Ea. $0.20 $30.00 $1.38 $1.82 $0.69

$ $ $ $2,160 $3,000 $14,904 $72,800 $27,600 $ $ Construction Subtotal Insurance and Bonds Site supervision and contract requirements 1 1 0 0 1 1 1 LS LS LS LS LS LS LS 3.5% 10% 28% 0.5% 10% 2% 4% $ $ $16,684 $13,715 $2,743 $5,486 $21,944 $120,464 $4,216 $12,468

Construction General 3

G.C. overhead & profit Permits and Review Fees General Construction Phase Subtotal Preparation of construction documents Applicant Cost to Manage Design

Applicant Costs

Applicant Cost to Manage Construction Applicant Cost Subtotal

59

Estimating Step

Project Phase Maintenance

Description

Quantity

Unit

Unit Cost $ $ $

Task Cost

Maintenance Annual Maintenance Subtotal

$ 11 Months 0.42% $ $120,464 $16,684 $21,944 $ $6,291 $165,383 $6,291

Escalation

Escalation (to mid-point of construction) Pre-construction subtotal Construction subtotal

Estimate Review & Confirmation

General Construction Phase Subtotal Applicant Cost Subtotal Annual Maintenance Subtotal Escalation Subtotal

PROJECT TOTAL

60

Applicant Project Title Preparer:

BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATE Springflow, NY Public Works Dept. Easthill Road Slope Stabilization R. Mountain HAZARD: Landslide MITIGATION STRATEGY Toe Armoring
Description Quantity Unit Unit Cost $ $ Task Cost

Estimating Step

Project Phase

Pre-Construction (Specify) Pre-construction subtotal Sheet piling, steel, 22 psf, 15' excavation, drive, extract and salvage, excludes wales Excavating, trench or continuous footing, common earth, 3/8 C.Y. excavator, 1' to 4' deep, excludes sheeting or dewatering Gabions, galvanized steel mesh mats or boxes, stone filled, 36" deep 150 120 350 700 700 1,000 1,000 Ton B.C.Y. S.Y. S.Y. S.Y. Ea. Ea. $1,675.00 $7.25 $126.00 $0.20 $1.38 $2.09 $3.70

$ $ $ $251,250 $870 $44,100 $140 $966 $2,090 $3,700 $303,116 1 1 1 0 1 1 1 LS LS LS LS LS LS LS 3.5% 10% 28% 0.5% 10% 2% 4% $ $138,609 $44,172 $8,834 $17,669 $70,676 $10,609 $31,373 $96,627

Construction (Specify Phases)

Fine grade, slopes, steep, gentle, finish grading Mulch, filter fabric weed barrier Ground covers, vines and climbing plants, achillea tomentosa, (Woolly Yarrow), container, zone 4, 1 quart Planting, trees, shrubs and ground cover, light soil, bare root seedlings, 3" to 5", includes planting only Construction Subtotal Insurance and Bonds Site supervision and contract requirements

Construction General 3

G.C. overhead & profit Permits and Review Fees General Construction Phase Subtotal Preparation of construction documents Applicant Cost to Manage Design

Applicant Costs

Applicant Cost to Manage Construction Applicant Cost Subtotal

61

Estimating Step

Project Phase Maintenance

Description

Quantity

Unit

Unit Cost $ $ $

Task Cost

Maintenance Annual Maintenance Subtotal

$ 12 Months 0.33% $ $303,116 $138,609 $70,676 $ $17,227 $529,628 $ 17,227

Escalation

Escalation (to mid-point of construction) Pre-construction subtotal Construction subtotal

Estimate Review & Confirmation

General Construction Phase Subtotal Applicant Cost Subtotal Annual Maintenance Subtotal Escalation Subtotal

PROJECT TOTAL

62

Applicant Project Title Preparer:

BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATE Sweep Township Department of Roads South School Road Retaining Wall W. Swagit HAZARD: Landslide MITIGATION STRATEGY Retaining Wall
Description Quantity Unit Unit Cost $ $ Task Cost

