ACERGY POLARIS

INCLINING TEST REPORT


12-NOV 2006

Prepared by : Antoine Fandeux


VISA Tah BI Boli

3.0 For BV approval 07 Dec 06 AFA BV

Version Reason for Issue Issue Date Prepared by VISA by


th
Acergy Afmed 07 Dec 06

Ver. 3.0 POLARIS- inclining test 2006 report Page 2 of 18

This is an electronically generated document, which has been reviewed and approved in accordance with Acergy’s
Management System. An audit trail of review and approval is available within the electronic system and a master
approved copy is available from the HSEQ Department.

The screen version of this document is the CONTROLLED COPY at all times. When printed it is considered a FOR
INFORMATION ONLY copy, and it is the holder’s responsibility that he / she holds the latest valid version

REVISION RECORD SHEET

List of updated /
Rev. N° Purpose modified sections if any
0.1 First issue

1.0 For BV approval

2.0 For BV approval Capacities updated

3.0 For BV approval Updated with BV comments

2
th
Acergy Afmed 07 Dec 06

Ver. 3.0 POLARIS- inclining test 2006 report Page 3 of 18

TABLE OF CONTENTS

TABLE OF CONTENTS .......................................................................................................................3


GENERAL ..............................................................................................................................................4

DRAUGHT SURVEY AND DENSITY OF WATER .....................................................................................5


DENSITY .............................................................................................................................................5
DRAUGHT SURVEY ............................................................................................................................5
INCLINING WEIGHTS DATA...................................................................................................................6
WEIGHT DESCRIPTION ......................................................................................................................6
PENDULUM DESCRIPTION ...............................................................................................................7
DEFLECTION MEASUREMENT...........................................................................................................7
INITIAL SOUNDING OF CAPACITIES .....................................................................................................7

WEIGHTS TO BE DEDUCTED FROM LIGHTSHIP WEIGHT.....................................................................9

HYDROSTATICS PROPERTIES DURING INCLINING TEST .................................................................. 10


DRAUGHT AND TRIM .............................................................................................................................. 10
HYDROSTATICS DATA DURING THE INCLINING TEST (ARGOS DATA) ............................................. 11

CENTRE OF GRAVITY.......................................................................................................................... 12

LIGHT SHIP.......................................................................................................................................... 14

3
th
Acergy Afmed 07 Dec 06

Ver. 3.0 POLARIS- inclining test 2006 report Page 4 of 18

NAME OF THE SHIP : ACERGY POLARIS

BV REGISTER (HULL Nb) :12W417

FLAG : FRENCH

OWNER : ACERGY

SHIPYARD :MITSUI

Main dimensions :

Overall = 137.16 m LBP= 137.16 m B = 39.014 m D= 9.144 m

references:

<1> Argos database used for stability booklet (Tecnitas 2005)


<2> capacities plan ref Stolt Offshore PL011 du 22/11/01
<3> deck lay out ref ACERGY OB 891 du 12/11/06

GENERAL
Date : 12/11/2006 Location : PORT GENTIL

Wind: - less than 3 Beaufort……………

Sea: - less than 1 m

Current : - less than 2 nodes

The barge was moored at around 3 miles off shore. The 4 mooring lines were totally slack.

Wind is coming form the stern, and current is coming transversally from PS and SB

Person in charge of the inclining experiment:


Antoine FANDEUX. ACERGY (naval Architect)
Assisted by: Geoffroy Enos ACERGY (field engineer)

Names of persons attending the I/E :


Gerard Dubreuil ACERGY(Captain)
Tah bi boli Bureau Veritas (local surveyor)

4
th
Acergy Afmed 07 Dec 06

Ver. 3.0 POLARIS- inclining test 2006 report Page 5 of 18

-Are accommodation ladders properly stored on deck ? Xo YES o NO

-Are mooring arrangement such that the ship can be freely inclined ? Xo YES o NO

-Are free surface of liquid minimum ? Xo YES o NO

-Are connections between pipes closed ? Xo YES o NO

-Is the ship freely afloat ? Xo YES o NO

DRAUGHT SURVEY AND DENSITY OF WATER

DENSITY

Measuring device (type) : ………………………………………………

Location and densities


Measure n°1 Measure n° 2 Measure n° 3 Measure N° 4
Location FORE
Measure 1025
Mean density

Only one measure was made, as the barge was moored on shore, water density is the same around the
barge.

