ESTIMASI RESUME PEKERJAAN JEMBATAN GORONTALO STA 3+300

No Type Satuan Volume


1 Utilitas Ls 1.00
2 Loading test Ls 1.00
3 Pekerjaan Tanah (Approching Road : 50m)
3.1 Timbunan tanah m3 8504.1
3.2 Galian tanah m3 15312.8
TOTAL 23816.9

4 Pekerjaan Struktur Baja


4.1 Rangka A+ 60 STA 3+300 kg 388660.0
4.2 I-Girder A+ 25 STA 3+350 kg 66786.0
4.3 I-Girder A+ 25 STA 3+250 kg 66786.0
4.4 Expansion Joint m' 87.00
TOTAL 522319.0

5 Pekerjaan Approach Slab


5.1 Sub Base Agregat m3 378.1
5.2 Base Course m3 378.1
5.3 Lean Concrete K175 m3 69.9
5.4 Lantai Beton K350 (approach road) m3 412.5
TOTAL 1238.6

6 Pekerjaan Struktur Beton (Slab,Pier, & Abt)


6.1 Lantai Beton K350 (Jembatan) m3 496.3
6.2 Abutment K350 (2 abutment) m3 549.8
6.3 Pier (2 pier) K350 m3 2393.7
6.4 Lean Concrete K175 m3 124.7
TOTAL 3439.8

7 Pekerjaan Struktur Beton (Pondasi)


7.1 Borepile Dia. 1,2m m' 48.0
TOTAL 48.0

8 Pekerjaan Tulangan Baja


8.1 Besi Tulangan Abutment kg 84939.2
8.2 Besi Tulangan Pier kg 369830.7
8.3 Besi Tulangan Lantai Beton (Jembatan) kg 76684.0
8.4 Besi Tulangan Lantai Beton (Approach Slab) kg 63731.3
TOTAL 595185

9 Pekerjaan Aspal
9.1 Aspal kg 363980.1
TOTAL 363980.1

Note : - Perhitungan volume pekerjaan berdasarkan gambar dari tim konsultan pertanggal
19/06/2023
- Berat struktur jembatan baja menggunakan desain PT BMI
- Rasio volume tulangan untuk struktur beton menggunakan asumsi 150