Anda di halaman 1dari 4

Sheet2_2

KOP LEMBAGA

(ALAMAT LENGKAP)

RENCANA ANGGARAN BIAYA


PEKERJAAN : PEMBANGUNAN WORKSHOP BLK KOMUNITAS
PEMBERI : BANTUAN KEMENTRIAN KETENAGA KERJAAN RI
KEJURUAN : ........................ (GRUP B)
TAHUN ANGGARAN : 2023

HARGA
JUMLAH
No. URAIAN PEKERJAAN VOLUME SAT. SATUAN
HARGA (Rp.)
(Rp.)
1 2,00 4,00 5,00 6,00
A PEKERJAAN PERSIAPAN
1 Papan Proyek 1,00 unit -284 -284
2 Pek. Laporan & Dokumentasi 1,00 ls -284 -284
Sub Total A -567 -567
B PEKERJAAN PFONDASI DAN TANAH
1 Pek. Galian Tanah Pondasi 79,84 m3 96.716 7.721.834
2 Pek. Urug Tanah Kemabali 26,61 m3 24.716 657.702
3 Pek. Urug Tanah Peniggian Pell Lantai (1 -10 cm) 22,40 m3 -284 -6.354
4 Pek. Pasir Urug
- Bawah Fondasi 7,79 m3 89.716 698.890
- Bawah Lantai 11,20 m3 89.716 1.004.823
5 Pek. Findasi Tepok P1 (90 x 90 x 20)
- Beton K-225 2,59 m3 64.716 167.615
- Pembesian 639,36 kg 10.216 6.531.932
- Bekisting 11,52 m2 39.716 457.532
6 Pek. Fondasi Batu Belah P2 27,51 m3 159.716 4.393.797
7 Pek. Fondasi Tapak P3 (50 x 50 x 20)
- Beton K-255 0,10 m3 64.716 6.472
- Pembersian 26,64 kg 10.216 272.164
- Bekisting 0,80 m2 39.716 31.773
8 Pek. Sloof Beton S1 (15/30)
- Beton K-255 4,14 m3 64.716 267.926
- Pembesian 752,64 kg 10.216 7.689.241
- Bekisting 55,26 m2 39.716 2.194.726
9 Pek. Sloof Beton S2 (15/25)
- Beton K-255 0,26 m3 64.716 16.826
- Pembesian 53,42 kg 10.216 545.758
- Bekisting 3,40 m2 39.716 135.036
Sub Total B 918.894 32.787.694
C PEKERJAAN STRUKTURAL
C.1 STRUKTUR BETON
1 Pek. Kolam Beton K1 (25/25) T.1,35 m
- Beton K-255 0,17 m3 64.716 11.002
- Pembesian 27,71 kg 10.216 283.095
- Bekisting 2,70 m2 39.716 107.234
2 Pek. Kolam Beton K2 (25/25) T.4,93 m
- Beton K-255 1,85 m3 64.716 119.725
- Pembesian 303,61 kg 10.216 3.101.789
- Bekisting 29,58 m2 59.716 1.766.410
3 Pek. Kolam Beton K3 (25/25) T.4,58 m
- Beton K-255 0,57 m3 64.716 36.888
- Pembesian 94,02 kg 10.216 960.542
- Bekisting 9,16 m2 59.716 547.002