DRAUGHT SURVEY

Distance from fore marks to FP (forward perpendiculars): -15.956m

Distance from aft marks to AP (aft perpendiculars): 1.526

Note : + : forward
- : afterward

5
th
Acergy Afmed 07 Dec 06

Ver. 3.0 POLARIS- inclining test 2006 report Page 6 of 18

Draughts are measured from :draft marks and load line marks

DRAUGHTS
FORE STARBOARD 5.00m
FORE PORTSIDE 4.06m
MEAN FORE 4.53
MI STARBOARD 5.79
MI PORTSIDE 4.74
AFT STARBOARD 6.76m
AFT PORTSIDE 5.79m
MEAN AFT 6.27m

INCLINING WEIGHTS DATA

WEIGHT DESCRIPTION

a) Individual weight : water transfers Number: Water ballasts 1AB, 1DE,

Location: see capacity plan ref PL-011 rev1 22/11/01


(on which deck, which frame number, …)

b) Individual weight : water transfers Number :Water ballasts and 9AB 9 DE

Location: see capacity plan PL-011 rev1 22/11/01


(on which deck, which frame number, …)

Vertical centre of gravity/OH : see table Sounding capacities


Longitudinal centre of gravity/AP : see table Sounding capacities

4 submerged pumps are installed inside the tanks. As we have 1 motor brake down on 1 pump and 1 pump
working badly, we limited the transfers of 4 steps instead of 8 planned.

6
th
Acergy Afmed 07 Dec 06

Ver. 3.0 POLARIS- inclining test 2006 report Page 7 of 18

PENDULUM DESCRIPTION

N°1 pendulum N°2 pendulum N°3 pendulum


Location 133m form AP 120m form AP 32m form AP
Length 7270 mm 7170 mm 8550 mm

DEFLECTION MEASUREMENT

deflection
Pendulum Pendulum pendulum
Mov.
Tank N°1 N°2 N°3
Nr
(mm) (mm) (mm)

1 1AB->1DE 20 20 19
2 9AB->9DE 102 103 110
3 9DE->9AB 104 107 110
4 9DE->9AB 135 134 151

7
Acergy Afmed 07th Dec 06

Ver. 3.0 POLARIS- inclining test 2006 report Page 7 of 18

INITIAL SOUNDING OF CAPACITIES


The volume put in the table corresponded to specific sounding data taking into account a heel of 1° and trim of 1.8m. Position of the centre of
gravity of capacities are given by the standard capacity calibrations (heel and trim zero)

Item sounding (m) volume density weight Zg moment Xg moment Yg moment


TOTAL 4128.00 4181.22 2.86 11969.64 79.25 331368.80 -6.90 -28855.91 14624

water ballast total 3699.80 3792.30 3.02 11464.93 78.74 298609.19 -7.56 -28662.33 13014
1AB 5.300 629.80 1.025 645.545 4.60 2969.51 131.70 85018.28 -10.29 -6642.66 900.0
1DE 3.710 445.20 1.025 456.330 4.01 1829.88 131.40 59961.76 10.49 4786.90 3600.
2A 5.090 377.80 1.025 387.245 2.92 1130.76 121.70 47127.72 -16.12 -6242.39 286.4
2E 0.150 5.05 1.025 5.176 0.80 4.14 120.40 623.22 15.85 82.04 215.5
4A 8.550 566.80 1.025 580.970 3.96 2301.22 93.20 54146.40 -16.15 -9382.67 256.3
4E 0.000 0.00 1.025 0.000 0.00 0.00 0.00
5A 3.270 356.00 1.025 364.900 1.81 660.47 75.60 27586.44 -16.10 -5874.89
5E 0.000 1.025 0.000 0.00 0.00 0.00
6A 3.390 347.00 1.025 355.675 1.81 643.77 53.90 19170.88 -16.10 -5726.37
6E 0.000 1.025 0.000 0.00 0.00 0.00
7A 0.370 13.15 1.025 13.479 0.60 8.09 34.82 469.33 -15.33 -206.63 397.4
7E 0.030 2.00 1.025 2.050 0.47 0.96 34.82 71.38 13.75 28.19 19.0
9AB 3.600 465.00 1.025 476.625 1.83 872.22 4.52 2154.35 -10.45 -4980.73 3669.
9DE 3.500 492.00 1.025 504.300 2.07 1043.90 4.52 2279.44 10.90 5496.87 3669.
marine diesel tank 248.20 0.83 209.73 1.66 348.82 68.85 14440.73 -5.78 -1212.29 805.0
101 4.00 0.85 3.380 7.80 26.35 113.94 385.12 9.91 33.49
701 4.50 0.85 3.803 2.90 11.03 16.65 63.31 14.99 57.00
5B 2.920 219.70 0.85 185.65 1.45 269.19 68.88 12787.33 -7.50 -1392.35 805.0
5D 0.000 0.85 0.00 0.00 0.00 0.00
2B (conversion in 2006) 0.000 0.85 0.00 0.00 0.00 0.00
8BC 0.000 0.85 0.00 0.00 0.00 0.00
8CD 0.000 0.85 0.00 0.00 0.00 0.00