Estimating Step

Project Phase

Pre-Construction (Specify) Pre-construction subtotal Excavating, trench or continuous footing, common earth, 3/4 C.Y. excavator, 1' to 4' deep, excludes sheeting or dewatering Dewatering, pumping, 8 hr., attended 2 hours per day, 2" diaphragm pump used for 8 hours, includes 20 L.F. of suction hose and 100 L.F. of discharge hose Hauling, excavated or borrow material, loose cubic yards, 10 mile round trip, .6 loads/hr , base wide rate, 12 C.Y. truck, highway haulers, excludes loading Fine grade, slopes, steep, gentle, finish grading Gabion retaining wall, sloped backfill, 1.5:1, stepped face, 9' base, 15' high, counterforts @ 16", clay soil Stolens, sprigging, 6" O.C., walk behind sprig planter Construction Subtotal Insurance and Bonds Site supervision and contract requirements Construction General G.C. overhead & profit Permits and Review Fees 0 1 1 1 General Construction Phase Subtotal Preparation of construction documents Applicant Cost to Manage Design Applicant Costs Applicant Cost to Manage Construction Applicant Cost Subtotal LS LS LS 10% 2% 4% 250 B.C.Y. $5.20

$ $ $ $1,300

10

Day

$177.00

$1,770

Construction (Specify Phases)

150 200 150 2

L.C.Y. S.Y. L.F. M.S.F.

$16.36 $0.20 $2,085.00 $20.50

$2,454 $40 $312,750 $31 $318,345

1 1

LS LS LS LS

3.5% 10% 28% 0.5% $ $

$11,142 $32,949

$44,091 $36,244 $7,249 $14,497 $57,990

63

Estimating Step

Project Phase Maintenance

Description

Quantity

Unit

Unit Cost $ $ $

Task Cost

Maintenance Annual Maintenance Subtotal

$ 12 Months 0.42% $ $318,345 $44,091 $57,990 $ $18,136 $438,561 $18,136

Escalation

Escalation (to mid-point of construction) Pre-construction subtotal Construction subtotal

Estimate Review & Confirmation

General Construction Phase Subtotal Applicant Cost Subtotal Annual Maintenance Subtotal Escalation Subtotal

PROJECT TOTAL

64

Applicant Project Title Preparer:

BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATE Hudson Township, NY Acquire 4 homes on River Road C. Flood HAZARD: Flood MITIGATION STRATEGY Acquisition
Description Purchase property and improvements Appraisal fees Property surveys Transaction closing fees Pre-construction subtotal Bulk Asbestos Removal, asbestos shingle roofing, incl. disp. & tools Building demolition, single family, one story house, wood, 4,800 4 275 275 10,000 S.F. Ea. C.Y. C.Y. S.Y. $1.13 $6,050.00 $17.75 $18.30 $2.72 $ $ Construction Subtotal Insurance and Bonds Site supervision and contract requirements G.C. overhead & profit Permits and Review Fees General Construction Phase Subtotal Preparation of construction documents Applicant Cost to Manage Design 1 1 1 LS LS LS 10% 2% 4% 1 1 1 1 LS LS LS LS 3.5% 10% 28% 0.5% $ $31,004 $9,774 $1,955 $3,910 $15,639 $66,738 $2,336 $6,907 $21,275 $486 Quantity 4 4 4 4 Unit Ea. Lots Lots Lots Unit Cost $275,000.00 $1,500 $750 $1,000 $ $1,113,000 $5,424 $24,200 $4,881 $5,033 $27,200 Task Cost $1,100,000 $6,000 $3,000 $4,000

Estimating Step

Project Phase

Pre-Construction (Specify)

Construction (Specify Phases)

Selective demolition, disposal only, Rubbish handling, loading & trucking, machine loading truck. Seeding, fine grading and seeding, with equipment

Construction General 3

Applicant Costs

Applicant Cost to Manage Construction Applicant Cost Subtotal

65

Estimating Step

Project Phase

Description Maintenance Mowing, lawn mowing, 3 gang reel, 7', with tractor & attachments Annual Maintenance Subtotal

Quantity

Unit

Unit Cost $

Task Cost

Maintenance

170.00

M.S.F.

