RENCANA ANGGARAN BIAYA

(RAB)
PEKERJAAN : PEMBANGUNAN MUSHOLAH KANTOR PAJAK SERUI
LOKASI : SERUI, DISTRIK YAPEN SELATAN
T/A : 2022

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN VOLUME SAT
( Rp ) ( Rp )
1 2 3 4 5 6 = (4 x 5)

I PEKERJAAN PERSIAPAN
1 Pas. Bouwplank 14.50 M' 80,104.00 1,161,508.00
Sub Total 1,161,508.00
II PEKERJAAN TANAH DAN PASIR
1 Pekerjaan Galian Pondasi 2.73 M3 107,783.00 294,247.59
3
2 Urugan kembali 1/4 Galian 0.68 M 33,097.00 22,588.70
3 Urugan Tanah Bawah Lantai 3.71 M3 329,198.00 1,222,147.58
4 Urugan Pasir Bawah Lantai 0.74 M3 329,198.00 244,429.52
Sub Total 1,783,413.38
III PEKERJAAN PASANGAN, BATU DAN BETON
1 Pasangan Pondasi Camp. 1 : 3 3.12 M3 1,396,443.00 4,356,902.16
2 Pekerjaan Sloof 15/20 0.47 M3 9,836,986.00 4,603,709.45
3 Pekerjaan Ringbalk 10/20 15.60 M1 233,886.42 3,648,628.15
4 Pekerjaan Kolom Praktis 10/15 21.00 M1 279,950.81 5,878,967.01
5 Pekerjaan Kanopi Beton 0.10 M3 12,696,472.00 1,218,861.31
6 Pas. Batu Tela Camp. 1 : 3 59.06 M2 211,000.00 12,461,660.00
7 Pekerjaan Plesteran dinding Camp. 1 : 3 112.32 M2 114,192.00 12,826,045.44
2
8 Pekerjaan Acian Dinding 112.32 M 27,688.00 3,109,916.16
9 Plint keramik dinding 14.70 M1 93,748.00 1,378,095.60
Sub Total 49,482,785.28
IV PEKERJAAN KAYU DAN ATAP
1 Pekerjaan Kuda-Kuda Kayu Kls. I 5/10 0.25 M3 10,657,245.00 2,664,311.25
2 Pekerjaan Gording Kayu Kls II 5/10 0.21 M3 7,729,045.00 1,623,099.45
3 Pekerjaan Lesplank Papan Kayu Besi 15.60 M1 106,062.00 1,654,567.20
4 Pekerjaan Pasang Atap Galvalum Spandek 29.89 M2 169,256.00 5,059,061.84
5 Pasang talang kotak PVC 14.00 M1 161,715.00 2,264,010.00
2
6 Pekerjaan Plafond gypsum + Rangka ky. Kls. II 25.41 M 279,455.00 7,100,951.55
7 Pasang les plafond 15.60 M1 71,171.00 1,110,267.60
8 Pekerjaan Kusen Kayu Kls. I M3 12,993,921.00 0.00
Sub Total 21,476,268.89
V PEKERJAAN LANTAI
1 Cor Lantai Kerja Bawah Lantai 1.12 M3 1,493,251.00 1,668,707.99
2 Screed Lantai tempat wudhu 3.00 M3 93,907.00 281,721.00
3 Pas. Keramik Hoogenous Tile uk. 60 x 60 16.61 M2 538,849.00 8,950,281.89
4 Pas. Keramik Unpolished uk. 30x30 area rabatan 4.50 M2 330,686.00 1,488,087.00
Sub Total 12,388,797.88
VI PEKERJAAN DAUN PINTU, JENDELA, DAN KACA
1 Pekerjaan Kusen Aluminium 17.10 M1 205,796.00 3,519,111.60
2 Pek. Daun Pintu Aluminium + Kaca 1.00 Bh 2,401,550.00 2,401,550.00
3 Pasang Kaca mati kaca reiben 1.30 M2 392,846.00 508,735.57
4 Pas. Daun Jendela Panil Kaca 2.59 M2 1,147,859.00 2,972,954.81
Sub Total 9,402,351.98
VII PEKERJAAN KUNCI DAN PENGGANTUNG
1 Pas. Engsel Daun Pintu 3.00 Bh 78,746.00 236,238.00
2 Pas. Kunci Tanam 2 Slag 1.00 Bh 285,041.00 285,041.00
3 Pas. Engsel Daun Jendela Panil 4.00 Bh 53,792.00 215,168.00
4 Pas. Handle Jendela 2.00 Bh 66,096.00 132,192.00
5 Pas. Hak Angin 4.00 Bh 66,096.00 264,384.00
6 Pas. Grendel Jendela 2.00 Bh 73,370.00 146,740.00
Sub Total 1,279,763.00
RENCANA ANGGARAN BIAYA
(RAB)
PEKERJAAN : PEMBANGUNAN MUSHOLAH KANTOR PAJAK SERUI
LOKASI : SERUI, DISTRIK YAPEN SELATAN
T/A : 2022

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN VOLUME SAT
( Rp ) ( Rp )
1 2 3 4 5 6 = (4 x 5)

VIII PEKERJAAN PENGECATAN


1 Pengecatan Dinding 112.32 M2 31,075.00 3,490,344.00
2 Pengecatan Kusen M2 75,762.00 0.00
3 Pengecatan Pintu Panil M2 75,762.00 0.00
2
4 Pengecatan Daun Jendela Panil M 75,762.00 0.00
5 Pengecatan Plafond 25.41 M2 42,125.00 1,070,396.25
6 Pengecatan Lesplank 4.68 M2 75,762.00 354,566.16
Sub Total 4,915,306.41
IX PEKERJAAN INSTALASI LISTRIK
1 Pas. Sekring Khas 1 Group 1.00 Titik 184,897.00 184,897.00
2 Pas. Lampu XL 18 Watt 2.00 Titik 911,145.00 1,822,290.00
3 Pas. Stop Kontak 1.00 Titik 681,483.00 681,483.00
Sub Total 2,688,670.00
X PEKERJAAN SANITAIR
1 Pas. Kran Air 3.00 Titik 72,963.00 218,889.00
2 Pas. Pipa 1/2" Air Bersih 6.00 M' 60,282.00 361,692.00
Sub Total 580,581.00
RENCANA ANGGARAN BIAYA
(RAB)
PEKERJAAN : PEMBANGUNAN MUSHOLAH KANTOR PAJAK SERUI
LOKASI : SERUI, DISTRIK YAPEN SELATAN
T/A : 2022

REKAPITULASI
A BIAYA FISIK
I PEKERJAAN PERSIAPAN 1,161,508.00
II PEKERJAAN TANAH DAN PASIR 1,783,413.38
III PEKERJAAN PASANGAN, BATU DAN BETON 49,482,785.28
IV PEKERJAAN KAYU DAN ATAP 21,476,268.89
V PEKERJAAN LANTAI 12,388,797.88
VI PEKERJAAN DAUN PINTU, JENDELA, DAN KACA 9,402,351.98
VII PEKERJAAN KUNCI DAN PENGGANTUNG 1,279,763.00
VIII PEKERJAAN PENGECATAN 4,915,306.41
IX PEKERJAAN INSTALASI LISTRIK 2,688,670.00
X PEKERJAAN SANITAIR 580,581.00
Real Cost 105,159,445.83
Dibulatkan 105,150,000.00
Terbilang : SERATUS LIMA JUTA SERATUS LIMA PULUH RIBU RUPIAH
DAFTAR HARGA SATUAN BAHAN DAN UPAH KABUPATEN KEPULAUAN YAPEN

HARGA SATUAN
DISTRIK
NO URAIAN SATUAN
KETERANGAN
YAPEN SELATAN
ZONA A (Rp.)
1 2 3 16

I UPAH KERJA
1 Mandor OH 261,642.48 Harga di Lokasi
2 Kepala Tukang OH 235,478.23 Harga di Lokasi
3 Tukang OH 209,313.98 Harga di Lokasi
4 Pekerja Terlatih OH 156,985.49 Harga di Lokasi
5 Pekerja Tidak Terlatih OH 130,821.24 Harga di Lokasi
6 Operator OH 261,642.48 Harga di Lokasi
7 Pembantu Operator OH 235,478.23 Harga di Lokasi
8 Sopir OH 209,313.98 Harga di Lokasi
9 Pembantu Sopir OH 156,985.49 Harga di Lokasi
10 Mekanik OH 235,478.23 Harga di Lokasi
11 Pembantu Mekanik OH 209,313.98 Harga di Lokasi

II MATERIAL LOKAL
A BAHAN GALIAN
A.2 Cipta Karya / Analisa SNI
1 Pasir Beton (Sudah diayak ) M3 358,000.00 Harga di Lokasi
2 Pasir Pasang M3 403,506.94 Harga di Lokasi
3 Pasir Plester halus M3 403,506.94 Harga di Lokasi
4 Koral / Kerikil Beton (sudah diayak) M3 403,506.94 Harga di Lokasi
5 Batu Kali M3 295,000.00 Harga di Lokasi
6 Batu Karang / Gunung M3 214,506.94 Harga di Lokasi
7 Pasir Urug / Sirtu M3 214,506.94 Harga di Lokasi
8 Karang Urug M3 214,506.94 Harga di Lokasi
9 Tanah Urug M3 214,506.94 Harga di Lokasi
10 Batu Pecah 5 - 7 cm M3 662,500.00 Harga di Lokasi
11 Batu Pecah 3 - 5 cm M3 767,500.00 Harga di Lokasi
12 Batu Pecah 2 - 3 cm M3 820,000.00 Harga di Lokasi
13 Batu Pecah 1 - 2 cm M3 925,000.00 Harga di Lokasi
14 Batu Pecah 0,5 - 1 cm M3 872,500.00 Harga di Lokasi
15 Abu Batu M3 557,500.00 Harga di Lokasi
16 Batu Tela 17 x 24 x 7 cm Bh 2,600.00 Harga di Lokasi
17 Bata Merah 5 x 11 x 24 cm Bh 1,575.00
18 Batu Alam/Candi M2 400,000.00 Harga di Lokasi
19 Paving Blok Segi 6 ( Ø 20 cm, tebal 7 cm ) M2 78,750.00 Harga di Lokasi
20 Paving Blok Segi 4 ( 10 x 20 x 7 cm ) M2 78,750.00 Harga di Lokasi
21 Bond Beam 40 x 20 x 20 cm M2 32,550.00

B BAHAN KAYU
1 Kayu Balok / Papan Klas III M3 2,310,000.00 Harga di Lokasi
2 Kayu Balok / Papan Klas II ( Matoa) M3 3,300,000.00 Harga di Lokasi
3 Papan Klas I ( Kayu Besi ) M3 6,600,000.00 Harga di Lokasi
4 Kayu Balok 5/10 & 10/10 ( Kayu Besi ) M3 5,720,000.00 Harga di Lokasi
5 Kayu Bakar M3 550,000.00 Harga di Lokasi
6 Dolken Ø 8-10/ 400 cm M3 132,000.00 Harga di Lokasi
7 Dolken Ø 20/ 400 cm Bh 440,000.00 Harga di Lokasi
8 Dolken Ø 40/ 400 cm Bh 660,000.00 Harga di Lokasi
9 Kayu List Plafond 400 cm M' 28,000.00 Harga di Lokasi

III MATERIAL NON LOKAL


A Material Pengikat
1 Semen / PC 40 Kg (Tonasa) Kg 2,281.25 Harga di Lokasi
2 Semen Warna Kg 17,250.00 Harga di Lokasi
3 Semen Putih Kg 5,750.00 Harga di Lokasi
DAFTAR HARGA SATUAN BAHAN DAN UPAH KABUPATEN KEPULAUAN YAPEN

HARGA SATUAN
DISTRIK
NO URAIAN SATUAN
KETERANGAN
YAPEN SELATAN
ZONA A (Rp.)
1 2 3 16
4 Waterproofing Ex. Fosroc/Sika/No Drop/Setara Kg 150,000.00 Harga di Lokasi
5 Compound Kg 7,500.00 Harga di Lokasi

B Keramik / Porselin
1 Porselin 20 x20 warna M2 92,000.00 Harga di Lokasi
2 Mozaik 30x30 cm M2 91,080.00 Harga di Lokasi
3 Keramik 20 x 20 cm M2 103,500.00 Harga di Lokasi
4 Keramik 20 x 25 cm M2 109,250.00 Harga di Lokasi
5 Keramik 30 x 30 xm M2 102,465.00 Harga di Lokasi
6 Keramik 40 x 40 cm M2 105,984.00 Harga di Lokasi
7 Granit 60x60 cm M2 274,500.00 Harga di Lokasi
8 Keramik 40x40 cm Kwalitas 1 M2 165,600.00 Harga di Lokasi
9 Keramik 30x30 cm Kwalitas 1 M2 125,235.00 Harga di Lokasi
10 Keramik anti slip 30 x 30 cm M2 102,465.00 Harga di Lokasi
11 Plint Keramik 10 x 60 Bh 25,000.00 Harga di Lokasi
12 Washtavel INA & Assesoris Bh 825,000.00 Harga di Lokasi
13 Washtavel Alumunium 1 lubang & Assesoris Bh 525,833.33 Harga di Lokasi
14 Washtavel Alumunium 2 lubang & Assesoris Bh 585,000.00 Harga di Lokasi
15 Sealt Tape Bh 7,000.00 Harga di Lokasi
16 Klosed Jongkok INA Bh 269,500.00 Harga di Lokasi
17 Klosed Duduk INA & Assesoris Bh 1,845,000.00 Harga di Lokasi
18 Urinoir Porselin & Assesoris Bh
19 Floor Drain KM/WC Kuningan Bh 40,392.86 Harga di Lokasi
20 Floor Drain Bak KM Bh 23,142.86 Harga di Lokasi

C Kayu Lapis
1 Tripleks 3 mm Lbr 80,500.00 Harga di Lokasi
2 Tripleks 4 mm Lbr 97,750.00 Harga di Lokasi
3 Triplek 6 mm Lbr 189,750.00
4 Tripleks 9 mm Lbr 208,150.00 Harga di Lokasi
5 Tripleks 12 mm Lbr 212,750.00
6 Teak Wood 3 mm Lbr 109,250.00 Harga di Lokasi
7 Teak Wood 4 mm Lbr 120,750.00 Harga di Lokasi
8 Teak Wood 1,2 mm Lbr - Harga di Lokasi
9 Formika Lbr 212,750.00 Harga di Lokasi
10 Eternit Lbr 97,750.00 Harga di Lokasi
11 Gypsum Board Ex. Jaya Board/Setara Lbr 225,000.00 Harga di Lokasi
12 Kassa Gypsum Roll 25,000.00 Harga di Lokasi
13 Cornis Gypsum uk. 5-10 cm M' 30,000.00 Harga di Lokasi

D Besi Beton , Kawat dan Paku


1 Besi Beton (Polos) U24 Kg 22,080.58 Harga di Lokasi
2 Besi Beton (Ulir) U32 Kg 29,966.59 Harga di Lokasi
3 Kawat Ikat Beton Kg 37,950.00 Harga di Lokasi
4 Kawat Bronjong Ø 3 mm Kg 31,050.00 Harga di Lokasi
5 Kawat Bronjong Ø 4 mm Kg 31,050.00 Harga di Lokasi
6 Kawat Bronjong Ø 5 mm Kg 31,050.00 Harga di Lokasi
7 Kawat Duri / Pagar M' 2,530.00 Harga di Lokasi
8 Kawat Nyamuk M2 34,500.00 Harga di Lokasi
9 Kawat Burung M2 28,750.00 Harga di Lokasi
10 Kawat Las Listrik RD 3,2 Kg 46,000.00 Harga di Lokasi
11 Kawat Las Listrik RD 2,6 (Dos/5Kg) Kg 46,000.00 Harga di Lokasi
12 Paku Triplek Kg 39,675.00 Harga di Lokasi
13 Paku 3, 5, 7, 10, 12 Kg 33,062.50 Harga di Lokasi
14 Paku Jembatan Kg 33,062.50 Harga di Lokasi
DAFTAR HARGA SATUAN BAHAN DAN UPAH KABUPATEN KEPULAUAN YAPEN

HARGA SATUAN
DISTRIK
NO URAIAN SATUAN
KETERANGAN
YAPEN SELATAN
ZONA A (Rp.)
1 2 3 16
15 Paku Seng Kg 39,675.00 Harga di Lokasi
16 Paku Iternit Kg 46,287.50 Harga di Lokasi
17 Paku Ardek Kg - Harga di Lokasi
18 Paku Sekrup 3,5 mm Pak 23,000.00 Harga di Lokasi
19 Paku Sekrup 2 - 3 mm Pak 17,250.00 Harga di Lokasi
20 Besi Siku 50 x 50 x 3 mm M' 38,333.33 Harga di Lokasi
21 Besi Siku 40 x 40 x 3 mm M' 28,750.00 Harga di Lokasi
22 Besi Siku 30 x 30 x 3 mm M' 19,166.67 Harga di Lokasi
23 Besi Siku 20 x 20 x 2 mm M' 12,458.33 Harga di Lokasi
24 Besi Strip 2 x 0,3 x 400 cm Kg 74,750.00 Harga di Lokasi
25 Besi Hollow Kotak 50x50x1,2 mm M' 39,100.00 Harga di Lokasi
26 Besi Hollow Kotak 40x40x1,2 mm M' 34,500.00 Harga di Lokasi
27 Besi Hollow Kotak 30x30x1,2 mm M' 28,750.00 Harga di Lokasi
28 Besi Hollow Kotak 50x20x1,2 mm M' 25,300.00 Harga di Lokasi
29 Besi Hollow Kotak 50x30x1,2 mm M' 28,750.00 Harga di Lokasi
30 Besi Hollow Kotak 40x10x1,2 mm M' 20,700.00 Harga di Lokasi
31 Besi Hollow Kotak 40x20x1,2 mm M' 28,750.00 Harga di Lokasi
32 Besi Hollow Kotak 40x30x1,2 mm M' 31,050.00 Harga di Lokasi
33 Besi Hollow Bulat 1"x1,2 mm M' 25,300.00 Harga di Lokasi
34 Besi Hollow Bulat 1,5"x1,2 mm M' 28,750.00 Harga di Lokasi
35 Besi Hollow Bulat 2"x1,2 mm M' 40,250.00 Harga di Lokasi
36 Besi Plat ( 1,22 x 2,44 ), 2 mm Lbr 1,610,000.00 Harga di Lokasi
37 Baja Profil WF, H Beam, CNP Kg 27,288.14 Harga di Lokasi
38 Kusen Aluminium M' 120,000.00 Harga di Lokasi

E Bahan Atap
1 Seng Gelombang BJLS 30 Lbr 109,250.00 Harga di Lokasi
Seng Gelombang Warna BJLS 25 Lbr 109,250.00 Harga di Lokasi
2 Seng Plat BJLS 30 Lbr 80,500.00 Harga di Lokasi
3 Seng Gelombang BJLS 20 Lbr 63,250.00 Harga di Lokasi
4 Seng Plat BJLS 20 Lbr 69,000.00 Harga di Lokasi
5 Talang Seng BJLS 20 lebar 40 cm M 28,750.00 Harga di Lokasi
6 Talang Seng BJLS 30 lebar 40 cm M 34,500.00 Harga di Lokasi
7 Talang Seng BJLS 20 lebar 80 cm M 57,500.00 Harga di Lokasi
8 Talang Seng BJLS 30 lebar 80 cm M 69,000.00 Harga di Lokasi
9 Atap Seng Alumunium Tebal 0,25 mm Lbr 80,500.00 Harga di Lokasi
10 Atap Alumunium tebal 0,55 mm Lbr 161,000.00 Harga di Lokasi
11 Atap Seng Galvalum 0,25 mm Lbr 134,550.00 Harga di Lokasi
12 Atap Multi Roof Lbr 51,750.00 Harga di Lokasi
13 Nok Multi Roof Lbr 43,700.00 Harga di Lokasi
14 Talang Paralon Dia. 4" M' 20,125.00 Harga di Lokasi
15 Talang Paralon Kotak M' 27,312.50 Harga di Lokasi