7
Acergy Afmed 07th Dec 06

Ver. 3.0 POLARIS- inclining test 2006 report Page 8 of 18

settling tank 502 20.00 0.85 16.90 2.50 42.25 71.30 1204.97 5.30 89.57
fresh water total 170.00 170.00 0.89 151.30 106.00 18020.00 7.15 1215.50 805.0
2D 0.00 1.00 0.000 0.00 0.00 0.00
3B 0.00 1.00 0.000 0.00 0.00 0.00
3D 1.800 170.00 1.00 170.000 0.89 151.30 106.00 18020.00 7.15 1215.50 805.0
waste oil tank 10.00 0.92 9.20 0.48 4.60 32.49 298.87 -21.39 - 196.79
W.O.T 501 10.00 0.92 9.200 0.50 4.60 32.49 298.87 -21.39 -196.79

The capacities without height of liquid (Hliq) were given by the board

8
Acergy Afmed 07th Dec 06

Ver. 3.0 POLARIS- inclining test 2006 report Page 9 of 18

WEIGHTS TO BE DEDUCTED FROM LIGHTSHIP WEIGHT

The locations and weights of those following items are referenced in the ref<3>f

Item weight Zg moment Xg moment Yg moment


GRAND TOTAL 427.50 13.33 5697.00 49.82 21298.05 -5.57 -2380.44
ROV aft PS 120.0 16.00 1920.00 7.10 852.00 -15.50 -1860.00
container sanitory 2.0 10.00 20.00 29.50 59.00 -16.77 -33.54
caterpillar generator n°1 1.0 10.00 10.00 23.50 23.50 -16.70 -16.70
FFI pump 0.5 10 5.00 11.3 5.65 -17.40 -8.70
basket & miscendellous equip 1.0 10 10.00 38.5 38.50 -11.80 -11.80
caterpillard generator n°2 1.0 10 10.00 103.5 103.50 -10.50 -10.50
container Sodexo 1.0 10 10.00 40.7 40.70 -10.30 -10.30
container 10" x3 2.0 10 20.00 40 80.00 -16.5 -33.00
manitowoc PS 150.0 12 1800.00 56.1 8415.00 -13.3 -1995.00
steel ropes along side the Slay 5.0 15 75.00 46.8 234.00 -4 -20.00
tunnel
fender x4 4.0 9 36.00 55 220.00 -21 -84.00
submerged pum aft 1.0 0.5 0.50 2 2.00 0 0.00
submerged pum fore 1.0 1.5 1.50 132 132.00 0 0.00
container CTPM 2.0 10 20.00 25.5 51.00 16.6 33.20
scrapp UPG 2.0 9.5 19.00 27 54.00 16.6 33.20
wastel oil tank on deck (full) 10.0 12 120.00 45.8 458.00 15.4 154.00
aggreco on main deck 10.0 11 110.00 42.5 425.00 6.7 67.00
aggreco on spare deck 10.0 17 170.00 36 360.00 0 0.00
stock of steel plate and pipes 10.0 11 110.00 83.5 835.00 3.5 35.00
container ROV (store)x3 5.0 11 55.00 83 415.00 16.1 80.50
container ROV (office) x2 2.0 13 26.00 103 206.00 13.5 27.00
ROV SB 80.0 13 1040.00 98 7840.00 15.6 1248.00
stock of steel ropes 5.0 15 75.00 46.8 234.00 4 20.00
office container on client 2.0 17 34.00 107.1 214.20 2.6 5.20
accomadation deck

9
Acergy Afmed 07th DEC 06

Ver 3.0 POLARIS- inclining test 2006 report Page 10 of 18

HYDROSTATICS PROPERTIES DURING INCLINING TEST


Mean density: 1.025

Draught and trim

Initial DRAUGHTS at marks


FORE STARBOARD 5.00m
FORE PORTSIDE 4.06m
MEAN FORE 4.53m
AFT STARBOARD 6.76m
AFT PORTSIDE 5.79m
MEAN AFT 6.27m

Trim at marks 1.74m (0.73°)


Distance between marks 119.68m
Trim at perpendicular (PP) 1.99m
Distance between PP 137.16 m
Distance of the fore mark -15.956 m
from FP
Distance of the aft mark 1.526 m
from AP

Initial DRAUGHTS AT PP
FORE 4.30 m
AFT 6.29 m
MEAN DRAUGHT 5.28 m

10
Acergy Afmed 07th DEC 06

Ver 3.0 POLARIS- inclining test 2006 report Page 11 of 18

HYDROSTATICS DATA DURING THE INCLINING TEST (ARGOS


DATA)
TRIM 1.74 m
DRAUGHT 5.28 m
LCF 68.68 m
DRAUGHT AT LCF 5.27 m

DISPLACEMENT 26103 t
LCB 62.68 m
KMt 29.03 m
MOMENT to change trim 568.4 m
one cm MCT/CM
KMl 304.1 m
Immersion par cm 52.77 t/cm

