RAB SEKOLAH ISLAM TERPADU AL-AZHAR REGOL BANDUNG 2023 (AutoRecovered)
RAB SEKOLAH ISLAM TERPADU AL-AZHAR REGOL BANDUNG 2023 (AutoRecovered)
C PEKERJAAN KONSTRUKSI
I PEKERJAAN PERSIAPAN Unit 1.00 Rp 312,750,000
II BANGUNAN MASJID Unit 1.00 Rp 3,209,773,602
III GEDUNG ADMINISTRASI Unit 1.00 Rp 18,116,419,823
IV GEDUNG SEKOLAH TK Unit 10.00 Rp 13,097,716,603
V GEDUNG SEKOLAH SD Unit 18.00 Rp 23,575,889,885
VI GEDUNG SEKOLAH SMP Unit 27.00 Rp 35,363,834,828
VII GEDUNG SEKOLAH SMA Unit 21.00 Rp 27,505,204,866
VIII GEDUNG LABORATORIUM Unit 6.00 Rp 53,578,773,618
XI GEDUNG PERPUSTAKAAN Unit 3.00 Rp 11,887,832,148
X GARDU PLN & R.GENSET Unit 1.00 Rp 457,647,463
XI RUMAH POMPA DAN MENARA AIR Unit 1.00 Rp 1,095,301,424
XII PEK.SITE DEVELOP INFRASTRUKTUR LANDSCAPE Unit 1.00 Rp 2,118,071,276
XII PEK.TOILET BERSAMA Unit 4.00 Rp 1,698,816,503
XIV GEDUNG SERBAGUNA Unit 1.00 Rp 7,404,795,984
XV TAMAN BERMAIN Unit 1.00 Rp 250,000,000
XVI LAP.SEPAK BOLA OUT DOOR Unit 1.00 Rp 1,086,793,000
XVII LAP.FUTSAL OUT DOOR Unit 2.00 Rp 552,261,854
XVIII LAP.BOLA BASKET OUT DOOR Unit 2.00 Rp 483,180,152
XIX LAP. BOLA VOLLY OUT DOOR Unit 2.00 Rp 83,277,300
SUB.JUMLAH Rp 201,311,882,875
JUMLAH A+B+C Rp 355,494,531,496
PPN 11 % Rp 39,104,398,465
JUMLAH Rp 394,598,929,961
DIBULATKAN Rp 394,598,929,000
Catatan :Estimasi Perhitungan RAB Berdasarkan Desai Gambar Kerja Sementara dan Dapat Berubah Sesuai Gambar Final
RENCANA ANGGARAN BIAYA
PROYEK : PERENCANAAN PEMBANGUNAN
LOKASI : GEDUNGSEKOLAH
BANDUNG
BANGUNAN : PERSIAPAN
TAHUN ANGGARAN :
I PEKERJAAN PERSIAPAN
Persiapan - 2
RENCANA ANGGARAN BIAYA
PROYEK : PERENCANAAN PEMBANGUNAN
LOKASI : GEDUNGSEKOLAH
BANDUNG
BANGUNAN : PERSIAPAN
TAHUN ANGGARAN :
b. Pemborong wajib menyediakan fasilitas MCK sesuai dengan keper- Ls 1.00 Rp 12,500,000.00 Rp 12,500,000.00
luan tenaga kerja yang penempatannya dikordinasikan dengan MK
Persiapan - 3
RENCANA ANGGARAN BIAYA
PROYEK : PERENCANAAN PEMBANGUNAN
LOKASI : GEDUNGSEKOLAH
BANDUNG
BANGUNAN : MASJID
TAHUN ANGGARAN :
II BANGUNAN MASJID
A Pekerjaan Pondasi
1 Pengukuran dan pasang bouwplank m1 130.00 Rp 45,000.00 Rp 5,850,000.00
2 Galian tanah pondasi m3 176.72 Rp 108,904.50 Rp 19,245,603.24
3 Urugan pasir urug m3 9.28 Rp 295,561.00 Rp 2,744,224.77
4 Beton lantai kerja m2 132.64 Rp 50,781.00 Rp 6,735,591.84
5 Beton poor m3 20.03 Rp 3,019,418.00 Rp 60,478,942.54
6 Beton sloof m3 49.60 Rp 5,050,715.00 Rp 250,515,464.00
7 Urugan tanah kembali m3 40.20 Rp 44,311.00 Rp 1,781,302.20
8 Buang tanah bekas galian (dalam area proyek) m3 136.52 Rp 81,663.00 Rp 11,148,632.76
Sub Jumlah Pekerjaan Pondasi Rp 358,499,761.35
B Pekerjaan Struktur
1 Beton kolom m3 39.66 Rp 4,830,070.00 Rp 191,560,576.20
2 Beton balok m3 22.69 Rp 7,119,312.00 Rp 161,568,514.25
3 Beton plat atap m3 28.20 Rp 4,207,925.00 Rp 118,683,683.04
4 Rangka atap baja kg 17500.00 Rp 20,000.00 Rp 350,000,000.00
5 Beton listplank m3 5.42 Rp 5,096,993.00 Rp 27,646,090.03
6 Rangka baja ringan (kaso dan reng) m2 1188.00 Rp 150,000.00 Rp 178,200,000.00
Sub Jumlah Pekerjaan Struktur Rp 1,027,658,863.52
C Pekerjaan Dinding
1 Pas. Dining bata 1Pc:3Ps m2 39.00 Rp 168,596.00 Rp 6,575,244.00
2 Pas. Dining bata 1Pc:5Ps m2 711.80 Rp 164,096.00 Rp 116,803,532.80
3 Plesteran dinding 1Pc:3Ps m2 78.00 Rp 98,311.00 Rp 7,668,258.00
4 Plesteran dinding 1Pc:5Ps m2 1423.60 Rp 93,083.00 Rp 132,512,958.80
5 Beton kolom praktis m1 328.00 Rp 78,316.00 Rp 25,687,648.00
6 Beton balok praktis m1 354.00 Rp 78,316.00 Rp 27,723,864.00
7 Pasang dinding keramik 30x30 cm m2 53.00 Rp 1,029,270.00 Rp 54,551,310.00
8 Pasang dinding batu alam m2 229.00 Rp 302,357.14 Rp 69,239,785.71
9 Plesteran beton kolom m2 376.00 Rp 98,311.00 Rp 36,964,936.00
Sub Jumlah Pekerjaan Dinding Rp 477,727,537.31
D Pekerjaan Lantai
1 Urugan pasir dibawah lantai dasar m3 47.50 Rp 295,561.00 Rp 14,039,147.50
2 Lantai homogenous 40x40 cm m2 717.00 Rp 442,619.00 Rp 317,357,823.00
3 Lantai keramik 30x30 cm km. mandi m2 53.00 Rp 258,869.47 Rp 13,720,081.91
4 Plint homogenous 10x40 cm m1 75.00 Rp 57,243.00 Rp 4,293,225.00
5 Beton lantai dasar (work floor) m2 770.00 Rp 50,781.00 Rp 39,101,370.00
