RINCIAN RENOVASI BANGUNAN RUMAH TANGGAL 1 JANUARI 2023 SAMPAI DENGAN 8 AGUSTUS

2023 TERHITUNG DARI BAHAN BANGUNAN SERTA UPAH TUKANG SELAMA 8 BULAN

1. BATU BATA BESAR : 2200 X 11.600 BATU BATA


= Rp. 25.520.000
2. BATU BATA KECIL PONDASI 1 METER : 550 X 4.000 BATU BATA
= Rp. 2.200.000
3. PASIR PLASTERAN : 142 KUBIK PASIR X 125.000
= Rp. 17.750.000
4. PASIR TIMBUN LANTAI : 28 KUBIK PASIR X 115.000
= Rp. 3.220.000
5. SEMEN BATURAJA : 268 SHAK SEMENT BATURAJA X
72.000 = Rp. 19.296.000
6. BESI 12 TI : 10 BATANG X 155.000
= Rp. 1.550.000
7. BESI 10 TI : 125 BATANG X 110.000
= Rp. 13.750.000
8. BESI 8 TI : 360 BATANG X 58.000
= Rp. 20.880.000
9. BESI 6 TI : 355 BATANG X 26.000
= Rp. 9.230.000
10. KAWAT IKAT : 70 KG X 50.000
= Rp. 3.500.000
11. 8 R0LL BENANG : 8 X 10.000
= Rp. 80.000
12. 4 BUAH PAHAT : 4 X 25.000
= Rp. 100.000
13. 2 BUAH DODOS : 2 X 80.000
= Rp. 160.000
14. 2 BUAH DODOS 2 MATA : 2 X 120.000
= Rp. 240.000
15. PAKU 1 1/2 INC : 8 KG X 6.500
= Rp. 52.000
16. PAKU 1 INC : 12 KG X 5.000
= Rp. 60.000
17. PAKU 2 INC : 10 KG X 20.000
= Rp. 200.000
18. PAKU 3 INC : 15 KG X 23.000
= Rp. 345.000
19. PAKU BETON : 10 KOTAK PAKU BETON X 34.000
= Rp. 340.000
20. PAKU BETON 2 INC : 5 KOTAK PAKU BETON X 38.000
= Rp. 190.000
21. PAKU BETON 1 1/2 INC : 5 KOTAK PAKU BETON X 34.000
= Rp. 170.000
22. 2 ROLI GEROBAK SORONG : 2 GEROBAK SORONG X 582.000
= Rp. 1.164.000
23. KAYU HAK : 17 IKAT KAYU HAK X 90.000
= Rp. 1.530.000
24. KAYU GELAM : 160 BATANG KAYU GELAM X 9.000
= Rp. 1.440.000
25. PAPAN : 40 KUBIK PAPAN X 320.000
= Rp. 12.800.000
26. PLIWOOD 8 MILI : 6 KEPING X 97.000
= Rp. 582.000
27. 30 EMBER : 30 BUAH EMBER X 15.000
= Rp. 450.000
28. 4 CANGKUL : 4 BUAH CANGKUL X 110.000
= Rp. 440.000
29. 4 SEKOP : 4 BUAH SEKOP X 65.000
= Rp. 260.000
30. SEPATU : 5 X SEPATU BOT X 80.000.00
= Rp. 400.000
31. PASIR URUK LANTAI : 66 MOBIL KECIL X 120.000
= Rp. 7.920.000
32. SEMENT UNTUK KERAMIK LANTAI : 35 SHAK SEMENT DINAMIK X 68.000
= Rp. 2.380.000
33. KORAL SPLIT UNTUK COR BALKON BELAKANG : 5 MOBIL BATU KORAL X 560.000
= Rp. 2.800.000
34. KORAL SPLIT UNTUK COR BALKON DEPAN : 5 MOBIL BATU KORAL X 560.000
= Rp. 2.800.000
35. KORAL SPLIT UNTUK COR PONDASI LANTAI : 17 MOBIL BATU KORAL X 560.000
= Rp. 9.520.000
36. KORAL SPLIT UNTUK COR PONDASI LANTAI : 7 MOBIL BATU KORAL X 560.000
= Rp. 3.920.000