F Cat / Minyak
1 Cat Kilap Kayu Kg 57,500.00 Harga di Lokasi
2 Cat Besi Kg 57,500.00 Harga di Lokasi
3 Teak Oil Kg 40,250.00 Harga di Lokasi
4 Vernis Kg 74,750.00 Harga di Lokasi
5 Pelitur Kg 69,000.00 Harga di Lokasi
6 Residu / Teer Kg 40,250.00 Harga di Lokasi
7 Aspal Kg 18,400.00 Harga di Lokasi
8 Minyak Solar Ltr 12,650.00 Harga di Lokasi
9 Premium Ltr 7,360.00 Harga di Lokasi
10 Minyak Tanah Ltr 10,350.00 Harga di Lokasi
11 Pelumas/Oli Ltr 46,000.00 Harga di Lokasi
DAFTAR HARGA SATUAN BAHAN DAN UPAH KABUPATEN KEPULAUAN YAPEN

HARGA SATUAN
DISTRIK
NO URAIAN SATUAN
KETERANGAN
YAPEN SELATAN
ZONA A (Rp.)
1 2 3 16
12 Minyak Bekesting Ltr 28,750.00 Harga di Lokasi
13 Minyak Cat Ltr 51,750.00 Harga di Lokasi
14 Meni Kayu Kg 40,250.00 Harga di Lokasi
15 Meni Besi Kg 40,250.00 Harga di Lokasi
16 Cat Tembok Merk Kunci Mas Kg 14,375.00 Harga di Lokasi
17 Cat Tembok Merk Fukuda Kg 10,925.00 Harga di Lokasi
18 Cat Tembok Merk Altex Biasa Kg 20,700.00 Harga di Lokasi
19 Cat Tembok Merk Altex Bintang Kg 26,162.50 Harga di Lokasi
20 Cat Tembok Merk Marlin Kg 13,225.00 Harga di Lokasi
21 Cat Tembok Merk Dulux Pentalite Kg 109,250.00 Harga di Lokasi
22 Cat Tembok Merk Dulux Wheater shield Kg 138,000.00 Harga di Lokasi
23 Cat Genteng Kg 51,750.00 Harga di Lokasi
24 Cat Marka (Non Thermoplas) Kg 34,500.00 Harga di Lokasi
25 Cat Marka (Thermoplastic) Kg 74,750.00 Harga di Lokasi
26 Dempul Kayu Kg 40,250.00 Harga di Lokasi
27 Ampelas Kayu Lbr 5,750.00 Harga di Lokasi
28 Plamur Tembok Kg 14,375.00 Harga di Lokasi
29 Lem Kayu / Fox Kg 28,750.00 Harga di Lokasi
30 Air Kerja Ltr 100.00 Harga di Lokasi

G Instalasi Lampu
1 Lampu TL 20 Watt + Box Bh 103,500.00 Harga di Lokasi
2 Lampu TL 40 Watt + Box Bh 138,000.00 Harga di Lokasi
3 Lampu Xl 8 Watt ( SNI ) Bh 46,000.00 Harga di Lokasi
4 Lampu Xl 14 Watt ( SNI ) Bh 51,750.00 Harga di Lokasi
5 Lampu Xl 18 Watt ( SNI ) Bh 57,500.00 Harga di Lokasi
6 Lampu Xl 23 Watt ( SNI ) Bh 74,750.00 Harga di Lokasi
7 Lampu Xl 40 Watt ( SNI ) Bh 143,750.00 Harga di Lokasi
8 Vitting Lampu Tempel / Putih Bh 34,500.00 Harga di Lokasi
9 Vitting Lampu Gantung / Hitam Bh 11,500.00 Harga di Lokasi
10 Saklar Dinding Tunggal Bh 34,500.00 Harga di Lokasi
11 Saklar Dinding Dobel Bh 34,500.00 Harga di Lokasi
12 Stop Kontak Dinding Bh 34,500.00 Harga di Lokasi
13 Sekring Kas Lokal 1 Grup Bh 115,000.00 Harga di Lokasi
14 Sekring Kas Lokal 2 Grup Bh 138,000.00 Harga di Lokasi
15 Sekring Kas Lokal 3 Grup Bh 103,500.00 Harga di Lokasi
16 Kabel Serat Tunggal 2 x 1 mm M 10,350.00 Harga di Lokasi
17 Kabel Serat Tunggal 2 x 1,5 mm M 11,500.00 Harga di Lokasi
18 Kabel Serat Tunggal 2 x 2 mm M 12,650.00 Harga di Lokasi
19 Kabel Serat Tunggal 2 x 2,5 mm M 14,950.00 Harga di Lokasi
20 Kabel Serat Serabut 2 x 1 mm M 10,350.00 Harga di Lokasi
21 Kabel Serat Serabut 2 x 1,5 mm M 11,500.00 Harga di Lokasi
22 Kabel Serat Serabut 2 x 2 mm M 16,100.00 Harga di Lokasi
23 Klamp Kabel Pak 17,250.00 Harga di Lokasi
24 Isolatipe Bh 17,250.00 Harga di Lokasi
25 Pipa listrik Ø 5/8" - 4 m M 5,850.00 Harga di Lokasi
26 Instalasi Titik 250,000.00 Harga di Lokasi

H Aksesoris Pintu dan Jendela


1 Kunci Pintu 2 Slag Kecil Bh 149,500.00 Harga di Lokasi
2 Kunci Pintu 2 Slag Besar Bh 253,000.00 Harga di Lokasi
3 Kunci Pintu Bulat Bh 97,750.00 Harga di Lokasi
4 Engsel Pintu ring Nilon Bh 23,000.00 Harga di Lokasi
5 Engsel Pintu ring Kuningan Bh 34,500.00 Harga di Lokasi
6 Engsel Jendela ring Nilon Bh 13,800.00 Harga di Lokasi
DAFTAR HARGA SATUAN BAHAN DAN UPAH KABUPATEN KEPULAUAN YAPEN

HARGA SATUAN
DISTRIK
NO URAIAN SATUAN
KETERANGAN
YAPEN SELATAN
ZONA A (Rp.)
1 2 3 16
7 Engsel Jendela ring Kuningan Bh 23,000.00 Harga di Lokasi
8 Kait Angin Bh 23,000.00 Harga di Lokasi
Tarikan Jendela 23,000.00 Harga di Lokasi
9 Grendel Pintu Bh 20,125.00 Harga di Lokasi
10 Grendel Jendela Bh 17,250.00 Harga di Lokasi
11 Rangka Jendela Lover / Nako 8 Klip + Terali Set 172,500.00 Harga di Lokasi
12 Rangka Jendela Lover / Nako 7 Klip + Terali Set 207,000.00 Harga di Lokasi
13 Kaca Nako bening 5 mm Lbr 19,837.50 Harga di Lokasi
14 Kaca Nako Riben 5 mm Lbr 22,482.50 Harga di Lokasi
15 Kaca Bening 5 mm ( 122 x 153 cm) M2 251,275.00 Harga di Lokasi
16 Kaca Riben 5 mm ( 122 x 153 cm) M2 290,950.00 Harga di Lokasi
17 Kawat Nyamuk Alumunium parabola M2 34,500.00 Harga di Lokasi
Pintu Aluminium Kaca + Frame Bh 1,800,000.00 Harga di Lokasi

I Instalasi Air Minum dan Aksesoris


1 Pipa GIP 1/2" Medium A M' 28,750.00 Harga di Lokasi
2 Pipa GIP 3/4" Medium A M' 40,250.00 Harga di Lokasi
3 Pipa GIP 1" Medium A M' 64,400.00 Harga di Lokasi
4 Pipa GIP 1,5" Medium A M' 89,125.00 Harga di Lokasi
5 Pipa GIP 2" Medium A M' 129,950.00 Harga di Lokasi
16 Gate Valve 2" Bh - Harga di Lokasi
17 Gate Valve 3" Bh - Harga di Lokasi
18 Gate Valve 4" Bh - Harga di Lokasi
19 Gate Valve 6" Bh - Harga di Lokasi
20 Gate Valve 8" Bh - Harga di Lokasi
21 Pipa PVC 1/2" M' 8,625.00 Harga di Lokasi
22 Pipa PVC 3/4" M' 10,062.50 Harga di Lokasi
23 Pipa PVC 1" M' 14,375.00 Harga di Lokasi
24 Pipa PVC 1,5" M' 21,562.50 Harga di Lokasi
25 Pipa PVC 2" M' 37,375.00 Harga di Lokasi
26 Pipa PVC 3" M' 57,500.00 Harga di Lokasi
27 Pipa PVC 4" M' 80,500.00 Harga di Lokasi
28 Pipa PVC 5" M' - Harga di Lokasi
29 Tee GIP 1/2" Bh 13,800.00 Harga di Lokasi
30 Tee GIP 3/4" Bh 17,250.00 Harga di Lokasi
31 Tee GIP 1" Bh 23,000.00 Harga di Lokasi
32 Tee GIP 1,5" Bh 40,250.00 Harga di Lokasi
33 Tee GIP 2" Bh 74,750.00 Harga di Lokasi
34 Tee GIP 3" Bh 189,750.00 Harga di Lokasi
35 Tee GIP 4" Bh 270,250.00 Harga di Lokasi
36 Tee PVC 1/2" Bh 4,600.00 Harga di Lokasi
37 Tee PVC 3/4" Bh 5,750.00 Harga di Lokasi
38 Tee PVC 1" Bh 8,050.00
39 Tee PVC 1,5" Bh 17,250.00 Harga di Lokasi
40 Tee PVC 2" Bh 17,250.00 Harga di Lokasi
41 Tee PVC 3" Bh 23,000.00 Harga di Lokasi
42 Tee PVC 4" Bh 40,250.00 Harga di Lokasi
43 Sock 1/2" Pipa GIP Bh 9,200.00 Harga di Lokasi
44 Sock 3/4" Pipa GIP Bh 11,500.00 Harga di Lokasi
45 Sock 1" Pipa GIP Bh 17,250.00 Harga di Lokasi
46 Sock 1,5" Pipa GIP Bh 40,250.00 Harga di Lokasi
47 Sock 2" Pipa GIP Bh 57,500.00 Harga di Lokasi
48 Sock 3" Pipa Gip Bh 143,750.00 Harga di Lokasi
49 Sock 4" Pipa GIP Bh 172,500.00 Harga di Lokasi
50 Sock 1/2" Pipa PVC Bh 4,600.00 Harga di Lokasi
DAFTAR HARGA SATUAN BAHAN DAN UPAH KABUPATEN KEPULAUAN YAPEN

HARGA SATUAN
DISTRIK
NO URAIAN SATUAN
KETERANGAN
YAPEN SELATAN
ZONA A (Rp.)
1 2 3 16
51 Sock 3/4" Pipa PVC Bh 5,750.00 Harga di Lokasi
52 Sock 1" Pipa PVC Bh 8,050.00 Harga di Lokasi
53 Sock 1,5" Pipa PVC Bh 14,950.00 Harga di Lokasi
54 Sock 2" Pipa PVC Bh 14,950.00 Harga di Lokasi
55 Sock 3" Pipa PVC Bh 25,300.00 Harga di Lokasi
56 Sock 4" Pipa PVC Bh 40,250.00 Harga di Lokasi
57 Keni 1/2" Pipa GIP Bh 13,800.00 Harga di Lokasi
58 Keni 3/4" Pipa GIP Bh 17,250.00 Harga di Lokasi
59 Keni 1" Pipa GIP Bh 23,000.00 Harga di Lokasi
60 Keni 1,5" Pipa GIP Bh 40,250.00 Harga di Lokasi
61 Keni 2" Pipa GIP Bh 69,000.00 Harga di Lokasi
62 Keni 3" Pipa GIP Bh 155,250.00 Harga di Lokasi
63 Keni 4" Pipa GIP Bh 241,500.00 Harga di Lokasi
64 Keni 5" Pipa GIP Bh 0.00 Harga di Lokasi
65 Keni 1/2" Pipa PVC Bh 5,750.00 Harga di Lokasi
66 Keni 3/4" Pipa PVC Bh 8,050.00 Harga di Lokasi
67 Keni 1" Pipa PVC Bh 10,350.00 Harga di Lokasi
68 Keni 1,5" Pipa PVC Bh 13,800.00 Harga di Lokasi
69 Keni 2" Pipa PVC Bh 17,250.00 Harga di Lokasi
70 Keni 3" Pipa PVC Bh 28,750.00 Harga di Lokasi
71 Keni 4" Pipa PVC Bh 40,250.00 Harga di Lokasi
72 Keni 5" Pipa PVC Bh 0.00 Harga di Lokasi
73 Kran Air Ø 1/2" Bh 40,250.00 Harga di Lokasi
74 Kran Air Ø 3/4" Bh 46,000.00
75 Kran Air Ø 1" Bh 57,500.00 Harga di Lokasi
76 Kran Air Ø 1,5" Bh 74,750.00 Harga di Lokasi
77 Kran Air Ø 2" Bh 103,500.00 Harga di Lokasi
78 Accesories Pipa Set 0.00 Harga di Lokasi
79 Lem Pipa PVC Bh 11,500.00 Harga di Lokasi
80 Sealtipe Pipa Bh 6,900.00 Harga di Lokasi
81 Kopling Pipa GIP 3/4" Bh 40,250.00 Harga di Lokasi
82 Kopling Pipa GIP 1" Bh 51,750.00
83 Kopling Pipa GIP 1,5" Bh 103,500.00 Harga di Lokasi
84 Kopling Pipa GIP 2" Bh 126,500.00 Harga di Lokasi
ANALISA SATUAN PEKERJAAN PENDAHULUAN DAN TANAH
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)

PEKERJAAN PERSIAPAN
SNI 1.0000 m 1 Pengukuran dan pemasangan bouwplank untuk gedung dan saluran
6.4 0.0100 m3 Kayu Kls. III @ Rp. 2,310,000.00 23,100.00
03-2835-2002 0.0150 kg Paku reng @ Rp. 33,062.50 495.94
0.0050 m3 Kayu papan Ky. III @ Rp. 2,310,000.00 11,550.00
0.1000 org Tukang kayu @ Rp. 209,313.98 20,931.40
0.0100 org Kepala tukang kayu @ Rp. 235,478.23 2,354.78
0.1000 org Pekerja @ Rp. 130,821.24 13,082.12
0.0050 org Mandor @ Rp. 261,642.48 1,308.21
JUMLAH 37,676.52 35,145.94 72,822.45
Overhead + Profit (10%) 7,282.25
Harga Satuan Pekerjaan 80,104.70
DIBULATKAN 80,104.00

SNI 1.0000 m 2 Membersihkan lapangan dan perataan


6.8 0.1000 org Pekerja @ Rp. 130,821.24 13,082.12
03-2835-2002 0.0500 org Mandor @ Rp. 261,642.48 13,082.12
JUMLAH 26,164.25 26,164.25
Overhead + Profit (10%) 2,616.42
Harga Satuan Pekerjaan 28,780.67
DIBULATKAN 28,780.00

PEKERJAAN TANAH
SNI 1.0000 m 3 Galian tanah biasa sedalam sampai 1 meter
6.1 0.4000 org Pekerja @ Rp. 130,821.24 52,328.50
0.0400 org Mandor @ Rp. 261,642.48 10,465.70
JUMLAH 62,794.20 62,794.20
Overhead + Profit (10%) 6,279.42
Harga Satuan Pekerjaan 69,073.61
DIBULATKAN 69,073.00

SNI 1.0000 m 3 Galian tanah biasa sedalam 1 - 2 meter


6.2 0.5260 org Pekerja @ Rp. 130,821.24 68,811.97
0.0526 org Mandor @ Rp. 261,642.48 13,762.39
JUMLAH 82,574.37 82,574.37
Overhead + Profit (10%) 8,257.44
Harga Satuan Pekerjaan 90,831.80
DIBULATKAN 90,831.00

SNI 1.0000 m 3 Galian tanah keras sedalam sampai 1 meter


6.4 0.6250 org Pekerja @ Rp. 130,821.24 81,763.28
0.0620 org Mandor @ Rp. 261,642.48 16,221.83
JUMLAH 97,985.11 97,985.11
Overhead + Profit (10%) 9,798.51
Harga Satuan Pekerjaan 107,783.62
DIBULATKAN 107,783.00

SNI 1.0000 m 3 Galian tanah cadas sedalam sampai 1 meter


6.5 1.2500 org Pekerja @ Rp. 130,821.24 163,526.55
0.1250 org Mandor @ Rp. 261,642.48 32,705.31
JUMLAH 196,231.86 196,231.86
Overhead + Profit (10%) 19,623.19
Harga Satuan Pekerjaan 215,855.05
DIBULATKAN 215,855.00
ANALISA SATUAN PEKERJAAN PENDAHULUAN DAN TANAH
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)

A6 1.0000 m 3 Mengangkut tanah sejauh 30 meter


0.3300 org Pekerja @ Rp. 130,821.24 43,171.01
0.0100 org Mandor @ Rp. 261,642.48 2,616.42
JUMLAH 45,787.43 45,787.43
Overhead + Profit (10%) 4,578.74
Harga Satuan Pekerjaan 50,366.18
DIBULATKAN 50,366.00

SNI 1.0000 m 3 Pembuangan tanah sejauh 150 meter


6.8 0.5160 org Pekerja @ Rp. 130,821.24 67,503.76
0.0500 org Mandor @ Rp. 261,642.48 13,082.12
JUMLAH 80,585.88 80,585.88
Overhead + Profit (10%) 8,058.59
Harga Satuan Pekerjaan 88,644.47
DIBULATKAN 88,644.00

A14 1.0000 m 3 Membuang tanah dengan menghampar


0.2500 org Pekerja @ Rp. 130,821.24 32,705.31
0.0100 org Mandor @ Rp. 261,642.48 2,616.42
JUMLAH 35,321.73 35,321.73
Overhead + Profit (10%) 3,532.17
Harga Satuan Pekerjaan 38,853.91
DIBULATKAN 38,853.00

SNI 1.0000 m 3 Urug kembali bekas galian


0.0190 org Mandor @ Rp. 261,642.48 4,971.21
JUMLAH 30,088.89 30,088.89
Overhead + Profit (10%) 3,008.89
Harga Satuan Pekerjaan 33,097.77
DIBULATKAN 33,097.00

A18 1.0000 m 3 Urug pasir


1.2000 m3 Pasir urug @ Rp. 214,506.94 257,408.33
0.3000 org Pekerja @ Rp. 130,821.24 39,246.37
0.0100 org Mandor @ Rp. 261,642.48 2,616.42
JUMLAH 41,862.80 257,408.33 299,271.12
Overhead + Profit (10%) 29,927.11
Harga Satuan Pekerjaan 329,198.24
DIBULATKAN 329,198.00

MOD 1.0000 m 3 Urug tanah mendatangkan


A18 1.2000 m3 Tanah urug @ Rp. 214,506.94 257,408.33
0.3000 org Pekerja @ Rp. 130,821.24 39,246.37
0.0100 org Mandor @ Rp. 261,642.48 2,616.42
JUMLAH 41,862.80 257,408.33 299,271.12
Overhead + Profit (10%) 29,927.11
Harga Satuan Pekerjaan 329,198.24
DIBULATKAN 329,198.00

SNI 1.0000 m 3 Urugan sirtu


6.15 1.2000 m3 Sirtu @ Rp. 214,506.94 257,408.33
0.2500 org Pekerja @ Rp. 130,821.24 32,705.31
0.0250 org Mandor @ Rp. 261,642.48 6,541.06
JUMLAH 39,246.37 257,408.33 296,654.70
Overhead + Profit (10%) 29,665.47
Harga Satuan Pekerjaan 326,320.17
DIBULATKAN 326,320.00
ANALISA SATUAN PEKERJAAN BETON
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)