$0.71 $

$121

$121 17 Months 0.33% $5,400 $1,113,000 $66,738 $31,004 $15,639 $121 $5,400 $1,231,901

Escalation

Escalation (To mid-point of construction) Pre-construction subtotal Construction subtotal

Estimate Review & Confirmation

General Construction Phase Subtotal Applicant Cost Subtotal Annual Maintenance Subtotal Escalation Subtotal

PROJECT TOTAL

66

APPENDIX C: Cost Estimating Storyboard

67

Sample BCA Tool Cost Estimating Screenshot

68

APPENDIX D: Scope Builder Checklists

69

Scope Builder Checklist Flood - Proofing Project


Pre Construction Inspection Fees Content Relocation Content Storage Rental Construction Prep Foundation General Demolition Replace Wallboard Finish and Paint Water Stops for Sewer & Drains Shelves to Elevate Contents Window & Door Seals Elevate Outlet Locations Structural Modifications Landscaping/Planting Ancillary Costs (if not included with construction costs) Mobilization/De-Mobilization CG Overhead & Profit Site Supervision
The above checklist is in no way inclusive of all possible elements that may be encountered with any given project. Some project may have a greater number of elements, while others may have fewer elements. This checklist is to help the user to start to think of elements to be considered.

Ancillary Costs (if not included with construction costs) contd Bonds & Insurance Architect/Engineer/Planner Fees Permits and Plan Review Fees Project Management Costs Maintenance Access/Egress Drainage Structure Cleaning Total Annual Maintenance Costs Maintenance Period in Years

70

Pre Construction Appraisers Fees Inspection Fees Site Acquisition Costs Property Survey Moving Expenses Construction

Scope Builder Checklist Flood - Relocation Project

Ancillary Costs (if not included with construction costs) contd Bonds & Insurance Architect/Engineer/Planner Fees Permits and Plan Review Fees Attorney Fees/Appraisals Real Estate Transaction Fees/Closing Costs Project Management Costs Maintenance Mowing Access/Egress Drainage Structure Cleaning Landscaping/Planting Total Annual Maintenance Costs Maintenance Period in Years

Hazardous Material Disposition General Demolition Activities Well & Septic Abandonment Utilities Disconnect Underground Storage Tank Removal Import/Export Fill Final Grading Access/Egress Drainage Features Landscaping/Planting Ancillary Costs (if not included with construction costs) Mobilization/De-Mobilization CG Overhead & Profit Site Supervision

The above checklist is in no way inclusive of all possible elements that may be encountered with any given project. Some project may have a greater number of elements, while others may have fewer elements. This checklist is to help the user to start to think of elements to be considered.

71

Scope Builder Checklist Flood - Drainage Structure Project


Pre Construction Property Survey Drainage Study Construction Equipment Rental General Demolition Activities Materials Hauling Excavation Dewatering Import/Export Fill Final Grading Access/Egress Drainage Structures/Features Landscaping/Planting Ancillary Costs (if not included with construction costs) Mobilization/De-Mobilization CG Overhead & Profit Site Supervision
The above checklist is in no way inclusive of all possible elements that may be encountered with any given project. Some project may have a greater number of elements, while others may have fewer elements. This checklist is to help the user to start to think of elements to be considered.

Ancillary Costs (if not included with construction costs) contd Bonds & Insurance Architect/Engineer/Planner Fees Permits and Plan Review Fees Project Management Costs Maintenance Mowing Access/Egress Drainage Structure Cleaning Landscaping/Planting Total Annual Maintenance Costs Maintenance Period in Years

72

Scope Builder Checklist Flood - Elevation Project


Pre Construction Appraisers Fees Inspection Fees Property Survey Construction General Demolition Activities Material Disposal Utilities Disconnect New Utilities Extensions New Foundations/Piles/Piers Import/Export Fill ADA Compliance Final Grading Access/Egress Drainage Features Landscaping/Planting Ancillary Costs (if not included with construction costs) Mobilization/De-Mobilization CG Overhead & Profit Site Supervision
The above checklist is in no way inclusive of all possible elements that may be encountered with any given project. Some project may have a greater number of elements, while others may have fewer elements. This checklist is to help the user to start to think of elements to be considered.

