PT BANGUNINDO KARYA LUTAMA

CONTRACTOR _ ASPHALT MIXING PLANT_GENERAL TRADING

PENGUJIAN KEPADATAN LAPANGAN


DENGAN METODA SAND CONE

Jenis material : Aggregat Klas B


Tanggal Test 26 JULI 2023
RUAS POMALAA
STA (KM) 1+375 1+100 00+900 00+000 00+000
TEBAL LAYER TOP TOP TOP TOP TOP
L/R/CL

PENENTUAN ISI LOBANG

1 Berat Pasir+Botol+Corong 6719 6714 6709


2 Berat Sisa Pasir+Botol+Corong 2560 2653 2631
3 Berat Pasir (1-2) 4159 4061 4078
4 Berat Pasir di Dalam Corong 1784 1784 1784
5 Berat Pasir di Dalam Lubang (3-4) 2375 2277 2294
6 Berat Isi Pasir 1,565 1,565 1,565
7 Volume Lubang (5/6) 1517,6 1455,0 1465,8

PENENTUAN KADAR AIR

8 Berat Tanah Basah + Cawan 38 41 43


9 Berat Tanah Kering + Cawan 30 31 33,0
10 Berat Cawan 12 15 14
11 Berat Air (8-9) 8,0 10,0 10,0
12 Berat Tanah Kering + Cawan (9-10) 18 16 19
13 Kadar Air (11/12) * 100 44,4 62,5 52,6

PENENTUAN KEPADATAN

14 Berat Aggregate + Cawan 3529 3624 3615


15 Berat Cawan 134 134 134
16 Berat Aggregate 3395 3490 3481
17 Berat Aggregate Tertahan Saringan 3/4 1210 1737 1952
18 Berat Aggregate Lolos Saringan 3/4 2185 1753 1529
19 Presentase Aggregate Tertahan Saringan 3/4 = (17/16) * 100 35,64 49,77 56,08
20 Presentase Aggregate Lolos Saringan 3/4 = (18/16) * 100 64,36 50,23 43,92
21 SPGR Aggregate (Lab) 3,251 3,251 3,251
22 Derajat Kepadatan Basah Aggregate (16/7) 2,237 2,399 2,375
23 Derajat Kepadatan Kering Aggregate = (22*100) / (100+13) 1,549 1,476 1,556
24 Kepadatan Kering Maksimum (Lab) 2,222 2,222 2,222
100
25 Faktor Koreksi = 2,505 2,637 2,701
(19/21) + (20/24)
26 Derajat Kepadatan di Lapangan = (23/25) * 100 61,84 55,97 57,59
27 Spesifikasi Min 60% Min 60% Min 60% Min 60% Min 60%
Prepared , Approved,
PT BANGUNINDO KARYA LUTAMA PT. VALE INDONESIA Tbk,

ARSIN
Quality Controll Quality Control