Back Up Data Bronjong Rev Lagi
Back Up Data Bronjong Rev Lagi
KECAMATAN HILIDUHO
BACK UP DATA
PEKERJAAN
Gambar Perhitungan
2 Galian Tanah
V = Panjang x lebar x tinggi
V = 6 x 3 x 1,57 = 28,26 m3
3 Timbunan Batu
V = Panjang x luas
V = 7,0 x 1,9133 = 13,39 m3
4 Timbunan Sirtu
V = Panjang x luas
V = 10,0 x 0,75 = 7,50 m3
KEGIATAN
DANA DESA TA. 2022
LANJUTAN PEMBANGUNAN BRONJONG DI UNJUNG
BACK UP DATA YANG DIKELOLA OLEH DESA SISOBALURU KABUPATEN NIAS
JEMBATAN NO'UO DUSUN II DESA SISOBALAURU
Gambar Perhitungan
Gambar Perhitungan
6 Geotekstil
L = Panjang x lebar
L = 7x 4,5 = 31,5 m3
7 Cerucuk bambu
P = P : P.tipe 3 x Julh ceruck t.cerucuk
P1 = 6 : 3 x 6 x 1,5 = 18,0 M'