RENCANA ANGGARAN BIAYA (RAB)

NO URAIAN MATERIAL VOL SAT HARGA SATUAN JUMLAH TOTAL


1 Tiang PJU 7 Meter 4 Btg 4,780,000 19,120,000
2 Lampu PJU LED 70 Watt 8 Set 3,680,000 29,440,000
3 Kabel Twisteed 2x10 mm 420 Mtr 10,500 4,410,000
4 Kabel NYM 2x2.5 mm 80 Mtr 18,200 1,456,000
5 Wedge Clamp 12 Set 12,500 150,000
6 Box Panel 40x30x20 mm 1 Set 350,000 350,000
7 MCB 6A 7 Bh 120,000 840,000
8 Instalasi Listrik 3 Titik 180,000 540,000
JUMLAH 56,306,000
PPN 11% 6,193,660
JUMLAH TOTAL 62,499,660

Terbilang : Enam Puluh Dua Juta Empat Ratus Sembilan Puluh Sembilan Ribu Enam Ratus Enam
Puluh Rupiah

Tebo, 24 Mei 2023


PT. SALSA TEKNIK PRIMA

BUDI DATENG SUBAGIYO


Direktur
SPESIFIKASI TEKNIS

NO URAIAN MATERIAL SPESIFIKASI TEKNIS KET


1 Tiang PJU 7 Meter Bahan Besi Galvanis, Tinggi 7 meter ,

2 Lampu PJU LED 70 Watt Warna sumber cahaya 757 putih dingin, Jenis
LED engine LED, bahan perumahan Aluminium
cetak permanen, Panjang keseluruhan 382,5
mm, Lebar keseluruhan 248,4 mm, Tinggi
keseluruhan 85 mm

Tebo, 24 Mei 2023


PT. SALSA TEKNIK PRIMA

BUDI DATENG SUBAGIYO


Direktur
JADWAL PELAKSANAAN
HARI KE-
NO RINCIAN PEKERJAAN
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 Pekerjaan Persiapan (Mobilisasi Material)
2 Pemasangan Tiang dan Lampu
3 Pemasangan Instalasi Pos Jaga
4 Connecting dan Testing
5 Serah Terima Pekerjaan
PELAKSANAAN
HARI KE-
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45