Ancillary Costs (if not included with construction costs) contd Bonds & Insurance Architect/Engineer/Planner Fees Permits and Plan Review Fees Attorney Fees/Appraisals Real Estate Transaction Fees/Closing Costs Project Management Costs Maintenance Mowing Access/Egress Drainage Structure Cleaning Landscaping/Planting Total Annual Maintenance Costs Maintenance Period in Years

73

Scope Builder Checklist Flood - Acquisition Project


Pre Construction Appraisers Fees Inspection Fees Property Survey Construction Hazardous Material Disposition General Demolition Activities Well & Septic Abandonment Utilities Disconnect Underground Storage Tank Removal Import/Export Fill Final Grading Access/Egress Drainage Features Landscaping/Planting Ancillary Costs (if not included with construction costs) Mobilization/De-Mobilization CG Overhead & Profit Site Supervision
The above checklist is in no way inclusive of all possible elements that may be encountered with any given project. Some project may have a greater number of elements, while others may have fewer elements. This checklist is to help the user to start to think of elements to be considered.

Ancillary Costs (if not included with construction costs) contd Bonds & Insurance Architect/Engineer/Planner Fees Permits and Plan Review Fees Attorney Fees/Appraisals Real Estate Transaction Fees/Closing Costs Project Management Costs Maintenance Mowing Access/Egress Drainage Structure Cleaning Landscaping/Planting Total Annual Maintenance Costs Maintenance Period in Years

74

Scope Builder Checklist Seismic - Non-Structural Elements Project


Pre Construction Inspection Fees Property Survey Construction General Demolition Activities Special Access Requirements Removal of Old Improvements Utility Considerations Equipment Anchors Interior Finishing & Painting ADA Requirements Shut-off Valves Flex Connections Ancillary Costs (if not included with construction costs) Mobilization/De-Mobilization CG Overhead & Profit Site Supervision
The above checklist is in no way inclusive of all possible elements that may be encountered with any given project. Some project may have a greater number of elements, while others may have fewer elements. This checklist is to help the user to start to think of elements to be considered.

Ancillary Costs (if not included with construction costs) contd Bonds & Insurance Architect/Engineer/Planner Fees Permits and Plan Review Fees Project Management Costs Maintenance Access/Egress Inspections/Replacement Painting Total Annual Maintenance Costs Maintenance Period in Years

75

Scope Builder Checklist Seismic - Structural Elements Project


Pre Construction Inspection Fees Property Survey Construction General Demolition Activities Special Access Requirements Utilities Considerations Moment Framing Cross Bracing Roof/Floor Systems Roof to Wall Connections Wall to Floor Connections Shear Anchors Foundation Modifications Ancillary Costs (if not included with construction costs) Mobilization/De-Mobilization CG Overhead & Profit Site Supervision
The above checklist is in no way inclusive of all possible elements that may be encountered with any given project. Some project may have a greater number of elements, while others may have fewer elements. This checklist is to help the user to start to think of elements to be considered.

Ancillary Costs (if not included with construction costs) contd Bonds & Insurance Architect/Engineer/Planner Fees Permits and Plan Review Fees Attorney Fees/Appraisals Project Management Costs Maintenance Access/Egress Total Annual Maintenance Costs Maintenance Period in Years

76

Scope Builder Checklist Wildfire - Vegetation Control Project


Pre Construction Erosion/Environmental Study Property Survey Construction Selective Clearing & Grubbing Debris Disposal Re-planting Vegetation Ground Cover Erosion Controls Final Grading Access/Egress Drainage Features Landscaping/Planting Ancillary Costs (if not included with construction costs) Mobilization/De-Mobilization CG Overhead & Profit Site Supervision
The above checklist is in no way inclusive of all possible elements that may be encountered with any given project. Some project may have a greater number of elements, while others may have fewer elements. This checklist is to help the user to start to think of elements to be considered.

