Anda di halaman 1dari 44

`

LAPORAN KERJA PRAKTEK


“PEMBANGUNAN TERMINAL TYPE C”

OLEH:
JUNASRIL : 18.023.22.201.085
RIFQI ROZA AFRIZAL :18.023.22.201.058
LUWTRAMA M : 19.023.22.201.047

FAKULTAS TEKNIK PROGRAM STUDI


TEKNIK SIPIL UNIVERSITAS ANDI
DJEMMA PALOPO
2021/2022
DAFTAR ISI

DAFTAR ISI ........................................................................................................ 1


BAB I PENDAHULUAN ...................................................................................... 2
1.1 Latar Belakang ....................................................................... 2
1.2 Maksud Dan Tujuan ............................................................... 3
1.3 Batasan Masalah ............................................................................ 3
1.4 Waktu dan Tempat ................................................................. 4
1.5 Metode pengumpulan data ..................................................... 4
BAB II MENAJEMEN PROYEK.......................................................................... 6
2.1 Pengertian Menajemen proyek .............................................. 5
2.1 Tujuan Menajeen Proyek....................................................... 5

BAB III LAPORAN PELAKSANAAN KERJA PRAKTEK ................................ 16


3.1 Uraian kegiatan .................................................................. 16
3.2 Uraian Permasalahan…………………………………………………………………………… 22

BAB IV PENUTUP ............................................................................................ 24


5.1 Kesimpulan ........................................................................ 24
5.2 Kendala .............................................................................. 24
5.3 Saran.................................................................................. 25
5.2 Lampiran ............................................................................ 26

1
KATA PENGANTAR

Segala puji dan syukur kami panjatkan kepada Allah SWT,


Pencipta dan Pemelihara alam semesta ini, atas karunianya kami
dapat menyelesaikan Kerja Praktek (KP) dengan waktu yang di berikan
90 hari ditempat pembangunan terminal type c kota belopa yang berda di
kabupaten Luwu. Shalawat serta salam semoga terlimpah curahkan bagi
nabi Muhammad SAW, keluarga dan para pengikutnya yang setia
hingga akhir zaman termasuk kita semua.
Laporan ini kami susun sebagai bahan pembelajaran bagi
mahasiswa sipil dan diharapkan dengan disusunnya laporan ini akan
menjadi acuan untuk mendukung proses penyelesainya Kerja Praktek
(KP) secara sederhana dan mengena pada permasalahan yang ada di
pembangunan terminal type c kota belopa.
Disadari sepenuhnya masih banyak kekurangan dalam
pembahasan kami ini dari teknis penulisan sampai dengan
pembahasan materi untuk itu besar harapan kami akan saran dan
masukan yang sifatnya mendukung untuk perbaikan ke depannya.
Tidak lupa kami ucapkan banyak terima kasih kepada
Dosen pembimbing kami yang telah memberi arahan untuk
membuat laporan Kerja Praktek (KP) ini dan tidak lupa kepada Panitia
pembangunan terminal type c kota belopa atas didikan dan
bimbingannya selama kami melaksanakan Kerja Praktek (KP) kami
ucapkan terima kasih semoga apa yang kami susun bermanfaat.

Palopo,15 februari 2023

Penyusun

2
BAB I
PENDAHULUAN

1.1. Latar Belakang


Bekal bagi seorang calon sarjana teknik sipil tidak cukup dengan
pembekalan teori di bangku kuliah saja. Ada berbagai pengetahuan penting
lain yang hanya bisa didapat dari pengamatan visual di lapangan secara
langsung, seperti pemahaman yang lebih mendalam mengenai proses dan
tahapan dalam kegiatan konstruksi, keterampilan berkomunikasi, dan kerja
sama dengan tim.
Kerja praktek adalah suatu kegiatan dimana mahasiswa memiliki
kesempatan untuk mengamati kegiatan konstruksi secara langsung serta
mengasah kemampuan berinterakasi dengan orang orang yang ada di lokasi
tersebut, mahasiswa dapat lebih siap untuk menjadi calon sarjana teknik sipil
yang tidak hanya memiliki kemampuan teori, namun juga pemahaman akan
ilmu yang ada di lapangan, dan kemampuan praktis sebagai bekal
memasuki dunia kerja kelak.
Berdasarkan hal tersebut maka setelah mengikuti teori-teori dibangku
perkuliahan, serta kurikulum yang ada pada program studi teknik sipil
fakultas teknik universitas andi djemma mahasiswa diwajibkan mengikuti
Kerja Praktek (KP) di lapangan yang merupakan persyaratan dalam rangka
penyelesaian studi sekaligus untuk menerapkan beberapa teori-teori yang
didapat di bangku kuliah untuk di terapkan di lapangan.
Atas dasar inilah maka kami memilih lokas, proyek pembangunan
gedung Dinas Pertanian Kota Palopo. sebagai tempat pelaksanaan kerja
praktek (KP) kami, karena tidak hanya anggarannya yang cukup besar juga
karena mencakup berbagai item pekerjaan seperti pekerjaan Penimbunan
lahan bangunan, pekerjaan taman dan gedung pengadilan agama Tujuan
awal dari kerja praktek ini memang untuk belajar dan mencari pengalaman
yang baru juga mengenal orang baru, entah itu dengan adanya
kontraktornya dan konsultannya kami dapat mengambil ilmu yang di berikan
mereka selama kegitan praktek tersebut.

3
1.2. Maksud&Tujuan
Maksud :
1) Untuk mendapatkan pengetahuan dan pengalaman dalam kegiatan
konstruksi bangunan beserta berbagai aspeknya melalui pengamatan.
2) Untuk mengasah keterampilan dan kemampuan mahasiswa dan
meyelesaikan salah satu syarat kelulusan.
3) Untuk menerapkan teori yang telah didapatkan di bangku kuliah dan
berbagai literatur ketekniksipilan dengan kenyataan di lapangan.
Tujuan:
1) Mendapatkan pengetahuan dan pengalaman mengenai kegiatan
konstruksi beserta berbagai aspeknya melalui pengamatan secara
langsung di lapangan.
2) Mengasah keterampilan dan kemampuan mahasiswa, terutama kerja
sama, komunikasi lisan dan tulisan melalui keterlibatan langsung di
lapangan dan bisa agar bisa mendapatkan gelar sarjana.
3) Melihat dan membandingkan antara teori yang didapatkan di bangku
kuliah dengan teknis pekerjaan di lapangan.
1.3. Batasan Masalah
Laporan ini mencakup pekerjaan pada Proyek Pembangunan
Terminal Type C KEC.BELOPA UTARA KAB. LUWU, meliputi : Item
Pekerjaan
1. Pekerjaan Lantai 1
2. Pekerjaan Lantai 2
3. Pekerjaan halte
Lingkup kerja praktek dibatasi dalam bidang pengawasan.Dalam hal
ini menyangkut pengamatan langsung untuk mengetahui bagaimana
pelaksanaan dan penyelesaian pekerjaan, baik teknis maupun non teknis
di lokasi pekerjaan yang sedang berlangsung .

4
1.4 Waktu Dan Tempat PelaksanaanKerja Praktek
Waktu :Kerja praktek dilaksanakan pada tanggal 15 september
2021 hingga 15 desember 2022
Tempat :JL. Sawerigading Kel.Sebe Kec. Belopa Utara Kab. Luwu
Prov. Sulawesi Selatan
1.5. Metode Pengumpulan Data
Laporan Kerja Praktek ini ditulis berdasarkan data-data yang
dikumpulkan diantaranya :
1. Mengadakan pengamatan secara langsung ke lapangan untuk melihat
pekerjaan yang sedang dilaksanakan.
2. Mengadakan wawancara dengan pihak-pihak yang terlibat langsung
dalam proyek.
3. Studi kepustakaan data yang ada yaitu dengan membaca dan
mengumpulkan data yang berhubungan dengan Kerja Praktek ini.
Dalam penulisan laporan Kerja Praktek ini disusun berdasarkan
kegiatan di lapangan dan data-data yang diperoleh dari berbagai sumber,
dimana penyusun terlibat aktif dalam pelaksanaan Proyek Pembangunan
Terminal Type C KEC.BELOPA UTARA KAB. LUWU . Metode yang
digunakan dalam penulisan laporan ini adalah :
1. Metode pengamatan ( Observasi )
Pengamatan (observasi), yaitu dengan melihat langsung proses
pelaksanaan pekerjaan di lapangan.
2. Metode wawancara ( Interview)
Wawancara (interview), yaitu dengan melakukan kegiatan tanya jawab
dengan pihak-pihak yang terlibat dalam pengelolaan proyek, ini
dilakukan untuk mendapatkan data-data tentang hal-hal yang teknis
maupun nonteknis.

5
BAB II
MANAJEMEN PROYEK
2.1 Pengertian Manajemen Proyek
Manajemen secara umum adalah suatu upaya untuk mencapai suatu
tujuan dengan sumber daya seminimal mungkin (efisien).Sementara itu,
proyek adalah rencana pekerjaan dengan suatu target pencapaian tertentu
yang diselesaikan dalam rentang wakt rencana yang ada di kontrak.
Secara kolektif, manajemen proyek adalah suatu pendekatan/metode
untuk mengelola suatu proyek dengan efektif dan efisien. Sistem ini hadir
sebagai perangkat untuk membantu mengelola kegiatan-kegiatan berbentuk
proyek, misalnya proyek konstruksi. Tanpanya, suatu proyek akan sulit
dieksekusi baik dari segi biaya, waktu, atau bahkan kualitasnya
2.2 Tujuan Manajemen Proyek
Manajemen proyek memiliki sejumlah tujuan, di antaranya:
a. Menyelesaikan tepat waktu
Pada manajemen waktu, ditentukan linimasa yang berisi kapan suatu
kegiatan harus dimulai dan kapan harus selesai. Dengan adanya hal
tersebut, proyek akan selalu dimonitor dan mengevaluasi
keterlambatan kegiatan supaya dapat selesai dalam waktu yang telah
ditentukan. Pengawasan seperti ini melancarkan pengerjaan proyek.
b. Menjaga anggaran
Anggaran merupakan salah satu aspek yang dikaji dalam manajemen
ini. Dengan pengkajian tersebut, akan dicari jumlah anggaran
seminimal mungkin dengan kualiatas yang baik, tetapi masih dapat
menunjang tercapainya kriteria proyek yang telah ditentukan di awal
(efektif dan efisien).

c. Menjaga kualitas
Sebagaimana telah disinggung pada poin sebelumnya, kriteria proyek
yang ditentukan di awal harus tercapai dengan memenuhi standar
nasional indonesia. Artinya, manajemen proyek juga membuat standar
kualitas dari suatu proyek sehingga ia tidak dikerjakan secara
seenaknya saja.