6 Lantai rabat beton m2 19.00 Rp 45,000.00 Rp 855,000.00
Sub Jumlah Pekerjaan Lantai Rp 389,366,647.41
Masjid-67
RENCANA ANGGARAN BIAYA
PROYEK : PERENCANAAN PEMBANGUNAN
LOKASI : GEDUNGSEKOLAH
BANDUNG
BANGUNAN : MASJID
TAHUN ANGGARAN :
G Pekerjaan Sanitasi
1 Pas.closet jongkok bh 1.00 Rp 350,000.00 Rp 350,000.00
2 Pas.washtafel bh Rp 750,000.00 Rp -
3 Pas.Urinoir bh Rp 1,750,000.00 Rp -
4 Pas.floor drain bh 5.00 Rp 140,000.00 Rp 700,000.00
5 Pas.clean out bh 2.00 Rp 135,000.00 Rp 270,000.00
6 Pas. Kaca cermin bh 1.00 Rp 500,000.00 Rp 500,000.00
7 Pas. Bak mandi bh 1.00 Rp 350,000.00 Rp 350,000.00
8 Pas.kran air bh 28.00 Rp 150,000.00 Rp 4,200,000.00
9 Pas. Roof drain bh 6.00 Rp 150,000.00 Rp 900,000.00
Sub Jumlah Pekerjaan Plafond Rp 7,270,000.00
H Pekerjaan Pengecatan
1 Cat dinding luar m2 388.00 Rp 22,500.00 Rp 8,730,000.00
2 Cat dinding dalam m2 572.00 Rp 17,500.00 Rp 10,010,000.00
3 Cat plafond beton exposed m2 335.00 Rp 17,500.00 Rp 5,862,500.00
4 cat plafond multiplek m2 874.00 Rp 20,000.00 Rp 17,480,000.00
Sub Jumlah Pekerjaan Pengecatan Rp 42,082,500.00
I Pekerjaan Atap
1 Waterproofing dak beton m2 271.00 Rp 50,000.00 Rp 13,550,000.00
2 Screed pelindung waterproofing m2 271.00 Rp 35,000.00 Rp 9,485,000.00
3 Penutup atap metal m2 1188.00 Rp 144,343.00 Rp 171,479,484.00
4 Lapisan alluminium foil + kawat ayam m2 1188.00 Rp 20,000.00 Rp 23,760,000.00
5 Nok atap metal m1 81.50 Rp 60,000.00 Rp 4,890,000.00
6 Listplank m1 171.50 Rp 95,000.00 Rp 16,292,500.00
7 Flashing m1 52.00 Rp 50,000.00 Rp 2,600,000.00
Sub Jumlah Pekerjaan Atap Rp 242,056,984.00
Masjid-67
RENCANA ANGGARAN BIAYA
PROYEK : PERENCANAAN PEMBANGUNAN
LOKASI : GEDUNGSEKOLAH
BANDUNG
BANGUNAN : MASJID
TAHUN ANGGARAN :
REKAPITULASI MASJID
JUMLAH Rp 3,209,773,602.00
Masjid-67
RENCANA ANGGARAN BIAYA
PROYEK : PERENCANAAN PEMBANGUNAN GEDUNGSEKOLAH
LOKASI : BANDUNG
BANGUNAN : GEDUNG ADMINISTRASI
TAHUN ANGGARAN :
Lantai 1
A Pekerjaan Pondasi
1 Pengukuran dan pasang bouwplank m1 528.00 Rp 45,000.00 Rp 23,760,000.00
2 Galian tanah pondasi m3 1836.49 Rp 108,904.50 Rp 200,002,460.82
3 Urugan pasir urug m3 149.19 Rp 295,561.00 Rp 44,095,927.83
4 Beton lantai kerja m2 1491.94 Rp 50,781.00 Rp 75,762,205.14
5 Beton foot plat m3 247.65 Rp 3,144,314.00 Rp 778,694,393.00
6 Beton sloof m3 120.79 Rp 5,120,849.00 Rp 618,537,109.01
7 Urugan tanah kembali m3 734.60 Rp 44,311.00 Rp 32,550,754.25
8 Buang tanah bekas galian m3 1101.90 Rp 81,663.00 Rp 89,984,165.71
Sub Jumlah Pekerjaan Pondasi Rp 1,863,387,015.78
B Pekerjaan Struktur
1 Beton kolom m3 132.85 Rp 6,507,677.00 Rp 864,561,158.64
2 Beton balok m3 210.47 Rp 5,692,818.00 Rp 1,198,160,003.80
3 Beton plat lantai m3 254.79 Rp 4,241,367.00 Rp 1,080,648,598.14
4 Beton tangga m3 30.00 Rp 5,313,000.00 Rp 159,390,000.00
Sub Jumlah Pekerjaan Struktur Rp 3,302,759,760.58
C Pekerjaan Dinding
1 Pas. Dining bata 1Pc:3Ps m2 197.90 Rp 168,596.00 Rp 33,365,148.40
2 Pas. Dining bata 1Pc:5Ps m2 1579.60 Rp 164,096.00 Rp 259,206,041.60
3 Plesteran dinding 1Pc:3Ps m2 395.80 Rp 98,311.00 Rp 38,911,493.80
4 Plesteran dinding 1Pc:5Ps m2 3159.20 Rp 93,083.00 Rp 294,067,813.60
5 Beton kolom praktis m1 474.00 Rp 78,316.00 Rp 37,121,784.00
6 Beton balok praktis m1 368.00 Rp 78,316.00 Rp 28,820,288.00
7 Pasang dinding keramik 20x25 cm m2 414.00 Rp 1,029,270.00 Rp 426,117,780.00
8 Plesteran beton m2 700.00 Rp 98,311.00 Rp 68,817,700.00
9 Pas.dinding batu alaam m2 155.00 Rp 302,357.14 Rp 46,865,357.14
10 Ornamen dinding bh 24.00 Rp 1,250,000.00 Rp 30,000,000.00
11 Profilan dinding m1 58.00 Rp 75,000.00 Rp 4,350,000.00
Sub Jumlah Pekerjaan Dinding Rp 1,267,643,406.54
D Pekerjaan Lantai
1 Urugan pasir dibawah lantai dasar m3 115.92 Rp 295,561.00 Rp 34,261,431.12
2 Lantai keramik 30x30 cm m2 3093.08 Rp 258,869.00 Rp 800,702,526.52
3 Lantai keramik 30x30 cm di halaman m2 1162.00 Rp 258,869.00 Rp 300,805,778.00
4 Plint keramik 10x40 cm m1 717.60 Rp 57,243.00 Rp 41,077,576.80
5 Lantai keramik 20x20 cm Toilet m2 110.92 Rp 248,369.00 Rp 27,549,089.48
6 Plint keramik 10x30 cm m1 322.00 Rp 46,355.00 Rp 14,926,310.00
7 Lantai tangga keramik m2 242.70 Rp 258,869.47 Rp 62,827,620.37