PEKERJAAN BETON
3
SNI 1.0000 m Membuat beton bertulang, 1 Pc : 2 Ps : 3 Kr
6.13 336.0000 kg PC @ Rp. 2,281.25 766,500.00
0.5400 m3 Pasir beton @ Rp. 358,000.00 193,320.00
0.8100 m3 Kerikil beton @ Rp. 403,506.94 326,840.62
215.0000 Ltr Air Kerja @ Rp. 100.00 21,500.00
0.2750 org Tukang batu @ Rp. 209,313.98 57,561.35
0.0275 org Kepala tukang batu @ Rp. 235,478.23 6,475.65
1.6500 org Pekerja @ Rp. 130,821.24 215,855.05
0.0825 org Mandor @ Rp. 261,642.48 21,585.50
JUMLAH 301,477.55 1,308,160.62 1,609,638.17
Overhead + Profit (10%) 160,963.82
Harga Satuan Pekerjaan 1,770,601.99
DIBULATKAN 1,770,601.00

SNI 1.0000 m3 Membuat beton tumbuk, 1 Pc : 3 Ps : 5 Kr


6.1 218.0000 kg PC @ Rp. 2,281.25 497,312.50
0.5200 m3 Pasir beton @ Rp. 358,000.00 186,160.00
0.8700 m3 Kerikil beton @ Rp. 403,506.94 351,051.04
215.0000 Ltr Air Kerja @ Rp. 100.00 21,500.00
0.2750 org Tukang batu @ Rp. 209,313.98 57,561.35
0.0275 org Kepala tukang batu @ Rp. 235,478.23 6,475.65
1.6500 org Pekerja @ Rp. 130,821.24 215,855.05
0.0825 org Mandor @ Rp. 261,642.48 21,585.50
JUMLAH 301,477.55 1,056,023.54 1,357,501.09
Overhead + Profit (10%) 135,750.11
Harga Satuan Pekerjaan 1,493,251.19
DIBULATKAN 1,493,251.00

SNI 1.0000 kg Pembesian dengan besi polos


6.25 1.0500 kg Besi beton polos @ Rp. 22,080.58 23,184.60
0.0150 kg Kawat beton @ Rp. 37,950.00 569.25
0.0070 org Tukang besi @ Rp. 209,313.98 1,465.20
0.0007 org Kepala tukang besi @ Rp. 235,478.23 164.83
0.0070 org Pekerja @ Rp. 130,821.24 915.75
0.0004 org Mandor @ Rp. 261,642.48 91.57
JUMLAH 2,637.36 23,753.85 26,391.21
Overhead + Profit (10%) 2,639.12
Harga Satuan Pekerjaan 29,030.33
DIBULATKAN 29,030.00

SNI 1.0000 kg Pembesian dengan besi ulir


6.25 1.0500 kg Besi beton ulir @ Rp. 29,966.59 31,464.91
0.0150 kg Kawat beton @ Rp. 37,950.00 569.25
0.0070 org Tukang besi @ Rp. 209,313.98 1,465.20
0.0007 org Kepala tukang besi @ Rp. 235,478.23 164.83
0.0070 org Pekerja @ Rp. 130,821.24 915.75
0.0004 org Mandor @ Rp. 261,642.48 91.57
JUMLAH 2,637.36 32,034.16 34,671.52
Overhead + Profit (10%) 3,467.15
Harga Satuan Pekerjaan 38,138.67
DIBULATKAN 38,138.00

F.8 1.0000 m2 Cetakan beton / begisting memakai papan


0.0170 m3 Usuk ky. Kls. III @ Rp. 2,310,000.00 39,270.00
0.0240 m3 Papan cetakan ky. Kls. III @ Rp. 2,310,000.00 55,440.00
0.4000 kg Paku @ Rp. 33,062.50 13,225.00
0.5000 org Tukang kayu @ Rp. 209,313.98 104,656.99
0.0500 org Kep. Tk. Kayu @ Rp. 235,478.23 11,773.91
0.2000 org Pekerja @ Rp. 130,821.24 26,164.25
0.0100 org Mandor @ Rp. 261,642.48 2,616.42
ANALISA SATUAN PEKERJAAN BETON
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
JUMLAH 145,211.58 107,935.00 253,146.58
Overhead + Profit (10%) 25,314.66
Harga Satuan Pekerjaan 278,461.23
DIBULATKAN 278,461.00

F.8 1.0000 m2 Cetakan beton / begisting memakai multiplek


0.0170 m3 Usuk ky. Kls. III @ Rp. 2,310,000.00 39,270.00
0.3470 lbr Tripleks 9 mm @ Rp. 208,150.00 72,228.05
0.4000 kg Paku @ Rp. 33,062.50 13,225.00
0.5000 org Tukang kayu @ Rp. 209,313.98 104,656.99
0.0500 org Kep. Tk. Kayu @ Rp. 235,478.23 11,773.91
0.2000 org Pekerja @ Rp. 130,821.24 26,164.25
0.0100 org Mandor @ Rp. 261,642.48 2,616.42
JUMLAH 145,211.58 124,723.05 269,934.63
Overhead + Profit (10%) 26,993.46
Harga Satuan Pekerjaan 296,928.09
DIBULATKAN 296,928.00

F.V 1.0000 m3 Membongkar cetakan


4.0000 org Pekerja @ Rp. 130,821.24 523,284.96
JUMLAH 523,284.96 523,284.96
Overhead + Profit (10%) 52,328.50
Harga Satuan Pekerjaan 575,613.46
DIBULATKAN 575,613.00

1.0000 Bh Kanstin Beton uk. 20x40


0.0080 m3 Beton camp. 1 : 2 : 3 @ Rp. 1,770,601.00 14,164.81
0.2400 m2 Papan Bekisting @ Rp. 278,461.00 66,830.64
JUMLAH 80,995.45
DIBULATKAN 80,995.00

1.0000 m3 Pondasi Poer Beton Bertulang pembesian 175 kg


1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 1,770,601.00 1,770,601.00
175.0000 kg Besi Beton @ Rp. 29,030.00 5,080,250.00
3.3300 m2 Papan Bekisting @ Rp. 278,461.00 927,275.13
JUMLAH 7,778,126.13
DIBULATKAN 7,778,126.00

1.0000 m3 Soof Beton Bertulang camp. 1 : 2 : 3 uk. 15x20 cm pembesian 150 kg


1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 1,770,601.00 1,770,601.00
150.0000 kg Besi Beton @ Rp. 29,030.00 4,354,500.00
13.3300 m2 Papan Bekisting @ Rp. 278,461.00 3,711,885.13
JUMLAH 9,836,986.13
DIBULATKAN 9,836,986.00

1.0000 m3 Soof Beton Bertulang uk. 15x30 cm pembesian 110 kg


1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 1,770,601.00 1,770,601.00
180.0000 kg Besi Beton @ Rp. 29,030.00 5,225,400.00
13.3300 m2 Papan Bekisting @ Rp. 278,461.00 3,711,885.13
JUMLAH 10,707,886.13
DIBULATKAN 10,707,886.00

1.0000 m3 Soof Beton Bertulang uk. 25x40 cm pembesian 230 kg


1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 1,770,601.00 1,770,601.00
230.0000 kg Besi Beton @ Rp. 29,030.00 6,676,900.00
8.0000 m2 Papan Bekisting @ Rp. 278,461.00 2,227,688.00
JUMLAH 10,675,189.00
DIBULATKAN 10,675,189.00

1.0000 m3 Soof Beton Bertulang uk. 20x30 cm pembesian 200 kg


1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 1,770,601.00 1,770,601.00
175.0000 kg Besi Beton @ Rp. 29,030.00 5,080,250.00
ANALISA SATUAN PEKERJAAN BETON
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
10.0000 m2 Papan Bekisting @ Rp. 278,461.00 2,784,610.00
JUMLAH 9,635,461.00
DIBULATKAN 9,635,461.00

1.0000 m3 Kolom praktis beton bertulang (10x10 cm) camp. 1 : 2 : 3


1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 1,770,601.00 1,770,601.00
390.0000 kg Besi Beton @ Rp. 29,030.00 11,321,700.00
20.0000 m2 Papan Bekisting @ Rp. 278,461.00 5,569,220.00
JUMLAH 18,661,521.00
DIBULATKAN 18,661,521.00
1.0000 m' Kolom praktis beton bertulang (10x10 cm) 186,615.21
1.0000 m' Kolom praktis beton bertulang (10x15 cm) 279,950.81

1.0000 m3 Balok beton bertulang praktis (10x20 cm)


1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 1,770,601.00 1,770,601.00
150.0000 kg Besi Beton @ Rp. 29,030.00 4,354,500.00
20.0000 m2 Papan Bekisting @ Rp. 278,461.00 5,569,220.00
JUMLAH 11,694,321.00
DIBULATKAN 11,694,321.00
1.0000 m' Balok praktis beton bertulang (10x20 cm) 233,886.42

1.0000 m3 Kolom Beton Bertulang uk. 15x15 cm dan 15x20 cm


1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 1,770,601.00 1,770,601.00
105.0000 kg Besi Beton @ Rp. 29,030.00 3,048,150.00
26.6600 m2 Papan Bekisting @ Rp. 278,461.00 7,423,770.26
JUMLAH 12,242,521.26
DIBULATKAN 12,242,521.00
1.0000 m' Kolom beton bertulang 15x15 cm 275,484.27
1.0000 m' Kolom beton bertulang 15x20 cm 367,312.36

1.0000 m3 Kolom Beton Bertulang camp. 1 : 2 : 3 uk. 20x20 cm pembesian 110 kg


1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 1,770,601.00 1,770,601.00
110.0000 kg Besi Beton @ Rp. 29,030.00 3,193,300.00
15.0000 m2 Papan Bekisting @ Rp. 278,461.00 4,176,915.00
JUMLAH 9,140,816.00
DIBULATKAN 9,140,816.00

1.0000 m3 Balok praktis beton bertulang (10x20 cm)


1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 1,770,601.00 1,770,601.00
150.0000 kg Besi Beton @ Rp. 29,030.00 4,354,500.00
20.0000 m2 Papan Bekisting @ Rp. 278,461.00 5,569,220.00
JUMLAH 11,694,321.00
DIBULATKAN 11,694,321.00
1.0000 m' Ringbalk praktis beton bertulang (10x20 cm) 233,886.42

1.0000 m3 Dinding Beton Bertulang uk. 12x75 cm pembesian 145 kg


1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 1,770,601.00 1,770,601.00
145.0000 kg Besi Beton @ Rp. 29,030.00 4,209,350.00
22.1000 m2 Papan Bekisting @ Rp. 278,461.00 6,153,988.10
JUMLAH 12,133,939.10
DIBULATKAN 12,133,939.00

1.0000 m3 Kolom Beton Bertulang uk. 30x30 cm pembesian 115 kg


1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 1,770,601.00 1,770,601.00
115.0000 kg Besi Beton @ Rp. 29,030.00 3,338,450.00
13.3300 m2 Papan Bekisting @ Rp. 278,461.00 3,711,885.13
JUMLAH 8,820,936.13
DIBULATKAN 8,820,936.00

1.0000 m3 Kolom Beton Bertulang uk. 40x40 cm


1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 1,770,601.00 1,770,601.00
250.0000 kg Besi Beton @ Rp. 29,030.00 7,257,500.00
10.0000 m2 Papan Bekisting @ Rp. 278,461.00 2,784,610.00
ANALISA SATUAN PEKERJAAN BETON
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
JUMLAH 11,812,711.00
DIBULATKAN 11,812,711.00

1.0000 m3 Kolom Beton Bertulang uk. 20x40 cm pembesian 275 kg


1.0000 m3 Beton K250 @ Rp. 1,770,601.00 1,770,601.00
130.0000 kg Besi Beton @ Rp. 29,030.00 3,773,900.00
15.0000 m2 Papan Bekisting @ Rp. 278,461.00 4,176,915.00
JUMLAH 9,721,416.00
DIBULATKAN 9,721,416.00

1.0000 m3 Kolom Beton Bertulang camp. 1 : 2 : 3 uk. 15x45 cm pembesian 230 kg


1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 1,770,601.00 1,770,601.00
230.0000 kg Besi Beton @ Rp. 29,030.00 6,676,900.00
17.7778 m2 Papan Bekisting @ Rp. 278,461.00 4,950,423.97
JUMLAH 13,397,924.97
DIBULATKAN 13,397,924.00

1.0000 m3 Pondasi Poer Beton Bertulang pembesian 175 kg


1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 1,770,601.00 1,770,601.00
175.0000 kg Besi Beton @ Rp. 29,030.00 5,080,250.00
3.3300 m2 Papan Bekisting @ Rp. 278,461.00 927,275.13
JUMLAH 7,778,126.13
DIBULATKAN 7,778,126.00

1.0000 m3 Balok Beton Bertulang K250 uk. 25x40 cm pembesian 205 kg


1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 1,770,601.00 1,770,601.00
205.0000 kg Besi Beton @ Rp. 29,030.00 5,951,150.00
11.5000 m2 Papan Bekisting @ Rp. 278,461.00 3,202,301.50
JUMLAH 10,924,052.50
DIBULATKAN 10,924,052.00

1.0000 m3 Balok Beton Bertulang K250 uk. 20x30 cm pembesian 145 kg


1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 1,770,601.00 1,770,601.00
155.0000 kg Besi Beton @ Rp. 29,030.00 4,499,650.00
13.3300 m2 Papan Bekisting @ Rp. 278,461.00 3,711,885.13
JUMLAH 9,982,136.13
DIBULATKAN 9,982,136.00

1.0000 m3 Balok Beton Bertulang K250 uk. 30x50 cm pembesian 185 kg


1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 1,770,601.00 1,770,601.00
185.0000 kg Besi Beton @ Rp. 29,030.00 5,370,550.00
8.6660 m2 Papan Bekisting @ Rp. 278,461.00 2,413,143.03
JUMLAH 9,554,294.03
DIBULATKAN 9,554,294.00

1.0000 m3 Ring Balok Beton Bertulang camp. 1:2:3 uk. 15x20 cm pembesian 140 kg
1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 1,770,601.00 1,770,601.00
140.0000 kg Besi Beton @ Rp. 29,030.00 4,064,200.00
13.3300 m2 Papan Bekisting @ Rp. 278,461.00 3,711,885.13
JUMLAH 9,546,686.13
DIBULATKAN 9,546,686.00

1.0000 m3 Ring Balok Beton Bertulang uk. 15x30 cm pembesian 145 kg


1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 1,770,601.00 1,770,601.00
145.0000 kg Besi Beton @ Rp. 29,030.00 4,209,350.00
16.6660 m2 Papan Bekisting @ Rp. 278,461.00 4,640,831.03
JUMLAH 10,620,782.03
DIBULATKAN 10,620,782.00

1.0000 m3 Balok Beton Bertulang camp. 1 : 2 : 3 uk. 12x30 cm pembesian 200 kg


1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 1,770,601.00 1,770,601.00
210.0000 kg Besi Beton @ Rp. 29,030.00 6,096,300.00
20.0000 m2 Papan Bekisting @ Rp. 278,461.00 5,569,220.00
ANALISA SATUAN PEKERJAAN BETON
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
JUMLAH 13,436,121.00
DIBULATKAN 13,436,121.00

1.0000 m3 Duk Beton Bertulang camp. 1 : 2 : 3 tebal 6 cm pembesian 150 kg


1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 1,770,601.00 1,770,601.00
130.0000 kg Besi Beton @ Rp. 29,030.00 3,773,900.00
16.6660 m2 Papan Bekisting @ Rp. 278,461.00 4,640,831.03
0.5000 Perancah/Stuwerk @ Rp. 5,022,281.00 2,511,140.50
JUMLAH 12,696,472.53
DIBULATKAN 12,696,472.00
ANALISA SATUAN PEKERJAAN BATU DAN PASANGAN
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)

PEKERJAAN PASANGAN
SNI 1.0000 m3 Pasangan pondasi batu kosong
6.14 1.2000 m3 Batu belah 15/20 cm @ Rp. 295,000.00 354,000.00
03-2836-2002 0.3000 m3 Pasir urug @ Rp. 214,506.94 64,352.08
0.3900 org Tukang batu @ Rp. 209,313.98 81,632.45
0.0390 org Kepala tukang batu @ Rp. 235,478.23 9,183.65
0.7800 org Pekerja @ Rp. 130,821.24 102,040.57
0.0390 org Mandor @ Rp. 261,642.48 10,204.06
JUMLAH 203,060.73 418,352.08 621,412.81
Overhead + Profit (10%) 62,141.28
Harga Satuan Pekerjaan 683,554.09
DIBULATKAN 683,554.00

SNI 1.0000 m3 Pasangan pondasi 1 Pc : 3 Ps


6.5 1.200 m3 Batu belah 15/20 cm @ Rp. 214,506.94 257,408.33
03-2836-2002 202.000 kg PC @ Rp. 2,281.25 460,812.50
0.485 m3 Pasir pasang @ Rp. 403,506.94 195,700.87
0.6000 org Tukang batu @ Rp. 209,313.98 125,588.39
0.0600 org Kepala tukang batu @ Rp. 235,478.23 14,128.69
1.5000 org Pekerja @ Rp. 130,821.24 196,231.86
0.0750 org Mandor @ Rp. 261,642.48 19,623.19
JUMLAH 355,572.13 913,921.69 1,269,493.82
Overhead + Profit (10%) 126,949.38
Harga Satuan Pekerjaan 1,396,443.21
DIBULATKAN 1,396,443.00

1.0000 m2 Pasangan bata Tela, 1 Pc : 4 Ps


20.0000 bh Batu Tela @ Rp. 2,600.00 52,000.00
10.6000 kg PC @ Rp. 2,281.25 24,181.25
0.0280 m3 Pasir pasang @ Rp. 403,506.94 11,298.19
0.1500 org Tukang batu @ Rp. 209,313.98 31,397.10
0.0150 org Kepala tukang batu @ Rp. 235,478.23 3,532.17
0.4500 org Pekerja @ Rp. 130,821.24 58,869.56
0.0225 org Mandor @ Rp. 261,642.48 5,886.96
JUMLAH 99,685.78 87,479.44 187,165.23
Overhead + Profit (10%) 18,716.52
Harga Satuan Pekerjaan 205,881.75
DIBULATKAN 205,881.00
1.0000 m2 Pasangan Rolag bata Tela, 1 Pc : 4 Ps 411,762.00

1.0000 m2 Pasangan bata Tela, 1 Pc : 3 Ps


20.0000 bh Batu Tela @ Rp. 2,600.00 52,000.00
12.6400 kg PC @ Rp. 2,281.25 28,835.00
0.0280 m3 Pasir pasang @ Rp. 403,506.94 11,298.19
0.1500 org Tukang batu @ Rp. 209,313.98 31,397.10
0.0150 org Kepala tukang batu @ Rp. 235,478.23 3,532.17
0.4500 org Pekerja @ Rp. 130,821.24 58,869.56
0.0225 org Mandor @ Rp. 261,642.48 5,886.96
JUMLAH 99,685.78 92,133.19 191,818.98
Overhead + Profit (10%) 19,181.90
Harga Satuan Pekerjaan 211,000.88
DIBULATKAN 211,000.00
1.0000 m2 Pasangan Rolag bata Tela, 1 Pc : 3 Ps 422,000.00