6
d. Melancarkan proyek
Pada akhirnya, proyek yang ideal adalah proyek yang selesai sesuai
dengan perencanaan awal, baik dari segi waktu, anggaran, maupun
kualitas.Manajemen ini membantu pengerjaan proyek supaya selesai
dengan lancar sesuai dengan rencana awal.
e. Sasaran Manajemen Proyek
Sasaran manajemen proyek adalah sebagai berikut:
Menyelesaikan dan mengembangkan proyek sesuai dengan anggaran
biaya dan tenggat waktu yang telah ditentukan sekaligus dalam
kualitas/spesifikasi sesuai dengan yang telah disepakati di awal di
kontrak proyek.
1. Meningkatkan nama baik pelaksana proyek berdasarkan kualitas
hasil proyek.
2. Menciptakan suasana kerja kondusif untuk mendukung kelancaran
aktivitas proyek. Hal ini meliputi ketersediaan keadaan, sarana-
prasarana, dan keselamatan kerja.
3. Menjaga keharmonisan antar pihak dalam proyek sehingga seluruh
pihak terlibat akan memberikan yang terbaik untuk proyek yang
sedang dijalankan.
f. Ruang Lingkup Manajemen Proyek

1. Waktu proyek dimulai


2. Perencanaan lingkup proyek
3. Pendefinisian ruang lingkup proyek
4. Verifikasi proyek dan kontrol ketika proyek sedang dijalankan

7
Beberapa Contoh Manajemen Proyek di antaranya adalah sebagai
berikut:
1. Proyek Konstruksi
Proyek konstruksi adalah proyek yang berhubungan dengan
pembangunan sarana public .Terminal Type C
2. Proyek Penelitian
Proyek penelitian pada dasarnya adalah suatu proyek yang dilakukan
untuk kepentingan penelitian dan pengembangan.Hasil dari penelitian
tersebut nanti digunakan untuk meningkatkan kualitas dari suatu barang
atau jasa, atau hanya untuk pengembangan ilmu pengetahuan saja.
3. Proyek Padat Modal
Proyek padat modal adalah proyek produksi besar dengan bantuan
mekanik (robot).Proyek ini disebut “padat” karena pada eksekusinya
membutuhkan modal yang banyak.Banyaknya modal yang diperlukan
membuatnya hanya bisa dilakukan oleh perusahaan besar
4. Proyek Manufaktur
Proyek manufaktur adalah proyek yang melakukan rancangan untuk
memproduksi suatu produk secara menyeluruh
2.3 . Definisi Konsultan Pengawasan
Konsultan pengawas adalah pihak yang diberi tugas oleh owner untuk
merencanakan atau mengawasi pelaksanaan pekerjaan supaya hasil
pekerjaan sesuai dengan spesifikasi yang diharapkan. Tugas sebuah
perusahaan konsultan adalah mengawal owner pada tahap awal proyek
(tahap perencanaan dan perancangan) untuk mempersiapkan tahap
selanjutnya, serta pada masa konstruksi pelaksanaan pembangunan fisik
job description konsultan secara umum adalah menerjemahkan
keinginan dan kebutuhan owner dengan mendampingi konsultan
perencana dalam proses desain yang dituangkan ke dalam dokumen
gambar, perhitungan, dan dokumen pendukung lainnya. Kemudian
melakukan pengawasan dan bimbingan kontraktor pada fase
pelaksanaannya. Perencanaan diawal proyek yang matang akan
menghasilkan sebuah produk pedoman pelaksanaan yang akurat, yang
nantinya akan sangat turut menentukan kesuksesan sebuah proyek.

8
2.4 . Peran Dan Jenis Pekerjaan Konsultan
Konsultan adalah seorang tenaga professional yang menyediakan
jasa kepenasihatan (consultancy service) dalam bidang keahlian tertentu.
Dalam bidang konstruksi, konsultan dibedakan menjadi dua macam yaitu
konsultan perencana dan konsultan pengawas.
1. Konsultan Perecana
Konsultan perencana adalah pihak yang ditunjuk oleh pemberi tugas
untuk melaksanakan pekerjaan perencanaan, perencana dapat berupa
perorangan atau badan usaha baik swasta maupun pemerintah. Saat
pelaksanaan pembangunan berlangsung, pihak konsultan perencana
dapat membuat jadwal pertemuan rutin dengan kontraktor untuk
membahas hal-hal yang mungkin perlu mendapat pemecahan dari
perencana, misalnya saat approval material atau pembuatan gambar shop
drawing sebagai pedoman pelaksanaan proyek. Berikut peran konsultan
perencana:
a) Mengadakan penyesuaian keadaan lapangan dengan keinginan
pemilik bangunan.
b) Membuat gambar kerja pelaksanaan.
c) Membuat rencana kerja dan syarat pelaksanaan bangunan (RKS)
sebagai pedoman pelaksanaan.
d) Membuat Rencana Anggaran Biaya (RAB).
e) Memproyeksikan keinginan atau ide-ide pemilik kedalam desain
bangunan.

f) Melakukan perubahan desain bila terjadi penyimpangan pelaksanaan


pekerjaan dilapangan yang tidak memungkinkan desain terwujud
diwujudkan.
g) Mempertanggung jawabkan desain dan perhitungan struktur jika
terjadi kegagalan konstruksi.

9
2.Konsultan Pengawas

konsultan pengawas adalah pihak yang ditunjuk oleh pemilik proyek


(Owner) untuk melaksanakan pekerjaan pengawsan. Konsultan pengawas
dapat berupa badan usaha atau perorangan. Perlu sumber daya manusia
yang ahli di bidangnya masing-masing seperti Teknik sipil, arsitektur,
mekanikal elektrikal, listrik, dan lain-lain sehingga sebuah bangunan dapat
dibangun dengan baik dalam waktu cepat dan efisien.
Peran konsultan pengawas :
a) Menyelenggarakan administrasi umum mengenai pelaksanaan
kontrak kerja.
b) Melaksanakan pengawasan secara rutin dalam perjalanan
pelaksanaan proyek.
c) Menerbitkan laporan prestasi pekerjaan proyek untuk dapat dilihat
oleh pemilik proyek.
d) Konsultam pengawas memberikan saran atau pertimbangan kepada
pemilik proyek pelaksanaan pekerjaan.
e) Mengoreksi dan menyetujui gambar shop drawing yang diajukan
kontraktor sebagai pedoman pelaksanaan pembangunan proyek.
f) Memilih dan memberikan persetujuan mengenai tipe dan merek yang
diusulkan oleh kontraktor proyek namun tetap berpedoman dengan
kontrak kerja konstruksi yang sudah dibuat sebelumnya.
2.5. Gambaran Umum Proyek
Pembangunan yang berkesinambungan yang bertujuan untuk
kemakmuran seluruh lapisan masyarakat tentunya harus didukung oleh
pembangunan diberbagai bidang salah satunya adalah pembangunan
gedung Dinas Pertanian. Yang berada di Kota Palopo yang di
laksanakan.
CV.INDEPENDENT ENGINEERING CONSULTANT merupakan
perusahaan yan berperan dalam pengawasan pembangunan terminal
type c yang berlokasi di kota Belopa dan perusahaan ini juga sudah
termasuk berpengalaman dalam dunia konstruksi.

10
2.6. Lokasi Proyek
Proyek Pembangunan Terminal Type C KEC.BELOPA UTARA KAB.
LUWU

Gambar 1: Lokasi Proyek

11
2.7. Data Proyek

Gambar 2: Papan Proyek


Proyek pembangunan Terminal Type C Kota Belopa
ini memiliki data kontrak sebagai berikut:

Nama Paket : PEMBANGUNAN TERMINAL TYPE C


KOTA BELOPA
Tanggal Kontrak :-
Lokasi Kegiatan : JL. Sawerigading Kel. Sebe Kec. Belopa
Utara
Tahun Anggaran : DAU TA 2002
Nilai Kontrak : Rp. 1.721.438,000,00

12
.
2.7. LINGKUP PEKERJAAN PROYEK
A. Lingkup Pengerjaan Keseluruhan Proyek

Pekerjaan yang terdapat di P e m b a n g u n a n T e r m i n a l T y p e C


K o t a B e l o p a meliputi :
1. Perkerjaan Pondasi
2. Pekerjaan Sloof
3. Pekerjaan Kolom
5. Pekerjaan Balok
6. Pekerjaan Pemasangan Dinding
7. Pekerjaan Plat Pengecoran Dan Pemasangan Lantai
8. Pekerjaan Atap
B. Lingkup Pekerjaan Selama lingkup kerja praktek
1. Pekerjaan Balok
2. Pekerjaan Pemasangan Dinding
3. Pekerjaan Plat Pengecoran Dan Pemasangan Lantai
4.Pekerjaan Atap

2.8. Organisasi Pelaksanaan ( Bagan Organisasi )


Organisasi proyek system usaha bersama dalam sekelompok
orang atau badan usaha untuk mencapai tujuan bersama. Unsur –
unsur dalam suatu organisasi adalah unsur kerjasama, dan unsur
mencapai tujuan bersama. Organisasi adalah wadah untuk melakukan
aktivitas dimana sistem pembagian tugas menurut keahlian masing-
masing Adapun susunan organisasi pelaksanaan lapangan pada Proyek
P e m b a n g u n a n T e r m i n a l T y p e C K o t a B e l o p a adalah sebagai
berikut:

PEMERINTAH

PPK

KONSULTAN KONTRAKTOR

13
PERAN PEMERINTAH
1. Perumusan kebijakan teknis sesuai dengan rencana strategis daerah.
2. Perencanaan, perumusan, penyelenggaraan, pembinaan Da
pengendalian kebijakan teknis. n
3. Pembinaan kelompok jabatan fungsional.
4. Pelaksanaan unit pelaksanaan teknis dinas.
PERAN PPK
1. Menyusun perencanaan pengadaan.
2. Menetapkan spesifikasi teknis.
3. Menetapkan rencana kontrak.
4. Menetapkan HPS.
5. Menetapkan besaran uang muka yang akan dibayar kepada
penyedia.
6. Menentukan tim pendukung /tenaga ahli.
7. Mengendalikan kontrak.

PERAN KONSULTAN
Peran utama perusahaan konsultan proyek adalah memastikan kualitas
proyek konstruksi sesuai dengan perencanaan. Sedangkan untuk tugas
antara lain sebagai berikut :
1. Mengolah administrasi dalam kontrak kerja.
2. Melakukan pengawasan selama proyek konstruksi berjalan.

3. Melampirkan/membuat laporan pekerjaan yang diserahkan kepada


pemilik proyek.
4. Memberikan saran atau pertimbangan kepala pemilik proyek maupun
kontraktor.
5. Melakukan koreksi dan memberikan persetujuan mengenai hasil
gambar.
6. Memilih dan menyetujui tipe dan merek bahan/material konstruksi yang
diusulkan kontraktor.

PERAN KONTRAKTOR
Kontraktor adalah pihak yang ditunjuk oleh pemilik proyek sebagai
pelaksana proyek. Adapun tugas kontraktor antara lain.
1. Memahami gambar desain, konsep, dan spesifikasi sebagai acuan
didalam proyek.
2. Menyusun kembali metode pelaksanaan konstruksi dan jadwal
pelaksanaan pekerjaan bersama site engineering dan stuktural
engineering.
14
3. Memimpin dan mengendalikan pelaksanaan pekerjaan sesuai dengan
persyaratan waktu, mutu, dan biaya yang sudah ditentukan.
4. Membuat proyek kerja harian dan memberikan pengarahan kegiatan
harian kepada pelaksanaan pekerja/tenaga kerja.
5. Membuat evaluasi dan membuat laporan hasil pelaksanaan pekerjaan
dilapangan.
2.8 Prosedur Perencanaan Kerja Praktek
a. Memprogramkan Kerja Praktek pada kartu rencana studi(KRS)
sesuai persyaratan yang ditentukan.
b. Menentukan dan mencari tempat Kerja Praktek.
c. Mengajukan Surat Permohonan Kerja Praktek pada perusahaan
yang dimaksu (CV.INDEPENDENT ENGINEERING CONSULTANT.)
d. Mendapatkansurat balasan dari perusahaan yang dimaksud
(CV.INDEPENDENT ENGINEERING CONSULTANT).
e. Menyerahkan surat balasan CV.INDEPENDENT ENGINEERING
CONSULTANT ke bagian Akademik untuk selanjutnya penetapan
SK Pembimbing.

f. Penetapan SK Pembimbing Kerja Praktek pada tangga 16


September 2022 dengan Nomor Surat:035/KP/F06.07/023/IX/2022.
Kemudian,
g. Melaksanakan Kerja Pratek dari tanggal 16 September 2022 – 16
Desember 2022.
h. Dalam pelaksanaan kerja praktek ini kami sebagai pelaksana
i. Membuat Laporan
j. Konsultasi dan revisi laporan KP kepada Dosen Pembimbing.
k. Mengajukan permohonan Seminar KP sesuai jadwal yang telah
ditentukan.