8 Step nozing tangga m1 1080.00 Rp 63,743.00 Rp 68,842,440.00
9 Beton lantai dasar(work floor) m2 4366.00 Rp 50,781.00 Rp 221,709,846.00
10 Beton rabat sekeliling bangunan m2 212.00 Rp 50,000.00 Rp 10,600,000.00
Sub Jumlah Pekerjaan Lantai Rp 1,583,302,618.29
Gd Arministrasi-67
RENCANA ANGGARAN BIAYA
PROYEK : PERENCANAAN PEMBANGUNAN GEDUNGSEKOLAH
LOKASI : BANDUNG
BANGUNAN : GEDUNG ADMINISTRASI
TAHUN ANGGARAN :
G. Pekerjaan Sanitasi
1 Closet duduk bh 14.00 Rp 2,000,000.00 Rp 28,000,000.00
2 Washtafel bh 10.00 Rp 750,000.00 Rp 7,500,000.00
3 Urinoir type AS bh 6.00 Rp 1,250,000.00 Rp 7,500,000.00
4 Pas.floor drain bh 20.00 Rp 140,000.00 Rp 2,800,000.00
5 Clean out bh 10.00 Rp 135,000.00 Rp 1,350,000.00
6 Pas. Kaca cermin bh 4.00 Rp 500,000.00 Rp 2,000,000.00
7 Watrproofing km.mandi m2 135.00 Rp 35,000.00 Rp 4,725,000.00
8 Kran air bh 16.00 Rp 150,000.00 Rp 2,400,000.00
9 Shower spray bh 14.00 Rp 275,000.00 Rp 3,850,000.00
10 Soap holder bh 14.00 Rp 140,000.00 Rp 1,960,000.00
11 Partisi urinoir bh 6.00 Rp 1,150,000.00 Rp 6,900,000.00
Sub Jumlah Pekerjaan Sanitair Rp 68,985,000.00
H. Pekerjaan pengecatan
1 Cat dinding luar m2 1161.60 Rp 22,500.00 Rp 26,136,000.00
2 Cat dinding dalam m2 2994.00 Rp 17,500.00 Rp 52,395,000.00
3 Cat plafond calcyboard m2 98.00 Rp 17,500.00 Rp 1,715,000.00
4 Cat plafond gypsum m2 2114.00 Rp 17,500.00 Rp 36,995,000.00
Sub Jumlah Pekerjaan Pengecatan Rp 117,241,000.00
I Pekerjaan Lain-Lain
1 Septiktank lengkap dengan rembesan (Pekerjaan sipil) unit 4.00 Rp 2,500,000.00 Rp 10,000,000.00
2 Saluran keliling bangunan m1 264.00 Rp 110,000.00 Rp 29,040,000.00
3 Bak kontrol bh 8.00 Rp 250,000.00 Rp 2,000,000.00
4 Railing tangga m1 138.00 Rp 550,000.00 Rp 75,900,000.00
Sub Jumlah Pekerjaan Lain-lain Rp 116,940,000.00
Lantai 2
A Pekerjaan Struktur
1 Beton kolom m3 146.83 Rp 5,912,533.00 Rp 868,137,220.39
2 Bton balok m3 178.33 Rp 5,932,851.00 Rp 1,058,005,318.83
3 Beton plat atap m3 136.14 Rp 4,241,367.00 Rp 577,409,524.10
4 Beton truss m3 47.70 Rp 5,928,534.00 Rp 282,791,071.80
4 Rangka atap dom (pipa) kg 19296.00 Rp 20,000.00 Rp 385,920,000.00
Sub Jumlah Pekerjaan Beton Rp 3,172,263,135.12
Gd Arministrasi-67
RENCANA ANGGARAN BIAYA
PROYEK : PERENCANAAN PEMBANGUNAN GEDUNGSEKOLAH
LOKASI : BANDUNG
BANGUNAN : GEDUNG ADMINISTRASI
TAHUN ANGGARAN :
C Pekerjaan Lantai
1 lantai keramik 30x30 cm ruangan kantor m2 1796.00 Rp 258,869.00 Rp 464,928,724.00
2 Lantai keramik 20x20 cm ruangan toilet m2 103.36 Rp 248,369.00 Rp 25,671,419.84
3 Plint keramik 10x30 cm m1 308.00 Rp 46,355.00 Rp 14,277,340.00
0.00 Rp -
Sub Jumlah Pekerjaan lantai Rp 504,877,483.84
D Pekerjaan Plafond
1 Plafond gypsum 60x60 cm rk.metal furing m2 2558.00 Rp 144,248.00 Rp 368,986,384.00
2 Plafond calcyboard 60x60 cm ( r.toilet ) rk.metal furing m2 98.00 Rp 175,778.00 Rp 17,226,244.00
3 List plafond calcyboard m1 104.00 Rp 25,000.00 Rp 2,600,000.00
4 List plafond gypsum m1 978.00 Rp 25,000.00 Rp 24,450,000.00
Sub.Pekerjaan plafond Rp 413,262,628.00
F Pekerjaan Sanitair
1 Pas.closet duduk bh 14.00 Rp 2,000,000.00 Rp 28,000,000.00
2 Washtafel As bh 10.00 Rp 750,000.00 Rp 7,500,000.00
3 Urinoir type AS bh 6.00 Rp 1,250,000.00 Rp 7,500,000.00
4 Pas.floor drain bh 20.00 Rp 140,000.00 Rp 2,800,000.00
5 Clean out bh 10.00 Rp 135,000.00 Rp 1,350,000.00
6 Pas. Kaca cermin bh 4.00 Rp 500,000.00 Rp 2,000,000.00
7 Watrproofing km.mandi m2 135.00 Rp 35,000.00 Rp 4,725,000.00
8 Kran air bh 16.00 Rp 150,000.00 Rp 2,400,000.00
9 Zet shower bh 14.00 Rp 275,000.00 Rp 3,850,000.00
10 Soap holder bh 14.00 Rp 140,000.00 Rp 1,960,000.00
11 Partisi urinoir bh 6.00 Rp 1,150,000.00 Rp 6,900,000.00
Sub Jumlah Pekerjaan sanitair Rp 68,985,000.00
Gd Arministrasi-67
RENCANA ANGGARAN BIAYA
PROYEK : PERENCANAAN PEMBANGUNAN GEDUNGSEKOLAH
LOKASI : BANDUNG
BANGUNAN : GEDUNG ADMINISTRASI
TAHUN ANGGARAN :
H Pekerjaan Atap
1 Waterproofing atap beton m2 366.00 Rp 50,000.00 Rp 18,300,000.00
2 Screed pelinung waterproofing m2 366.00 Rp 35,000.00 Rp 12,810,000.00
3 Roof drain bh 12.00 Rp 250,000.00 Rp 3,000,000.00
4 Atap kubah GRC fin.cat m2 1144.52 Rp 500,000.00 Rp 572,260,000.00