Page 1
Sheet2_2
4 Pek. Kolam Beton K4 (25/25) T.4,08 m
- Beton K-255 0,51 m3 64.716 33.005
- Pembesian 83,86 kg 10.216 856.744
- Bekisting 8,17 m2 59.716 487.883
5 Pek. Kolam Beton K5 (25/25) T.3,5 m
- Beton K-255 1,31 m3 64.716 84.778
- Pembesian 215,54 kg 10.216 2.202.034
- Bekisting 21,00 m2 44.716 939.044
6 Pek. Kolam Beton K1 (25/25) T.90 cm
- Beton K-255 1,01 m3 64.716 65.364
- Pembesian 166,28 kg 10.216 1.698.776
- Bekisting 16,20 m2 39.716 643.405
7 Pek. Kolam Praktis K{ (11/11)
- Beton K-175 0,51 m3 64.716 33.005
- Pembesian 341,04 kg 10.216 3.484.187
- Bekisting 18,48 m2 39.716 733.958
8 Pek. Kolam Beton B1, B2 (20/30)
- Beton K-255 2,88 m3 64.716 186.383
- Pembesian 322,18 kg 10.216 3.291.507
- Bekisting 28,40 m2 59.716 1.695.945
9 Pek. Kolam Balok Lintel BL (12/15). RB (12/15)
- Beton K-175 1,65 m3 59.716 98.532
- Pembesian 384,73 kg 10.216 3.930.540
- Bekisting 38,60 m2 39.716 1.533.051
10 Pek. Ramp Beton T = 10 cm
- Beton K-175 0,46 m3 59.716 27.470
- Pembesian 33,07 kg 10.216 337.855
- Bekisting 0,66 m2 39.716 26.213
11 Pek. Balok B3 dan Balokl Sopi-Sopi (15/20)
- Beton K-175 1,02 m3 59.716 60.911
- Pembesian 195,98 kg 10.216 2.002.202
- Bekisting 18,70 m2 59.716 1.116.696
12 Pek. Plat Beton Topi-Topi (10/55)
- Beton K-255 0,62 m3 59.716 37.024
- Pembesian 83,33 kg 10.216 851.329
- Bekisting 7,39 m2 39.716 293.504
13 Pek. Kolam pipa besi 3”
- Pipa besi 18,70 m1 54.716 1.023.196
- Ankur Ø 12mm 16,00 bh 49.716 795.462
- Baut 12 m 16,00 bh 29.716 475.462
- Base plate 6 mm uk. 25 x 25 cm 5,89 kg 49.716 292.829
- Plate 6 mm uk. 7,5 x 7,5 cm dudukan rangka atap 1,06 kg 59.716 63.299
C.2 PEKERJAAN ATAP
Rangka Atap
1 L 40.40.4 320,04 kg -284 -90.776
2 2 X L 50,50,5 985,50 kg -284 -279.528
3 Kuda Kuda 2 x C 100.50.20.2,3 34,44 kg -284 -9.769
4 Gording C 100.50.20.2,3 811,80 kg -284 -230.259
5 L 50,50,5 dudukan gording 41,45 kg -284 -11.757
6 Trekstang Ø 12 94,25 kg -284 -26.733
7 Ikat angin Ø 16 187,70 kg -284 -53.239
8 Pelat sampin g T 10 mm 339,12 kg -284 -96.188
9 Angker Ø 16 x 300 mm 64,00 bh -284 -18.153
10 Bout M12 x 30 mm 608,00 bh -284 -172.453
11 Cat Sincromat Rangkas baja 101,18 m2 -284 -28.699
Penutup
1 Atap Spandek t = 0,35 mm 285,12 m2 -284 -80.872
2 Pasang Alumunium Foil, Glosuol, Roofmesh 140,00 m2 -284 -39.710