15
BAB III
LAPORAN PELAKSANAAN
3.1 Tahap Pelaksanaan Di Lokasi
Selama kerja praktek berlangsung, pengamatan dan
pengawasan hampir diakukan setiap harinya. Pengawasan ini
dilakukan dengan tujuan selain demi kelangsungn dan normalisasi
pekerjaan ini juga betujuan agar kami sebagai peserta kerja praktek
itu dapat mempelajari hal-hal dalam pekerjaan yang dilaksanakan.
Dari pengawasan tersebut , dapat dipelajari beberapa item pekerjaan
yang dilaksanakan dengan mengetahui material-material pendukung
dalam item pekerjaan yang diawasi. Dibawah ini akan dijelasakn
mengenai laporan pengawasan yang kami lakukan di lokasi kerja
praktek.

NO HARI PEKERJAAN TAHAP PENGAWASAN DOKUMENTASI

MINGGU PERTAMA PENGAWASAN TERHADAP


1
16/09/2022-23/09/2022 ITEM PENGERJAAN BETON

16
NO HARI PEKERJAAN TAHAP PENGAWASANN DOKUMENTASI

MELAKUKAN PENGAWASAN
TERHADAP PEMASANGAN
MINGGU KEDUA -
BATU-BATA UNTUK
2 MINGGU KELIMA
PEMBUATAN DINDING
23/09/2022- 14/10/2022
SELAMA BEBERAPA HARI
KEDEPAN

17
NO HARI PEKERJAAN TAHAP PENGAWASAN DOKUMENTASI

MINGGU KELIMA - pengawasan terhadap


33 MINGGU KESEMBILAN pekerjaan beton yang
16/10/2022-07/11/2022 dikerjakan selama 3 minggu

18
NO HARI PEKERJAAN TAHAP PENGAWASAN DOKUMENTASI

MINNGGU KESEMBILAN PENGAWASAN TERHADAP


4 SAMPAI MINGGU KESEPULUH ITEM PENGERJAAN FLAT
25/10/2022-07/11/2022 BETON LANTAI 2

19
NO HARI PEKERJAAN TAHAP PENGAWASAN DOKUMENTASI

MINGGU KESEBELAS
PENGAWASAN PEKERJAAN
SAMPAI MINGGU
5 KOLOM BETON DAN
KEDUABELAS 09/11/2022-
DINDING DILANTAI 2
24/11/2022

20
NO HARI PEKERJAAN TAHAP PENGAWASAN DOKUMENTASI

MINGGU KETIGA BELAS


PENGAWASAN TERHADAP
6 SAMPAI KELIMA BELAS
PEKERJAAN HALTE
24/11/2022- 16/12/2022

21
3.2. Permasalahan Yang Terjadi Dalam Proyek Pembangunan Terminal Type C
Kota belopa.
Dari hasil pengawasan pembanguan Terminal Type C, Kami menemukan
beberapa permasalahan yang terjadi dari proyek tersebut:
1. Kurangnya tenaga kerja yang terdapat di proyek Pembangunan Terminal Type
C Kota belopa, hal ini didasari dari pihak kontraktor itu memiliki 2 lokasi proyek
yang mereka laksanakan dan pada akhirnya ini pasti akan memperlambat
progres pekerjaan.
2. Terlambatnya pengantaran material ke lokasi Proyek dikarenakan faktor jarak
tempat material yang berada di Kota Makassar , pastinya hal ini akan
memperlambat progres pekerjaan.
3. Kurangnya kedisiplinan hingga tdk memperdulikan K3 ( kesehatan keselamatan
Kerja ) dan ini termasuk kesalahan yang bisa berakibat fatal nanti baik dari
pihak pekerja hingga pelaksana.

22
23
BAB V
PENUTUP

5.1. KESIMPULAN

Pelaksanaan kerja praktek selama dua bulan lebih di Pembangunan


Terminal Type C KEC.BELOPA UTARA KAB. LUWU, telah memberikan
pengalaman dan pengetahuan mengenai hal-hal yang berkaitan dengan
pembangunan suatu proyek. Kami melaksanakan kerja praktek di kantor
dinas pertinian kota palopo sebagai kontraktor pelaksana.

Berdasarkan pengalaman yang kami peroleh selama pelaksanaan


kerja praktek selama kurang lebih 80 hari, pada Pembangunan Terminal
Type C KEC.BELOPA UTARA KAB. LUWU untuk pekerjaan di lapangan
maka kami dapat menyimpulkan beberapa hal yang terkait dengan proyek
dan pelaksanaan kerja praktek adalah sebagai berikut:

1. pada bulan pertama kerja praktek kami, 26,52 % bobot pelaksanaan


pekerjaan Pembangunan Terminal Type C KEC.BELOPA UTARA KAB.
LUWU mencapai
39,22%.
2. pada bulan kedua kerja praktek kami, 44,69 % bobot pelaksanaan
pekerjaan Pembangunan Terminal Type C KEC.BELOPA UTARA KAB.
LUWU mencapai
61,33 %
3. pada akhir kerja praktek kami., bobot pelaksanaan Pembangunan
Terminal Type C KEC.BELOPA UTARA KAB. LUWU mencapai 90 %.
4. Time schedule realisasi pelaksanaan proyek pada bulan pertama dan
bulan kedua kerja praktek Pembangunan Terminal Type C KEC.BELOPA
UTARA KAB. LUWU mengalami peningkatan dari perencanaan
(planning) berdasarkan kontrak.

24
5. Pada pelaksanaan proyek pembangunan kantor dinas pertanian kota
palopo di bulan terakhir kerja praktek kami mengalami keterlambatan
akibat lambatnya material yang di sebabkan terputusnya akses jalan
sehingga bahan yang dibutuhkan perlu waktu untuk sampai kelokasi
proyek.

.5.2 SARAN-SARAN
Selama pelaksanaan kerja praktek, menurut pengamatan kami ada
beberapa hal yang perlu mendapatkan perhatian agar dalam pelaksanaan
diperoleh hasil yang semaksimal mungkin. Untuk itu kami memberikan
sedikit saran, sebagai berikut :
1. Sebelum memulai suatu pekerjaan sebaiknya pelaksana lapangan
melakukan komunikasi yang baik kepada konsultan pengawas, apalagi
bila pekerjaan yang kurang jelas bersifat struktural. Hal ini untuk
mencegah terjadinya kekurangan tenaga, material, dan waktu yang
kesemuanya itu dapat merugikan pihak-pihak yang terlibat di dalamnya.
2. Perlu ditetapkan suku cadang dari peralatan utama yang sering
mengalami kerusakan, sehingga sewaktu-waktu apabila alat tersebut
rusak dapat langsung diperabaiki. Dengan demikian kelengkapan
pekerjaan dapat terjamin.
3. Perluh adanya penerapan K3 ( Kesehatan, keselamatan kerja )

25
LAMPIRAN/LOGBOOK

26
SCHEDULE PELAKSANAAN PEKERJAAN
PEKERJAAN : PEKERJAAN PEMBANGUNAN TERMINAL TYPE C
LOKASI : KEC. BELOPA UTARA KABUPATEN LUWU
TAHUN
: 2022 24.2857142
ANGGARAN
BOBOT 170 Hari Kalender
KONTRAK I II III IV V VI
KET
No. URAIAN PEKERJAAN AWAL

(%)
I II III IV V VI VII VIII IX X XI XII XIII XIV XV XVI XVII XVIII XIX XX XXI XXII XXIII XXIV

A. PEKERJAAN PENDAHULUAN 100

I PEKERJAAN PERSIAPAN 0.713 0.356 0.356

B. GEDUNG KANTOR PENGELOLAH

B1. LANTAI SATU


90
I PEKERJAAN TANAH DAN PONDASI 12.049 3.012 3.012 3.012 3.012

II PEKERJAAN BETON 25.619 3.202 3.202 3.202 3.202 3.202 3.202 3.202 3.202

III PEKERJAAN DINDING 12.179 3.045 3.045 3.045 3.045


IV PEK. PINTU DAN JENDELA 0.348 0.348 80

V PEKERJAAN PLAFOND 0.000

VI PEKERJAAN LANTAI / KERAMIK 1.661 0.830 0.830

VII PEKERJAAN PENGECETAN 0.000

VIII PEKERJAAN INSTALASI LSTRIK 0.773 0.387 0.387


70
IX PEKERJAAN PENGGANTUNG / PENGUNCI 0.000

X PEKERJAAN SANITASI 3.121 1.561 1.561

B2. LANTAI DUA


60
I PEKERJAAN BETON 8.476 1.413 1.413 1.413 1.413 1.413 1.413
II PEKERJAAN DINDING 10.373 3.458 3.458 3.458

III PEKERJAAN PINTU DAN JENDELA 3.429 1.715 1.715


IV PEKERJAAN KUDA - KUDA DAN ATAP 4.876 2.438 2.438
50
V PEKERJAAN PLAFOND 1.573 1.573

VI PEKERJAAN LANTAI / KERAMIK 0.000

VII PEKERJAAN PENGECATAN 0.320 0.320

VIII PEKERJAAN INSTALASI LISTRIK 0.519 0.519


40
IX PEKERJAAN PENGGANTUNG / PENGUNCI 0.000

X PEKERJAAN SANITASI 0.606 0.303 0.303

XI PEKERJAAN FINISHING & AKSESORIES 0.129 0.129

C HALTE 30

I PEKERJAAN TANAH DAN PONDASI 5.144 1.715 1.715 1.715

II PEKERJAAN BETON 0.000

III PEKERJAAN ATAP 6.149 2.050 2.050 2.050

IV PEKERJAAN LANTAI / KERAMIK 1.845 0.923 0.923 10


V PEKERJAAN INSTALASI LSTRIK 0.000

D PEKERJAAN AKHIR
0
I FINISHING 0.097 0.097

RENCANA KEMAJUAN PEKERJAAN MINGGUAN % 0.36 0.36 3.01 3.01 3.01 3.01 3.20 3.20 3.20 6.25 9.83 7.96 7.96 4.61 1.41 1.41 1.41 4.87 4.87 3.46 2.44 4.49 7.07 9.58
KOMULATIF RENCANA KEMAJUAN PEKERJAAN MINGGUAN % 0.36 0.71 3.73 6.74 9.75 12.76 15.96 19.17 22.37 28.62 38.44 46.40 54.37 58.98 60.39 61.81 63.22 68.09 72.96 76.42 78.85 83.34 90.42 100.00
NAMA KEGIATAN : PENINGKATAN SARANA DAN PRASARANA PERHUBUNGAN

