2 Persiapan Penambangan
a. Pembuatan Camp / Sewa mess, ATK dll IDR 50,000,000
3 Kegiatan Penambangan
OVER BURDEN ( 100 meter x 150 meter x 15 meter ) : 225.000 BCM
1 Sewa Exavator PC 300 (1 unit) @ Rp.190.000.000,-/400 jam IDR 190,000,000
2 Sewa Exavator PC 200 (1 unit) @ Rp.120.000.000,-/400 jam IDR 120,000,000
3 Sewa DOZER D85-SS (1 unit) @ Rp.150.000.000,-/400 jam IDR 150,000,000
4 Sewa Dump Truck OB (5 unit) @ Rp.60.000.000,-/400 jam IDR 300,000,000
5 Sewa LV TRITON (1 unit) @ Rp.12.000.000,-/ bulan IDR 12,000,000
6 Sewa Mobil AVANZA (1 unit) @ Rp.7.000.000,-/bulan IDR 7,000,000
7 Sewa GENSET (penerangan tambang) 1 unit @ Rp.40.000.000,-/bulan IDR 40,000,000
8 BBM Solar (@7.000 Litter) (20 Tangki x Rp.35.000.000,-)/bulan IDR 700,000,000
9 Sewa Water Pump (1 unit) @ Rp.30.000.000,-/bulan IDR 30,000,000
10 Pembelian TANDON BBM SOLAR (2 unit) @ Rp.6.000.000,- IDR 12,000,000
11
12 Biaya Operasional Makan Crew 25 Orang @Rp.75.000/hari x 30 Hari IDR 56,250,000
13 Gaji dan premi Karyawan /bulan IDR 156,250,000
TOTAL IDR 1,773,500,000