5 Rangka atap baja ringan (kaso dan reng) m2 1467.00 Rp 150,000.00 Rp 220,050,000.00
6 Penutup atap metal m2 1467.00 Rp 145,000.00 Rp 212,715,000.00
7 Nok atap metal m1 98.00 Rp 60,000.00 Rp 5,880,000.00
8 Flashing metal m1 60.00 Rp 50,000.00 Rp 3,000,000.00
9 Ornamen listplank bh 4.00 Rp 1,500,000.00 Rp 6,000,000.00
Sub Jumlah Pekerjaan atap Rp 1,054,015,000.00
JUMLAH Rp 18,116,419,822.55
Gd Arministrasi-67
RENCANA ANGGARAN BIAYA
PROYEK : PERENCANAAN PEMBANGUNAN GEDUNGSEKOLAH
LOKASI : BANDUNG
BANGUNAN : GEDUNG SEKOLAH
TAHUN ANGGARAN :
IV GEDUNG SEKOLAH
A Pekerjaan Pondasi
1 Pengukuran dan pasang bouwplank m1 62.00 Rp 45,000.00 Rp 2,790,000.00
2 Galian tanah pondasi m3 162.00 Rp 108,904.50 Rp 17,642,529.00
3 Urugan pasir urug m3 16.20 Rp 295,561.00 Rp 4,788,088.20
4 beton lantai kerja m2 162.00 Rp 50,781.00 Rp 8,226,522.00
5 Beton poor m3 20.03 Rp 3,888,147.00 Rp 77,879,584.41
6 Beton sloof m3 13.36 Rp 7,711,190.00 Rp 103,021,498.40
7 Urugan tanah kembali m3 48.60 Rp 44,311.00 Rp 2,153,514.60
8 Buang tanah bekas galian m3 113.40 Rp 81,663.00 Rp 9,260,584.20
Sub Jumlah Pekerjaan Pondasi Rp 225,762,320.81
B Pekerjaan Struktur
1 Beton kolom m3 21.27 Rp 8,597,282.00 Rp 182,864,188.14
2 Beton balok ring m3 10.86 Rp 9,302,259.00 Rp 101,022,532.74
Sub Jumlah Pekerjaan Struktur Rp 283,886,720.88
C. Pekerjaan Dinding
1 Pas. Dining bata 1Pc:3Ps m2 95.00 Rp 168,596.00 Rp 16,016,620.00
2 Pas. Dining bata 1Pc:5Ps m2 539.40 Rp 164,096.00 Rp 88,513,382.40
3 Plesteran dinding 1Pc:3Ps m2 190.00 Rp 98,311.00 Rp 18,679,090.00
4 Plesteran dinding 1Pc:5Ps m2 1078.80 Rp 93,083.00 Rp 100,417,940.40
5 Beton kolom praktis m1 120.00 Rp 78,316.00 Rp 9,397,920.00
6 Beton balok praktis m1 60.00 Rp 78,316.00 Rp 4,698,960.00
8 Plesteran beton m2 79.50 Rp 32,500.00 Rp 2,583,750.00
Sub Jumlah Pekerjaan Dinding Rp 240,307,662.80
D Pekerjaan Lantai
1 Urugan pasir dibawah lantai dasar m3 37.80 Rp 295,561.00 Rp 11,172,205.80
2 Lantai keramik Roman 30x30 cm R.kelas m2 356.00 Rp 258,869.00 Rp 92,157,364.00
6 Plint keramik 10x30 cm m1 158.00 Rp 46,355.00 Rp 7,324,090.00
8 Beton lantai dasar ( work floor ) m2 356.00 Rp 50,781.00 Rp 18,078,036.00
Sub Jumlah Pekerjaan Lantai Rp 128,731,695.80
E Pekerjaan Plafond
1 Plafond calcyboard rk.metal furing m2 478.00 Rp 175,778.00 Rp 84,021,884.00
3 List plafond calcyboard m1 470.00 Rp 25,000.00 Rp 11,750,000.00
Sub Jumlah Pekerjaan plafond Rp 95,771,884.00
Sekolah-67
RENCANA ANGGARAN BIAYA
PROYEK : PERENCANAAN PEMBANGUNAN GEDUNGSEKOLAH
LOKASI : BANDUNG
BANGUNAN : GEDUNG SEKOLAH
TAHUN ANGGARAN :
H Pekerjaan Lain-Lain
1 Pas.saluran keliling L=30 Cm m1 57.00 Rp 110,000.00 Rp 6,270,000.00
2 Bak kontrol bh 4.00 Rp 250,000.00 Rp 1,000,000.00
Sub Jumlah Pekerjaan Lain-lain Rp 7,270,000.00
I Pekerjaan Atap
1 Rangka atap baja ringan m2 712.00 Rp 170,000.00 Rp 121,040,000.00
2 Atap genteng metal m2 712.00 Rp 144,343.00 Rp 102,772,216.00
3 Lap.alluminium foil + kawat ayam m2 712.00 Rp 20,000.00 Rp 14,240,000.00
4 Nok metal m1 48.00 Rp 65,000.00 Rp 3,120,000.00
5 Pas.listplank kayu m1 140.00 Rp 95,000.00 Rp 13,300,000.00
6 Pas. Roof drain bh 4.00 Rp 200,000.00 Rp 800,000.00
Sub Jumlah Pekerjaan atap Rp 255,272,216.00
Sekolah-67
RENCANA ANGGARAN BIAYA
PROYEK : PERENCANAAN PEMBANGUNAN GEDUNGSEKOLAH
LOKASI : BANDUNG
BANGUNAN : GEDUNG SEKOLAH
TAHUN ANGGARAN :
V GEDUNG LABORATORIUM
A Pekerjaan Pondasi
1 Pengukuran dan pasang bouwplank m1 62.00 Rp 45,000.00 Rp 2,790,000.00
2 Galian tanah pondasi m3 162.00 Rp 108,904.50 Rp 17,642,529.00
3 Urugan pasir urug m3 19.05 Rp 295,561.00 Rp 5,630,791.72
4 beton lantai kerja m2 190.50 Rp 50,781.00 Rp 9,673,780.50
5 Beton poor m3 20.03 Rp 3,898,147.00 Rp 78,079,884.41
6 Beton sloof m3 13.36 Rp 7,711,190.00 Rp 103,021,498.40
7 Urugan tanah kembali m3 55.00 Rp 44,311.00 Rp 2,437,105.00
8 Buang tanah bekas galian (dalam area proyek) m3 107.00 Rp 81,663.00 Rp 8,737,941.00
Sub Jumlah Pekerjaan pondasi Rp 228,013,530.03
B Pekerjaan Struktur
1 Beton kolom m3 21.27 Rp 9,389,140.00 Rp 199,707,007.80
2 Beton balok m3 10.86 Rp 9,302,259.00 Rp 101,022,532.74
Sub Jumlah Pekerjaan struktur Rp 300,729,540.54
C. Pekerjaan Dinding
1 Pas. Dining bata 1Pc:3Ps m2 95.16 Rp 168,596.00 Rp 16,043,595.36