PAKET PEKERJAAN : PEMBANGUNAN TERMINAL TIPE C KOTA BELOPA

LOKASI : KEC. BELOPA UTARA KABUPATEN LUWU

REKAPITULASI BOBOT PEKERJAAN


No. URAIAN PEKERJAAN JUMLAH HARGA BOBOT
KONTRA S/D BULAN LALU BULAN INI S/D BULAN INI
K
A PENDAHULUAN KOMULATIF BOBOT KOMULATIF BOBOT KOMULATIF BOBOT
I PEKERJAAN PERSIAPAN Rp 12,700,000.00 0.75 24.11 0.18 24.11 0.18
TOTAL (A) Rp 12,700,000.00 0.18
B GEDUNG KANTOR PENGELOLAH
B.1 LANTAI SATU
I PEKERJAAN TANAH DAN PONDASI Rp 123,303,423.70 7.25 - - -
II PEKERJAAN BETON BERTULANG DAN RABAT BETON Rp 252,785,312.69 14.86 - - -
III PEKERJAAN DINDING Rp 166,341,695.61 9.78 - - -
IV PEKERJAAN PINTU DAN JENDELA Rp 13,440,562.18 0.79 - - -
V PEKERJAAN PLAFOND Rp 23,543,507.25 1.38 - - -
VI PEKERJAAN LANTAI / KERAMIK Rp 125,277,198.53 7.36 - - -
VII PEKERJAAN PENGECATAN Rp 10,575,891.63 0.62 - - -
VIII PEKERJAAN INSTALASI LISTRIK Rp 15,359,754.78 0.90 - - -
IX PEKERJAAN PENGGANTUNG / PENGUNCI Rp 8,780,411.00 0.52 - - -
X PEKERJAAN SANITASI Rp 49,836,341.35 2.93 - - -
TOTAL (B1) Rp 789,244,098.72
-
B.2 LANTAI DUA
I PEKERJAAN BETON Rp 129,430,008.25 7.61 - - -
II PEKERJAAN DINDING Rp 110,847,095.26 6.52 - - -
III PEKERJAAN PINTU DAN JENDELA Rp 52,488,608.38 3.09 - - -
IV PEKERJAAN KUDA - KUDA DAN ATAP Rp 61,077,943.20 3.59 - - -
V PEKERJAAN PLAFOND Rp 23,724,603.36 1.39 - - -
VI PEKERJAAN LANTAI / KERAMIK Rp 54,653,194.07 3.21 - - -
VII PEKERJAAN PENGECATAN Rp 18,805,409.62 1.11 - - -
VIII PEKERJAAN INSTALASI LISTRIK Rp 13,158,633.50 0.77 - - -
IX PEKERJAAN PENGGANTUNG / PENGUNCI Rp 8,356,641.75 0.49 - - -
X PEKERJAAN SANITASI Rp 9,545,662.06 0.56 - - -
XI PEKERJAAN FINISHING & AKSESORIES Rp 147,258,635.84 8.66 - - -
TOTAL (B2) Rp 629,346,435.28
-
C HALTE
I PEKERJAAN TANAH DAN PONDASI Rp 54,305,809.40 3.19 - - -
II PEKERJAAN BETON Rp 11,406,730.22 0.67 - - -
IV PEKERJAAN ATAP Rp 167,603,509.98 9.85 - - -
VI PEKERJAAN LANTAI / KERAMIK Rp 32,049,547.06 1.88 - - -
VIII PEKERJAAN INSTALASI LSTRIK Rp 3,414,810.00 0.20 - - -
TOTAL (C) 1 UNIT Rp 268,780,406.67
0
E PEKERJAAN AKHIR
I FINISHING Rp 1,042,686.18 0.06
TOTAL (E) Rp 1,042,686.18 100.00
REAL COST (RC) Rp 1,701,113,626.84
0.18
PPN 11% Rp 187,122,498.95
JUMLAH Rp 1,888,236,125.80
DIBULATKAN Rp 1,888,236,000.00.-
TERBILANG :

SATU MILYAR DELAPAN RATUS DELAPAN PULUH DELAPAN JUTA DUA RATUS TIGA PULUH ENAM
RIBU RUPIAH
REKAPITULASI RAB

SATUAN KERJA : DINAS PERHUBUNGAN KABUPATEN LUWU


NAMA KEGIATAN : PENINGKATAN SARANA DAN PRASARANA PERHUBUNGAN

PAKET PEKERJAAN : PEMBANGUNAN TERMINAL TIPE C KOTA BELOPA


LOKASI : KEC. BELOPA UTARA KABUPATEN LUWU

REKAPITULASI BOBOT PEKERJAAN


No. URAIAN PEKERJAAN JUMLAH HARGA BOBOT
KONTRA S/D BULAN LALU BULAN INI S/D BULAN INI
K
A PENDAHULUAN KOMULATIF BOBOT KOMULATIF BOBOT KOMULATIF BOBOT
I PEKERJAAN PERSIAPAN Rp 12,700,000.00 0.75 60.28 0.45 60.28 0.45
TOTAL (A) Rp 12,700,000.00
B GEDUNG KANTOR PENGELOLAH
B.1 LANTAI SATU
I PEKERJAAN TANAH DAN PONDASI Rp 123,303,423.70 7.25 - 100 7.25 100 7.25
II PEKERJAAN BETON BERTULANG DAN RABAT BETON Rp 252,785,312.69 14.86 - - -
III PEKERJAAN DINDING Rp 166,341,695.61 9.78 - - -
IV PEKERJAAN PINTU DAN JENDELA Rp 13,440,562.18 0.79 - - -
V PEKERJAAN PLAFOND Rp 23,543,507.25 1.38 - - -
VI PEKERJAAN LANTAI / KERAMIK Rp 125,277,198.53 7.36 - - -
VII PEKERJAAN PENGECATAN Rp 10,575,891.63 0.62 - - -
VIII PEKERJAAN INSTALASI LISTRIK Rp 15,359,754.78 0.90 - - -
IX PEKERJAAN PENGGANTUNG / PENGUNCI Rp 8,780,411.00 0.52 - - -
X PEKERJAAN SANITASI Rp 49,836,341.35 2.93 - - -
TOTAL (B1) Rp 789,244,098.72
7.25
B.2 LANTAI DUA
I PEKERJAAN BETON Rp 129,430,008.25 7.61 - - -
II PEKERJAAN DINDING Rp 110,847,095.26 6.52 - - -
III PEKERJAAN PINTU DAN JENDELA Rp 52,488,608.38 3.09 - - -
IV PEKERJAAN KUDA - KUDA DAN ATAP Rp 61,077,943.20 3.59 - - -
V PEKERJAAN PLAFOND Rp 23,724,603.36 1.39 - - -
VI PEKERJAAN LANTAI / KERAMIK Rp 54,653,194.07 3.21 - - -
VII PEKERJAAN PENGECATAN Rp 18,805,409.62 1.11 - - -
VIII PEKERJAAN INSTALASI LISTRIK Rp 13,158,633.50 0.77 - - -
IX PEKERJAAN PENGGANTUNG / PENGUNCI Rp 8,356,641.75 0.49 - - -
X PEKERJAAN SANITASI Rp 9,545,662.06 0.56 - - -
XI PEKERJAAN FINISHING & AKSESORIES Rp 147,258,635.84 8.66 - - -
TOTAL (B2) Rp 629,346,435.28
-
C HALTE
I PEKERJAAN TANAH DAN PONDASI Rp 54,305,809.40 3.19 - - -
II PEKERJAAN BETON Rp 11,406,730.22 0.67 - - -
IV PEKERJAAN ATAP Rp 167,603,509.98 9.85 - - -
VI PEKERJAAN LANTAI / KERAMIK Rp 32,049,547.06 1.88 - - -
VIII PEKERJAAN INSTALASI LSTRIK Rp 3,414,810.00 0.20 - - -
TOTAL (C) 1 UNIT Rp 268,780,406.67
0
E PEKERJAAN AKHIR
I FINISHING Rp 1,042,686.18 0.06
TOTAL (E) Rp 1,042,686.18 100.00
REAL COST (RC) Rp 1,701,113,626.84
7.25
PPN 11% Rp 187,122,498.95
JUMLAH Rp 1,888,236,125.80
DIBULATKAN Rp 1,888,236,000.00.-
TERBILANG :

SATU MILYAR DELAPAN RATUS DELAPAN PULUH DELAPAN JUTA DUA RATUS TIGA PULUH ENAM
RIBU RUPIAH
NAMA KEGIATAN : PENINGKATAN SARANA DAN PRASARANA PERHUBUNGAN

PAKET PEKERJAAN : PEMBANGUNAN TERMINAL TIPE C KOTA BELOPA

LOKASI : KEC. BELOPA UTARA KABUPATEN LUWU

REKAPITULASI BOBOT PEKERJAAN


No. URAIAN PEKERJAAN JUMLAH HARGA BOBOT
KONTRA S/D BULAN LALU BULAN INI S/D BULAN INI
K
A PENDAHULUAN KOMULATIF BOBOT KOMULATIF BOBOT KOMULATIF BOBOT
I PEKERJAAN PERSIAPAN Rp 12,700,000.00 0.75 60.63 0.45
TOTAL (A) Rp 12,700,000.00 0
B GEDUNG KANTOR PENGELOLAH
B.1 LANTAI SATU
I PEKERJAAN TANAH DAN PONDASI Rp 123,303,423.70 7.25 100.00 7.25 - -
II PEKERJAAN BETON BERTULANG DAN RABAT BETON Rp 252,785,312.69 14.86 37.28 5.54 - -
III PEKERJAAN DINDING Rp 166,341,695.61 9.78 38.57 3.77 - -
IV PEKERJAAN PINTU DAN JENDELA Rp 13,440,562.18 0.79 - - -
V PEKERJAAN PLAFOND Rp 23,543,507.25 1.38 - - -
VI PEKERJAAN LANTAI / KERAMIK Rp 125,277,198.53 7.36 - - -
VII PEKERJAAN PENGECATAN Rp 10,575,891.63 0.62 - - -
VIII PEKERJAAN INSTALASI LISTRIK Rp 15,359,754.78 0.90 - - -
IX PEKERJAAN PENGGANTUNG / PENGUNCI Rp 8,780,411.00 0.52 - - -
X PEKERJAAN SANITASI Rp 49,836,341.35 2.93 - - -
TOTAL (B1) Rp 789,244,098.72
-
B.2 LANTAI DUA
I PEKERJAAN BETON Rp 129,430,008.25 7.61 - - -
II PEKERJAAN DINDING Rp 110,847,095.26 6.52 - - -
III PEKERJAAN PINTU DAN JENDELA Rp 52,488,608.38 3.09 - - -
IV PEKERJAAN KUDA - KUDA DAN ATAP Rp 61,077,943.20 3.59 - - -
V PEKERJAAN PLAFOND Rp 23,724,603.36 1.39 - - -
VI PEKERJAAN LANTAI / KERAMIK Rp 54,653,194.07 3.21 - - -
VII PEKERJAAN PENGECATAN Rp 18,805,409.62 1.11 - - -
VIII PEKERJAAN INSTALASI LISTRIK Rp 13,158,633.50 0.77 - - -
IX PEKERJAAN PENGGANTUNG / PENGUNCI Rp 8,356,641.75 0.49 - - -
X PEKERJAAN SANITASI Rp 9,545,662.06 0.56 - - -
XI PEKERJAAN FINISHING & AKSESORIES Rp 147,258,635.84 8.66 - - -
TOTAL (B2) Rp 629,346,435.28
-
C HALTE
I PEKERJAAN TANAH DAN PONDASI Rp 54,305,809.40 3.19 - - -
II PEKERJAAN BETON Rp 11,406,730.22 0.67 - - -
IV PEKERJAAN ATAP Rp 167,603,509.98 9.85 - - -
VI PEKERJAAN LANTAI / KERAMIK Rp 32,049,547.06 1.88 - - -
VIII PEKERJAAN INSTALASI LSTRIK Rp 3,414,810.00 0.20 - - -
TOTAL (C) 1 UNIT Rp 268,780,406.67
-
E PEKERJAAN AKHIR
I FINISHING Rp 1,042,686.18 0.06
TOTAL (E) Rp 1,042,686.18 100.00
REAL COST (RC) Rp 1,701,113,626.84
0
PPN 11% Rp 187,122,498.95
JUMLAH Rp 1,888,236,125.80
DIBULATKAN Rp 1,888,236,000.00.-
TERBILANG :