TOTAL KESELURUHAN 36 ITEM DI ATAS BIAYA BELI BAHAN BANGUNAN SELAMA 8 BULAN
= Rp.167.239.000

TERHITUNG 8 BULAN = 240 HARI DI KURANG 32 HARI ( HARI LIBUR MINGGU ) = 208 HARI
TOTAL PENGERJAAN RUMAH

- TOTAL BIAYA UPAH TUKANG SELAMA 8 BULAN : 5 ORANG X 150.000 = 750.000 X 208
HARI TOTAL PENGERJAAN = Rp. 156.000.000
- TOTAL BIAYA BIAYA UPAH KENEK SELAMA 8 BULAN : 4 ORANG X 100.000 = 400.000 X 208
HARI TOTAL PENGERJAAN = Rp. 83.200.000
- BIAYA NGOPI + GORENGAN TUKANG PAGI DAN SORE : 50.000 X 8 BULAN
= Rp. 6.500.000

TOTAL KESELURUHAN DI ATAS = Rp. 412.939.000

1. BIAYA BORONGAN ATAP 86 METER : SUDAH TERHITUNG JASA UPAH PASANG


= Rp. 32.500.000
2. BIAYA BORONGAN PLAPON PVC : SUDAH TERHITUNG JASA UPAH PASANG
= Rp. 25.000.000
3. BIAYA BORONGAN LISTRIK : SUDAH TERHITUNG JASA UPAH PASANG
= Rp. 3.500.000
4. BIAYA BORONGAN WALLMOUDING : SUDAH TERHITUNG JASA UPAH PASANG
= Rp. 25.000.000
5. BIAYA BORONGAN CAT DALAM RUMAH : SUDAH TERHITUNG JASA UPAH PASANG
= Rp. 3.000.000
6. BIAYA BORONGAN CAT LUAR RUMAH : SUDAH TERHITUNG JASA UPAH PASANG
= Rp. 2.800.000
7. BIAYA BORONGAN CUSTOM PINTU DEPAN : SUDAH TERHITUNG JASA UPAH PASANG
= Rp. 5.900.000
8. BIAYA BORONGAN CUSTOM 3 PINTU KAMAR : SUDAH TERHITUNG JASA UPAH PASANG
= Rp. 10.500.000
9. BIAYA BORONGAN CUSTOM 1 PINTU SAMPING : SUDAH TERHITUNG JASA UPAH PASANG
= Rp. 3.500.000
10. BIAYA BORONGAN CUSTOM 3 JENDELA KAMAR BESAR : SUDAH TERHITUNG JASA UPAH PASANG
= Rp. 11.400.000
11. BIAYA BORONGAN CUSTOM 2 JENDELA KECIL : SUDAH TERHITUNG JASA UPAH PASANG
= Rp. 2.700.000 12. BIAYA BORONGAN 2 HEXS0S KAMAR
MANDI : SUDAH TERHITUNG JASA UPAH PASANG =
Rp. 1.700.000
13. BIAYA BORONGAN PLASTER LUAR DALAM : SUDAH TERHITUNG JASA
= Rp. 10.000.000
14. BIAYA BORONGAN PLAMIR LUAR DALAM : SUDAH TERHITUNG JASA
= Rp. 7.000.000
15. BIAYA BORONGAN KERAMIK RUMAH + KAMAR MANDI : SUDAH TERHITUNG JASA
= Rp. 13.500.000
16. BIAYA TERAS DEPAN + KRAMIK + PASANG ROSTER : SUDAH TERHITUNG JASA
= Rp. 11.500.000
17. BIAYA BORONGAN BIKIN MEJA DAPUR : SUDAH TERHITUNG JASA
= Rp. 2.500.000
18. BIAYA BORONGAN PLASTER RUMAH PAKDE + PLAMIR : SUDAH TERHITUNG JASA
= Rp. 3.500.000
29. BIAYA TANGGA SAMPING + FINISING SAMPING : SUDAH TERHITUNG JASA
= Rp. 4.500.000
20. BIAYA BORONGAN PLASTER + CAT BALKON DEPAN : SUDAH TERHITUNG JASA
= Rp. 3.000.000
21. BIAYA BORONGAN BIKIN BESI TEDMOND : SUDAH TERHITUNG JASA
= Rp. 3.950.000
22. BIAYA BORONGAN CANOPI SAMPING : SUDAH TERHITUNG JASA PASANG
= Rp. 11.350.000
23. BIAYA BORONGAN CANOPI BALKON BELAKANG : SUDAH TERHITUNG JASA
= Rp. 18.900.000
24. BIAYA BONGKAR PASANG GAS ALAM PIPA BARU : SUDAH TERHITUNG JASA
= Rp. 2.050.000
25. BIAYA BONGKAR PASANG PDAM PIPA BARU : SUDAH TERHITUNG JASA
= Rp. 850.000