2 Pas. Dining bata 1Pc:5Ps m2 539.24 Rp 164,096.00 Rp 88,487,127.04
3 Plesteran dinding 1Pc:3Ps m2 190.32 Rp 98,311.00 Rp 18,710,549.52
4 Plesteran dinding 1Pc:5Ps m2 1078.48 Rp 93,083.00 Rp 100,388,153.84
5 Beton kolom praktis m1 120.00 Rp 78,316.00 Rp 9,397,920.00
6 Beton balok praktis m1 60.00 Rp 78,316.00 Rp 4,698,960.00
Sub Jumlah Pekerjaan dinding Rp 237,726,305.76
D Pekerjaan Lantai
1 Urugan pasir dibawah lantai dasar m3 35.60 Rp 295,561.00 Rp 10,521,971.60
2 Lantai keramik 30x30 cm m2 356.00 Rp 258,869.00 Rp 92,157,364.00
4 Plint keramik 10x30 cm m1 158.00 Rp 46,355.00 Rp 7,324,090.00
7 Beton lantai dasar (work floor) m2 357.00 Rp 50,781.00 Rp 18,128,817.00
Sub Jumlah Pekerjaan lantai Rp 128,132,242.60
E Pekerjaan Plafond
1 Plafon calcyboard rk.metal furing m2 478.00 Rp 175,778.00 Rp 84,021,884.00
2 List plafond calcyboard m1 470.00 Rp 25,000.00 Rp 11,750,000.00
Sub Jumlah Pekerjaan plafond Rp 95,771,884.00
Lab-67
RENCANA ANGGARAN BIAYA
PROYEK : PERENCANAAN PEMBANGUNAN GEDUNGSEKOLAH
LOKASI : BANDUNG
BANGUNAN : GEDUNG SEKOLAH
TAHUN ANGGARAN :
H Pekerjaan Lain-Lain
1 Saluran keliling bangunan U-20 cm m1 57.00 Rp 75,000.00 Rp 4,275,000.00
2 Bak kontrol bh 2.00 Rp 250,000.00 Rp 500,000.00
Sub Jumlah Pekerjaan Lain-lain Rp 4,775,000.00
I Pekerjaan Atap
1 Rangka atap baja ringan m2 712.00 Rp 170,000.00 Rp 121,040,000.00
2 Atap genteng metal m2 712.00 Rp 144,343.00 Rp 102,772,216.00
3 Lap.alluminium foil + kawat ayam m2 712.00 Rp 20,000.00 Rp 14,240,000.00
4 Nok metal m1 48.00 Rp 65,000.00 Rp 3,120,000.00
5 Pas.listplank kayu m1 140.00 Rp 95,000.00 Rp 13,300,000.00
6 Pas. Roof drain bh 4.00 Rp 200,000.00 Rp 800,000.00
Sub Jumlah Pekerjaan atap Rp 255,272,216.00
Lab-67
RENCANA ANGGARAN BIAYA
PROYEK : PERENCANAAN PEMBANGUNAN
LOKASI : GEDUNGSEKOLAH
BANDUNG
BANGUNAN : PERPUSTAKAAN
TAHUN ANGGARAN :
VII PERPUSTAKAAN
Lantai 1
A Pekerjaan Pondasi
1 Pengukuran dan ps.bouwplank m1 104.00 Rp 45,000.00 Rp 4,680,000.00
2 Pembersihan lokasi m2 1575.00 Rp 5,000.00 Rp 7,875,000.00
3 Galian tanah pondasi m3 506.18 Rp 108,904.50 Rp 55,125,279.81
4 Urugan pasir urug m3 22.89 Rp 295,561.00 Rp 6,765,391.29
5 beton lantai kerja m2 228.90 Rp 50,781.00 Rp 11,623,770.90
6 Beton foot plat m3 56.06 Rp 3,245,552.00 Rp 181,945,645.12
7 Beton sloof m3 11.52 Rp 6,791,535.00 Rp 78,238,483.20
8 Urugan tanah kembali m3 129.00 Rp 44,311.00 Rp 5,716,119.00
9 Buang tanah bekas galian m3 377.18 Rp 81,663.00 Rp 30,801,650.34
Sub Jumlah Pekerjaan pondasi Rp 382,771,339.66
B Pekerjaan Struktur
1 Beton kolom m3 16.20 Rp 6,597,446.00 Rp 106,878,625.20
2 Beton balok m3 53.70 Rp 5,700,964.00 Rp 306,164,570.66
3 Beton lantai m3 25.92 Rp 4,418,577.00 Rp 114,529,515.84
4 Beton tangga m3 7.80 Rp 5,313,000.00 Rp 41,441,400.00
5 Beton lplat lantai dasr m3 59.05 Rp 2,509,705.00 Rp 148,198,080.25
Sub Jumlah Pekerjaan struktur Rp 717,212,191.95
C. Pekerjaan Dinding
1 Pas. Dining bata 1Pc:3Ps m2 59.00 Rp 168,596.00 Rp 9,947,164.00
2 Pas. Dining bata 1Pc:5Ps m2 617.74 Rp 164,096.00 Rp 101,368,663.04
3 Plesteran dinding 1Pc:3Ps m2 118.00 Rp 98,311.00 Rp 11,600,698.00
4 Plesteran dinding 1Pc:5Ps m2 1235.48 Rp 93,083.00 Rp 115,002,184.84
5 Beton kolom praktis m1 156.00 Rp 78,316.00 Rp 12,217,296.00
6 Beton balok praktis m1 115.00 Rp 78,316.00 Rp 9,006,340.00
7 Pasang dinding keramik 20x25 cm m2 75.60 Rp 32,500.00 Rp 2,457,000.00
Sub Jumlah Pekerjaan dinding Rp 261,599,345.88
D Pekerjaan Lantai
1 Urugan pasir urug dibawah lantai dasar m3 63.20 Rp 295,561.00 Rp 18,679,455.20
2 Lantai keramik 30x30 cm ex Roman KR.01 m2 595.33 Rp 258,869.47 Rp 154,111,467.23
3 Lantai keramik 30x30 cm km. mandiKR.02 m2 36.68 Rp 258,869.47 Rp 9,494,037.81
4 Plint keramik 10x30 cm m1 187.30 Rp 46,355.00 Rp 8,682,291.50
5 Lantai tangga keramik m2 24.00 Rp 258,869.47 Rp 6,212,867.28
6 Step nozing tangga m1 60.00 Rp 63,743.00 Rp 3,824,580.00
E Pekerjaan Plafond
1 Plafond calcyboard tile rk.metal furing m2 565.93 Rp 175,778.00 Rp 99,477,164.65
2 List plafond calcyboard m1 243.10 Rp 25,000.00 Rp 6,077,500.00
3 Plafond beton exposed m2 50.70 Rp 30,000.00 Rp 1,521,000.00