SATU MILYAR DELAPAN RATUS DELAPAN PULUH DELAPAN JUTA DUA RATUS TIGA PULUH ENAM
RIBU RUPIAH
REKAPITULASI RAB

SATUAN KERJA : DINAS PERHUBUNGAN KABUPATEN LUWU

NAMA KEGIATAN : PENINGKATAN SARANA DAN PRASARANA PERHUBUNGAN

PAKET PEKERJAAN : PEMBANGUNAN TERMINAL TIPE C KOTA BELOPA


LOKASI : KEC. BELOPA UTARA KABUPATEN LUWU

REKAPITULASI BOBOT PEKERJAAN


No. URAIAN PEKERJAAN JUMLAH HARGA BOBOT
KONTRA S/D BULAN LALU BULAN INI S/D BULAN INI
K
A PENDAHULUAN KOMULATIF BOBOT KOMULATIF BOBOT KOMULATIF BOBOT
I PEKERJAAN PERSIAPAN Rp 12,700,000.00 0.75
TOTAL (A) Rp 12,700,000.00 0
B GEDUNG KANTOR PENGELOLAH
B.1 LANTAI SATU
I PEKERJAAN TANAH DAN PONDASI Rp 123,303,423.70 7.25 - - -
II PEKERJAAN BETON BERTULANG DAN RABAT BETON Rp 252,785,312.69 14.86 - - -
III PEKERJAAN DINDING Rp 166,341,695.61 9.78 - - -
IV PEKERJAAN PINTU DAN JENDELA Rp 13,440,562.18 0.79 - - -
V PEKERJAAN PLAFOND Rp 23,543,507.25 1.38 - - -
VI PEKERJAAN LANTAI / KERAMIK Rp 125,277,198.53 7.36 - - -
VII PEKERJAAN PENGECATAN Rp 10,575,891.63 0.62 - - -
VIII PEKERJAAN INSTALASI LISTRIK Rp 15,359,754.78 0.90 - - -
IX PEKERJAAN PENGGANTUNG / PENGUNCI Rp 8,780,411.00 0.52 - - -
X PEKERJAAN SANITASI Rp 49,836,341.35 2.93 - - -
TOTAL (B1) Rp 789,244,098.72
-
B.2 LANTAI DUA
I PEKERJAAN BETON Rp 129,430,008.25 7.61 - - -
II PEKERJAAN DINDING Rp 110,847,095.26 6.52 - - -
III PEKERJAAN PINTU DAN JENDELA Rp 52,488,608.38 3.09 - - -
IV PEKERJAAN KUDA - KUDA DAN ATAP Rp 61,077,943.20 3.59 - - -
V PEKERJAAN PLAFOND Rp 23,724,603.36 1.39 - - -
VI PEKERJAAN LANTAI / KERAMIK Rp 54,653,194.07 3.21 - - -
VII PEKERJAAN PENGECATAN Rp 18,805,409.62 1.11 - - -
VIII PEKERJAAN INSTALASI LISTRIK Rp 13,158,633.50 0.77 - - -
IX PEKERJAAN PENGGANTUNG / PENGUNCI Rp 8,356,641.75 0.49 - - -
X PEKERJAAN SANITASI Rp 9,545,662.06 0.56 - - -
XI PEKERJAAN FINISHING & AKSESORIES Rp 147,258,635.84 8.66 - - -
TOTAL (B2) Rp 629,346,435.28
-
C HALTE
I PEKERJAAN TANAH DAN PONDASI Rp 54,305,809.40 3.19 - - -
II PEKERJAAN BETON Rp 11,406,730.22 0.67 - - -
IV PEKERJAAN ATAP Rp 167,603,509.98 9.85 - - -
VI PEKERJAAN LANTAI / KERAMIK Rp 32,049,547.06 1.88 - - -
VIII PEKERJAAN INSTALASI LSTRIK Rp 3,414,810.00 0.20 - - -
TOTAL (C) 1 UNIT Rp 268,780,406.67
0
E PEKERJAAN AKHIR
I FINISHING Rp 1,042,686.18 0.06
TOTAL (E) Rp 1,042,686.18 100.00
REAL COST (RC) Rp 1,701,113,626.84
0
PPN 11% Rp 187,122,498.95
JUMLAH Rp 1,888,236,125.80
DIBULATKAN Rp 1,888,236,000.00.-
TERBILANG :

SATU MILYAR DELAPAN RATUS DELAPAN PULUH DELAPAN JUTA DUA RATUS TIGA PULUH ENAM
RIBU RUPIAH
REKAPITULASI RAB

SATUAN KERJA : DINAS PERHUBUNGAN KABUPATEN LUWU


NAMA KEGIATAN : PENINGKATAN SARANA DAN PRASARANA PERHUBUNGAN
PAKET PEKERJAAN : PEMBANGUNAN TERMINAL TIPE C KOTA BELOPA
LOKASI : KEC. BELOPA UTARA KABUPATEN LUWU
REKAPITULASI BOBOT PEKERJAAN
No. URAIAN PEKERJAAN JUMLAH HARGA BOBOT
KONTRA S/D BULAN LALU BULAN INI S/D BULAN INI
K
A PENDAHULUAN KOMULATIF BOBOT KOMULATIF BOBOT KOMULATIF BOBOT
I PEKERJAAN PERSIAPAN Rp 12,700,000.00 0.75
TOTAL (A) Rp 12,700,000.00 0
B GEDUNG KANTOR PENGELOLAH
B.1 LANTAI SATU
I PEKERJAAN TANAH DAN PONDASI Rp 123,303,423.70 7.25 - - -
II PEKERJAAN BETON BERTULANG DAN RABAT BETON Rp 252,785,312.69 14.86 - - -
III PEKERJAAN DINDING Rp 166,341,695.61 9.78 - - -
IV PEKERJAAN PINTU DAN JENDELA Rp 13,440,562.18 0.79 - - -
V PEKERJAAN PLAFOND Rp 23,543,507.25 1.38 - - -
VI PEKERJAAN LANTAI / KERAMIK Rp 125,277,198.53 7.36 - - -
VII PEKERJAAN PENGECATAN Rp 10,575,891.63 0.62 - - -
VIII PEKERJAAN INSTALASI LISTRIK Rp 15,359,754.78 0.90 - - -
IX PEKERJAAN PENGGANTUNG / PENGUNCI Rp 8,780,411.00 0.52 - - -
X PEKERJAAN SANITASI Rp 49,836,341.35 2.93 - - -
TOTAL (B1) Rp 789,244,098.72
-
B.2 LANTAI DUA
I PEKERJAAN BETON Rp 129,430,008.25 7.61 - - -
II PEKERJAAN DINDING Rp 110,847,095.26 6.52 - - -
III PEKERJAAN PINTU DAN JENDELA Rp 52,488,608.38 3.09 - - -
IV PEKERJAAN KUDA - KUDA DAN ATAP Rp 61,077,943.20 3.59 - - -
V PEKERJAAN PLAFOND Rp 23,724,603.36 1.39 - - -
VI PEKERJAAN LANTAI / KERAMIK Rp 54,653,194.07 3.21 - - -
VII PEKERJAAN PENGECATAN Rp 18,805,409.62 1.11 - - -
VIII PEKERJAAN INSTALASI LISTRIK Rp 13,158,633.50 0.77 - - -
IX PEKERJAAN PENGGANTUNG / PENGUNCI Rp 8,356,641.75 0.49 - - -
X PEKERJAAN SANITASI Rp 9,545,662.06 0.56 - - -
XI PEKERJAAN FINISHING & AKSESORIES Rp 147,258,635.84 8.66 - - -
TOTAL (B2) Rp 629,346,435.28
-
C HALTE
I PEKERJAAN TANAH DAN PONDASI Rp 54,305,809.40 3.19 - - -
II PEKERJAAN BETON Rp 11,406,730.22 0.67 - - -
IV PEKERJAAN ATAP Rp 167,603,509.98 9.85 - - -
VI PEKERJAAN LANTAI / KERAMIK Rp 32,049,547.06 1.88 - - -
VIII PEKERJAAN INSTALASI LSTRIK Rp 3,414,810.00 0.20 - - -
TOTAL (C) 1 UNIT Rp 268,780,406.67
0
E PEKERJAAN AKHIR
I FINISHING Rp 1,042,686.18 0.06
TOTAL (E) Rp 1,042,686.18 100.00
REAL COST (RC) Rp 1,701,113,626.84
0
PPN 11% Rp 187,122,498.95
JUMLAH Rp 1,888,236,125.80
DIBULATKAN Rp 1,888,236,000.00.-
TERBILANG :

SATU MILYAR DELAPAN RATUS DELAPAN PULUH DELAPAN JUTA DUA RATUS TIGA PULUH ENAM
RIBU RUPIAH
BACK UP DATA

SATUAN KERJA : DINAS PERHUBUNGAN KABUPATEN LUWU


NAMA KEGIATAN : PENINGKATAN SARANA & PRASARANA PERHUBUNGAN
PAKET PEKERJAAN : PEMBANGUNAN TERMINAL DARAT KABUPATEN LUWU
LOKASI : KEC. BELOPA UTARA KABUPATEN LUWU