G.50.q 1.0000 m2 Plesteran batu kali 1pc:4ps


6.5110 kg PC @ Rp. 2,281.25 14,853.22
0.0209 m3 Pasir pasang @ Rp. 403,506.94 8,433.30
0.2000 org Tukang batu @ Rp. 209,313.98 41,862.80
0.0200 org Kep. Tk. Batu @ Rp. 235,478.23 4,709.56
0.4000 org Pekerja @ Rp. 130,821.24 52,328.50
ANALISA SATUAN PEKERJAAN BATU DAN PASANGAN
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
0.0200 org Mandor @ Rp. 261,642.48 5,232.85
JUMLAH 104,133.71 23,286.51 127,420.22
Overhead + Profit (10%) 12,742.02
Harga Satuan Pekerjaan 140,162.24
DIBULATKAN 140,162.00

SNI 1.0000 m2 Plesteran 1 Pc : 4 Ps, tebal 15 mm


6.4 5.2000 kg PC @ Rp. 2,281.25 11,862.50
03-2837-2002 0.0200 m3 Pasir pasang @ Rp. 403,506.94 8,070.14
0.1500 org Tukang batu @ Rp. 209,313.98 31,397.10
0.0150 org Kepala tukang batu @ Rp. 235,478.23 3,532.17
0.2000 org Pekerja @ Rp. 130,821.24 26,164.25
0.0100 org Mandor @ Rp. 261,642.48 2,616.42
JUMLAH 63,709.94 19,932.64 83,642.58
Overhead + Profit (10%) 8,364.26
Harga Satuan Pekerjaan 92,006.84
DIBULATKAN 92,006.00
2
SNI 1.0000 m Plesteran dinding 1 Pc : 3 Ps, tebal 15 mm
6.30 7.7760 kg PC @ Rp. 2,281.25 17,739.00
03-2837-2002 0.0230 m3 Pasir pasang @ Rp. 403,506.94 9,280.66
0.1500 org Tukang batu @ Rp. 209,313.98 31,397.10
0.0150 org Kepala tukang batu @ Rp. 235,478.23 3,532.17
0.3000 org Pekerja @ Rp. 130,821.24 39,246.37
0.0100 org Mandor @ Rp. 261,642.48 2,616.42
JUMLAH 76,792.07 27,019.66 103,811.73
Overhead + Profit (10%) 10,381.17
Harga Satuan Pekerjaan 114,192.90
DIBULATKAN 114,192.00

SNI 1.0000 m2 Plesteran dinding 1 Pc : 3 Ps, tebal 25 mm


6.30 12.9000 kg PC @ Rp. 2,281.25 29,428.13
03-2837-2002 0.0380 m3 Pasir pasang @ Rp. 403,506.94 15,333.26
0.2500 org Tukang batu @ Rp. 209,313.98 52,328.50
0.0250 org Kepala tukang batu @ Rp. 235,478.23 5,886.96
0.5000 org Pekerja @ Rp. 130,821.24 65,410.62
0.0167 org Mandor @ Rp. 261,642.48 4,369.43
JUMLAH 127,995.50 44,761.39 172,756.89
Overhead + Profit (10%) 17,275.69
Harga Satuan Pekerjaan 190,032.58
DIBULATKAN 190,032.00

SNI 1.0000 m1 Les Profil dinding campuran 1 Pc : 3 Ps, tebal 25 mm dan lebar 5-10 cm
6.30 0.7740 kg PC @ Rp. 2,281.25 1,765.69
03-2837-2002 0.0023 m3 Pasir pasang @ Rp. 403,506.94 928.07
0.0500 org Tukang batu @ Rp. 209,313.98 10,465.70
0.0050 org Kepala tukang batu @ Rp. 235,478.23 1,177.39
0.1000 org Pekerja @ Rp. 130,821.24 13,082.12
0.0100 org Mandor @ Rp. 261,642.48 2,616.42
JUMLAH 27,341.64 2,693.75 30,035.39
Overhead + Profit (10%) 3,003.54
Harga Satuan Pekerjaan 33,038.93
DIBULATKAN 33,038.00

SNI 1.0000 m1 Plesteran skoneng 1 Pc : 2 Ps ( untuk gedung )


6.31 0.5000 kg PC @ Rp. 2,281.25 1,140.63
03-2837-2002 0.0130 m3 Pasir pasang @ Rp. 403,506.94 5,245.59
0.4000 org Tukang batu @ Rp. 209,313.98 83,725.59
0.0400 org Kepala tukang batu @ Rp. 235,478.23 9,419.13
0.0800 org Pekerja @ Rp. 130,821.24 10,465.70
0.0040 org Mandor @ Rp. 261,642.48 1,046.57
JUMLAH 104,656.99 6,386.22 111,043.21
ANALISA SATUAN PEKERJAAN BATU DAN PASANGAN
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
Overhead + Profit (10%) 11,104.32
Harga Satuan Pekerjaan 122,147.53
DIBULATKAN 122,147.00

SNI 1.0000 m2 Plesteran siar adukan 1 Pc : 2 Ps


6.35 4.3200 kg PC @ Rp. 2,281.25 9,855.00
03-2837-2002 0.0160 m3 Pasir pasang @ Rp. 403,506.94 6,456.11
0.0700 org Tukang batu @ Rp. 209,313.98 14,651.98
0.0070 org Kepala tukang batu @ Rp. 235,478.23 1,648.35
0.1500 org Pekerja @ Rp. 130,821.24 19,623.19
0.0080 org Mandor @ Rp. 261,642.48 2,093.14
JUMLAH 38,016.65 16,311.11 54,327.76
Overhead + Profit (10%) 5,432.78
Harga Satuan Pekerjaan 59,760.54
DIBULATKAN 59,760.00

SNI 1.0000 m2 Plesteran Ciprat, 1 Pc : 2 Ps


6.34 4.3200 kg PC @ Rp. 2,281.25 9,855.00
0.0160 m3 Pasir pasang @ Rp. 403,506.94 6,456.11
0.1000 org Tukang batu @ Rp. 209,313.98 20,931.40
0.0100 org Kepala tukang batu @ Rp. 235,478.23 2,354.78
0.2500 org Pekerja @ Rp. 130,821.24 32,705.31
0.0150 org Mandor @ Rp. 261,642.48 3,924.64
JUMLAH 59,916.13 16,311.11 76,227.24
Overhead + Profit (10%) 7,622.72
Harga Satuan Pekerjaan 83,849.96
DIBULATKAN 83,849.00

Analisa ZAZ 1.0000 m2 Acian dinding bata


3.2500 kg PC @ Rp. 2,281.25 7,414.06
0.0330 org Tukang batu @ Rp. 209,313.98 6,907.36
0.0033 org Kep. Tk. Batu @ Rp. 235,478.23 777.08
0.0700 org Pekerja @ Rp. 130,821.24 9,157.49
0.0035 org Mandor @ Rp. 261,642.48 915.75
JUMLAH 17,757.68 7,414.06 25,171.74
Overhead + Profit (10%) 2,517.17
Harga Satuan Pekerjaan 27,688.91
DIBULATKAN 27,688.00

SNI 1.0000 m2 Pasang dinding batu hias tempel


6.74 1.0500 m2 Batu tempel/candi @ Rp. 400,000.00 420,000.00
11.7500 kg PC @ Rp. 2,281.25 26,804.69
0.0350 m3 Pasir pasang @ Rp. 403,506.94 14,122.74
0.3500 org Tukang batu @ Rp. 209,313.98 73,259.89
0.0350 org Kepala tukang batu @ Rp. 235,478.23 8,241.74
0.6500 org Pekerja @ Rp. 130,821.24 85,033.81
0.0300 org Mandor @ Rp. 261,642.48 7,849.27
JUMLAH 174,384.71 460,927.43 635,312.14
Overhead + Profit (10%) 63,531.21
Harga Satuan Pekerjaan 698,843.36
DIBULATKAN 698,843.00

1.0000 m' Pasang kanstin uk. 15x25x40


2.5000 bh Kanstin @ Rp. 80,995.00 202,487.50
0.1500 kg Semen PC @ Rp. 2,281.25 342.19
0.0500 m3 Pasir pasang @ Rp. 403,506.94 20,175.35
0.1000 org Tukang batu @ Rp. 209,313.98 20,931.40
0.0500 org Kep. Tk. Batu @ Rp. 235,478.23 11,773.91
0.0500 org Pekerja @ Rp. 130,821.24 6,541.06
0.0250 org Mandor @ Rp. 261,642.48 6,541.06
ANALISA SATUAN PEKERJAAN BATU DAN PASANGAN
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
JUMLAH 45,787.43 223,005.03 268,792.47
DIBULATKAN 45,787.00 223,005.00 268,792.00

1.0000 m2 Pasang paving blok uk. 10x20x7


1.1000 bh paving blok @ Rp. 78,750.00 86,625.00
0.0500 m3 Pasir urug @ Rp. 214,506.94 10,725.35
0.1600 org Tukang batu @ Rp. 209,313.98 33,490.24
0.0500 org Kep. Tk. Batu @ Rp. 235,478.23 11,773.91
0.0100 org Pekerja @ Rp. 130,821.24 1,308.21
0.0250 org Mandor @ Rp. 261,642.48 6,541.06
JUMLAH 53,113.42 97,350.35 150,463.77
Overhead + Profit (10%) 15,046.38
Harga Satuan Pekerjaan 165,510.15
DIBULATKAN 165,510.00

SNI 1.0000 m2 Screed lantai tebal 2 cm


6.34 10.0000 kg PC @ Rp. 2,281.25 22,812.50
0.0260 m3 Pasir pasang @ Rp. 403,506.94 10,491.18
0.1000 org Tukang batu @ Rp. 209,313.98 20,931.40
0.0100 org Kepala tukang batu @ Rp. 235,478.23 2,354.78
0.2000 org Pekerja @ Rp. 130,821.24 26,164.25
0.0100 org Mandor @ Rp. 261,642.48 2,616.42
JUMLAH 52,066.85 33,303.68 85,370.53
Overhead + Profit (10%) 8,537.05
Harga Satuan Pekerjaan 93,907.59
DIBULATKAN 93,907.00

1.0000 m2 Pekerjaan Waterproofing Coating


1.0000 kg Waterproofing @ Rp. 150,000.00 150,000.00
0.0750 org Tukang batu @ Rp. 209,313.98 15,698.55
0.0075 org Kep. Tk. Batu @ Rp. 235,478.23 1,766.09
0.0500 org Pekerja @ Rp. 130,821.24 6,541.06
0.0250 org Mandor @ Rp. 261,642.48 6,541.06
JUMLAH 30,546.76 150,000.00 180,546.76
Overhead + Profit (10%) 18,054.68
Harga Satuan Pekerjaan 198,601.44
DIBULATKAN 198,601.00

1.0000 m2 Pasangan keramik 20 x 20 campuran 1 PC : 3 PP


1.1000 m2 Keramik 20 x 20 @ Rp. 103,500.00 113,850.00
14.1500 kg Semen PC @ Rp. 2,281.25 32,279.69
0.0390 m3 Pasir pasang @ Rp. 403,506.94 15,736.77
0.2000 kg Semen nat (tile grout) @ Rp. 17,250.00 3,450.00
0.3500 org Tukang batu @ Rp. 209,313.98 73,259.89
0.0350 org Kep. Tk. Batu @ Rp. 235,478.23 8,241.74
0.3500 org Pekerja @ Rp. 130,821.24 45,787.43
0.0350 org Mandor @ Rp. 261,642.48 9,157.49
JUMLAH 136,446.55 165,316.46 301,763.01
Overhead + Profit (10%) 30,176.30
Harga Satuan Pekerjaan 331,939.31
DIBULATKAN 331,939.00

1.0000 m2 Pasangan keramik 20 x 25 campuran 1 PC : 3 PP


1.1000 m2 Keramik 20 x 25 @ Rp. 109,250.00 120,175.00
14.1500 kg Semen PC @ Rp. 2,281.25 32,279.69
0.0390 m3 Pasir pasang @ Rp. 403,506.94 15,736.77
0.2000 kg Semen nat (tile grout) @ Rp. 17,250.00 3,450.00
0.3500 org Tukang batu @ Rp. 209,313.98 73,259.89
0.0350 org Kep. Tk. Batu @ Rp. 235,478.23 8,241.74
0.3500 org Pekerja @ Rp. 130,821.24 45,787.43
0.0350 org Mandor @ Rp. 261,642.48 9,157.49
ANALISA SATUAN PEKERJAAN BATU DAN PASANGAN
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
JUMLAH 136,446.55 171,641.46 308,088.01
Overhead + Profit (10%) 30,808.80
Harga Satuan Pekerjaan 338,896.81
DIBULATKAN 338,896.00

1.0000 m2 Pasangan keramik polos uk. 30 x 30 ex. Asia Tile campuran 1 PC : 3 PP


1.1000 m2 Keramik 30 x 30 @ Rp. 102,465.00 112,711.50
14.1500 kg Semen PC @ Rp. 2,281.25 32,279.69
0.0390 m3 Pasir pasang @ Rp. 403,506.94 15,736.77
0.2000 kg Semen nat (tile grout) @ Rp. 17,250.00 3,450.00
0.3500 org Tukang batu @ Rp. 209,313.98 73,259.89
0.0350 org Kep. Tk. Batu @ Rp. 235,478.23 8,241.74
0.3500 org Pekerja @ Rp. 130,821.24 45,787.43
0.0350 org Mandor @ Rp. 261,642.48 9,157.49
JUMLAH 136,446.55 164,177.96 300,624.51
Overhead + Profit (10%) 30,062.45
Harga Satuan Pekerjaan 330,686.96
DIBULATKAN 330,686.00

1.0000 m2 Pasangan keramik 30 x 30 anti slip campuran 1 PC : 3 PP


1.1000 m2 Keramik 30 x 30 anti slip @ Rp. 102,465.00 112,711.50
14.1500 kg Semen PC @ Rp. 2,281.25 32,279.69
0.0390 m3 Pasir pasang @ Rp. 403,506.94 15,736.77
0.2000 kg Semen nat (tile grout) @ Rp. 17,250.00 3,450.00
0.3500 org Tukang batu @ Rp. 209,313.98 73,259.89
0.0350 org Kep. Tk. Batu @ Rp. 235,478.23 8,241.74
0.3500 org Pekerja @ Rp. 130,821.24 45,787.43
0.0350 org Mandor @ Rp. 261,642.48 9,157.49
JUMLAH 136,446.55 164,177.96 300,624.51
Overhead + Profit (10%) 30,062.45
Harga Satuan Pekerjaan 330,686.96
DIBULATKAN 330,686.00

1.0000 m2 Pasangan keramik 40 x 40 KW 1 campuran 1 PC : 3 PP


1.1000 m2 Keramik 40 x 40 KW 1 @ Rp. 165,600.00 182,160.00
14.1500 kg Semen PC @ Rp. 2,281.25 32,279.69
0.0390 m3 Pasir pasang @ Rp. 403,506.94 15,736.77
0.2000 kg Semen nat (tile grout) @ Rp. 17,250.00 3,450.00
0.3500 org Tukang batu @ Rp. 209,313.98 73,259.89
0.0350 org Kep. Tk. Batu @ Rp. 235,478.23 8,241.74
0.3500 org Pekerja @ Rp. 130,821.24 45,787.43
0.0350 org Mandor @ Rp. 261,642.48 9,157.49
JUMLAH 136,446.55 233,626.46 370,073.01
Overhead + Profit (10%) 37,007.30
Harga Satuan Pekerjaan 407,080.31
DIBULATKAN 407,080.00

1.0000 m2 Pasangan keramik 60 x 60 KW 1 campuran 1 PC : 3 PP


1.1000 m2 Keramik 60 x 60 KW 1 @ Rp. 274,500.00 301,950.00
14.1500 kg Semen PC @ Rp. 2,281.25 32,279.69
0.0390 m3 Pasir pasang @ Rp. 403,506.94 15,736.77
0.2000 kg Semen nat (tile grout) @ Rp. 17,250.00 3,450.00
0.3500 org Tukang batu @ Rp. 209,313.98 73,259.89
0.0350 org Kep. Tk. Batu @ Rp. 235,478.23 8,241.74
0.3500 org Pekerja @ Rp. 130,821.24 45,787.43
0.0350 org Mandor @ Rp. 261,642.48 9,157.49
JUMLAH 136,446.55 353,416.46 489,863.01
Overhead + Profit (10%) 48,986.30
Harga Satuan Pekerjaan 538,849.31
DIBULATKAN 538,849.00
ANALISA SATUAN PEKERJAAN BATU DAN PASANGAN
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)

1.0000 m' Pasangan Plint keramik Dinding 10 x 60 campuran 1 PC : 3 PP


1.8260 bh Plint keramik 10 x 60 @ Rp. 25,000.00 45,650.00
1.1400 kg Semen PC @ Rp. 2,281.25 2,600.63
0.0030 m3 Pasir pasang @ Rp. 403,506.94 1,210.52
0.1000 kg Semen nat (tile grout) @ Rp. 17,250.00 1,725.00
0.0900 org Tukang batu @ Rp. 209,313.98 18,838.26
0.0090 org Kep. Tk. Batu @ Rp. 235,478.23 2,119.30
0.0900 org Pekerja @ Rp. 130,821.24 11,773.91
0.0050 org Mandor @ Rp. 261,642.48 1,308.21
JUMLAH 34,039.69 51,186.15 85,225.83
Overhead + Profit (10%) 8,522.58
Harga Satuan Pekerjaan 93,748.42
DIBULATKAN 93,748.00

1.0000 m' Selokan pas. Batu tela camp. 1 : 3 uk. 25x25 cm diplester camp. 1 : 3
0.0900 m3 Galian saluran @ Rp. 69,073.00 6,216.57
0.6000 m2 Pasangan batu tela @ Rp. 211,000.00 126,600.00
0.0125 m3 Cor lantai 1 : 3 : 6 @ Rp. 1,451,934.00 18,149.18
0.5000 m2 Plesteran saluran @ Rp. 114,192.00 57,096.00
JUMLAH 532,363.95 1,042,831.67 208,061.75
DIBULATKAN 532,363.00 1,042,831.00 208,061.00
ANJALISA PEKERJAAN LISTRIK
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)

23. 1.0000 bh Pasang sekering khas dua grup


1.0000 bh Sekering khas dua grup @ Rp. 138,000.00 138,000.00
0.0500 org Tukang listrik @ Rp. 209,313.98 10,465.70
0.1000 org Pekerja @ Rp. 130,821.24 13,082.12
0.0250 org Mandor @ Rp. 261,642.48 6,541.06
JUMLAH 30,088.89 138,000.00 168,088.89
Overhead + Profit (10%) 16,808.89
Harga Satuan Pekerjaan 184,897.77
DIBULATKAN 184,897.00

1.0000 TITIK PASANG LAMPU XL 8 WATT


1.0000 Bh Fitting 34,500.00 34,500.00
1.0000 Bh Lampu Pijar XL-8 Watt 46,000.00 46,000.00
10.0000 M1 Kabel NYY 3x2½ 14,950.00 149,500.00
10.0000 M1 Pipa Paralon instalasi 5/8" 5,850.00 58,500.00
1.0000 Bh Saklar 34,500.00 34,500.00
2.0000 Bh Isolator 17,250.00 34,500.00
1.0000 H/O Tukang Listrik 209,313.98 209,313.98
1.0000 TTK Instalasi 250,000.00 250,000.00
JUMLAH 607,500.00 209,313.98 816,813.98
Overhead + Profit (10%) 81,681.40
Harga Satuan Pekerjaan 898,495.38
DIBULATKAN 898,495.00

1.0000 TITIK PASANG LAMPU XL 18 WATT


1.0000 Bh Fitting 34,500.00 34,500.00
1.0000 Bh Lampu Pijar XL 18 Watt 57,500.00 57,500.00
10.0000 M1 Kabel NYY 3x2½ 14,950.00 149,500.00
10.0000 M1 Pipa Paralon instalasi 5/8" 5,850.00 58,500.00
1.0000 Bh Saklar 34,500.00 34,500.00
2.0000 Bh Isolator 17,250.00 34,500.00
1.0000 H/O Tukang Listrik 209,313.98 209,313.98
1.0000 TTK Instalasi 250,000.00 250,000.00
JUMLAH 619,000.00 209,313.98 828,313.98
Overhead + Profit (10%) 82,831.40
Harga Satuan Pekerjaan 911,145.38
DIBULATKAN 911,145.00