Ancillary Costs (if not included with construction costs) contd Bonds & Insurance Architect/Engineer/Planner Fees Permits and Plan Review Fees Attorney Fees/Appraisals Real Estate Transaction Fees/Closing Costs Project Management Costs Maintenance Mowing Access/Egress Fire-break Maintenance/Clearing Landscaping/Planting Total Annual Maintenance Costs Maintenance Period in Years

77

Scope Builder Checklist Wildfire - Resistant Exterior Project


Pre Construction Appraisers Fees Property Survey Construction Hazardous Material Disposition General Demolition Activities Debris Disposal Utilities Consideration Windows & Doors Roofing Material Glazing Exterior Wall Materials Landscaping/Planting Ancillary Costs (if not included with construction costs) Mobilization/De-Mobilization CG Overhead & Profit Site Supervision
The above checklist is in no way inclusive of all possible elements that may be encountered with any given project. Some project may have a greater number of elements, while others may have fewer elements. This checklist is to help the user to start to think of elements to be considered.

Ancillary Costs (if not included with construction costs) contd Bonds & Insurance Architect/Engineer/Planner Fees Permits and Plan Review Fees Attorney Fees/Appraisals Project Management Costs Maintenance General Material Maintenance Total Annual Maintenance Costs Maintenance Period in Years

78

Scope Builder Checklist Wildfire - Suppression Project


Pre Construction Property Acquisition Inspection Fees Property Survey Construction General Demolition Activities Clearing & Grubbing Well Installation Storage Tank Installation Waterline Installation Hydrant Installation Import/Export Fill Final Grading Access/Egress Landscaping/Planting Ancillary Costs (if not included with construction costs) Mobilization/De-Mobilization CG Overhead & Profit Site Supervision
The above checklist is in no way inclusive of all possible elements that may be encountered with any given project. Some project may have a greater number of elements, while others may have fewer elements. This checklist is to help the user to start to think of elements to be considered.

Ancillary Costs (if not included with construction costs) contd Bonds & Insurance Architect/Engineer/Planner Fees Permits and Plan Review Fees Attorney Fees/Appraisals Real Estate Transaction Fees/Closing Costs Project Management Costs Maintenance Mowing Access/Egress Drainage Structure Cleaning Landscaping/Planting Total Annual Maintenance Costs Maintenance Period in Years

79

Scope Builder Checklist Wind - Load Path Strengthening & Shutters Project
Pre Construction Content Relocation Content Storage Fees Construction Hazardous Material Disposition General Demolition Activities Debris Disposal Framing Roof to Wall Connector Installation Wall to Floor Connector Installation Anchor Installation Shutter Installation Finishing & Painting Special Access/Inspection Ports Glazing & Coatings Shutters Ancillary Costs (if not included with construction costs) Mobilization/De-Mobilization CG Overhead & Profit Site Supervision
The above checklist is in no way inclusive of all possible elements that may be encountered with any given project. Some project may have a greater number of elements, while others may have fewer elements. This checklist is to help the user to start to think of elements to be considered.

Ancillary Costs (if not included with construction costs) contd Bonds & Insurance Architect/Engineer/Planner Fees Permits and Plan Review Fees Project Management Costs Maintenance Routine Inspections Routine Painting Total Annual Maintenance Costs Maintenance Period in Years

80

Scope Builder Checklist Wind - Tornado Shelter Project


Pre Construction Site Acquisition Inspection Fees Property Survey Construction General Demolition Activities Re-enforce Envelope Re-locate Equipment ADA Compliance Interior Finishes Heavy Duty Windows & Doors HVAC Utility Considerations Rest Room Facilities Ancillary Costs (if not included with construction costs) Mobilization/De-Mobilization CG Overhead & Profit Site Supervision
The above checklist is in no way inclusive of all possible elements that may be encountered with any given project. Some project may have a greater number of elements, while others may have fewer elements. This checklist is to help the user to start to think of elements to be considered.