A. GEDUNG KANTOR PENGELOLA LANTAI 1


BERAT UKURAN PANJANG JUMLAH TOTAL BERAT
Ø PANJANG TOTAL
No TULANGAN
(mm)
Per M Btg Btg KET
A B C D KAIT
(Kg/M) (M) (Bh) Btg (Kg)
Kaki Poer Plat
- Tul Pokok 12 0.887 1.00 0.12 1.12 6.40 7.17 6.36
- Tul Bagi 12 0.887 1.00 0.12 1.12 6.40 7.17 6.36
TOTAL 23.00 292.59
Kolom 30 x 30
- Tul Pokok 12 0.887 3.55 0.12 3.67 8.00 29.36 26.05
- Bugel 8 0.394 0.25 0.25 0.25 0.25 0.08 1.08 23.67 25.56 10.08
TOTAL 23.00 831.07
Sloof (20 x 30)
- Tul Pokok 12 0.887 141.45 0.12 141.57 6.00 849.42 753.74
- Bugel 8 0.394 0.15 0.25 0.15 0.25 0.08 0.88 943.00 829.84 327.28
TOTAL 1081.02
Kolom pondasi tapak
- Tul Pokok 12 0.887 1.00 0.12 1.12 8.00 8.96 7.95
- Bugel 8 0.394 0.15 0.15 0.15 0.15 0.08 0.68 6.67 4.53 1.79
TOTAL 23.00 223.99
Kolom praktis (15 x 15)
- Tul Pokok 10 0.616 3.80 0.1 3.90 4.00 15.60 9.61
- Bugel 6 0.222 0.10 0.10 0.10 0.10 0.06 0.46 25.33 11.65 2.59
TOTAL 43.00 524.53
Balok Latei (15 x 20)
- Tul Pokok 10 0.616 15.60 0.1 15.70 4.00 62.80 38.70
- Bugel 6 0.222 0.10 0.15 0.10 0.15 0.06 0.56 104.00 58.24 12.92
TOTAL 51.62
Beton Balok (25/20)
- Tul Pokok 12 0.887 141.45 0.12 141.57 6.00 849.42 753.74
- Bugel 8 0.394 0.10 0.15 0.10 0.15 0.08 0.58 943.00 546.94 215.70
TOTAL 969.45
Plat lantai
- Tul Pokok 12 0.887 22.50 0.12 22.62 50.00 1131.00 1003.61
- Tul Bagi 8 0.394 7.50 0.08 7.58 150.00 1137.00 448.41
TOTAL 1.00 1452.02
Plat Tangga
- Tul Pokok 10 0.616 1.10 0.1 1.20 23.53 28.24 17.40
- Tul Bagi 6 0.222 3.53 0.06 3.59 7.33 26.33 5.84
TOTAL 1.00 23.24
Bordes
- Tul Pokok 12 0.887 2.20 0.12 2.32 10.00 23.20 20.59
- Tul Bagi 8 0.394 1.50 0.08 1.58 14.67 23.17 9.14
TOTAL 1.00 29.73
Anak Tangga
- Tul Pokok 10 0.616 0.20 0.1 0.30 2.00 0.60 0.37
- Tul Bagi 8 0.394 0.30 0.08 0.38 1.33 0.51 0.20
TOTAL 19.00 10.82
B. GEDUNG KANTOR PENGELOLAH LANTAI 2
BERAT UKURAN PANJANG JUMLAH TOTAL BERAT
Ø PANJANG TOTAL
No TULANGAN
(mm)
Per M Btg Btg KET
A B C D KAIT
(Kg/M) (M) (Bh) Btg (Kg)
Kolom praktis (15 x 15)
- Tul Pokok 10 0.616 3.55 0.1 3.65 4.00 14.60 9.00
- Bugel 6 0.222 0.15 0.10 0.15 0.10 0.06 0.56 23.67 13.25 2.94
TOTAL 8.00 95.50
Kolom Utama 30x30
- Tul Pokok 12 0.887 3.70 0.12 3.82 8.00 30.56 27.12
- Bugel 8 0.394 0.25 0.25 0.25 0.25 0.08 1.08 24.67 26.64 10.51
23.00 865.36
Balok Latai (15 x 20)
- Tul Pokok 10 0.616 50.82 0.1 50.92 4.00 203.68 125.51
1
- Bugel 6 0.222 0.15 0.15 0.15 0.15 0.06 0.66 338.80 223.61 49.61
TOTAL 175.12
Ringbalok ( 15 x 20 )
- Tul Pokok 10 0.616 139.00 0.1 139.10 4.00 556.40 342.87
- Bugel 6 0.222 0.10 0.10 0.10 0.10 0.06 0.46 926.67 426.27 94.56
TOTAL 437.43
Dak Beton
- Tul Pokok 10 0.616 7.50 0.1 7.60 50.00 380.00 234.17
- Tul Bagi 6 0.222 7.50 0.06 7.56 50.00 378.00 83.86
TOTAL 1.00 318.02
C. HALTE
BERAT UKURAN PANJANG JUMLAH TOTAL BERAT
Ø PANJANG TOTAL
No TULANGAN
(mm)
Per M Btg Btg KET
A B C D KAIT
(Kg/M) (M) (Bh) Btg (Kg)
Sloof (20 x 15)
- Tul Pokok 10 0.616 70.00 0.1 70.10 4.00 280.40 172.79
- Bugel 6 0.222 0.20 0.25 0.20 0.25 0.06 0.96 466.67 448.00 99.38
TOTAL 272.17
1
Rangka Pipa Galvanis
Pipa Gip 4" 100 41.082 101.71 101.71 1.00 101.71 4178.42
Pipa Gip 1" 25 2.568 38.34 38.34 1.00 38.34 98.44
TOTAL 4276.86
DAFTAR HARGA BAHAN DAN UPAH KERJA

NO BAHAN KODE SATUAN UPAH

H BAHAN LISTRIK

1 Kabel listrik -NYM 3x2.5 M.83 M' Rp 13,500

2 Kabel Listrik -NY 2x2,5 mm M.84 M' Rp 15,000

3 Kabel TV M.84b M' Rp 16,000

4 Pipa Instalasi PVC ø5/8" M.85a Btg Rp 8,800

5 Stop Kontak - Putih M.86 Bh Rp 15,800

6 Saklar Ganda - Putih M.87 Bh Rp 26,800

7 Saklar Tunggal - Putih M.88 Bh Rp 21,400

8 Fitting Tempel M.89a Bh Rp 13,700

9 Fitting Tanam M.89b Bh Rp 36,400

10 Lampu Selang M.90 M' Rp 29,100

11 Lampu Neon RM 2x 18 Watt M.91 Set Rp 318,200

12 Lampu Out Blow LED 6 Watt M.92a Bh Rp 112,000

13 Lampu SL 8 Watt M.92b Bh Rp 27,500

14 Lampu Sorot Mini M.93 Bh Rp 145,500

15 Socket TV Kabel M.94 Bh Rp 49,500

16 Boks Sekring/MCB 40A M.95 Set Rp 305,000

17 T Dos 5/8" M.85b Bh Rp 1,200


DAFTAR HARGA BAHAN DAN UPAH KERJA
PEKERJAAN : PEMBANGUNAN TERMINAL DARAT KAB. LUWU
LOKASI : KEC. BELOPA UTARA KABUPATEN LUWU
I. DAFTAR UPAH KERJA
NO TENAGA KERJA KODE SATUAN UPAH HARGA UPAH / 7 JAM
A. PEKERJA
1 Pekerja Orang - Hari Rp 115,000 Rp 16,428.57
B. TUKANG
1 Tukang Batu Orang - Hari Rp 140,000 Rp 20,000.00
2 Tukang Besi Orang - Hari Rp 140,000 Rp 20,000.00
3 Tukang Cat Orang - Hari Rp 140,000 Rp 20,000.00
4 Tukang Kayu Orang - Hari Rp 140,000 Rp 20,000.00
5 Tukang Listrik Orang - Hari Rp 140,000 Rp 20,000.00
6 Tukang Pipa Orang - Hari Rp 140,000 Rp 20,000.00
7 Tukang Penganyam Boronjong Orang - Hari Rp 140,000 Rp 20,000.00
8 Tukang Plafon Orang - Hari Rp 140,000 Rp 20,000.00
9 Tukang Alumunium Orang - Hari Rp 140,000 Rp 20,000.00
10 Tukang Rangka Orang - Hari Rp 140,000 Rp 20,000.00
11 Tukang Las Orang - Hari Rp 140,000 Rp 20,000.00
C. KEPALA TUKANG
1 KepalaTukang Batu Orang - Hari Rp 175,000 Rp 25,000.00
2 KepalaTukang Besi Orang - Hari Rp 175,000 Rp 25,000.00
3 Kepala Tukang Cat Orang - Hari Rp 175,000 Rp 25,000.00
4 Kepala Tukang Kayu Orang - Hari Rp 175,000 Rp 25,000.00
5 Kepala Tukang Listrik Orang - Hari Rp 175,000 Rp 25,000.00
6 Kepala Tukang Pipa Orang - Hari Rp 175,000 Rp 25,000.00
7 Kepala Tukang Orang - Hari Rp 175,000 Rp 25,000.00
D. MANDOR LAPANGAN
1 Mandor Lapangan Orang - Hari Rp 180,000 Rp 25,714.29
RENCANA ANGGARAN BIAYA (RAB)

SATUAN KERJA : DINAS PERHUBUNGAN KABUPATEN LUWU


NAMA KEGIATAN : PENINGKATAN SARANA & PRASARANA PERHUBUNGAN
PAKET PEKERJAAN : PEMBANGUNAN TERMINAL TIPE C KEC. BELOPA
LOKASI : KEC. BELOPA KABUPATEN LUWU

