DATE: 20 July 2007

PROJECT NAME: Pamarutan Village

DSCA PROJECT NUMBER:


ODC PRIORITY:

PROJECT DESCRIPTION:





Construct 150-foot concrete pier on pilings at beach area of village at a location
determined based on evaluation of wave/wind directions, shoreline and offshore features,
and village input. Pier designed to accommodate major storm events and small boat
landings at village.

Provide sealed well head and hand pump for village water well. Well is approximately 4
feet in diameter, a depth to water of 5 to 10 feet, has 3 feet of standing water, and
connects to an aboveground water storage tank. Discharge pressure head for pump will be
designed to allow hand pumpage into the aboveground tank.

Project will also include demolition of existing latrine facility and construction of a new
latrine building with three toilets, with new latrines connected into new septic system and
drain field. Sinks for hand washing will be installed adjacent to the new latrines.

FUNDING STATUS:

LOCATION: Pamarutan Village, Lembeh Island, Bitung City, Northern Sulewesi


Province
GPS COORDINATES: N 01-23-59.4, E 125-11-35.4
ELEVATION:

SITE DESCRIPTION: Parmurutan Village is located on Lembeh Island accessible only


by sea. Site includes 10 to 15 small houses, a public bathroom facility, and an existing
open water well with water bucket attached to rope, equipped with an aboveground water
tank that was once filled by an electric pump. Access to site is marginal, with all boat
landings required to be conducted on an open beach area, creating difficulties for
transporting equipment and materials in, and produce and other materials out of the
village. Existing toilets (2) are located in a separate building, are flushed using a water
bucket and small water tank (mende) in bathroom, and are generally in average condition,
although with a poorly functioning septic system.

DESIGN STRATEGY/CONST: Local construction company conducting design-build


project with QA firm providing oversight
INITIAL USACE ENGR ASSESSMENT : 20 Jul 07 – John Emmerson, Mark Schnabel,
Jon Herwig

PROJECT POCS:
ODC: LTC Kenneth Comer, (62-21) 3435-9603, cccomer@san.osd.mil
CA PLANNER: MAJ Steve Lewis, (62-21) 3435-9610
Bitung City Planner: James Romas, cell 08124300872, jamesrompas@yahoo.com
USACE: Mark Schnabel/John Emmerson (808-477-0880 / 808-438-6968)
CH2MHill: Jon Herwig: (cell 808-372-9644, office 808-440-0238))
:

PROJECT ISSUES: An appropriate location of the pier must be identified based on an


evaluation of shoreline, weather, and efficiency considerations. Permitting requirements
for pier must be identified. A hand pump with appropriate discharge pressure to fill the
aboveground tank must be identified.

TAB A: PROJECT LOCATION MAP


TAB B: SITE SKETCH
TAB C: SITE PICTURES