Sub Jumlah Pekerjaan plafond Rp 107,075,664.65
Perpust-67
RENCANA ANGGARAN BIAYA
PROYEK : PERENCANAAN PEMBANGUNAN
LOKASI : GEDUNGSEKOLAH
BANDUNG
BANGUNAN : PERPUSTAKAAN
TAHUN ANGGARAN :
G. Pekerjaan Sanitair
1 pas. Closet duduk AS Granada bh 5.00 Rp 2,000,000.00 Rp 10,000,000.00
2 Pas.Washtafel AS type TULIP bh 4.00 Rp 750,000.00 Rp 3,000,000.00
3 Pas.Shower sprey AS type IN 402 bh 5.00 Rp 275,000.00 Rp 1,375,000.00
4 Pas. Floor drain AS type In.23 bh 6.00 Rp 140,000.00 Rp 840,000.00
5 Pas. Kaca cermin bh 2.00 Rp 500,000.00 Rp 1,000,000.00
6 Pas. Urinoir bh 4.00 Rp 1,650,000.00 Rp 6,600,000.00
7 Pas. Kran air AS type IN301 A bh 4.00 Rp 150,000.00 Rp 600,000.00
8 Meja washtafel finish keramik m2 2.70 Rp 250,000.00 Rp 675,000.00
9 Dinding urinoir bh 3.00 Rp 1,150,000.00 Rp 3,450,000.00
Sub Jumlah Pekerjaan sanitair Rp 27,540,000.00
H. Pekerjaan pengecatan
1 Cat dinding luar m2 320.00 Rp 22,500.00 Rp 7,200,000.00
2 Cat dinding dalam m2 957.88 Rp 17,500.00 Rp 16,762,900.00
3 Cat plafond calcyboard m2 565.93 Rp 17,500.00 Rp 9,903,687.50
4 Cat plafond beton exposed m2 50.70 Rp 20,000.00 Rp 1,014,000.00
Sub Jumlah Pekerjaan Pengecatan Rp 34,880,587.50
I Pekerjaan lain-Lain
1 Pas.Railling tangga pipa BS m1 18.00 Rp 575,000.00 Rp 10,350,000.00
2 Pembuatan septictank dan rembesan (Pekerjaan sipil) unit 1.00 Rp 2,500,000.00 Rp 2,500,000.00
3 Saluran terbuka bis beton U.20 m1 100.00 Rp 75,000.00 Rp 7,500,000.00
4 Bak kontrol bh 4.00 Rp 250,000.00 Rp 1,000,000.00
Sub Jumlah Pekerjaan lain-lain Rp 21,350,000.00
Lantai.2
A Pekerjaan struktur
1 Beton kolom m3 14.90 Rp 6,263,026.00 Rp 93,344,139.50
2 Beton ring balok m3 70.07 Rp 5,567,148.00 Rp 390,090,060.36
3 Pet beton plat konsol m3 21.60 Rp 2,509,705.00 Rp 54,209,628.00
Sub Jumlah Pekerjaan struktur Rp 537,643,827.86
Perpust-67
RENCANA ANGGARAN BIAYA
PROYEK : PERENCANAAN PEMBANGUNAN
LOKASI : GEDUNGSEKOLAH
BANDUNG
BANGUNAN : PERPUSTAKAAN
TAHUN ANGGARAN :
C Pekerjaan Lantai
1 Lantai keramik 30x30 cm ex Roman m2 344.85 Rp 258,869.47 Rp 89,271,136.73
2 Lantai keramik 20x20 cm ex Roman di km.mandi m2 14.42 Rp 248,369.00 Rp 3,581,480.98
3 Plint keramik 10x30 cm m1 175.00 Rp 46,355.00 Rp 8,112,125.00
4 Waterproofing km.mandi m2 14.42 Rp 50,000.00 Rp 721,000.00
5 Waterproofing dak beton m2 196.50 Rp 50,000.00 Rp 9,825,000.00
6 Screding pelindung waterproofing m2 196.50 Rp 35,000.00 Rp 6,877,500.00
Sub Jumlah pekerjaan lantai Rp 118,388,242.71
D Pekerjaan Plafond
1 Plafond gypsum tile 60x60 cm rk.metal furing m2 465.75 Rp 144,248.00 Rp 67,183,506.00
2 List plafon gypsum m1 192.90 Rp 25,000.00 Rp 4,822,500.00
3 Plafond calcyboard rk.metal furing (tritisan) m2 169.50 Rp 175,778.00 Rp 29,794,371.00
4 List plafond calcyboard m1 226.00 Rp 25,000.00 Rp 5,650,000.00
Sub Jumlah Pekerjaan plafond Rp 107,450,377.00
F Pekerjaan Sanitair
1 Pas.closet duduk bh 8.00 Rp 2,000,000.00 Rp 16,000,000.00
2 Pas.washtafel bh 3.00 Rp 750,000.00 Rp 2,250,000.00
3 Pas.floor drain bh 2.00 Rp 140,000.00 Rp 280,000.00
4 Pas.shower spray bh 3.00 Rp 275,000.00 Rp 825,000.00
5 Pas.kran air bh 3.00 Rp 150,000.00 Rp 450,000.00
6 Pas.soap holder bh 3.00 Rp 140,000.00 Rp 420,000.00
7 Meja washtafel fin.keramik bh 1.00 Rp 750,000.00 Rp 750,000.00
8 Pas.kaca cermin bh 1.00 Rp 600,000.00 Rp 600,000.00
Sub Jumlah Pekerjaan sanitair Rp 16,000,000.00
Perpust-67
RENCANA ANGGARAN BIAYA
PROYEK : PERENCANAAN PEMBANGUNAN
LOKASI : GEDUNGSEKOLAH
BANDUNG
BANGUNAN : PERPUSTAKAAN
TAHUN ANGGARAN :
H Pekerjaan Atap
1 Rangka atap baja ringan m2 864.00 Rp 170,000.00 Rp 146,880,000.00
2 Atap genteng metal m2 864.00 Rp 144,343.00 Rp 124,712,352.00
3 Lap.alluminium foil + kawat ayam m2 864.00 Rp 20,000.00 Rp 17,280,000.00
4 Nok genteng metal m1 41.00 Rp 60,000.00 Rp 2,460,000.00
5 Listplank kayu m1 92.00 Rp 95,000.00 Rp 8,740,000.00
6 Plashing metal m1 20.00 Rp 60,000.00 Rp 1,200,000.00
Sub Jumlah Pekerjaan atap Rp 301,272,352.00
I Pekerjaan Lain-Lain
1 Railling void dan tangga m1 15.00 Rp 550,000.00 Rp 8,250,000.00
Sub Jumlah Pekerjaan lain-lain Rp 8,250,000.00
Perpust-67
RENCANA ANGGARAN BIAYA
PROYEK : PERENCANAAN PEMBANGUNAN
LOKASI : GEDUNGSEKOLAH
BANDUNG
BANGUNAN : GARDU PLN DAN GENSET