KODE VOLUME BIAYA JUMLAH


No. URAIAN PEKERJAAN
ANALISA SATUAN KONSTRUKSI HARGA
(1) (2) (3) (4) (5) (6) = (4) x (5)
A. PENDAHULUAN
I PEKERJAAN PERSIAPAN
1 Pengukuran Awal dan Pemasangan Bowplank 1.00 Ls Rp 2,000,000.00 Rp 2,000,000.00
2 Pemasangan Papan Nama Proyek 1.00 Ls Rp 250,000.00 Rp 250,000.00
3 Pembuatan Direksi Keet 1.00 Ls Rp 5,000,000.00 Rp 5,000,000.00
4 Kesehatan & Keselamatan Kerja (K3) dan Penanganan Covid 1.00 Ls Rp 4,600,000.00 Rp 4,600,000.00
5 Pek. Pembersihan 1.00 Ls Rp 850,000.00 Rp 850,000.00
Jumlah Total (I) Rp 12,700,000.00
B. PEKERJAAN KANTOR PENGELOLA LANTAI SATU
I PEKERJAAN TANAH DAN PONDASI
DIVISI I
1 Pek.Galian Tanah Pondasi A.2.3.1.1 33.95 m3 Rp 104,362.50 Rp 3,542,898.15
2 Pek. Urugan Kembali Bekas Galian A.2.3.1.9 16.97 m3 Rp 76,475.00 Rp 1,298,086.65
3 Pek. Urugan Pasir Bawah Pondasi A.2.3.1.11 5.66 m3 Rp 214,245.00 Rp 1,212,198.21
4 Pek. Timbunan Biasa dari sumber galian termasuk pemadatan
A.2.2.1.3 84.38 m3 Rp 125,879.00 Rp 10,621,040.63
DEVISI II
1 Pek. Pondasi Tapak Beton 1 : 2 : 3 (P1)
a. Beton mutu f'c = 14,5 Mpa,slump (120 ± 20) cm A.4.1.1.6 18.40 m3 Rp 1,437,750.13 Rp 26,454,602.30
b. Pembesian A.4.1.1.17 292.59 kg Rp 18,394.83 Rp 5,382,118.98
c. Bekisting A.4.1.1.20 73.60 m2 Rp 52,000.32 Rp 3,827,223.31
2 Pek. Kolom Pondasi Tapak Beton 1 : 2 : 3 (K1 30/30)
a. Beton mutu f'c = 14,5 Mpa,slump (120 ± 20) cm A.4.1.1.6 1.86 m3 Rp 1,437,750.13 Rp 2,678,528.48
b. Pembesian A.4.1.1.17 223.99 kg Rp 18,394.83 Rp 4,120,239.90
c. Bekisting A.4.1.1.20 24.84 m2 Rp 52,000.32 Rp 1,291,687.87
3 Pas. Pondasi Batu Kali 1 Pc : 4 Ps A.3.2.1.2 54.46 m3 Rp 1,050,806.75 Rp 57,225,096.69
4 Pas. Pondasi Batu Kosong Batu Kali / Aanstamping A.3.2.1.9 11.32 m3 Rp 499,266.75 Rp 5,649,702.54
Jumlah Total (I) Rp 123,303,423.70
II PEKERJAAN BETON
1 Pek. Beton Sloof 1 : 2 : 3 S1 (20/30)
a. Beton mutu f'c = 14,5 Mpa,slump (120 ± 20) cm A.4.1.1.6 8.49 m3 Rp 1,437,750.13 Rp 12,202,185.31
b. Pembesian A.4.1.1.17 1081.02 kg Rp 18,394.83 Rp 19,885,180.11
c. Bekisting A.4.1.1.21 84.87 m2 Rp 76,233.50 Rp 6,469,937.15
2 Pek. Beton Kolom Utama 1 : 2 : 3 (K1 30/30)
a. Beton mutu f'c = 14,5 Mpa,slump (120 ± 20) cm A.4.1.1.6 7.35 m3 Rp 1,437,750.13 Rp 10,565,306.79
b. Pembesian A.4.1.1.17 831.07 kg Rp 18,394.83 Rp 15,287,380.37
c. Bekisting A.4.1.1.22 97.98 m2 Rp 114,880.59 Rp 11,256,000.37
3 Pek. Beton Kolom Praktis 1 : 2 : 3 (KP 15/15)
a. Beton mutu f'c = 7,4 Mpa A.4.1.1.4 3.43 m3 Rp 1,066,274.25 Rp 3,662,252.20
b. Pembesian A.4.1.1.17 524.53 kg Rp 18,394.83 Rp 9,648,578.26
c. Bekisting A.4.1.1.22 45.80 m2 Rp 114,880.59 Rp 5,260,956.70
4 Pek. Balok Latei Diatas Kusen (15/15)
a. Beton mutu f'c = 7,4 Mpa A.4.1.1.4 0.35 m3 Rp 1,066,274.25 Rp 374,262.26
b. Pembesian A.4.1.1.17 51.62 kg Rp 18,394.83 Rp 949,521.55
c. Bekisting A.4.1.1.23 4.68 m2 Rp 157,627.43 Rp 737,696.39
5 Pek. Beton Balok 1 : 2 : 3 (B1 25/20)
a. Beton mutu f'c = 14,5 Mpa,slump (120 ± 20) cm A.4.1.1.6 7.07 m3 Rp 1,437,750.13 Rp 10,168,487.76
b. Pembesian A.4.1.1.17 969.45 kg Rp 18,394.83 Rp 17,832,846.80
c. Bekisting A.4.1.1.23 99.02 m2 Rp 157,627.43 Rp 15,607,480.31
6 Pek. Rabat Beton Lantai 1 mutu f'c = 7,4 Mpa (K-100) A.4.1.1.4 26.89 m3 Rp 1,066,274.25 Rp 28,669,448.90
7 Pek. Plat Lantai 2 (1 : 2 : 3 t=12 cm)
a. Beton mutu f'c = 14,5 Mpa,slump (120 ± 20) cm A.4.1.1.6 19.98 m3 Rp 1,437,750.13 Rp 28,726,247.50
b. Pembesian A.4.1.1.17 1452.02 kg Rp 18,394.83 Rp 26,709,714.35
c. Bekisting A.4.1.1.19 166.50 m2 Rp 149,485.43 Rp 24,889,324.65
8 Pek. Tangga
a. Beton mutu f'c = 14,5 Mpa,slump (120 ± 20) cm A.4.1.1.6 1.29 m3 Rp 1,437,750.13 Rp 1,850,384.41
b. Pembesian A.4.1.1.17 63.79 kg Rp 18,394.83 Rp 1,173,408.33
c. Bekisting A.4.1.1.26 7.81 m2 Rp 109,950.35 Rp 858,712.23
Jumlah Total (II) Rp 252,785,312.69
III PEKERJAAN DINDING
1 Pas. Dinding Batu Bata Campuran 1 : 4 A.4.4.1.9 421.17 m2 Rp 152,317.50 Rp 64,150,799.89
2 Pek. Plsteran Dinding & Beton Campuran 1 : 4 A.4.4.2.5 842.33 m2 Rp 87,954.99 Rp 74,087,126.73
3 Pek. Acian Dinding A.4.4.2.27 683.70 m2 Rp 39,387.50 Rp 26,929,233.75
4 Pek. Acian Kolom K1 A.4.4.2.27 29.82 m2 Rp 39,387.50 Rp 1,174,535.25
Jumlah Total (III) Rp 166,341,695.61
IV PEK. PINTU DAN JENDELA
1 Kusen Pintu P1 Jumlah 4 Unit
a. Kusen Pintu Almunium A.4.2.1.11 22.80 m' Rp 130,806.18 Rp 2,982,380.79
b. Daun Pintu A.4.2.1.13 7.95 m2 Rp 427,659.13 Rp 3,399,890.04
c. Kaca Bening 5 mm A.4.6.2.17 0.69 m2 Rp 229,407.75 Rp 158,291.35
2 Kusen Pintu P2 Jumlah 12 Unit (PVC) 12.00 Ls Rp 575,000.00 Rp 6,900,000.00
Jumlah Total (IV) Rp 13,440,562.18
VI PEKERJAAN PLAFOND
1 Pek. Rangka Plafond Hollow 40 x 40 A.4.2.1.21 166.50 m2 Rp 73,502.25 Rp 12,238,124.63
2 Pek. Penutup Plafond Gypsum, Tebal 9 mm A.4.5.1.7 111.38 m2 Rp 70,886.00 Rp 7,894,928.25
3 Pek. Kalsibord A.4.5.1.8 56.25 m2 Rp 60,630.30 Rp 3,410,454.38
Jumlah Total (V) Rp 23,543,507.25
VII PEKERJAAN LANTAI / KERAMIK
1 Pek. Lantai Keramik 40 x 40 cm A.4.4.3.35b 287.15 m2 Rp 342,041.05 Rp 98,217,087.51
2 Pek.Lantai dan dinding Keramik WC 30 x 30 A.4.4.3.35 137.91 m2 Rp 160,625.20 Rp 22,151,821.96
3 Pek.Lantai Keramik Tangga 40 x 40 A.4.4.3.35b 14.35 m2 Rp 342,041.05 Rp 4,908,289.07
Jumlah Total (VI) Rp 125,277,198.53
VIII PEKERJAAN PENGECETAN
1 Pek. Cat Dinding A.4.7.1.10a 180.88 m2 Rp 31,685.38 Rp 5,731,092.20
2 Pek. Cat Plafond Berikut Plamir A.4.7.1.10c 111.38 m2 Rp 26,567.88 Rp 2,958,997.08
3 Pek. Cat Kalsibord A.4.7.1.10b 56.25 m2 Rp 33,525.38 Rp 1,885,802.34
Jumlah Total (VII) Rp 10,575,891.63
IX PEKERJAAN INSTALASI LSTRIK
1 Pas. Instalasi Listrik Kabel Utama 3 x 2,5 NYM A.6.1.1.1 46.65 m' Rp 114,643.50 Rp 5,348,119.28
2 Pas. Instalasi Titik Lampu 2 x 2,5 NYM A.6.2.1.1 37.00 ttk Rp 27,749.50 Rp 1,026,731.50
3 Pas. Instalasi Titik Saklar Tunggal 2 x 2,5 NYM A.6.1.1.4 5.00 ttk Rp 40,813.50 Rp 204,067.50
4 Pas. Instalasi Titik Saklar Ganda 3 x 2,5 NYM A.6.1.1.3 10.00 ttk Rp 47,023.50 Rp 470,235.00
5 Pas. Instalasi Titik Stop Kontak 3 x 2,5 NYM A.6.1.1.2 6.00 ttk Rp 34,373.50 Rp 206,241.00
6 Pas. Bohlam Lampu A.6.2.1.3b 37.00 ttk Rp 40,192.50 Rp 1,487,122.50
7 Pas. Kwh Meter A.6.2.1.12 1.00 Bh Rp 2,759,942.50 Rp 2,759,942.50
8 Pas. MCB + Box Sekring A.6.2.1.10 1.00 Bh Rp 359,317.50 Rp 359,317.50
9 Pas. Exhaust A.6.2.1.11 4.00 ttk Rp 874,494.50 Rp 3,497,978.00
Jumlah Total (VIII) Rp 15,359,754.78
X PEKERJAAN PENGGANTUNG / PENGUNCI
1 Pas. Engsel Pintu 4 (3bh/pintu) A.4.6.2.5 60.00 Bh Rp 121,307.75 Rp 7,278,465.00
2 Pas. Slot Pintu (2 bh/pintu) / Grendel Panjang A.4.6.2.11b 8.00 Bh Rp 81,397.00 Rp 651,176.00
3 Pas. Kunci Pintu 2 x Putar (Lever Handle) A.4.6.2.12 4.00 Bh Rp 212,692.50 Rp 850,770.00
Jumlah Total (IX) Rp 8,780,411.00
XI PEKERJAAN SANITASI
1 Pas. Instalasi Pipa PVC 3/4" Saluran Air Bersih A.5.1.1.26 25.00 m' Rp 27,501.10 Rp 687,527.50
2 Pas. Instalasi Pipa PVC 2" Saluran Air Bersih A.5.1.1.29 25.00 m' Rp 42,689.15 Rp 1,067,228.75
3 Pas. Instalasi Pipa PVC 3" Saluran Air Kotor A.5.1.1.31 20.00 m' Rp 73,377.48 Rp 1,467,549.50
4 Pas. Kran Air 1/2" A.5.1.1.19a 12.00 Bh Rp 106,852.25 Rp 1,282,227.00
5 Pas. Klosed Jongkok A.5.1.1.1 12.00 Bh Rp 2,479,273.50 Rp 29,751,282.00
6 Pas, Urinoir A.5.1.1.4 4.00 Bh Rp 2,020,941.00 Rp 8,083,764.00
7 Pas. Wasthafel A.5.1.1.5 2.00 Bh Rp 1,181,650.30 Rp 2,363,300.60
8 Pek. Floordrain A.5.1.1.14 12.00 Bh Rp 114,988.50 Rp 1,379,862.00
9 Pek. Septictank + Rembesan 1.00 Ls Rp 3,500,000.00 Rp 3,500,000.00
10 Pas. Kaca Muka 2.00 Bh Rp 126,800.00 Rp 253,600.00
Jumlah Total (X) Rp 49,836,341.35
C PEKERJAAN KANTOR PENGELOLAH LANTAI DUA
I PEKERJAAN BETON
1 Pek. Beton Kolom Utama 1 : 2 : 3 (30/30)
a. Beton mutu f'c = 14,5 Mpa,slump (120 ± 20) cm A.4.1.1.6 7.35 m3 Rp 1,437,750.13 Rp 10,565,306.79
b. Pembesian A.4.1.1.17 865.36 kg Rp 18,394.83 Rp 15,918,097.44
c. Bekisting A.4.1.1.22 97.98 m2 Rp 114,880.59 Rp 11,256,000.37
2 Pek. Beton Kolom Praktis 1 : 2 : 3 (KP 15/15)
a. Beton mutu f'c = 7,4 Mpa A.4.1.1.6 0.64 m3 Rp 1,066,274.25 Rp 681,349.25
b. Pembesian A.4.1.1.17 95.50 kg Rp 18,394.83 Rp 1,756,634.82
c. Bekisting A.4.1.1.22 8.52 m2 Rp 114,880.59 Rp 978,782.64
3 Pek. Balok Latei Diatas Kusen (15/15)
a. Beton mutu f'c = 7,4 Mpa A.4.1.1.6 1.14 m3 Rp 1,066,274.25 Rp 1,219,231.29
b. Pembesian A.4.1.1.17 175.12 kg Rp 18,394.83 Rp 3,221,267.36
c. Bekisting A.4.1.1.23 15.25 m2 Rp 157,627.43 Rp 2,403,187.85
4 Pek. Beton Ring Balok 1 : 2 : 3 (RB 15/20)
a. Beton mutu f'c = 16,9 Mpa,slump (120 ± 20) cm A.4.1.1.36 4.17 m3 Rp 1,437,750.13 Rp 5,995,418.02
b. Pembesian A.4.1.1.17 437.43 kg Rp 18,394.83 Rp 8,046,466.94
c. Bekisting A.4.1.1.23 76.45 m2 Rp 157,627.43 Rp 12,050,617.28
5 Pek. Dak Beton
a. Beton Mutu f'c =14,5 Mpa A.4.1.1.6 16.88 m3 Rp 1,437,750.13 Rp 24,262,033.36
b. Pembesian A.4.1.1.17 318.02 kg Rp 18,394.83 Rp 5,849,947.96
c. Bekisting A.4.1.1.22 168.75 m2 Rp 149,485.43 Rp 25,225,666.88
Jumlah Total (I) Rp 129,430,008.25
II PEKERJAAN DINDING
1 Pas. Dinding Batu Bata Camp 1 : 4 A.4.4.1.9 231.59 m2 Rp 152,317.50 Rp 35,274,829.03
2 Pek. Plesteran Dinding dan Beton Camp 1 : 4 A.4.4.2.5 608.03 m2 Rp 87,954.99 Rp 53,478,832.79
3 Pek. Acian Dinding dan Beton A.4.4.2.27 560.93 m2 Rp 39,387.50 Rp 22,093,433.44
Jumlah Total (II) Rp 110,847,095.26
III PEKERJAAN PINTU DAN JENDELA
1 Pek. Pintu P2 (PVC) 3 Unit 3.00 Ls Rp 575,000.00 Rp 1,725,000.00
2 Kusen Pintu P3 Jumlah 4 Unit
a. Kusen Pintu A.4.2.1.11 28.00 m' Rp 130,806.18 Rp 3,662,572.90
b. Daun Pintu A.4.2.1.13 6.02 m2 Rp 427,659.13 Rp 2,574,507.93
c. Kaca Bening 5 mm A.4.6.2.17 1.00 m2 Rp 229,407.75 Rp 229,407.75
3 Kusen Pintu P4 Jumlah 2 Unit
a. Kusen Pintu A.4.2.1.11 18.72 m' Rp 130,806.18 Rp 2,448,691.60
b. Daun Pintu A.4.6.2.17 6.52 m2 Rp 229,407.75 Rp 1,495,738.53
c. Kaca Bening 5 mm A.4.6.2.17 0.50 m2
4 Kusen Jendela J3 Jumlah 6 Unit
a. Kusen Jendela A.4.2.1.11 70.20 m' Rp 130,806.18 Rp 9,182,593.49
b. Kaca Bening 5 mm A.4.6.2.17 46.23 m2 Rp 229,407.75 Rp 10,605,520.28
5 Kusen Jendela J2 Jumlah 2 Unit
a. Kusen Jendela A.4.2.1.11 5.60 m' Rp 130,806.18 Rp 732,514.58
b. Kaca Bening 5 mm A.4.6.2.17 0.96 m2 Rp 229,407.75 Rp 220,231.44
6 Kusen Jendela J1 7 Unit
a. Kusen Jendela A.4.2.1.11 99.40 m' Rp 130,806.18 Rp 13,002,133.80
b. Kaca Bening 5 mm A.4.6.2.17 28.81 m2 Rp 229,407.75 Rp 6,609,696.09
Jumlah Total (III) Rp 52,488,608.38
IV PEKERJAAN KUDA - KUDA DAN ATAP
1 Pek. Rangka Atap Baja Ringan A.4.2.1.22 123.00 m2 Rp 247,485.75 Rp 30,440,747.25
2 Pek. Penutup Atap Spandek / Galvalyum 0,35 mm A.4.5.2.38 135.71 m2 Rp 192,562.90 Rp 26,132,711.16
3 Pek. Nok Spandek / Galvalyum 0,35 mm A.4.5.2.39 20.50 m' Rp 53,080.55 Rp 1,088,151.28
4 Pek. Listplank GRC Lebar 30 cm A.4.6.1.29 54.24 m' Rp 62,985.50 Rp 3,416,333.52
Jumlah Total (IV) Rp 61,077,943.20
V PEKERJAAN PLAFOND
1 Pek. Rangka Plafond Hollow 40 x 40 A.4.2.1.21 168.75 m2 Rp 73,502.25 Rp 12,403,504.69
2 Pek. Penutup Plafond Gypsum,Tebal 9 mm A.4.5.1.7 152.81 m2 Rp 70,886.00 Rp 10,832,266.88
3 Pek. Kalsibord A.4.5.1.8 8.06 m2 Rp 60,630.30 Rp 488,831.79
Jumlah Total (V) Rp 23,724,603.36
VI PEKERJAAN LANTAI / KERAMIK
1 Pek. Lantai Keramik 40 x 40 cm A.4.4.3.35b 144.94 m2 Rp 342,041.05 Rp 49,575,429.79