Ancillary Costs (if not included with construction costs) contd Bonds & Insurance Architect/Engineer/Planner Fees Permits and Plan Review Fees Real Estate Transaction Fees/Closing Costs Project Management Costs Maintenance Access/Egress Emergency Supplies Stocks Total Annual Maintenance Costs Maintenance Period in Years

81

Scope Builder Checklist Landslide - Drainage Improvements Project


Pre Construction Inspection Fees Property Survey Drainage Study Construction General Demolition Activities Clear & Grub Grading Drainage Structures Import/Export Fill Final Grading Outfall Armoring Drainage Features Landscaping/Planting Ancillary Costs (if not included with construction costs) Mobilization/De-Mobilization CG Overhead & Profit Site Supervision
The above checklist is in no way inclusive of all possible elements that may be encountered with any given project. Some project may have a greater number of elements, while others may have fewer elements. This checklist is to help the user to start to think of elements to be considered.

Ancillary Costs (if not included with construction costs) contd Bonds & Insurance Architect/Engineer/Planner Fees Permits and Plan Review Fees Attorney Fees/Appraisals Project Management Costs Maintenance Mowing Access/Egress Drainage Structure Cleaning Landscaping/Planting Total Annual Maintenance Costs Maintenance Period in Years

82

Scope Builder Checklist Landslide - Bio-Engineered Slope Stabilization Project


Pre Construction Stability Study Property Survey Construction Clear & Grub Rough Grading Import/Export Fill Final Grading Planting & Staking Geo-grids Erosion Control Access/Egress Drainage Features Ancillary Costs (if not included with construction costs) Mobilization/De-Mobilization CG Overhead & Profit Site Supervision
The above checklist is in no way inclusive of all possible elements that may be encountered with any given project. Some project may have a greater number of elements, while others may have fewer elements. This checklist is to help the user to start to think of elements to be considered.

Ancillary Costs (if not included with construction costs) contd Bonds & Insurance Architect/Engineer/Planner Fees Permits and Plan Review Fees Attorney Fees/Appraisals Real Estate Transaction Fees/Closing Costs Project Management Costs Maintenance Routine Inspections Routine Painting Total Annual Maintenance Costs Maintenance Period in Years

83

Scope Builder Checklist Landslide - Toe Armoring Project


Pre Construction Inspection Fees Property Survey Construction General Demolition Activities Clear & Grub Surface/Sub-surface Drains Paving or Armoring Import/Export Fill Final Grading Access/Egress Drainage Features Landscaping/Planting Ancillary Costs (if not included with construction costs) Mobilization/De-Mobilization CG Overhead & Profit Site Supervision
The above checklist is in no way inclusive of all possible elements that may be encountered with any given project. Some project may have a greater number of elements, while others may have fewer elements. This checklist is to help the user to start to think of elements to be considered.

Ancillary Costs (if not included with construction costs) contd Bonds & Insurance Architect/Engineer/Planner Fees Permits and Plan Review Fees Attorney Fees/Appraisals Project Management Costs Maintenance Mowing Access/Egress Drainage Structure Cleaning Landscaping/Planting Total Annual Maintenance Costs Maintenance Period in Years

84

Scope Builder Checklist Landslide - Retaining Wall Project


Pre Construction Inspection Fees Property Survey Construction Area Preparation General Demolition Activities Drainage Features Grading Import/Export Fill Final Grading Surface/Sub-surface Drains Landscaping/Planting Ancillary Costs (if not included with construction costs) Mobilization/De-Mobilization CG Overhead & Profit Site Supervision
The above checklist is in no way inclusive of all possible elements that may be encountered with any given project. Some project may have a greater number of elements, while others may have fewer elements. This checklist is to help the user to start to think of elements to be considered.

Ancillary Costs (if not included with construction costs) contd Bonds & Insurance Architect/Engineer/Planner Fees Permits and Plan Review Fees Attorney Fees/Appraisals Project Management Costs Maintenance Mowing Access/Egress Drainage Structure Cleaning Landscaping/Planting Total Annual Maintenance Costs Maintenance Period in Years

85

Anda mungkin juga menyukai