1.0000 TITIK PASANG LAMPU TL 40 WATT


1.0000 Set Lampu TL 40 Watt + Box lampu 138,000.00 138,000.00
10.0000 M1 Kabel NYY 3x2½ 14,950.00 149,500.00
10.0000 M1 Pipa Paralon instalasi 5/8" 5,850.00 58,500.00
1.0000 Bh Saklar 34,500.00 34,500.00
2.0000 Bh Isolator 17,250.00 34,500.00
1.0000 H/O Tukang Listrik 209,313.98 209,313.98
1.0000 TTK Instalasi 250,000.00 250,000.00
JUMLAH 665,000.00 209,313.98 874,313.98
Overhead + Profit (10%) 87,431.40
Harga Satuan Pekerjaan 961,745.38
DIBULATKAN 961,745.00
ANJALISA PEKERJAAN LISTRIK
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)

1.0000 TITIK PASANG STOP KONTAK


1.0000 Bh Stop Kontak 34,500.00 34,500.00
5.0000 M1 Kabel NYY 2x2½ 14,950.00 74,750.00
3.0000 M1 Pipa Paralon instalasi 5/8" 5,850.00 17,550.00
4.0000 Bh Isolator 17,250.00 69,000.00
0.8300 H/O Tukang Listrik 209,313.98 173,730.61
1.0000 TTK Instalasi 250,000.00 250,000.00
JUMLAH 445,800.00 173,730.61 619,530.61
Overhead + Profit (10%) 61,953.06
Harga Satuan Pekerjaan 681,483.67
DIBULATKAN 681,483.00

1.0000 TITIK PASANG SAKLAR TUNGGAL


1.0000 Bh Saklar Tunggal 34,500.00 34,500.00
5.0000 M1 Kabel NYY 2x2½ 14,950.00 74,750.00
3.0000 M1 Pipa Paralon instalasi 5/8" 5,850.00 17,550.00
4.0000 Bh Isolator 17,250.00 69,000.00
0.8300 H/O Tukang Listrik 209,313.98 173,730.61
1.0000 TTK Instalasi 250,000.00 250,000.00
JUMLAH 445,800.00 173,730.61 619,530.61
Overhead + Profit (10%) 61,953.06
Harga Satuan Pekerjaan 681,483.67
DIBULATKAN 681,483.00

1.0000 TITIK PASANG SAKLAR GANDA


1.0000 Bh Saklar Ganda 34,500.00 34,500.00
5.0000 M1 Kabel NYY 2x2½ 14,950.00 74,750.00
3.0000 M1 Pipa Paralon instalasi 5/8" 5,850.00 17,550.00
4.0000 Bh Isolator 17,250.00 69,000.00
0.8300 H/O Tukang Listrik 209,313.98 173,730.61
1.0000 TTK Instalasi 250,000.00 250,000.00
JUMLAH 445,800.00 173,730.61 619,530.61
Overhead + Profit (10%) 61,953.06
Harga Satuan Pekerjaan 681,483.67
DIBULATKAN 681,483.00
ANALISA SATUAN PEKERJAAN KAYU DAN ALUMINIUM
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)

PEKERJAAN RANGKA ATAP

SNI 1.000 m3 Membuat kuda-kuda kayu kelas I


6.28 1.100 m3 Kayu kls. I @ Rp. 5,720,000.00 6,292,000.00
03-3434-2002 0.800 kg Paku biasa 2" - 5" @ Rp. 33,062.50 26,450.00
12.000 OH Tukang kayu @ Rp. 209,313.98 2,511,767.81
1.200 OH Kepala tukang kayu @ Rp. 235,478.23 282,573.88
4.000 OH Pekerja @ Rp. 130,821.24 523,284.96
0.200 OH Mandor @ Rp. 261,642.48 52,328.50
JUMLAH 3,369,955.14 6,318,450.00 9,688,405.14
Overhead + Profit (10%) 968,840.51
Harga Satuan Pekerjaan 10,657,245.66
DIBULATKAN 10,657,245.00

SNI 1.000 m3 Pasang kuda-kuda kayu lama


03-3434-2002 0.800 kg Paku biasa 2" - 5" @ Rp. 33,062.50 26,450.00
12.000 OH Tukang kayu @ Rp. 209,313.98 2,511,767.81
1.200 OH Kepala tukang kayu @ Rp. 235,478.23 282,573.88
4.000 OH Pekerja @ Rp. 130,821.24 523,284.96
0.200 OH Mandor @ Rp. 261,642.48 52,328.50
JUMLAH 3,369,955.14 26,450.00 3,396,405.14
Overhead + Profit (10%) 339,640.51
Harga Satuan Pekerjaan 3,736,045.66
DIBULATKAN 3,736,045.00

SNI 1.000 m3 Pasang Nook,Goording dan Jurai kayu kelas II


1.100 m3 Kayu kls. II @ Rp. 3,300,000.00 3,630,000.00
0.800 kg Paku biasa 2" - 5" @ Rp. 33,062.50 26,450.00
12.000 OH Tukang kayu @ Rp. 209,313.98 2,511,767.81
1.200 OH Kepala tukang kayu @ Rp. 235,478.23 282,573.88
4.000 OH Pekerja @ Rp. 130,821.24 523,284.96
0.200 OH Mandor @ Rp. 261,642.48 52,328.50
JUMLAH 3,369,955.14 3,656,450.00 7,026,405.14
Overhead + Profit (10%) 702,640.51
Harga Satuan Pekerjaan 7,729,045.66
DIBULATKAN 7,729,045.00

SNI 1.000 m3 Pasang Goording Lama


0.800 kg Paku biasa 2" - 5" @ Rp. 33,062.50 26,450.00
12.000 OH Tukang kayu @ Rp. 209,313.98 2,511,767.81
1.200 OH Kepala tukang kayu @ Rp. 235,478.23 282,573.88
4.000 OH Pekerja @ Rp. 130,821.24 523,284.96
0.200 OH Mandor @ Rp. 261,642.48 52,328.50
JUMLAH ( BELUM PPN ) 3,369,955.14 26,450.00 3,396,405.14
Overhead + Profit (10%) 339,640.51
Harga Satuan Pekerjaan 3,736,045.66
DIBULATKAN 3,736,045.00

F.16 1.000 m2 Pasang usuk 5/5, reng 3/5 lama


0.150 kg Paku usuk @ Rp. 33,062.50 4,959.38
0.100 kg Paku reng @ Rp. 33,062.50 3,306.25
0.100 OH Tukang kayu @ Rp. 209,313.98 20,931.40
0.010 OH Kep. Tk. Kayu @ Rp. 235,478.23 2,354.78
0.100 OH Pekerja @ Rp. 130,821.24 13,082.12
0.003 OH Mandor @ Rp. 261,642.48 654.11
JUMLAH ( BELUM PPN ) 37,022.41 8,265.63 45,288.04
Overhead + Profit (10%) 4,528.80
Harga Satuan Pekerjaan 49,816.84
DIBULATKAN 49,816.00

F.16 1.000 m2 Pasang usuk 5/5, reng 3/5 kayu kls. II


0.006 m1 Usuk kayu kls. II 5/5 @ Rp. 3,300,000.00 18,150.00
0.008 m1 Reng kls. II 3/5 @ Rp. 3,300,000.00 24,750.00
ANALISA SATUAN PEKERJAAN KAYU DAN ALUMINIUM
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
0.150 kg Paku usuk @ Rp. 33,062.50 4,959.38
0.100 kg Paku reng @ Rp. 33,062.50 3,306.25
0.100 OH Tukang kayu @ Rp. 209,313.98 20,931.40
0.010 OH Kep. Tk. Kayu @ Rp. 235,478.23 2,354.78
0.100 OH Pekerja @ Rp. 130,821.24 13,082.12
0.003 OH Mandor @ Rp. 261,642.48 654.11
JUMLAH ( BELUM PPN ) 37,022.41 51,165.63 88,188.04
Overhead + Profit (10%) 8,818.80
Harga Satuan Pekerjaan 97,006.84
DIBULATKAN 97,006.00

F.16 1.000 m2 Pasang usuk 5/7, reng 3/4 kayu kls. I


0.008 m1 Usuk kayu kls. II 5/7 @ Rp. 3,300,000.00 25,410.00
0.005 m1 Reng kayu kls. II 3/4 @ Rp. 3,300,000.00 15,840.00
0.150 kg Paku usuk @ Rp. 33,062.50 4,959.38
0.100 kg Paku reng @ Rp. 33,062.50 3,306.25
0.100 OH Tukang kayu @ Rp. 209,313.98 20,931.40
0.010 OH Kep. Tk. Kayu @ Rp. 235,478.23 2,354.78
0.100 OH Pekerja @ Rp. 130,821.24 13,082.12
0.003 OH Mandor @ Rp. 261,642.48 654.11
JUMLAH 37,022.41 49,515.63 86,538.04
Overhead + Profit (10%) 8,653.80
Harga Satuan Pekerjaan 95,191.84
DIBULATKAN 95,191.00

1.000 m3 Pasang Gelagar dan balok skor


1.100 m3 Kayu Kls I @ Rp. 5,720,000.00 6,292,000.00
15.000 OH Tukang kayu @ Rp. 209,313.98 3,139,709.76
1.500 OH Kep. Tk. Kayu @ Rp. 235,478.23 353,217.35
5.000 OH Pekerja @ Rp. 130,821.24 654,106.20
0.250 OH Mandor @ Rp. 261,642.48 65,410.62
JUMLAH 4,212,443.93 6,292,000.00 10,504,443.93
Overhead + Profit (10%) 1,050,444.39
Harga Satuan Pekerjaan 11,554,888.32
DIBULATKAN 11,554,888.00

SNI 1.000 m3 Pasang Kolom Kayu Kelas I


1.100 m3 Kayu kls. I @ Rp. 5,720,000.00 6,292,000.00
0.250 kg Paku biasa 2" - 5" @ Rp. 33,062.50 8,265.63
12.000 OH Tukang kayu @ Rp. 209,313.98 2,511,767.81
1.200 OH Kepala tukang kayu @ Rp. 235,478.23 282,573.88
4.000 OH Pekerja @ Rp. 130,821.24 523,284.96
0.500 OH Mandor @ Rp. 261,642.48 130,821.24
JUMLAH 3,448,447.89 6,300,265.63 9,748,713.51
Overhead + Profit (10%) 974,871.35
Harga Satuan Pekerjaan 10,723,584.86
DIBULATKAN 10,723,584.00

SNI 1.000 m3 Pasang Murplat kayu kelas I


1.100 m3 Kayu kls. I @ Rp. 5,720,000.00 6,292,000.00
0.800 kg Paku biasa 2" - 5" @ Rp. 33,062.50 26,450.00
12.000 OH Tukang kayu @ Rp. 209,313.98 2,511,767.81
1.200 OH Kepala tukang kayu @ Rp. 235,478.23 282,573.88
4.000 OH Pekerja @ Rp. 130,821.24 523,284.96
0.200 OH Mandor @ Rp. 261,642.48 52,328.50
JUMLAH 3,369,955.14 6,318,450.00 9,688,405.14
Overhead + Profit (10%) 968,840.51
Harga Satuan Pekerjaan 10,657,245.66
DIBULATKAN 10,657,245.00

1.000 m2 Pasang Dinding Papan Kayu Kls. II 2/20


0.022 m3 Kayu kls. II @ Rp. 3,300,000.00 72,600.00
0.200 kg Paku biasa 2" - 5" @ Rp. 33,062.50 6,612.50
0.013 m3 Balok Kayu kls. II 5/10 @ Rp. 3,300,000.00 42,900.00
ANALISA SATUAN PEKERJAAN KAYU DAN ALUMINIUM
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
0.080 OH Tukang kayu @ Rp. 209,313.98 16,745.12
0.080 OH Kepala tukang kayu @ Rp. 235,478.23 18,838.26
0.200 OH Pekerja @ Rp. 130,821.24 26,164.25
0.100 OH Mandor @ Rp. 261,642.48 26,164.25
JUMLAH 87,911.87 122,112.50 210,024.37
Overhead + Profit (10%) 21,002.44
Harga Satuan Pekerjaan 231,026.81
DIBULATKAN 231,026.00

PEKERJAAN PINTU DAN JENDELA

SNI 1.000 m3 Membuat kusen pintu / jendela kayu kelas I


6.1 1.100 m3 Kayu kls. I @ Rp. 5,720,000.00 6,292,000.00
03-3434-2002 20.000 OH Tukang kayu @ Rp. 209,313.98 4,186,279.68
2.000 OH Kepala tukang kayu @ Rp. 235,478.23 470,956.46
6.000 OH Pekerja @ Rp. 130,821.24 784,927.44
0.300 OH Mandor @ Rp. 261,642.48 78,492.74
JUMLAH 5,520,656.33 6,292,000.00 11,812,656.33
Overhead + Profit (10%) 1,181,265.63
Harga Satuan Pekerjaan 12,993,921.96
DIBULATKAN 12,993,921.00

SNI 1.000 m3 Membuat kusen pintu / jendela kayu kelas II


6.1 1.100 m3 Kayu kls. II @ Rp. 3,300,000.00 3,630,000.00
03-3434-2002 20.000 OH Tukang kayu @ Rp. 209,313.98 4,186,279.68
2.000 OH Kepala tukang kayu @ Rp. 235,478.23 470,956.46
6.000 OH Pekerja @ Rp. 130,821.24 784,927.44
0.300 OH Mandor @ Rp. 261,642.48 78,492.74
JUMLAH 5,520,656.33 3,630,000.00 9,150,656.33
Overhead + Profit (10%) 915,065.63
Harga Satuan Pekerjaan 10,065,721.96
DIBULATKAN 10,065,721.00

SNI 1.000 m2 Pasang pintu tripleks rangkap, rangka kayu kelas II


6.19 0.020 m3 Papan kayu kls. II @ Rp. 3,300,000.00 64,680.00
03-3434-2002 0.030 kg Paku biasa 1/2" - 1" @ Rp. 33,062.50 991.88
0.300 kg Lem kayu @ Rp. 28,750.00 8,625.00
1.000 lbr Tripleks 4 mm @ Rp. 97,750.00 97,750.00
2.000 OH Tukang kayu @ Rp. 209,313.98 418,627.97
0.200 OH Kepala tukang kayu @ Rp. 235,478.23 47,095.65
0.600 OH Pekerja @ Rp. 130,821.24 78,492.74
0.030 OH Mandor @ Rp. 261,642.48 7,849.27
JUMLAH 552,065.63 172,046.88 724,112.51
Overhead + Profit (10%) 72,411.25
Harga Satuan Pekerjaan 796,523.76
DIBULATKAN 796,523.00

SNI 1.000 m2 Pasang pintu tripleks rangkap lapis seng plat BJLS 20, rangka kayu kelas II
6.19 0.020 m3 Papan kayu kls. II @ Rp. 3,300,000.00 64,680.00
03-3434-2002 0.030 kg Paku biasa 1/2" - 1" @ Rp. 33,062.50 991.88
0.300 kg Lem kayu @ Rp. 28,750.00 8,625.00
1.000 lbr Tripleks 4 mm @ Rp. 97,750.00 97,750.00
1.000 lbr Seng Plat bjls 20 @ Rp. 69,000.00 69,000.00
2.000 OH Tukang kayu @ Rp. 209,313.98 418,627.97
0.200 OH Kepala tukang kayu @ Rp. 235,478.23 47,095.65
0.600 OH Pekerja @ Rp. 130,821.24 78,492.74
0.030 OH Mandor @ Rp. 261,642.48 7,849.27
JUMLAH 552,065.63 241,046.88 793,112.51
Overhead + Profit (10%) 79,311.25
Harga Satuan Pekerjaan 872,423.76
DIBULATKAN 872,423.00

SNI 1.000 m2 Mengerjakan daun pintu / jendela panil kayu Kls I


6.7 0.040 m3 Kayu Kls I @ Rp. 6,600,000.00 264,000.00
ANALISA SATUAN PEKERJAAN KAYU DAN ALUMINIUM
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
03-3434-2002 2.500 OH Tukang kayu @ Rp. 209,313.98 523,284.96
0.250 OH Kepala tukang kayu @ Rp. 235,478.23 58,869.56
1.000 OH Pekerja @ Rp. 130,821.24 130,821.24
0.050 OH Mandor @ Rp. 261,642.48 13,082.12
JUMLAH 726,057.88 264,000.00 990,057.88
Overhead + Profit (10%) 99,005.79
Harga Satuan Pekerjaan 1,089,063.67
DIBULATKAN 1,089,063.00
SNI 1.000 m2 Mengerjakan daun pintu / jendela panil kayu Kls II
6.7 0.040 m3 Kayu Kls II @ Rp. 3,300,000.00 132,000.00
03-3434-2002 2.500 OH Tukang kayu @ Rp. 209,313.98 523,284.96
0.250 OH Kepala tukang kayu @ Rp. 235,478.23 58,869.56
1.000 OH Pekerja @ Rp. 130,821.24 130,821.24
0.050 OH Mandor @ Rp. 261,642.48 13,082.12
JUMLAH 726,057.88 132,000.00 858,057.88
Overhead + Profit (10%) 85,805.79
Harga Satuan Pekerjaan 943,863.67
DIBULATKAN 943,863.00

SNI 1.000 m2 Pasang Jalusi kayu kelas II


6.12 0.022 m3 Kayu Kls II @ Rp. 3,300,000.00 72,600.00
0.200 Kg Paku @ Rp. 33,062.50 6,612.50
03-3434-2002 1.800 OH Tukang kayu @ Rp. 209,313.98 376,765.17
0.180 OH Kepala tukang kayu @ Rp. 235,478.23 42,386.08
0.280 OH Pekerja @ Rp. 130,821.24 36,629.95
0.014 OH Mandor @ Rp. 261,642.48 3,662.99
JUMLAH 459,444.19 79,212.50 538,656.69
Overhead + Profit (10%) 53,865.67
Harga Satuan Pekerjaan 592,522.36
DIBULATKAN 592,522.00

1.000 m2 Mengerjakan daun pintu / jendela panil kaca 5 mm kayu Kls. I


0.025 m3 Kayu Kls I @ Rp. 6,600,000.00 165,000.00
0.800 m2 Kaca 5 mm Bening @ Rp. 251,275.00 201,020.00
3.000 OH Tukang kayu @ Rp. 209,313.98 627,941.95
0.300 OH Kepala tukang kayu @ Rp. 235,478.23 70,643.47
1.000 OH Pekerja @ Rp. 130,821.24 130,821.24
0.050 OH Mandor @ Rp. 261,642.48 13,082.12
JUMLAH 842,488.79 201,020.00 1,043,508.79
Overhead + Profit (10%) 104,350.88
Harga Satuan Pekerjaan 1,147,859.66
DIBULATKAN 1,147,859.00

PEKERJAAN PLAFOND
SNI 1.000 m2 Pasang rangka langit-langit (1,00 x 1,00) m, kayu lama
03-3434-2002 0.100 kg Paku biasa 2" - 5" @ Rp. 33,062.50 3,306.25
0.250 OH Tukang kayu @ Rp. 209,313.98 52,328.50
0.025 OH Kepala tukang kayu @ Rp. 235,478.23 5,886.96
0.150 OH Pekerja @ Rp. 130,821.24 19,623.19
0.008 OH Mandor @ Rp. 261,642.48 1,962.32
JUMLAH 79,800.96 0.00 79,800.96
Overhead + Profit (10%) 7,980.10
Harga Satuan Pekerjaan 87,781.05
DIBULATKAN 87,781.00