TAHUN ANGGARAN :
A Pekerjaan Pondasi
1 Pasang bouwplank m1 46.00 Rp 25,000.00 Rp 1,150,000.00
2 Galian tanah m3 73.78 Rp 108,904.50 Rp 8,034,429.49
3 Urugan pasir urug dibawah pondasi m3 3.86 Rp 295,561.00 Rp 1,139,978.78
4 Beton lantai kerja m2 55.10 Rp 50,781.00 Rp 2,798,033.10
5 Beton pondasi foot plat m3 2.96 Rp 3,429,353.00 Rp 10,150,884.88
6 Beton sloof m3 9.18 Rp 5,540,221.00 Rp 50,859,228.78
7 Urugan kembali m3 25.00 Rp 44,311.00 Rp 1,107,775.00
Sub jumlah Pekerjaan pondasi Rp 75,240,330.02
B Pekerjaan Struktur
1 Beton kolom m3 8.80 Rp 4,293,385.00 Rp 37,781,788.00
2 Beton balok m3 8.39 Rp 5,610,106.00 Rp 47,057,569.13
3 Beton plat atap m3 13.77 Rp 3,557,645.00 Rp 48,988,771.65
Sub jumlah Pekerjaan struktur Rp 133,828,128.78
C Pekerjaan Dinding
1 Pas. Dining bata 1Pc:5Ps m2 310.00 Rp 168,596.00 Rp 52,264,760.00
2 Plesteran dinding 1Pc:5Ps m2 620.00 Rp 164,096.00 Rp 101,739,520.00
3 Beton kolom praktis m1 74.00 Rp 78,316.00 Rp 5,795,384.00
4 Beton balok praktis m1 69.00 Rp 78,316.00 Rp 5,403,804.00
Sub Jumlah Pekerjaan dinding Rp 165,203,468.00
D Pekerjaan Lantai
1 Urugan pasir pasang dibawah lantai dasar m3 9.80 Rp 295,561.00 Rp 2,896,497.80
2 Beton lantai kerja m2 98.00 Rp 50,781.00 Rp 4,976,538.00
3 Beton lantai t=12 cm m3 11.76 Rp 1,750,000.00 Rp 20,580,000.00
4 Floor hardener m2 98.00 Rp 40,000.00 Rp 3,920,000.00
5 Lantai beton rabat m2 6.00 Rp 45,000.00 Rp 270,000.00
Sub Jumlah pekerjaan lantai Rp 32,643,035.80
E Pekerjaan Plafond
1 Plafond beton exposed m2 117.00 Rp 30,000.00 Rp 3,510,000.00
Sub jumlah Pekerjaan plafond Rp 3,510,000.00
G Pekerjaan pengecatan
1 Cat dinding luar m2 213.00 Rp 22,500.00 Rp 4,792,500.00
2 Cat dinding dalam oil paint m2 261.00 Rp 35,000.00 Rp 9,135,000.00
3 Cat plafond beton m2 117.00 Rp 20,000.00 Rp 2,340,000.00
Sub jumlah Pekerjaan Pengecatan Rp 16,267,500.00
Gardu PLN-67
RENCANA ANGGARAN BIAYA
PROYEK : PERENCANAAN PEMBANGUNAN
LOKASI : GEDUNGSEKOLAH
BANDUNG
BANGUNAN : GARDU PLN DAN GENSET
TAHUN ANGGARAN :
REKAPITULASI PEKERJAAN SATRUKTUR DAN ARSITEKTUR RUANG GARDU PLN DAN GENSET
NO URAIAN PEKERJAAN HARGA
A Pekerjaan Pondasi Rp 75,240,330.02
B Pekerjaan Struktur Rp 133,828,128.78
C Pekerjaan Dinding Rp 165,203,468.00
D Pekerjaan Lantai Rp 32,643,035.80
E Pekerjaan Plafond Rp 3,510,000.00
F Pekerjaan Pintu dan Jendela Rp 20,000,000.00
G Pekerjaan pengecatan Rp 16,267,500.00
H Pekerjaan Atap Rp 10,955,000.00
Jumlah Rp 457,647,462.60
Gardu PLN-67
RENCANA ANGGARAN BIAYA
PROYEK : PERENCANAAN PEMBANGUNAN GEDUNGSEKOLAH
LOKASI : BANDUNG
BANGUNAN : RUMAH POMPA DAN MENARA AIR
TAHUN ANGGARAN :
A Pekerjaan Struktur
1 Pengukuran dan pasang bouwplank m1 46.00 Rp 25,000.00 Rp 1,150,000.00
2 Galian tanah m3 259.00 Rp 108,904.50 Rp 28,206,265.50
3 Urugan pasir m3 11.80 Rp 295,561.00 Rp 3,487,619.80
4 Beton lantai kerja m2 118.00 Rp 50,781.00 Rp 5,992,158.00
5 Beton plat pondasi m3 62.08 Rp 2,528,260.00 Rp 156,954,380.80
6 Beton retaining wall m3 71.26 Rp 3,888,147.00 Rp 277,069,355.22
7 Beton kolom m3 7.42 Rp 4,454,920.00 Rp 33,055,506.40
8 Beton plat lantai m3 8.82 Rp 3,557,645.00 Rp 31,378,428.90
9 Beton balok m3 7.57 Rp 5,610,106.00 Rp 42,468,502.42
10 Urugan tanah kembali m3 93.00 Rp 44,311.00 Rp 4,120,923.00
11 Buang tanah sisa galian m3 246.00 Rp 150,000.00 Rp 36,900,000.00
12 Beton pedestal kolom bh 6.00 Rp 500,000.00 Rp 3,000,000.00
13 kg 5213.00 Rp 18,500.00 Rp 96,440,500.00
14 Balok WF 300.150 kg 1945.00 Rp 18,500.00 Rp 35,982,500.00
15 Balok Wf 150.75 kg 1638.00 Rp 18,500.00 Rp 30,303,000.00
16 Besi siku L.50.50.5 kg 5544.00 Rp 18,500.00 Rp 102,564,000.00
17 Besi plat t= 20 mm kg 7490.00 Rp 18,500.00 Rp 138,565,000.00
18 Besi plat t= 12 mm kg 402.00 Rp 18,500.00 Rp 7,437,000.00
19 Angkur baut dia 22 L= 50 cm bh 24.00 Rp 50,000.00 Rp 1,200,000.00
20 Besi plat t= 6 mm bh 169.00 Rp 12,500.00 Rp 2,112,500.00
21 Baut HTB dia 16 mm bh 252.00 Rp 15,000.00 Rp 3,780,000.00
22 Plat siku pengaku bh 48.00 Rp 12,500.00 Rp 600,000.00
Sub jumlah Pekerjaan struktur Rp 1,042,767,640.04
B Pekerjaan arsitektur
1 Pas.dinding bata 1PC:5PS m2 5.00 Rp 168,596.00 Rp 842,980.00
2 Pleteran dinding bata 1Pc:5Ps m2 10.00 Rp 164,096.00 Rp 1,640,960.00