TOTAL KESELURUHAN DI ATAS = Rp.220.100.000

PEMBELIAN BAHAN RENOVASI KEBUTUHAN RUMAH

1. GRANIT ESSENZA 63 DUS X 248.000


= Rp. 15.872.000
2. KERAMIK LANTAI TERAS DEPAN 15 DUS X 69.000
= Rp. 1.035.000
3. KERAMIK LANTAI KAMAR MANDI 4 DUS X 63.000
= Rp. 252.000
4. KERAMIK LANTAI KAMAR MANDI 4 DUS X 65.000
= Rp. 260.000
5. KERAMIK DINDING KAMAR MANDI 14 DUS X 98.000
= Rp. 1.372.000
6. KERAMIK DINDING KAMAR MANDI 14 DUS X 70.000
= Rp. 980.000
7. 1 BUAH TEDMOND
= Rp. 1.462.500
8. ROSTER COKELAT 4 BUAH X 67.500
= Rp. 270.000
9. ROSTER ANGIN KAMAR MANDI 4 BUAH X 65.500
= Rp. 262.000
10. GLAS BLOK KAMAR MANDI 10 BUAH X 26.000
= Rp. 260.000
11. WASHER KAMAR MANDI WC 2 BUAH X 411.000
= Rp. 822.000
12. CLOSET JONGKOK KAMAR MANDI 1 BUAH X 588.000
= Rp. 588.000
13. CLOSET DUDUK KAMAR MANDI 1 BUAH X 1.965.000
= Rp. 1.965.000
14. SARINGAN AIR KAMAR MANDI 2 BUAH X 275.000
= Rp. 550.000
15. LAMPU HIAS MINIMALIS 2 BUAH X 415.000
= Rp. 830.000
16. LAMPU HIAS MINIMALIS 1 BUAH X 115.000
= Rp. 115.000
17. 2 CAT TEMBOK DALAM 25 KG X 1.844.000
= Rp. 3.688.000
18. 2 CAT TEMBOK DALAM 5 KG X 440.000
= Rp. 880.000
19. 1 CAT TEMBOK LUAR PROPAN 25 KG X 2.154.000
= Rp. 2.154.000
20. ROSTER ANGIN TERAS LUAR 210 BUAH X 18.500
= Rp. 3.885.000
21. CAT MINYAK WARNA PUTIH 2 KALENG X 85.000
= Rp. 170.000
22. CAT DINDING NO DROOP WARNA PUTIH 1 KALENG 5 KG X 355.000
= Rp. 355.000
23. CAT DINDING NO DROOP WARNA PUTIH 1 KALENG 5 KG X 355.000
= Rp. 355.000
24. CAT DINDING NO DROOP WARNA PUTIH 5 KALENG X 68.000
= Rp. 340.000
25. TINER KOBRA 1 KALENG X 58.000
= Rp. 58.000
26. 10 KUAS KECIL X 10.000
= Rp. 100.000
27. 10 KUAS BESAR X 15.000
= Rp. 150.000
28. 4 KUAS ROLL X 25.000
= Rp. 100.000
29. 27 SHAK KINGKONG X 145.000
= Rp. 3.915.000
30. 4 BATANG PIPA BESAR X 210.000
= Rp. 840.000
31. 35 BUAH L BOW PIPA X 10.000
= Rp. 350.000

TOTAL KESELURUHAN DI ATAS = Rp. 44.235.500

BERIKUT TOTAL KESELURUHAN PENGERJAAN RENOVASI RUMAH DARI TANGGAL 1 JANUARI 2023
SAMPAI DENGAN 8 AGUSTUS 2023
TOTAL KESELURUHAN UNTUK RUMAH UTAMA SEBESAR Rp.677.274.000 & TOTAL PENGERJAAN RUMAH
KEDUA SEBESAR Rp. 152.760.000 ESTIMASI TOTAL KESELURUHAN TERHITUNG SAMPAI SAAT INI
BIAYA PENGELUARAN SEBESAR Rp.830.034.000