SNI 1.000 m2 Pasang rangka langit-langit (1,00 x 1,00) m, kayu kelas II


6.39 0.012 m3 Kayu kls. II @ Rp. 3,300,000.00 39,600.00
03-3434-2002 0.100 kg Paku biasa 2" - 5" @ Rp. 33,062.50 3,306.25
0.250 OH Tukang kayu @ Rp. 209,313.98 52,328.50
0.025 OH Kepala tukang kayu @ Rp. 235,478.23 5,886.96
0.150 OH Pekerja @ Rp. 130,821.24 19,623.19
0.008 OH Mandor @ Rp. 261,642.48 1,962.32
JUMLAH 79,800.96 42,906.25 122,707.21
Overhead + Profit (10%) 12,270.72
ANALISA SATUAN PEKERJAAN KAYU DAN ALUMINIUM
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
Harga Satuan Pekerjaan 134,977.93
DIBULATKAN 134,977.00

1.000 m2 Pasang rangka langit-langit (60 x 120) m, kayu kelas II


0.013 m3 Kayu kls. II @ Rp. 3,300,000.00 42,900.00
0.120 kg Paku @ Rp. 33,062.50 3,967.50
0.300 OH Tukang kayu @ Rp. 209,313.98 62,794.20
0.030 OH Kepala tukang kayu @ Rp. 235,478.23 7,064.35
0.180 OH Pekerja @ Rp. 130,821.24 23,547.82
0.009 OH Mandor @ Rp. 261,642.48 2,354.78
JUMLAH 95,761.15 46,867.50 142,628.65
Overhead + Profit (10%) 14,262.86
Harga Satuan Pekerjaan 156,891.51
DIBULATKAN 156,891.00

1.000 m2 Langit-langit tripleks t; 4 mm


0.336 Lbr Tripleks 4 mm @ Rp. 97,750.00 32,844.00
0.030 kg Paku @ Rp. 39,675.00 1,190.25
0.100 OH Tukang kayu @ Rp. 209,313.98 20,931.40
0.010 OH Kepala tukang kayu @ Rp. 235,478.23 2,354.78
0.100 OH Pekerja @ Rp. 130,821.24 13,082.12
0.005 OH Mandor @ Rp. 261,642.48 1,308.21
JUMLAH 37,676.52 34,034.25 71,710.77
Overhead + Profit (10%) 7,171.08
Harga Satuan Pekerjaan 78,881.84
DIBULATKAN 78,881.00

1.000 m2 Langit-langit tripleks t; 4 mm, rangka 60 x 120 kayu kls. II


0.336 Lbr Tripleks 4 mm @ Rp. 97,750.00 32,844.00
0.017 M3 Kayu Matoa @ Rp. 3,300,000.00 56,100.00
0.200 Kg Paku @ Rp. 33,062.50 6,612.50
0.020 Kg Paku Tripleks @ Rp. 39,675.00 793.50
0.400 OH Tukang kayu @ Rp. 209,313.98 83,725.59
0.040 OH Kepala tukang kayu @ Rp. 235,478.23 9,419.13
0.280 OH Pekerja @ Rp. 130,821.24 36,629.95
0.014 OH Mandor @ Rp. 261,642.48 3,662.99
JUMLAH 133,437.66 96,350.00 229,787.66
Overhead + Profit (10%) 22,978.77
Harga Satuan Pekerjaan 252,766.43
DIBULATKAN 252,766.00

6.13 1.000 m2 Langit2 gypsum t = 9 mm


0.360 lbr Gypsum board 9 mm @ Rp. 225,000.00 81,000.00
0.050 roll Kasa gypsum @ Rp. 25,000.00 1,250.00
0.450 kg Compound @ Rp. 7,500.00 3,375.00
0.050 kg Paku gypsum @ Rp. 17,250.00 862.50
0.100 OH Tukang kayu @ Rp. 209,313.98 20,931.40
0.010 OH Kepala tukang kayu @ Rp. 235,478.23 2,354.78
0.070 OH Pekerja @ Rp. 130,821.24 9,157.49
0.004 OH Mandor @ Rp. 261,642.48 915.75
JUMLAH 33,359.42 86,487.50 119,846.92
Overhead + Profit (10%) 11,984.69
Harga Satuan Pekerjaan 131,831.61
DIBULATKAN 131,831.00

2
6.13 1.000 m Langit2 gypsum t; 9 mm, rangka 60 x 120 kayu kls. II
3
0.013 m Kayu kls. II @ Rp. 3,300,000.00 42,900.00
0.360 lbr Gypsum board 9 mm @ Rp. 225,000.00 81,000.00
0.050 roll Kasa gypsum @ Rp. 25,000.00 1,250.00
0.450 kg Compound @ Rp. 7,500.00 3,375.00
0.050 kg Paku gypsum @ Rp. 17,250.00 862.50
0.120 kg Paku usuk @ Rp. 33,062.50 3,967.50
0.370 OH Tukang kayu @ Rp. 209,313.98 77,446.17
0.037 OH Kepala tukang kayu @ Rp. 235,478.23 8,712.69
ANALISA SATUAN PEKERJAAN KAYU DAN ALUMINIUM
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
0.240 OH Pekerja @ Rp. 130,821.24 31,397.10
0.012 OH Mandor @ Rp. 261,642.48 3,139.71
JUMLAH 120,695.68 133,355.00 254,050.68
Overhead + Profit (10%) 25,405.07
Harga Satuan Pekerjaan 279,455.74
DIBULATKAN 279,455.00

1.000 m1 Pasang list profil cornees gypsum lebar sampai 5 cm


1.100 m1 List profil cornees gypsum @ Rp. 30,000.00 33,000.00
0.700 kg Tepung gypsum @ Rp. 7,500.00 5,250.00
0.038 OH Tukang kayu @ Rp. 209,313.98 7,849.27
0.004 OH Kepala tukang kayu @ Rp. 235,478.23 871.27
0.113 OH Pekerja @ Rp. 130,821.24 14,717.39
0.007 OH Mandor @ Rp. 261,642.48 1,700.68
JUMLAH 25,138.61 38,250.00 63,388.61
Overhead + Profit (10%) 6,338.86
Harga Satuan Pekerjaan 69,727.47
DIBULATKAN 69,727.00

1.000 m1 Pasang list profil cornees gypsum lebar 5 - 10 cm


1.100 m1 List profil cornees gypsum @ Rp. 30,000.00 33,000.00
0.875 kg Tepung gypsum @ Rp. 7,500.00 6,562.50
0.038 OH Tukang kayu @ Rp. 209,313.98 7,849.27
0.004 OH Kepala tukang kayu @ Rp. 235,478.23 871.27
0.113 OH Pekerja @ Rp. 130,821.24 14,717.39
0.007 OH Mandor @ Rp. 261,642.48 1,700.68
JUMLAH ( BELUM PPN ) 25,138.61 39,562.50 64,701.11
Overhead + Profit (10%) 6,470.11
Harga Satuan Pekerjaan 71,171.22
DIBULATKAN 71,171.00

SNI 1.000 m1 List langit-langit kayu profil


6.19 0.275 btg List kayu profil @ Rp. 28,000.00 7,700.00
03-2838-2002 0.010 kg Paku @ Rp. 33,062.50 330.63
0.050 OH Tukang kayu @ Rp. 209,313.98 10,465.70
0.005 OH Kepala tukang kayu @ Rp. 235,478.23 1,177.39
0.050 OH Pekerja @ Rp. 130,821.24 6,541.06
0.003 OH Mandor @ Rp. 261,642.48 784.93
JUMLAH 18,969.08 8,030.63 26,999.70
Overhead + Profit (10%) 2,699.97
Harga Satuan Pekerjaan 29,699.68
DIBULATKAN 29,699.00

PEKERJAAN LISPLANK
SNI 1.000 m1 Pasang lisplank ukuran 2 x (2 x 20) cm, kayu kelas II
0.009 m3 Kayu kls. II papan @ Rp. 3,300,000.00 28,380.00
03-3434-2002 0.060 kg Paku biasa 2" - 5" @ Rp. 33,062.50 1,983.75
0.100 OH Tukang kayu @ Rp. 209,313.98 20,931.40
0.010 OH Kepala tukang kayu @ Rp. 235,478.23 2,354.78
0.100 OH Pekerja @ Rp. 130,821.24 13,082.12
0.005 OH Mandor @ Rp. 261,642.48 1,308.21
JUMLAH 37,676.52 30,363.75 68,040.27
Overhead + Profit (10%) 6,804.03
Harga Satuan Pekerjaan 74,844.29
DIBULATKAN 74,844.00

AK 1.000 m1 Pasang lisplank ukuran 2 x (2 x 20) cm, kayu kelas I


0.009 m3 Kayu kls. I papan @ Rp. 6,600,000.00 56,760.00
0.060 kg Paku biasa 2" - 5" @ Rp. 33,062.50 1,983.75
0.100 OH Tukang kayu @ Rp. 209,313.98 20,931.40
0.010 OH Kepala tukang kayu @ Rp. 235,478.23 2,354.78
0.100 OH Pekerja @ Rp. 130,821.24 13,082.12
0.005 OH Mandor @ Rp. 261,642.48 1,308.21
JUMLAH 37,676.52 58,743.75 96,420.27
ANALISA SATUAN PEKERJAAN KAYU DAN ALUMINIUM
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
Overhead + Profit (10%) 9,642.03
Harga Satuan Pekerjaan 106,062.29
DIBULATKAN 106,062.00

PEKERJAAN TALANG
SNI 1.000 m1 Pasang talang datar, seng BJLS 30, papan kayu kelas II
6.18 0.500 lbr Seng plat 3' x 6' BJLS 30 @ Rp. 80,500.00 40,250.00
0.015 kg Paku biasa 1/2" - 1" @ Rp. 33,062.50 495.94
0.010 m3 Kayu kls. II papan @ Rp. 3,300,000.00 31,680.00
0.400 OH Tukang kayu @ Rp. 209,313.98 83,725.59
0.025 OH Kepala tukang kayu @ Rp. 235,478.23 5,886.96
0.150 OH Pekerja @ Rp. 130,821.24 19,623.19
0.001 OH Mandor @ Rp. 261,642.48 327.05
JUMLAH 109,562.79 72,425.94 181,988.73
Overhead + Profit (10%) 18,198.87
Harga Satuan Pekerjaan 200,187.60
DIBULATKAN 200,187.00

SNI 1.000 m1 Pasang talang miring, seng BJLS 30, papan kayu kls. II
6.19 0.500 lbr Seng plat 3' x 6' BJLS 30 @ Rp. 80,500.00 40,250.00
0.015 kg Paku biasa 1/2" - 1" @ Rp. 33,062.50 495.94
0.019 m3 Kayu kls. II papan @ Rp. 3,300,000.00 62,700.00
0.250 kg Flincoat @ Rp. 0.00
0.400 OH Tukang kayu @ Rp. 209,313.98 83,725.59
0.025 OH Kepala tukang kayu @ Rp. 235,478.23 5,886.96
0.040 OH Pekerja @ Rp. 130,821.24 5,232.85
0.001 OH Mandor @ Rp. 261,642.48 327.05
JUMLAH 95,172.45 103,445.94 198,618.39
Overhead + Profit (10%) 19,861.84
Harga Satuan Pekerjaan 218,480.23
DIBULATKAN 218,480.00

H.18 1.000 m1 Pasang talang paralon kotak


1.000 m1 talang paralon kotak @ Rp. 27,312.50 27,312.50
0.375 OH Tukang @ Rp. 209,313.98 78,492.74
0.038 OH Kep. Tukang @ Rp. 235,478.23 8,830.43
0.225 OH Pekerja @ Rp. 130,821.24 29,434.78
0.011 OH Mandor @ Rp. 261,642.48 2,943.48
JUMLAH 119,701.43 27,312.50 147,013.93
Overhead + Profit (10%) 14,701.39
Harga Satuan Pekerjaan 161,715.33
DIBULATKAN 161,715.00

SNI 1.000 m2 Pasang dinding pemisah teakwood rangkap, rangka kayu kls. II
03-3434-2002 0.020 m3 Kayu kls. II @ Rp. 3,300,000.00 64,350.00
6.56 0.007 m3 Kayu kls, II papan @ Rp. 3,300,000.00 23,100.00
0.100 kg Paku biasa 2" - 5" @ Rp. 33,062.50 3,306.25
0.560 kg Lem kayu @ Rp. 28,750.00 16,100.00
1.000 lbr Teakwood 4' x 8' x 4 mm @ Rp. 109,250.00
0.450 OH Tukang kayu @ Rp. 209,313.98 94,191.29
0.045 OH Kepala tukang kayu @ Rp. 235,478.23 10,596.52
0.150 OH Pekerja @ Rp. 130,821.24 19,623.19
0.075 OH Mandor @ Rp. 261,642.48 19,623.19
JUMLAH 144,034.19 106,856.25 250,890.44
Overhead + Profit (10%) 25,089.04
Harga Satuan Pekerjaan 275,979.48
DIBULATKAN 275,979.00

SNI 1.000 m2 Pas. dinding pemisah plywoodwood rangkap, rangka ky kls. II


03-3434-2002 0.020 m3 Kayu kls. II balok @ Rp. 3,300,000.00 64,350.00
6.57 0.007 m3 Kayu kls. II papan @ Rp. 3,300,000.00 23,100.00
0.100 kg Paku biasa 2" - 5" @ Rp. 33,062.50 3,306.25
0.560 kg Lem kayu @ Rp. 28,750.00 16,100.00
1.000 lbr Plywood 4' x 8' x 4 mm @ Rp. 97,750.00 97,750.00
ANALISA SATUAN PEKERJAAN KAYU DAN ALUMINIUM
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
0.600 OH Tukang kayu @ Rp. 209,313.98 125,588.39
0.060 OH Kepala tukang kayu @ Rp. 235,478.23 14,128.69
0.200 OH Pekerja @ Rp. 130,821.24 26,164.25
0.010 OH Mandor @ Rp. 261,642.48 2,616.42
JUMLAH 168,497.76 204,606.25 373,104.01
Overhead + Profit (10%) 37,310.40
Harga Satuan Pekerjaan 410,414.41
DIBULATKAN 410,414.00

SNI 1.000 m2 Pasang plywood tebal 4 mm, untuk dinding


03-3434-2002 0.400 lbr Plywood 4' x 8' x 4 mm @ Rp. 97,750.00 39,100.00
6.59 0.050 kg Paku biasa 2" - 5" @ Rp. 33,062.50 1,653.13
0.075 OH Tukang kayu @ Rp. 209,313.98 15,698.55
0.008 OH Kepala tukang kayu @ Rp. 235,478.23 1,766.09
0.025 OH Pekerja @ Rp. 130,821.24 3,270.53
0.001 OH Mandor @ Rp. 261,642.48 340.14
JUMLAH 21,075.30 40,753.13 61,828.43
Overhead + Profit (10%) 6,182.84
Harga Satuan Pekerjaan 68,011.27
DIBULATKAN 68,011.00

PEKERJAAN ATAP
1.000 m2 Pasang genteng lama
0.100 OH Tukang batu @ Rp. 209,313.98 20,931.40
0.010 OH Kep. Tk. Batu @ Rp. 235,478.23 2,354.78
0.200 OH Pekerja @ Rp. 130,821.24 26,164.25
0.010 OH Mandor @ Rp. 261,642.48 2,616.42
JUMLAH 52,066.85 0.00 52,066.85
Overhead + Profit (10%) 5,206.69
Harga Satuan Pekerjaan 57,273.54
DIBULATKAN 57,273.00

SNI 1.000 m2 Pasang atap Galvalum 6 kaki


6.21 0.870 Lbr Atap Galvalum @ Rp. 134,550.00 117,058.50
03-3436-2002 0.025 Kg Paku Seng @ Rp. 39,675.00 991.88
0.067 OH Tukang kayu @ Rp. 209,313.98 14,024.04
0.007 OH Kepala tukang kayu @ Rp. 235,478.23 1,648.35
0.140 OH Pekerja @ Rp. 130,821.24 18,314.97
0.007 OH Mandor @ Rp. 261,642.48 1,831.50
JUMLAH 35,818.86 118,050.38 153,869.23
Overhead + Profit (10%) 15,386.92
Harga Satuan Pekerjaan 169,256.15
DIBULATKAN 169,256.00
SNI 1.000 m2 Pasang atap Seng gelombang BJLS 30
6.21 0.870 Lbr Seng gelombang BJLS 30 @ Rp. 109,250.00 95,047.50
03-3436-2002 0.025 Kg Paku seng @ Rp. 39,675.00 991.88
0.067 OH Tukang kayu @ Rp. 209,313.98 14,024.04
0.007 OH Kepala tukang kayu @ Rp. 235,478.23 1,648.35
0.140 OH Pekerja @ Rp. 130,821.24 18,314.97
0.007 OH Mandor @ Rp. 261,642.48 1,831.50
JUMLAH 35,818.86 96,039.38 131,858.23
Overhead + Profit (10%) 13,185.82
Harga Satuan Pekerjaan 145,044.05
DIBULATKAN 145,044.00

SNI 1.000 m2 Pasang nok Seng plat BJLS 30


6.22 0.380 Lbr Seng Plat BJLS 30 @ Rp. 80,500.00 30,590.00
03-3436-2002 0.004 M3 Kayu Matoa @ Rp. 3,300,000.00 13,200.00
0.020 Kg Paku Seng @ Rp. 39,675.00 793.50
0.125 OH Tukang kayu @ Rp. 209,313.98 26,164.25
0.013 OH Kepala tukang kayu @ Rp. 235,478.23 3,061.22
0.084 OH Pekerja @ Rp. 130,821.24 10,988.98
0.004 OH Mandor @ Rp. 261,642.48 1,046.57
JUMLAH 41,261.02 44,583.50 85,844.52
ANALISA SATUAN PEKERJAAN KAYU DAN ALUMINIUM
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
Overhead + Profit (10%) 8,584.45
Harga Satuan Pekerjaan 94,428.97
DIBULATKAN 94,428.00

SNI 1.000 m2 Pasang atap genteng metal zinc alume type prima roof
03-3436-2002 1.680 m2 Genteng metal @ Rp. 51,750.00 86,940.00
6.32 0.086 kg Paku anti karat @ Rp. 39,675.00 3,412.05
0.100 OH Tukang kayu @ Rp. 209,313.98 20,931.40
0.010 OH Kepala tukang kayu @ Rp. 235,478.23 2,354.78
0.200 OH Pekerja @ Rp. 130,821.24 26,164.25
0.001 OH Mandor @ Rp. 261,642.48 261.64
JUMLAH 49,712.07 90,352.05 140,064.12
Overhead + Profit (10%) 14,006.41
Harga Satuan Pekerjaan 154,070.53
DIBULATKAN 154,070.00

Mod. SNI 1.000 m2 Pasang atap metal roof ex. Sakura roof
03-3436-2002 1.680 lbr Atap metal ex. Sakura roof @ Rp. 51,750.00 86,940.00
6.32 0.086 kg Paku/skrup atap anti karat @ Rp. 39,675.00 3,412.05
0.100 OH Tukang kayu @ Rp. 209,313.98 20,931.40
0.010 OH Kepala tukang kayu @ Rp. 235,478.23 2,354.78
0.200 OH Pekerja @ Rp. 130,821.24 26,164.25
0.001 OH Mandor @ Rp. 261,642.48 261.64
JUMLAH 49,712.07 90,352.05 140,064.12
Overhead + Profit (10%) 14,006.41
Harga Satuan Pekerjaan 154,070.53
DIBULATKAN 154,070.00

