Anda di halaman 1dari 2

PT.

BASUKI RAHMANTA PUTRA


GENERAL CONTRACTOR
Yodya Tower Lt. 10 Jl. DI Panjaitan Kav. 8, Cipinang Cempedak, Jakarta Timur

REKAPITULASI OPERASIONAL ALAT RENTAL CV. REJEKI JAYA MAKMUR


A. MOBILISASI EXCAVATOR KOMATSU PC - 195 (TISON) TIBA DI BENDUNGAN AMERORO
- TANGGAL TIBA : SABTU, 23 AGUSTUS 2023

B. RINCIAN BIAYA EXCAVATOR KOMATSU PC - 195 (TISON)


- MOBILISASI ALAT & SEWA DP : Rp 25,000,000

- BIAYA UANG MAKAN & LEMBURAN : Rp 35,175,000

TOTAL : Rp 60,175,000

C. REKAPITULASI JAM-JAMAN EXCAVATOR KOMATSU PC - 195 (TISON)


TANGGAL
NAMA ALAT JAM BEKERJA
24-Aug 25-Aug 26-Aug 27-Aug 28-Aug 29-Aug 30-Aug 31-Aug 1-Sep 2-Sep 3-Sep 4-Sep 5-Sep 6-Sep 7-Sep 8-Sep 9-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep 18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep 25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep 1-Oct 2-Oct 3-Oct 4-Oct 5-Oct 6-Oct 7-Oct 8-Oct

EXCAVATOR PC - 195 KANTOR 8 7 8 0 0 0 0 8 7 8 0 0 4 8 8 7 8 0 8 0 8 8 7 0 0 8 8 8 8 5 0 0 3 0 0 0 7 4 0 8 8 4 0 0 0 0

TOTAL HARI BEKERJA : 46 HARI

TOTAL JAM PADA KONTRAK 200 JAM

TOTAL JAM BEKERJA S/D SAAT INI : 183 JAM

SISA JAM-JAMAN PADA KONTRAK : 17 JAM

SISA HARI BEKERJA : 2 HARI


PT. BASUKI RAHMANTA PUTRA
GENERAL CONTRACTOR
Yodya Tower Lt. 10 Jl. DI Panjaitan Kav. 8, Cipinang Cempedak, Jakarta Timur

REKAPITULASI OPERASIONAL ALAT RENTAL CV. REJEKI JAYA MAKMUR


A. MOBILISASI EXCAVATOR KOMATSU PC - 200 (HERMAN) TIBA DI BENDUNGAN AMERORO
- TANGGAL TIBA : MINGGU, 3 SEPTEMBER 2023

B. RINCIAN BIAYA EXCAVATOR KOMATSU PC - 200 (HERMAN)


- MOBILISASI ALAT & SEWA DP : Rp 25,000,000
- BIAYA UANG MAKAN & LEMBURAN : Rp 6,300,000
TOTAL : Rp 31,300,000

C. REKAPITULASI JAM-JAMAN EXCAVATOR KOMATSU PC - 200 (HERMAN)


TANGGAL
NAMA ALAT JAM BEKERJA
3-Sep 4-Sep 5-Sep 6-Sep 7-Sep 8-Sep 9-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep 18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep 25-Sep 26-Sep

EXCAVATOR PC - 200 KANTOR 0 4 0 0 7 8 8 0 0 4 6 8 8 8 0 1 0 0 0 0 0 0 4 6

TOTAL HARI BEKERJA : 24 HARI

TOTAL JAM PADA KONTRAK 200 JAM

TOTAL JAM BEKERJA S/D SAAT INI : 72 JAM

SISA JAM-JAMAN PADA KONTRAK : 128 JAM

SISA HARI BEKERJA : 16 HARI