Page 2
Sheet2_2
3 Listplank GRC 82,00 m2 -284 -23.259
4 Non samping flashing plat 63,20 m1 -284 -17.926
Sub Total C 1.700.116 35.155.961
D PEKERJAAN PLAFOND
1 Plafond Gipsum 9 mm + Ranka Hollow 4/4; t = 0,35 128,80 m2 39.716 5.115.467
2 Plafond Calsiboard 4,5 mm + Rangka 73,92 m2 29.716 2.196.633
3 Lis Gipsum 5 cm 227,20 m2 19.716 4.479.557
Sub Total D 89.149 11.791.657
E PEKERJAAN PASANGAN
1 Pasangan Dinding Bata 247,60 m2 99.716 24.689.771
2 Plester dan Acian 495,21 m2 69.716 34.524.238
3 Pasang Rolliang Bata 70,30 m2 19.716 1.386.060
4 Pekerjaan Lapis cor Beton t – 5 cm bawah lantai keramik 9,60 m2 79.716 765.277
5 Pekarjaan Meja Beton Wastafel t – 8 cm 0,10 m2 -284 -28
6 Pasangan Keramik Lantai 40/40 Polished 129,43 m2 54.716 7.081.938
7 Pasangan Keramik Lantai 30/30 UnPolished (rabat) 55,60 m2 49.716 2.764.230
8 Pasangan keramik Lantai 30/30 Unpolished 2,97 m2 49.716 147.658
9 Pasangan Kplint Keramik Lantai 40/10 polished 119,60 m2 34.716 4.152.077
10 Pasangan Keramik meja & dinding wastafel 30/30 Polished 3,99 m2 59.716 238.268
11 Pasangan Keramik Dinding 30/40 Polished 12,20 m2 59.716 728.540
12 Plestran & Acian Kaprot halus Kolam Entrace 5,12 m2 -284 -1.452
13 Pek. Logo & tulisan plat dinding fln. Cat duco 1,00 ls -284 -284
14 Pasang Prasasti granit 40/60 1,00 ls 99.716 99.716
15 Pasang Papan Nama (terpasang) 1,00 ls 149.716 149.716
Sub Total E 825.745 76.725.725
F PEKERJAAN KUSEN PINTU DAN JENDELA
1 Kusen/Pintu type P1 1,00 unt -284 -284
2 Kusen/Pintu type P2 4,00 unt -284 -1.135
3 Kusen/Pintu type P3 1,00 unt -284 -284
4 Kusen/Pintu type P4 (Spandrel) 1,00 unt -284 -284
5 Kusen/Pintu type J1 9,00 unt -284 -2.553
6 Kusen/Pintu type J3 4,00 unt -284 -1.135
7 Kusen/Pintu type BV 1,00 unt -284 -284
8 Tralis Jendela (Besi begel) 1,00 -284 -284
Sub Total F -2.269 -6.240
G PEKERJAAN PENGECATAN
1 Pek. Pengecatan Dinding Interior 247,60 m2 -284 -70.229
2 Pek. Pengecatan Dinding Exterior 247,60 m2 -284 -70.229
3 Pek. Pengecatan Plafond 202,72 m2 -284 -57.500
4 Pek. Pengecatan Listplank 32,80 m2 -284 -9.303
Sub Total G -1.135 -207.262
H PEKERJAAN PLUMBING DAN SANITER
1 Instalasi Pipa PVC AW 4” 17,00 m2 -284 -4.822
2 Instalasi Pipa PVC AW 3” 12,00 m2 -284 -3.404
3 Instalasi Pipa PVC AW 2” 2,00 m2 -284 -567
4 Instalasi Pipa PVC AW 3/4” 20,00 m2 -284 -5.673
5 Instalasi Pipa PVC AW 1/2” 10,00 m2 -284 -2.836
6 Septicktank dan Rembesan 1,00 unt -284 -284
7 Pemasangan Closet Jongkok 1,00 bh -284 -284
8 Pemasangan Keran Air 2,00 bh -284 -567
9 Pemasangan Wastafel dan Keran 2,00 bh -284 -567
10 Floor Drain 1,00 bh -284 -284
11 Pemasangan Cermin Wastafel 100 x 160 1,00 unt -284 -284
Sub Total H -3.120 -19.571
I PEKERJAAN LISTRIK
1 Penyambungan Daya Listrik (BP) dan UJL 55.000,00 VA -284 -15.600.225
2 Perijinan Sertifikat Layak Operasi (SLO) 55.000,00 VA -284 -15.600.225
3 Panel Listrik Indoor (30 x40 x 17) 1,00 unt -284 -284

Page 3
Sheet2_2
4 Pek. Instalasi Kabel Feeder NYY 4x10 mm2 2,00 m2 -284 -567
5 Pek. Instalasi Penerangan dan Power NYM 3 x 2,5 mm2 dan conduit 26,00 ttk -284 -7.375
6 Pek. Instalasi Power AC 2 PK (18000 BTU) 2,00 ttk -284 -567
7 Pemasangan Lampu TL LED 2 X 18 120 cm KAV V 13,00 bh -284 -3.687
8 Pemasangan Lampu Baret/Kap Baret LED 17 Watt Outbow 7,00 bh -284 -1.985
9 Pemasangan Lampu Sorot Outdoor 20 Watt 2,00 bh -284 -567
10 Pemasangan Lampu Philips Downlight LED 9 Watt Putih 4,00 bh -284 -1.135
11 Pemasangan Saklar Tunggal 4,00 bh -284 -1.135
12 Pemasangan Sakral Ganda 5,00 bh -284 -1.418
13 Pemasangan Stop Kibtak Single 8,00 bh -284 -2.269
14 Pemasangan Stop Kontak Ganda 16,00 bh -284 -4.538
15 Pemasangan Stop Kontak AC 2,00 bh -284 -567
16 Pemasangan AC split wall 2 PK (18.000 BTU) 2,00 unit -284 -567
17 Grounding (max 2 Ohm) 1,00 lot -284 -284
Sub Total I -4.822 -31.227.396
TOTAL 120.907,24 3.526.530 125.000.000

Page 4