Mod. SNI 1.000 m1 Pasang nok metal roof ex. Sakura roof
03-3436-2002 1.100 lbr nok metal ex. Sakura roof @ Rp. 43,700.00 48,070.00
6.32 0.050 kg Paku/skrup atap anti karat @ Rp. 39,675.00 1,983.75
0.150 OH Tukang kayu @ Rp. 209,313.98 31,397.10
0.015 OH Kepala tukang kayu @ Rp. 235,478.23 3,532.17
0.250 OH Pekerja @ Rp. 130,821.24 32,705.31
0.013 OH Mandor @ Rp. 261,642.48 3,401.35
JUMLAH 71,035.93 50,053.75 121,089.68
Overhead + Profit (10%) 12,108.97
Harga Satuan Pekerjaan 133,198.65
DIBULATKAN 133,198.00

PEKERJAAN BESI DAN ALUMUNIUM


3 1.000 M Pengelasan Single ( las listrik )
3.000 kg Kawat las @ Rp. 46,000.00 138,000.00
1.000 hari Peralatan las @ Rp. 150,000.00 150,000.00
0.500 OH Tukang las @ Rp. 209,313.98 104,656.99
0.050 OH Kepala tukang las @ Rp. 235,478.23 11,773.91
1.000 OH Pekerja @ Rp. 130,821.24 130,821.24
1.000 OH Mandor @ Rp. 261,642.48 261,642.48
JUMLAH ( BELUM PPN ) 508,894.62 288,000.00 796,894.62
Overhead + Profit (10%) 79,689.46
Harga Satuan Pekerjaan 876,584.09
DIBULATKAN 876,584.00

SNI 1.000 m2 Pasang pintu alumunium + Kaca


1.000 m2 Pintu alumunium + Kaca, uk. 80x210
@ Rp.
cm 1,800,000.00 1,800,000.00
6.9 1.050 OH Tukang besi konstruksi @ Rp. 209,313.98 219,779.68
0.105 OH Kepala tukang besi @ Rp. 235,478.23 24,725.21
1.050 OH Pekerja @ Rp. 130,821.24 137,362.30
0.005 OH Mandor @ Rp. 261,642.48 1,360.54
JUMLAH ( BELUM PPN ) 383,227.74 1,800,000.00 2,183,227.74
Overhead + Profit (10%) 218,322.77
Harga Satuan Pekerjaan 2,401,550.51
DIBULATKAN 2,401,550.00
ANALISA SATUAN PEKERJAAN KAYU DAN ALUMINIUM
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)

SNI 1.000 m2 Pasang teralis besi


11.500 m1 Baja strip 2 x 3 @ Rp. 74,750.00 859,625.00
6.12 1.200 OH Tukang las @ Rp. 209,313.98 251,176.78
0.012 OH Kepala tukang las @ Rp. 235,478.23 2,825.74
1.200 OH Pekerja @ Rp. 130,821.24 156,985.49
0.001 OH Mandor @ Rp. 261,642.48 156.99
JUMLAH ( BELUM PPN ) 411,144.99 859,625.00 1,270,769.99
Overhead + Profit (10%) 127,077.00
Harga Satuan Pekerjaan 1,397,846.99
DIBULATKAN 1,397,846.00

SNI 1.000 m2 Pasang kawat nyamuk


1.100 m2 Kawat nyamuk @ Rp. 34,500.00 37,950.00
6.14 0.020 kg Paku biasa 1/2" - 1" @ Rp. 33,062.50 661.25
0.002 m3 Kayu kls. II papan @ Rp. 3,300,000.00 5,940.00
0.100 OH Tukang kayu @ Rp. 209,313.98 20,931.40
0.010 OH Kepala tukang kayu @ Rp. 235,478.23 2,354.78
0.100 OH Pekerja @ Rp. 130,821.24 13,082.12
0.001 OH Mandor @ Rp. 261,642.48 130.82
JUMLAH 36,499.13 44,551.25 81,050.38
Overhead + Profit (10%) 8,105.04
Harga Satuan Pekerjaan 89,155.41
DIBULATKAN 89,155.00

SNI 1.000 set Pasang jendela louver lengkap teralis


1.100 set jendela louver lengkap teralis @ Rp. 207,000.00 227,700.00
6.17 0.020 kg Paku skrup @ Rp. 17,250.00 345.00
0.025 m2 Besi strip @ Rp. 1,610,000.00 40,250.00
0.200 OH Tukang kayu @ Rp. 209,313.98 41,862.80
0.020 OH Kepala tukang kayu @ Rp. 235,478.23 4,709.56
0.200 OH Pekerja @ Rp. 130,821.24 26,164.25
0.001 OH Mandor @ Rp. 261,642.48 261.64
JUMLAH ( BELUM PPN ) 72,998.25 268,295.00 341,293.25
Overhead + Profit (10%) 34,129.33
Harga Satuan Pekerjaan 375,422.58
DIBULATKAN 375,422.00

1
SNI 1.000 m Memasang Reiling Besi Hollow 40x40x1.2 mm
1
1.200 m Besi Hollow 40x40x1,2 @ Rp. 34,500.00 41,400.00
35% x Harga pipa (Pengelasan) @ Rp. 34,500.00 12,075.00
0.090 org Tukang Las @ Rp. 209,313.98 18,838.26
0.054 org Pekerja @ Rp. 130,821.24 7,064.35
0.027 org Mandor @ Rp. 261,642.48 7,064.35
JUMLAH 32,966.95 53,475.00 86,441.95
Overhead + Profit (10%) 8,644.20
Harga Satuan Pekerjaan 95,086.15
DIBULATKAN 95,086.00

1
SNI 1.000 m Memasang Reiling Besi Hollow 20x40x1.2 mm
1
1.200 m Besi Hollow 20x40x1,2 @ Rp. 28,750.00 34,500.00
35% x Harga pipa (Pengelasan) @ Rp. 28,750.00 10,062.50
0.090 org Tukang Las @ Rp. 209,313.98 18,838.26
0.054 org Pekerja @ Rp. 130,821.24 7,064.35
0.027 org Mandor @ Rp. 261,642.48 7,064.35
JUMLAH 32,966.95 44,562.50 77,529.45
Overhead + Profit (10%) 7,752.95
Harga Satuan Pekerjaan 85,282.40
DIBULATKAN 85,282.00

1
SNI 1.000 m Memasang Reiling Besi Hollow 50x50x1.2 mm
1
1.200 m Besi Hollow 50x50x1,2 @ Rp. 39,100.00 46,920.00
35% x Harga pipa (Pengelasan) @ Rp. 39,100.00 13,685.00
0.090 org Tukang Las @ Rp. 209,313.98 18,838.26
ANALISA SATUAN PEKERJAAN KAYU DAN ALUMINIUM
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
0.054 org Pekerja @ Rp. 130,821.24 7,064.35
0.027 org Mandor @ Rp. 261,642.48 7,064.35
JUMLAH 32,966.95 60,605.00 93,571.95
Overhead + Profit (10%) 9,357.20
Harga Satuan Pekerjaan 102,929.15
DIBULATKAN 102,929.00

1
SNI 1.000 m Memasang Reiling Besi Hollow 20x50x1.2 mm
1
1.200 m Besi Hollow 20x50x1,2 @ Rp. 25,300.00 30,360.00
35% x Harga pipa (Pengelasan) @ Rp. 25,300.00 8,855.00
0.090 org Tukang Las @ Rp. 209,313.98 18,838.26
0.054 org Pekerja @ Rp. 130,821.24 7,064.35
0.027 org Mandor @ Rp. 261,642.48 7,064.35
JUMLAH 32,966.95 39,215.00 72,181.95
Overhead + Profit (10%) 7,218.20
Harga Satuan Pekerjaan 79,400.15
DIBULATKAN 79,400.00

1
SNI 1.000 m Memasang Besi L 50x50x3 mm
1
0.200 m Besi L 50x50x3 @ Rp. 38,333.33 7,666.67
35% x Harga pipa (Pengelasan) @ Rp. 38,333.33 13,416.67
0.090 org Tukang Las @ Rp. 209,313.98 18,838.26
0.054 org Pekerja @ Rp. 130,821.24 7,064.35
0.027 org Mandor @ Rp. 261,642.48 7,064.35
JUMLAH 32,966.95 21,083.33 54,050.29
Overhead + Profit (10%) 5,405.03
Harga Satuan Pekerjaan 59,455.31
DIBULATKAN 59,455.00

1.000 m2 Memasang Kawat Duri


6.177 m1 Kawat Duri @ Rp. 2,530.00 15,627.81
1.000 m1 Besi L 40x40x3 @ Rp. 28,750.00 28,750.00
1.670 org Tukang @ Rp. 209,313.98 349,554.35
0.167 org Kep. Tukang @ Rp. 235,478.23 39,324.86
1.670 org Pekerja @ Rp. 130,821.24 218,471.47
0.083 org Mandor @ Rp. 261,642.48 21,716.33
JUMLAH 629,067.01 44,377.81 673,444.82
Overhead + Profit (10%) 67,344.48
Harga Satuan Pekerjaan 740,789.31
DIBULATKAN 740,789.00

PEKERJAAN KUNCI DAN KACA

6.1 1.000 bh Pasang kunci tanam antik


1.000 bh Kunci tanam antik @ Rp. 253,000.00 253,000.00
0.600 OH Tukang kayu @ Rp. 209,313.98 125,588.39
0.060 OH Kepala tukang kayu @ Rp. 235,478.23 14,128.69
0.060 OH Pekerja @ Rp. 130,821.24 7,849.27
0.003 OH Mandor @ Rp. 261,642.48 784.93
JUMLAH 148,351.29 253,000.00 401,351.29
Overhead + Profit (10%) 40,135.13
Harga Satuan Pekerjaan 441,486.41
DIBULATKAN 441,486.00

6.2 1.000 bh Pasang kunci tanam biasa


1.000 bh Kunci tanam biasa @ Rp. 149,500.00 149,500.00
0.500 OH Tukang kayu @ Rp. 209,313.98 104,656.99
0.010 OH Kepala tukang kayu @ Rp. 235,478.23 2,354.78
0.010 OH Pekerja @ Rp. 130,821.24 1,308.21
0.005 OH Mandor @ Rp. 261,642.48 1,308.21
JUMLAH 109,628.20 149,500.00 259,128.20
Overhead + Profit (10%) 25,912.82
Harga Satuan Pekerjaan 285,041.02
DIBULATKAN 285,041.00
ANALISA SATUAN PEKERJAAN KAYU DAN ALUMINIUM
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)

6.3 1.000 bh Pasang kunci tanam kamar mandi


1.000 bh Kunci tanam kamar mandi @ Rp. 97,750.00 97,750.00
0.500 OH Tukang kayu @ Rp. 209,313.98 104,656.99
0.005 OH Kepala tukang kayu @ Rp. 235,478.23 1,177.39
0.005 OH Pekerja @ Rp. 130,821.24 654.11
0.003 OH Mandor @ Rp. 261,642.48 654.11
JUMLAH 107,142.60 97,750.00 204,892.60
Overhead + Profit (10%) 20,489.26
Harga Satuan Pekerjaan 225,381.86
DIBULATKAN 225,381.00

6.4 1.000 bh Pasang kunci tanam silinder


1.000 bh Kunci silinder @ Rp. 97,750.00 97,750.00
0.500 OH Tukang kayu @ Rp. 209,313.98 104,656.99
0.005 OH Kepala tukang kayu @ Rp. 235,478.23 1,177.39
0.005 OH Pekerja @ Rp. 130,821.24 654.11
0.003 OH Mandor @ Rp. 261,642.48 654.11
JUMLAH 107,142.60 97,750.00 204,892.60
Overhead + Profit (10%) 20,489.26
Harga Satuan Pekerjaan 225,381.86
DIBULATKAN 225,381.00

6.5 1.000 bh Pasang engsel pintu


1.000 bh Engsel pintu @ Rp. 34,500.00 34,500.00
0.150 OH Tukang kayu @ Rp. 209,313.98 31,397.10
0.015 OH Kepala tukang kayu @ Rp. 235,478.23 3,532.17
0.015 OH Pekerja @ Rp. 130,821.24 1,962.32
0.001 OH Mandor @ Rp. 261,642.48 196.23
JUMLAH 37,087.82 34,500.00 71,587.82
Overhead + Profit (10%) 7,158.78
Harga Satuan Pekerjaan 78,746.60
DIBULATKAN 78,746.00

6.6 1.000 bh Pasang engsel jendela kupu-kupu


1.000 bh Engsel jendela @ Rp. 23,000.00 23,000.00
0.100 OH Tukang kayu @ Rp. 209,313.98 20,931.40
0.010 OH Kepala tukang kayu @ Rp. 235,478.23 2,354.78
0.010 OH Pekerja @ Rp. 130,821.24 1,308.21
0.005 OH Mandor @ Rp. 261,642.48 1,308.21
JUMLAH 25,902.61 23,000.00 48,902.61
Overhead + Profit (10%) 4,890.26
Harga Satuan Pekerjaan 53,792.87
DIBULATKAN 53,792.00

6.7 1.000 bh Pasang engsel angin


1.000 bh Engsel angin @ Rp. #REF! #REF!
0.200 OH Tukang kayu @ Rp. #REF! #REF!
0.020 OH Kepala tukang kayu @ Rp. #REF! #REF!
0.020 OH Pekerja @ Rp. #REF! #REF!
0.010 OH Mandor @ Rp. #REF! #REF!
JUMLAH #REF! #REF! #REF!
DIBULATKAN #REF! #REF! #REF!

6.9 1.000 bh Pasang kait angin


1.000 bh Kait angin @ Rp. 23,000.00 23,000.00
0.150 OH Tukang kayu @ Rp. 209,313.98 31,397.10
0.015 OH Kepala tukang kayu @ Rp. 235,478.23 3,532.17
0.015 OH Pekerja @ Rp. 130,821.24 1,962.32
0.001 OH Mandor @ Rp. 261,642.48 196.23
JUMLAH 37,087.82 23,000.00 60,087.82
Overhead + Profit (10%) 6,008.78
Harga Satuan Pekerjaan 66,096.60
DIBULATKAN 66,096.00
ANALISA SATUAN PEKERJAAN KAYU DAN ALUMINIUM
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)

1.000 bh Pasang Tarikan jendela


1.000 bh Tarikan jendela @ Rp. 23,000.00 23,000.00
0.150 OH Tukang kayu @ Rp. 209,313.98 31,397.10
0.015 OH Kepala tukang kayu @ Rp. 235,478.23 3,532.17
0.015 OH Pekerja @ Rp. 130,821.24 1,962.32
0.001 OH Mandor @ Rp. 261,642.48 196.23
JUMLAH 37,087.82 23,000.00 60,087.82
Overhead + Profit (10%) 6,008.78
Harga Satuan Pekerjaan 66,096.60
DIBULATKAN 66,096.00

6.10 1.000 bh Pasang door closer


1.000 bh Door closer @ Rp. 150,000.00 150,000.00
0.500 OH Tukang kayu @ Rp. 30,000.00 15,000.00
0.050 OH Kepala tukang kayu @ Rp. 32,500.00 1,625.00
0.050 OH Pekerja @ Rp. 20,000.00 1,000.00
0.003 OH Mandor @ Rp. 32,500.00 81.25
JUMLAH #REF! #REF! #REF!
DIBULATKAN #REF! #REF! #REF!

6.11 1.000 bh Pasang kunci grendel pintu


1.000 bh grendel pintu @ Rp. 20,125.00 20,125.00
0.200 OH Tukang kayu @ Rp. 209,313.98 41,862.80
0.020 OH Kepala tukang kayu @ Rp. 235,478.23 4,709.56
0.020 OH Pekerja @ Rp. 130,821.24 2,616.42
0.001 OH Mandor @ Rp. 261,642.48 261.64
JUMLAH 49,450.43 20,125.00 69,575.43
Overhead + Profit (10%) 6,957.54
Harga Satuan Pekerjaan 76,532.97
DIBULATKAN 76,532.00

6.11 1.000 bh Pasang kunci grendel jendela


1.000 bh grendel jendela @ Rp. 17,250.00 17,250.00
0.200 OH Tukang kayu @ Rp. 209,313.98 41,862.80
0.020 OH Kepala tukang kayu @ Rp. 235,478.23 4,709.56
0.020 OH Pekerja @ Rp. 130,821.24 2,616.42
0.001 OH Mandor @ Rp. 261,642.48 261.64
JUMLAH 49,450.43 17,250.00 66,700.43
Overhead + Profit (10%) 6,670.04
Harga Satuan Pekerjaan 73,370.47
DIBULATKAN 73,370.00

6.12 1.000 bh Pasang pegangan pintu / door holder


1.000 bh Door holder @ Rp. 15,000.00 15,000.00
0.500 OH Tukang kayu @ Rp. 30,000.00 15,000.00
0.050 OH Kepala tukang kayu @ Rp. 32,500.00 1,625.00
0.050 OH Pekerja @ Rp. 20,000.00 1,000.00
0.003 OH Mandor @ Rp. 32,500.00 81.25
JUMLAH #REF! #REF! #REF!
DIBULATKAN #REF! #REF! #REF!

6.13 1.000 bh Pasang door stop


1.000 bh Door stop @ Rp. 15,000.00 15,000.00
0.100 OH Tukang kayu @ Rp. 30,000.00 3,000.00
0.010 OH Kepala tukang kayu @ Rp. 32,500.00 325.00
0.010 OH Pekerja @ Rp. 20,000.00 200.00
0.001 OH Mandor @ Rp. 32,500.00 16.25
JUMLAH #REF! #REF! #REF!
DIBULATKAN #REF! #REF! #REF!

6.14 1.000 bh Pasang rel pintu dorong


1.000 bh Rel pintu dorong @ Rp. 200,000.00 200,000.00
0.600 OH Tukang kayu @ Rp. 30,000.00 18,000.00
ANALISA SATUAN PEKERJAAN KAYU DAN ALUMINIUM
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
0.060 OH Kepala tukang kayu @ Rp. 32,500.00 1,950.00
0.060 OH Pekerja @ Rp. 20,000.00 1,200.00
0.003 OH Mandor @ Rp. 32,500.00 97.50
JUMLAH #REF! #REF! #REF!
DIBULATKAN #REF! #REF! #REF!

6.16 1.000 m2 Pasang kaca, tebal 3 mm


1.100 m2 Kaca polos @ Rp. #REF! #REF!
0.150 OH Tukang kayu @ Rp. #REF! #REF!
0.015 OH Kepala tukang kayu @ Rp. #REF! #REF!
0.015 OH Pekerja @ Rp. #REF! #REF!
0.001 OH Mandor @ Rp. #REF! #REF!
JUMLAH #REF! #REF! #REF!
DIBULATKAN #REF! #REF! #REF!