2 Pek. Lantai dan dinding Keramik Kamar Mandi 30 x 30 cm A.4.4.3.35b 31.61 m2 Rp 160,625.20 Rp 5,077,764.28

Jumlah Total (VI) Rp 54,653,194.07


VII PEKERJAAN PENGECATAN
1 Pek. Cat Dinding A.4.7.1.10a 439.63 m2 Rp 31,685.38 Rp 13,929,682.98
2 Pek. Cat Plafond Berikut Plamir A.4.7.1.10c 152.81 m2 Rp 26,567.88 Rp 4,059,903.40
3 Pek. Cat Kalsibord A.4.7.1.10b 8.06 m2 Rp 33,525.38 Rp 270,298.34
4 Pek. Cat Listplank A.4.7.1.10b 16.27 m2 Rp 33,525.38 Rp 545,524.90
Jumlah Total (VII) Rp 18,805,409.62
VIII PEKERJAAN INSTALASI LISTRIK
1 Pas. Instalasi Listrik Kabel Utama 3 x 2,5 NYM A.6.1.1.1 26.00 m' Rp 114,643.50 Rp 2,980,731.00
2 Pas. Instalasi Titik Lampu 2 x 2,5 NYM A.6.2.1.1 38.00 ttk Rp 27,749.50 Rp 1,054,481.00
3 Pas. Instalasi Titik Saklar Ganda 3 x 2,5 NYM A.6.1.1.3 16.00 ttk Rp 47,023.50 Rp 752,376.00
4 Pas. Instalasi Titik Stop Kontak 3 x 2,5 NYM A.6.1.1.2 36.00 ttk Rp 34,373.50 Rp 1,237,446.00
5 Pas. Bohlam Lampu A.6.2.1.3b 38.00 Bh Rp 40,192.50 Rp 1,527,315.00
6 Pas. MCB + Box Sekring A.6.2.1.10 1.00 Bh Rp 359,317.50 Rp 359,317.50
7 Pas. Exhaust A.6.2.1.11 6.00 ttk Rp 874,494.50 Rp 5,246,967.00
Jumlah Total (VIII) Rp 13,158,633.50
IX PEKERJAAN PENGGANTUNG / PENGUNCI
1 Pas. Engsel Pintu 4" (3bh/pintu) A.4.6.2.5 53.00 Bh Rp 121,307.75 Rp 6,429,310.75
2 Pas. Slot Pintu (2 bh/pintu) / Grendel Panjang A.4.6.2.11b 8.00 Bh Rp 81,397.00 Rp 651,176.00
3 Pas. Kunci Pintu 2 x Putar (Lever Handle) A.4.6.2.12 6.00 Bh Rp 212,692.50 Rp 1,276,155.00
Jumlah Total (IX) Rp 8,356,641.75
X PEKERJAAN SANITASI
1 Pas. Instalasi Pipa PVC 3/4" Saluran Air Bersih A.5.1.1.26 15.35 m' Rp 27,501.10 Rp 422,141.89
2 Pas. Instalasi Pipa PVC 2" Saluran Air Bersih A.5.1.1.29 11.35 m' Rp 42,689.15 Rp 484,521.85
3 Pas. Instalasi Pipa PVC 3" Saluran Air Kotor A.5.1.1.31 7.30 m' Rp 73,377.48 Rp 535,655.57
4 Pas. Kran Air 1/2" A.5.1.1.19a 3.00 Bh Rp 106,852.25 Rp 320,556.75
5 Pas. Klosed Duduk A.5.1.1.2 3.00 Bh Rp 2,479,273.50 Rp 7,437,820.50
6 Pek. Floordrain A.5.1.1.14 3.00 Bh Rp 114,988.50 Rp 344,965.50
Jumlah Total (X) Rp 9,545,662.06
XI PEKERJAAN FINISHING & AKSESORIES
1 Pek. Pas Huruf 1.00 Ls Rp 12,000,000.00 Rp 12,000,000.00
2 Pek. Pas Logo 2.00 Ls Rp 1,000,000.00 Rp 2,000,000.00
3 Pek. Keramik Pasade Dinding Depan A.4.4.3.35b 20.15 m2 Rp 342,041.05 Rp 6,892,127.16

4 Pek. Alumunium Composite Panel A.4.6.1.30 152.94 m2 Rp 725,541.60 Rp 110,966,508.68


5 Pek. Pas Relling Tangga 1.00 Ls Rp 5,000,000.00 Rp 5,000,000.00

6 Pek. Profil Acrilic 13.00 Ls Rp 800,000.00 Rp 10,400,000.00

Jumlah Total (XI) Rp 147,258,635.84


D HALTE
I PEKERJAAN TANAH DAN PONDASI
DEVISI I
1 Pek.Galian Tanah Pondasi A.2.3.1.1 12.60 m3 Rp 104,362.50 Rp 1,314,967.50
2 Pek. Urugan Kembali Bekas Galian A.2.3.1.9 21.00 m3 Rp 76,475.00 Rp 1,605,975.00
3 Pek. Urugan Pasir Bawah Pondasi A.2.3.1.11 2.10 m3 Rp 214,245.00 Rp 449,914.50
4 Pek. Timbunan Biasa dari sumber galian A.2.3.1.1 48.60 m3 Rp 104,362.50 Rp 5,072,017.50
DEVISI II
1 Pek. Rabat Beton Lantai 1 : 2 : 3 A.4.1.1.4 14.85 m3 Rp 1,066,274.25 Rp 15,834,172.61
2 Pas. Pondasi Batu Kali 1 Pc : 4 Ps A.3.2.1.2 25.20 m3 Rp 1,050,806.75 Rp 26,480,330.10
3 Pas. Pondasi Batu Kosong Batu Kali / Aanstamping A.3.2.1.9 6.30 m3 Rp 499,266.75 Rp 3,145,380.53
4 Pek. Pondasi Ungkap A.4.1.1.4 0.38 m3 Rp 1,066,274.25 Rp 403,051.67
Jumlah Total (I) Rp 54,305,809.40
II PEKERJAAN BETON
1 Pek. Beton Sloof 1 : 2 : 3 (20/25)
a. Beton mutu f'c = 7,4 Mpa A.4.1.1.6 3.50 m3 Rp 1,066,274.25 Rp 3,731,959.88
b. Pembesian A.4.1.1.17 272.17 kg Rp 18,394.83 Rp 5,006,597.85
c. Bekisting A.4.1.1.21 35.00 m2 Rp 76,233.50 Rp 2,668,172.50
Jumlah Total (II) Rp 11,406,730.22
IV PEKERJAAN ATAP
1 Pek. Tiang dan Rangka Atap Pipa Galvanis 4" A.4.2.1.22 4276.86 Kg Rp 30,204.75 Rp 129,181,434.54
2 Pek. Penutup Atap Spandek / Galvalyum 0,35 mm A.4.5.2.38 199.53 m2 Rp 192,562.90 Rp 38,422,075.44
Jumlah Total (IV) Rp 167,603,509.98
VI PEKERJAAN LANTAI / KERAMIK
1 Pek. Lantai Keramik 30 x 30 cm A.4.4.3.35b 199.53 m2 Rp 160,625.20 Rp 32,049,547.06
Jumlah Total (VI) Rp 32,049,547.06
VIII PEKERJAAN INSTALASI LSTRIK
1 Pas. Instalasi Listrik Kabel Utama 3 x 2,5 NYM A.6.1.1.1 25.00 m' Rp 114,643.50 Rp 2,866,087.50
2 Pas. Instalasi Titik Lampu 2 x 2,5 NYM A.6.2.1.1 6.00 ttk Rp 27,749.50 Rp 166,497.00
3 Pas. Instalasi Titik Saklar Ganda 3 x 2,5 NYM A.6.1.1.3 3.00 ttk Rp 47,023.50 Rp 141,070.50
4 Pas. Bohlam lampu A.6.2.1.3b 6.00 Bh Rp 40,192.50 Rp 241,155.00
Jumlah Total (VIII) Rp 3,414,810.00
E PEKERJAAN AKHIR
II FINISHING
1 Pembersihan Lokasi Kerja 1.00 Ls Rp 1,042,686.18 Rp 1,042,686.18
Jumlah Total (I) Rp 1,042,686.18

Anda mungkin juga menyukai