11
Acergy Afmed 07th DEC 06

Ver 3.0 POLARIS- inclining test 2006 report Page 12 of 18

Centre of gravity
Water transfers are evaluated by sounding by hand the water ballast tanks at each step of the
inclining test

Step1 1AB->1DE start 7H30 Finish:10h30


Sounding Volume
1AB 1DE 1AB 1DE
Step1 5.3 3.71 630 445
Step2 4.8 4.3 556 544
Mean of weight transfer:89t
Heel read at the bridge (DP system):

Step2 9AB->9DE start 11h15 Finish: 12h00


Sounding Volume
9AB 9DE 9AB 9DE
Step1 3.6 3.46 465 492
Step2 1.85 5.16 193 751
Mean of weight transfer: 272.1t
Heel read at the bridge (Dp System):2.5°

Step3 9DE->9AB start 13h40 Finish 15h15


Sounding Volume
9AB 9DE 9AB 9DE
Step1 1.85 5.16 193 751
Step2 3.6 3.44 454 494
Mean of weight transfer:265.5t
Heel read at the bridge (DP system) 1.7°

Step6 9DE->9AB start 15h50 Finish 17h00


Sounding Volume
9AB 9DE 9AB 9DE
Step1 3.6 3.44 454 494
Step2 6.3 1.12 806 145
Mean of weight transfer:359.2t
Heel read at the bridge (DP system):0.7°

12
Acergy Afmed 07th DEC 06

Ver 3.0 POLARIS- inclining test 2006 report Page 13 of 18

deviation
Pendulum Pendulum Pendulum
Mov. Arm
Tank transfert (t) Moment (t.m) N°1 N°2 N°3
Nr (m)
(mm) (mm) (mm)

1 1AB->1DE 89 20.6 1824.7 20 20 19


2 9AB->9DE 272.1 21 5714.9 102 103 110
3 9DE->9AB 265.5 21 5575 104 107 110
4 9DE->9AB 359 21 7544.5 135 134 151

Pendulum angle AFT MID FORE


TAN θ 0.012414 0.01269 0.011404

TAN θ mean 0.011908

inclining moment
(Mt) 5164.7

GM (m) 16.61

inclining moment
for 1° 7468

KMt (m) 29.03

Corrections FSM 0.56

KG fluid (m) 12.42

SHIP CHARACTERISTICS AT INCLINING TEST

Displacement 26103 t
KG fluid 12.42 m
LCG 62.20 m

13
Acergy Afmed 07th DEC 06

Ver 3.0 POLARIS- inclining test 2006 report Page 14 of 18

LIGHT SHIP

weight Zg Xg Yg FMS
LIGHTSHIP operation Weight 15 874.68 8.45 65.31 -0.48 14 824.78
ship at survey status 26 103.00 12.42 62.20 0.27
Missing Weight
clyde crane -2 692.00 29.18 15.73 -0.14
PES -406.00 27.12 86.06 17.41
pes foundation -25.00 11.23 84.66 5.92
JLTS+TOWER -2 302.00 31.12 62.05 16.09
JLTS foundation -173.00 9.15 63.24 11.56
Capacities status -4 181.22 2.86 79.25 -6.90 14 824.78
Men inboard 240 men -21.60 8.00 50.00 0.00
extra weights to remove -427.50 13.33 49.82 -5.57

The light ship operation weight takes into account the fluid surface effect induced by capacities FSM

The light ship operating includes many weight dispatched in stores and on deck. Those items are
suppose to be all time on board, more or less at the same location.

14
Acergy Afmed 07th DEC 06

Ver 3.0 POLARIS- inclining test 2006 report Page 15 of 18

FORE SB

0.04

0.03

0.02

0.01
Tangente

0.00
-8 000 -6 000 -4 000 -2 000 0 2 000 4 000 6 000 8 000 10 000

-0.01

-0.02

-0.03

-0.04
Moment (tm)

15
Acergy Afmed 07th DEC 06

Ver 3.0 POLARIS- inclining test 2006 report Page 16 of 18

FORE PS

0.02

0.02

0.01

0.01
Tangente

0.00
-8 000 -6 000 -4 000 -2 000 0 2 000 4 000 6 000 8 000 10 000

-0.01

-0.01

-0.02

-0.02
Moment (tm)

16
Acergy Afmed 07th DEC 06

Ver 3.0 POLARIS- inclining test 2006 report Page 17 of 18

AFT SB

0.02

0.015

0.01

0.005
Tangente

0
-8 000 -6 000 -4 000 -2 000 0 2 000 4 000 6 000 8 000 10 000

-0.005

-0.01

-0.015

-0.02
Moment (tm)

17