6.17 1.000 m2 Pasang kaca, tebal 5 mm


1.100 m2 Kaca polos @ Rp. 251,275.00 276,402.50
0.150 OH Tukang kayu @ Rp. 209,313.98 31,397.10
0.015 OH Kepala tukang kayu @ Rp. 235,478.23 3,532.17
0.015 OH Pekerja @ Rp. 130,821.24 1,962.32
0.001 OH Mandor @ Rp. 261,642.48 196.23
JUMLAH 37,087.82 276,402.50 313,490.32
Overhead + Profit (10%) 31,349.03
Harga Satuan Pekerjaan 344,839.35
DIBULATKAN 344,839.00

6.17 1.000 m2 Pasang kaca reiben, tebal 5 mm


1.100 m2 Kaca reiben @ Rp. 290,950.00 320,045.00
0.150 OH Tukang kayu @ Rp. 209,313.98 31,397.10
0.015 OH Kepala tukang kayu @ Rp. 235,478.23 3,532.17
0.015 OH Pekerja @ Rp. 130,821.24 1,962.32
0.001 OH Mandor @ Rp. 261,642.48 196.23
JUMLAH 37,087.82 320,045.00 357,132.82
Overhead + Profit (10%) 35,713.28
Harga Satuan Pekerjaan 392,846.10
DIBULATKAN 392,846.00

6.20 1.000 m2 Pasang kaca cermin, tebal 5 mm


1.100 m2 Kaca cermin @ Rp. 120,000.00 132,000.00
0.150 OH Tukang kayu @ Rp. 30,000.00 4,500.00
0.015 OH Kepala tukang kayu @ Rp. 32,500.00 487.50
0.015 OH Pekerja @ Rp. 20,000.00 300.00
0.001 OH Mandor @ Rp. 32,500.00 24.38
JUMLAH 5,311.88 132,000.00 137,311.88
Overhead + Profit (10%) 13,731.19
Harga Satuan Pekerjaan 151,043.06
DIBULATKAN 151,043.00

6.24 1.000 m2 Pasang kaca patri, tebal 5 mm


1.100 m2 Kaca patri @ Rp. 0.00
0.150 OH Tukang kayu @ Rp. 209,313.98 31,397.10
0.015 OH Kepala tukang kayu @ Rp. 235,478.23 3,532.17
0.015 OH Pekerja @ Rp. 130,821.24 1,962.32
0.001 OH Mandor @ Rp. 261,642.48 196.23
JUMLAH 37,087.82 0.00 37,087.82
Overhead + Profit (10%) 3,708.78
Harga Satuan Pekerjaan 40,796.60
DIBULATKAN 40,796.00

6.17 1.000 m1 Pasang kusen alumunium


1.100 m1 Kusen alumunium @ Rp. 120,000.00 132,000.00
0.150 x Harga kusen (Perlengkapan) @ Rp. 120,000.00 18,000.00
0.150 oh Tukang alumunium @ Rp. 209,313.98 31,397.10
0.015 oh Kepala tukang @ Rp. 235,478.23 3,532.17
ANALISA SATUAN PEKERJAAN KAYU DAN ALUMINIUM
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
0.015 oh Pekerja @ Rp. 130,821.24 1,962.32
0.001 oh Mandor @ Rp. 261,642.48 196.23
JUMLAH 37,087.82 150,000.00 187,087.82
Overhead + Profit (10%) 18,708.78
Harga Satuan Pekerjaan 205,796.60
DIBULATKAN 205,796.00
ANALISA SATUAN PEKERJAAN PENGECATAN
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)

PEKERJAAN CAT-CATAN

SNI 1.0000 m2 Pengecatan bidang kayu lama


6.7 0.1500 kg Plamir @ Rp. 40,250.00 6,037.50
0.1700 kg Cat dasar @ Rp. 57,500.00 9,775.00
0.1700 kg Cat penutup @ Rp. 57,500.00 9,775.00
0.0750 org Tukang cat @ Rp. 209,313.98 15,698.55
0.0075 org Kepala tukang cat @ Rp. 235,478.23 1,766.09
0.0700 org Pekerja @ Rp. 130,821.24 9,157.49
0.0025 org Mandor @ Rp. 261,642.48 654.11
JUMLAH 27,276.23 25,587.50 52,863.73
Overhead + Profit (10%) 5,286.37
Harga Satuan Pekerjaan 58,150.10
DIBULATKAN 58,150.00

SNI 1.0000 m2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 2 lapis cat penutup
6.8 0.2000 kg Cat meni @ Rp. 40,250.00 8,050.00
0.1500 kg Plamir @ Rp. 40,250.00 6,037.50
0.1700 kg Cat dasar @ Rp. 57,500.00 9,775.00
0.2600 kg Cat penutup @ Rp. 57,500.00 14,950.00
0.0900 org Tukang cat @ Rp. 209,313.98 18,838.26
0.0060 org Kepala tukang cat @ Rp. 235,478.23 1,412.87
0.0700 org Pekerja @ Rp. 130,821.24 9,157.49
0.0025 org Mandor @ Rp. 261,642.48 654.11
JUMLAH 30,062.72 38,812.50 68,875.22
Overhead + Profit (10%) 6,887.52
Harga Satuan Pekerjaan 75,762.74
DIBULATKAN 75,762.00

SNI 1.0000 m2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 3 lapis cat penutup
6.9 0.2000 kg Cat meni @ Rp. 40,250.00 8,050.00
0.1500 kg Plamir @ Rp. 40,250.00 6,037.50
0.1700 kg Cat dasar @ Rp. 57,500.00 9,775.00
0.3500 kg Cat penutup @ Rp. 57,500.00 20,125.00
0.1050 org Tukang cat @ Rp. 209,313.98 21,977.97
0.0040 org Kepala tukang cat @ Rp. 235,478.23 941.91
0.0700 org Pekerja @ Rp. 130,821.24 9,157.49
0.0025 org Mandor @ Rp. 261,642.48 654.11
JUMLAH 32,731.47 43,987.50 76,718.97
Overhead + Profit (10%) 7,671.90
Harga Satuan Pekerjaan 84,390.87
DIBULATKAN 84,390.00

SNI 1.0000 m2 Pelaburan bidang kayu dengan politur


6.11 0.1500 ltr Politur @ Rp. 69,000.00 10,350.00
0.3720 ltr Politur jadi @ Rp. 69,000.00 25,668.00
2.0000 lbr Amplas @ Rp. 5,750.00 11,500.00
0.0600 org Tukang cat @ Rp. 209,313.98 12,558.84
0.0160 org Kepala tukang cat @ Rp. 235,478.23 3,767.65
0.0025 org Mandor @ Rp. 261,642.48 654.11
JUMLAH 16,980.60 47,518.00 64,498.60
Overhead + Profit (10%) 6,449.86
Harga Satuan Pekerjaan 70,948.46
DIBULATKAN 70,948.00
ANALISA SATUAN PEKERJAAN PENGECATAN
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)

SNI 1.0000 m2 Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
6.14 0.1000 kg Plamir tembok @ Rp. 14,375.00 1,437.50
0.1000 kg Cat dasar @ Rp. 20,700.00 2,070.00
0.2600 kg Cat penutup 2 x @ Rp. 26,162.50 6,802.25
0.0630 org Tukang cat @ Rp. 209,313.98 13,186.78
0.0063 org Kepala tukang cat @ Rp. 235,478.23 1,483.51
0.0200 org Pekerja @ Rp. 130,821.24 2,616.42
0.0025 org Mandor @ Rp. 261,642.48 654.11
JUMLAH 17,940.82 10,309.75 28,250.57
Overhead + Profit (10%) 2,825.06
Harga Satuan Pekerjaan 31,075.63
DIBULATKAN 31,075.00

SNI 1.0000 m2 Pengecatan tembok tidak terlindung dari panas dan hujan
6.14 0.1000 kg Cat alkali resisting primer @ Rp. 26,162.50 2,616.25
0.3600 kg Cat ICI Weathershield @ Rp. 138,000.00 49,680.00
0.0630 org Tukang cat @ Rp. 209,313.98 13,186.78
0.0063 org Kepala tukang cat @ Rp. 235,478.23 1,483.51
0.0200 org Pekerja @ Rp. 130,821.24 2,616.42
0.0025 org Mandor @ Rp. 261,642.48 654.11
JUMLAH 17,940.82 52,296.25 70,237.07
Overhead + Profit (10%) 7,023.71
Harga Satuan Pekerjaan 77,260.78
DIBULATKAN 77,260.00

SNI 1.0000 m2 Pengecatan plafond baru (1 lapis plamir, 1 lapis cat dasar, 1 lapis cat penutup)
6.14 0.1100 kg Plamir tembok @ Rp. 14,375.00 1,581.25
0.1300 kg Cat tembok @ Rp. 13,225.00 1,719.25
0.3300 lbr Amplas @ Rp. 5,750.00 1,897.50
0.1000 org Tukang cat @ Rp. 209,313.98 20,931.40
0.0100 org Kepala tukang cat @ Rp. 235,478.23 2,354.78
0.0650 org Pekerja @ Rp. 130,821.24 8,503.38
0.0050 org Mandor @ Rp. 261,642.48 1,308.21
JUMLAH 33,097.77 5,198.00 38,295.77
Overhead + Profit (10%) 3,829.58
Harga Satuan Pekerjaan 42,125.35
DIBULATKAN 42,125.00
ANALISA SATUAN PEKERJAAN SANITAIR
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)

PEKERJAAN SANITASI
SNI 1.0000 m1 Memasang pipa galvanis diameter 1/2"
1.2000 m1 Pipa galvanis @ Rp. 28,750.00 34,500.00
6.19 35% x Harga pipa (Perlengkapan) @ Rp. 28,750.00 10,062.50
0.0900 org Tukang batu @ Rp. 209,313.98 18,838.26
0.0090 org Kepala tukang batu @ Rp. 235,478.23 2,119.30
0.0540 org Pekerja @ Rp. 130,821.24 7,064.35
0.0270 org Mandor @ Rp. 261,642.48 7,064.35
JUMLAH 35,086.26 44,562.50 79,648.76
Overhead + Profit (10%) 7,964.88
Harga Satuan Pekerjaan 87,613.63
DIBULATKAN 87,613.00

SNI 1.0000 m1 Memasang pipa galvanis diameter 3/4"


1.2000 m1 Pipa galvanis @ Rp. 40,250.00 48,300.00
6.20 35% x Harga pipa (Perlengkapan) @ Rp. 40,250.00 14,087.50
0.0900 org Tukang batu @ Rp. 209,313.98 18,838.26
0.0090 org Kepala tukang batu @ Rp. 235,478.23 2,119.30
0.0540 org Pekerja @ Rp. 130,821.24 7,064.35
0.0270 org Mandor @ Rp. 261,642.48 7,064.35
JUMLAH 35,086.26 62,387.50 97,473.76
Overhead + Profit (10%) 9,747.38
Harga Satuan Pekerjaan 107,221.13
DIBULATKAN 107,221.00

SNI 1.0000 m1 Memasang pipa galvanis diameter 1"


1.2000 m1 Pipa galvanis @ Rp. 64,400.00 77,280.00
6.21 35% x Harga pipa (Perlengkapan) @ Rp. 64,400.00 22,540.00
0.0900 org Tukang batu @ Rp. 209,313.98 18,838.26
0.0090 org Kepala tukang batu @ Rp. 235,478.23 2,119.30
0.0540 org Pekerja @ Rp. 130,821.24 7,064.35
0.0270 org Mandor @ Rp. 261,642.48 7,064.35
JUMLAH 35,086.26 99,820.00 134,906.26
Overhead + Profit (10%) 13,490.63
Harga Satuan Pekerjaan 148,396.88
DIBULATKAN 148,396.00

SNI 1.0000 m1 Memasang pipa galvanis diameter 1 1/2"


1.2000 m1 Pipa galvanis @ Rp. 89,125.00 106,950.00
6.22 35% x Harga pipa (Perlengkapan) @ Rp. 89,125.00 31,193.75
0.1800 org Tukang batu @ Rp. 209,313.98 37,676.52
0.0180 org Kepala tukang batu @ Rp. 235,478.23 4,238.61
0.1080 org Pekerja @ Rp. 130,821.24 14,128.69
0.0054 org Mandor @ Rp. 261,642.48 1,412.87
JUMLAH 57,456.69 138,143.75 195,600.44
Overhead + Profit (10%) 19,560.04
Harga Satuan Pekerjaan 215,160.48
DIBULATKAN 215,160.00

SNI 1.0000 m1 Memasang pipa PVC tipe AW diameter 1/2"


1.2000 m1 Pipa PVC @ Rp. 23,000.00 27,600.00
6.25 35% x Harga pipa (Perlengkapan) @ Rp. 23,000.00 8,050.00
0.0600 org Tukang batu @ Rp. 209,313.98 12,558.84
0.0060 org Kepala tukang batu @ Rp. 235,478.23 1,412.87
0.0360 org Pekerja @ Rp. 130,821.24 4,709.56
0.0018 org Mandor @ Rp. 261,642.48 470.96
JUMLAH 19,152.23 35,650.00 54,802.23
Overhead + Profit (10%) 5,480.22
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
Harga Satuan Pekerjaan 60,282.45
DIBULATKAN 60,282.00

SNI 1.0000 m1 Memasang pipa PVC tipe AW diameter 3/4"


1.2000 m1 Pipa PVC @ Rp. 40,250.00 48,300.00
6.26 35% x Harga pipa (Perlengkapan) @ Rp. 40,250.00 14,087.50
0.0600 org Tukang batu @ Rp. 209,313.98 12,558.84
0.0060 org Kepala tukang batu @ Rp. 235,478.23 1,412.87
0.0360 org Pekerja @ Rp. 130,821.24 4,709.56
0.0018 org Mandor @ Rp. 261,642.48 470.96
JUMLAH 19,152.23 62,387.50 81,539.73
Overhead + Profit (10%) 8,153.97
Harga Satuan Pekerjaan 89,693.70
DIBULATKAN 89,693.00

SNI 1.0000 m1 Memasang pipa PVC tipe AW diameter 1"


1.2000 m1 Pipa PVC @ Rp. 74,750.00 89,700.00
6.27 35% x Harga pipa (Perlengkapan) @ Rp. 74,750.00 26,162.50
0.0600 org Tukang batu @ Rp. 209,313.98 12,558.84
0.0060 org Kepala tukang batu @ Rp. 235,478.23 1,412.87
0.0360 org Pekerja @ Rp. 130,821.24 4,709.56
0.0018 org Mandor @ Rp. 261,642.48 470.96
JUMLAH 19,152.23 115,862.50 135,014.73
Overhead + Profit (10%) 13,501.47
Harga Satuan Pekerjaan 148,516.20
DIBULATKAN 148,516.00

SNI 1.0000 m1 Memasang pipa PVC tipe AW diameter 1 1/2"


1.2000 m1 Pipa PVC @ Rp. 189,750.00 227,700.00
6.28 35% x Harga pipa (Perlengkapan) @ Rp. 189,750.00 66,412.50
0.0600 org Tukang batu @ Rp. 209,313.98 12,558.84
0.0060 org Kepala tukang batu @ Rp. 235,478.23 1,412.87
0.0360 org Pekerja @ Rp. 130,821.24 4,709.56
0.0018 org Mandor @ Rp. 261,642.48 470.96
JUMLAH 19,152.23 294,112.50 313,264.73
Overhead + Profit (10%) 31,326.47
Harga Satuan Pekerjaan 344,591.20
DIBULATKAN 344,591.00

SNI 1.0000 m1 Memasang pipa PVC tipe AW diameter 2"


1.2000 m1 Pipa PVC @ Rp. 270,250.00 324,300.00
6.29 35% x Harga pipa (Perlengkapan) @ Rp. 270,250.00 94,587.50
0.0900 org Tukang batu @ Rp. 209,313.98 18,838.26
0.0090 org Kepala tukang batu @ Rp. 235,478.23 2,119.30
0.0544 org Pekerja @ Rp. 130,821.24 7,116.68
0.0027 org Mandor @ Rp. 261,642.48 706.43
JUMLAH 28,780.67 418,887.50 447,668.17
Overhead + Profit (10%) 44,766.82
Harga Satuan Pekerjaan 492,434.99
DIBULATKAN 492,434.00

SNI 1.0000 m1 Memasang pipa PVC tipe AW diameter 2 1/2"


1.2000 m1 Pipa PVC @ Rp. 270,250.00 324,300.00
6.30 35% x Harga pipa (Perlengkapan) @ Rp. 270,250.00 94,587.50
0.0900 org Tukang batu @ Rp. 209,313.98 18,838.26
0.0090 org Kepala tukang batu @ Rp. 235,478.23 2,119.30
0.0544 org Pekerja @ Rp. 130,821.24 7,116.68
0.0027 org Mandor @ Rp. 261,642.48 706.43
JUMLAH 28,780.67 418,887.50 447,668.17
Overhead + Profit (10%) 44,766.82
Harga Satuan Pekerjaan 492,434.99
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
DIBULATKAN 492,434.00

SNI 1.0000 m1 Memasang pipa PVC tipe AW diameter 3"


1.2000 m1 Pipa PVC @ Rp. 4,600.00 5,520.00
6.31 35% x Harga pipa (Perlengkapan) @ Rp. 4,600.00 1,610.00
0.1350 org Tukang batu @ Rp. 209,313.98 28,257.39
0.0135 org Kepala tukang batu @ Rp. 235,478.23 3,178.96
0.0810 org Pekerja @ Rp. 130,821.24 10,596.52
0.0410 org Mandor @ Rp. 261,642.48 10,727.34
JUMLAH 52,760.21 7,130.00 59,890.21
Overhead + Profit (10%) 5,989.02
Harga Satuan Pekerjaan 65,879.23
DIBULATKAN 65,879.00

SNI 1.0000 m1 Memasang pipa PVC tipe AW diameter 4"


1.2000 m1 Pipa PVC @ Rp. 5,750.00 6,900.00
6.32 35% x Harga pipa (Perlengkapan) @ Rp. 5,750.00 2,012.50
0.1350 org Tukang batu @ Rp. 209,313.98 28,257.39
0.0135 org Kepala tukang batu @ Rp. 235,478.23 3,178.96
0.0810 org Pekerja @ Rp. 130,821.24 10,596.52
0.0410 org Mandor @ Rp. 261,642.48 10,727.34
JUMLAH 52,760.21 8,912.50 61,672.71
Overhead + Profit (10%) 6,167.27
Harga Satuan Pekerjaan 67,839.98
DIBULATKAN 67,839.00

SNI 1.0000 bh Memasang kran diameter 3/4" atau 1/2"


1.0000 bh Kran air @ Rp. 40,250.00 40,250.00
6.35 0.0250 bh Seal tape @ Rp. 7,100.00 177.50
0.1000 org Tukang batu @ Rp. 209,313.98 20,931.40
0.0100 org Kepala tukang batu @ Rp. 235,478.23 2,354.78
0.0100 org Pekerja @ Rp. 130,821.24 1,308.21
0.0050 org Mandor @ Rp. 261,642.48 1,308.21
JUMLAH 25,902.61 40,427.50 66,330.11
Overhead + Profit (10%) 6,633.01
Harga Satuan Pekerjaan 72,963.12
DIBULATKAN 72,963.00

1.0000 m1 Memasang talang Paralon Kotak


1.2000 m1 Talang Paralon Kotak @ Rp. 27,312.50 32,775.00
35% x Harga pipa (Perlengkapan) @ Rp. 27,312.50 9,559.38
0.1350 org Tukang batu @ Rp. 209,313.98 28,257.39
0.0135 org Kepala tukang batu @ Rp. 235,478.23 3,178.96
0.0810 org Pekerja @ Rp. 130,821.24 10,596.52
0.0410 org Mandor @ Rp. 261,642.48 10,727.34
JUMLAH 52,760.21 42,334.38 95,094.58
Overhead + Profit (10%) 9,509.46
Harga Satuan Pekerjaan 104,604.04
DIBULATKAN 104,604.00

SNI 1.0000 bh Memasang floor drain


1.0000 bh Floor drain @ Rp. 40,392.86 40,392.86
6.35 0.1000 org Tukang batu @ Rp. 209,313.98 20,931.40
0.0100 org Kepala tukang batu @ Rp. 235,478.23 2,354.78
0.0100 org Pekerja @ Rp. 130,821.24 1,308.21
0.0050 org Mandor @ Rp. 261,642.48 1,308.21
JUMLAH 25,902.61 40,392.86 66,295.47
Overhead + Profit (10%) 6,629.55
Harga Satuan Pekerjaan 72,925.01
DIBULATKAN 72,925.00
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)

1.0000 UNIT SEPTIC TANK DAN RESAPAN UK. 1.5x2x1.5 M


4.5000 M3 Galian Tanah @ Rp. 69,073.00 310,828.50
12.7500 M2 Pas. Batu Tela @ Rp. 211,000.00 2,690,250.00
23.8700 Kg Pembesian @ Rp. 29,030.00 692,946.10
0.3000 M3 Cor Beton Camp. 1 : 2 : 3 @ Rp. 1,770,601.00 531,180.30
3.0000 M2 Papan Bekisting @ Rp. 278,461.00 835,383.00
JUMLAH 5,060,587.90
DIBULATKAN 5,060,587.00