ACTION PLAN

PAKET PRESERVASI JALAN KABIH - TAPEN

JULI AGUSTUS SEPTEMBER OKTOBER NOVEMBER DESEMBER


Keterangan
Durasi 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
No Tahapan Kegiatan
(Minggu) 13-Jul-23 22-Jul-23 29-Jul-23 5-Aug-23 12-Aug-23 19-Aug-23 26-Aug-23 2-Sep-23 9-Sep-23 16-Sep-23 23-Sep-23 30-Sep-23 7-Oct-23 14-Oct-23 21-Oct-23 28-Oct-23 4-Nov-23 11-Nov-23 18-Nov-23 25-Nov-23 2-Dec-23 9-Dec-23 16-Dec-23 23-Dec-23 30-Dec-23
21-Jul-23 28-Jul-23 4-Aug-23 11-Aug-23 18-Aug-23 25-Aug-23 1-Sep-23 8-Sep-23 15-Sep-23 22-Sep-23 29-Sep-23 6-Oct-23 13-Oct-23 20-Oct-23 27-Oct-23 3-Nov-23 10-Nov-23 17-Nov-23 24-Nov-23 1-Dec-23 8-Dec-23 15-Dec-23 22-Dec-23 29-Dec-23 31-Dec-23
DIVISI 3. PEKERJAAN TANAH DAN
GEOSINTETIK
1 Galian Biasa 18

DIVISI 5. PERKERASAN BERBUTIR


DAN PERKERASAN BETON SEMEN
1 Lapis Pondasi Agregat Kelas A 19
2 Perkerasan Beton Semen 13
Perkerasan Beton Semen dengan
Anyaman Tulangan Tunggal
3 (Wiremesh M8-150) 16
4 Lapis Pondasi Bawah Beton Kurus 17

DIVISI 7. STRUKTUR
1 Beton Struktur fc' 30 Mpa 2
2 Pasangan Batu 19
Jumlah Hari Pelaksanaan 21 Minggu

KETERANGAN
Menambahkan tim pekerja dan peralatan dengan asumsi volume beton 225 M3 per hari

ACTION PLAN
PRESERVASI JALAN
PLOSO-SUMBERGONDANG

JULI AGUSTUS SEPTEMBER OKTOBER NOVEMBER DESEMBER


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
No Tahapan Kegiatan Durasi Keterangan
13-Jul-23 22-Jul-23 29-Jul-23 5-Aug-23 12-Aug-23 19-Aug-23 26-Aug-23 2-Sep-23 9-Sep-23 16-Sep-23 23-Sep-23 30-Sep-23 7-Oct-23 14-Oct-23 21-Oct-23 28-Oct-23 4-Nov-23 11-Nov-23 18-Nov-23 25-Nov-23 2-Dec-23 9-Dec-23 16-Dec-23 23-Dec-23 30-Dec-23
21-Jul-23 28-Jul-23 4-Aug-23 11-Aug-23 18-Aug-23 25-Aug-23 1-Sep-23 8-Sep-23 15-Sep-23 22-Sep-23 29-Sep-23 6-Oct-23 13-Oct-23 20-Oct-23 27-Oct-23 3-Nov-23 10-Nov-23 17-Nov-23 24-Nov-23 1-Dec-23 8-Dec-23 15-Dec-23 22-Dec-23 29-Dec-23 31-Dec-23

DIVISI 3. PEKERJAAN TANAH DAN


GEOSINTETIK
1 Galian Biasa 17 Minggu

DIVISI 5. PERKERASAN BERBUTIR


DAN PERKERASAN BETON SEMEN
1 Lapis Pondasi Agregat Kelas A 13 Minggu
2 Perkerasan Beton Semen 12 Minggu
Perkerasan Beton Semen Dengan
3 Anyaman Tulangan Tunggal 16 Minggu
(Wiremesh M8-150)
4 Lapis Pondasi bawah Beton Kurus 17 Minggu

DIVISI 7. STRUKTUR
1 Beton struktur, fc’30 MPa 2 Minggu
2 Pasangan Batu 21 Minggu

Jumlah Hari Pelaksanaan 20 Minggu

KETERANGAN
Menambahkan tim pekerja dan peralatan dgn asumsi volume beton 110,835 m3 per hari