3 Beton kolom & balok praktis m1 9.00 Rp 78,316.00 Rp 704,844.00
4 Pas.waterproofing (GWT) m2 245.00 Rp 65,000.00 Rp 15,925,000.00
5 Pas.lantai dan dinding keramik 30x30 cm m2 245.00 Rp 65,000.00 Rp 15,925,000.00
6 Pas.screed lantai m2 28.00 Rp 65,000.00 Rp 1,820,000.00
7 Pasang railling besi m1 28.00 Rp 550,000.00 Rp 15,400,000.00
8 Pas.tutup manhole bh 1.00 Rp 275,000.00 Rp 275,000.00
Sub jumlah Pekerjaan arsitektur Rp 52,533,784.00
Jumlah struktur dan arsitektur Rp 1,095,301,424.04
SERBAGUNA
A Pekerjaan pondasi
1 Pengukuran dan ps.bouwplank m1 168.00 Rp 45,000.00 Rp 7,560,000.00
2 Galian tanah pondasi m3 353.36 Rp 108,904.50 Rp 38,482,886.18
3 Urugan pasir dibawah pondasi m3 16.21 Rp 295,561.00 Rp 4,791,138.39
4 Beton lantai kerja m2 231.58 Rp 50,781.00 Rp 11,759,660.86
5 Beton pondasi foot plate m3 31.05 Rp 2,528,260.00 Rp 78,497,416.48
6 Beton sloof m3 32.11 Rp 5,589,402.00 Rp 179,491,348.55
7 Urugan kembali m3 98.00 Rp 44,311.00 Rp 4,342,478.00
8 Buang tanah bekas galian m3 255.36 Rp 81,663.00 Rp 20,853,757.67
Sub jumlah pek pondasi Rp 345,778,686.11
B Pekerjaan Struktur
1 Beton kolom m3 77.92 Rp 4,454,920.00 Rp 347,127,366.40
2 Beton balok m3 15.54 Rp 6,743,792.00 Rp 104,795,290.66
3 Beton plat m3 34.21 Rp 3,656,132.00 Rp 125,092,362.70
4 Beton tribun m3 48.80 Rp 6,231,112.00 Rp 304,098,205.16
5 Beton ring balok m3 18.13 Rp 5,784,885.00 Rp 104,901,947.61
6 Beton tribun atas m3 19.89 Rp 5,395,116.00 Rp 107,320,186.98
7 Beton tangga m3 7.80 Rp 5,313,000.00 Rp 41,441,400.00
8 Rangka atap baja kg 103629.14 Rp 20,000.00 Rp 2,072,582,880.00
Jumlah Pekerjaan struktur Rp 3,207,359,639.52
C Pekerjaan Dinding
1 Pas. Dining bata 1Pc:3Ps m2 90.30 Rp 168,596.00 Rp 15,224,218.80
2 Pas. Dining bata 1Pc:5Ps m2 3500.70 Rp 164,096.00 Rp 574,450,867.20
3 Plesteran dinding 1Pc:3Ps m2 180.60 Rp 98,311.00 Rp 17,754,966.60
4 Plesteran dinding 1Pc:5Ps m2 7001.40 Rp 93,083.00 Rp 651,711,316.20
5 Beton kolom praktis m1 488.00 Rp 78,316.00 Rp 38,218,208.00
6 Beton balok praktis m1 62.00 Rp 78,316.00 Rp 4,855,592.00
7 Pasang dinding keramik m2 173.00 Rp 32,500.00 Rp 5,622,500.00
8 Plesteran beton m2 985.00 Rp 98,311.00 Rp 96,836,335.00
9 Pas.dinding rooster m2 155.00 Rp 150,000.00 Rp 23,250,000.00
Sub Jumlah Pekerjaan dinding Rp 1,427,924,003.80
D Pekerjaan Lantai
1 Urugan pasir dibawah lantai dasar m3 128.00 Rp 295,561.00 Rp 37,831,808.00
2 Lantai keramik 30x30 cm m2 1005.00 Rp 258,869.00 Rp 260,163,345.00
3 #REF! m1 40.00 Rp 248,369.00 Rp 9,934,760.00
4 Lantai kramik 40x40 cm diteras & hall m2 240.50 Rp 442,619.00 Rp 106,449,869.50
5 Beton lantai dasar (work floor) m2 1280.00 Rp 50,781.00 Rp 64,999,680.00
6 Plint lantai 10/40 cm m1 107.00 Rp 35,000.00 Rp 3,745,000.00
7 Plint lantai 10/30 cm m1 177.00 Rp 46,355.00 Rp 8,204,835.00
8 Lantai floor hardener m2 550.00 Rp 35,000.00 Rp 19,250,000.00
Sub Jumlah pek lantai Rp 510,579,297.50
E Pekerjaan Plafond
1 Plafond calcyboard tile 60x60 cm rk metal furing m2 160.00 Rp 175,778.00 Rp 28,124,480.00
2 Plafond multiplek di tritisan m2 453.00 Rp 205,649.00 Rp 93,158,997.00
3 List plafon calcyboard, m1 88.00 Rp 25,000.00 Rp 2,200,000.00
4 Plafond beton exposed m2 243.00 Rp 25,000.00 Rp 6,075,000.00
5 Plafond multiplek m2 1166.00 Rp 205,649.00 Rp 239,786,734.00
6 List plafon multiplek m1 201.00 Rp 20,000.00 Rp 4,020,000.00
7 List plafond multiplek di tritisan m1 499.50 Rp 20,000.00 Rp 9,990,000.00
Sub jumlah Pekerjaan plafond Rp 383,355,211.00
RENCANA ANGGARAN BIAYA
PROYEK : PERENCANAAN PEMBANGUNAN GEDUNGSEKOLAH
LOKASI : BANDUNG
BANGUNAN : GEDUNG SERBAGUNA
TAHUN ANGGARAN :
G Pekerjaan Sanitair
1 Pas.closet jongkok bh 6.00 Rp 350,000.00 Rp 2,100,000.00
2 Pas.washtafel bh 5.00 Rp 750,000.00 Rp 3,750,000.00
3 Pas.Urinoir bh 2.00 Rp 1,650,000.00 Rp 3,300,000.00
4 #REF! bh 8.00 Rp 150,000.00 Rp 1,200,000.00
5 Pas.Shower spray bh 6.00 Rp 375,000.00 Rp 2,250,000.00
6 Pas.kaca cermin bh 5.00 Rp 600,000.00 Rp 3,000,000.00
7 Pas.soap holder bh 6.00 Rp 140,000.00 Rp 840,000.00
Sub jumlah Pekerjaan sanitair Rp 16,440,000.00
H Pekerjaan pengecatan
1 Cat dinding luar m2 1170.00 Rp 22,500.00 Rp 26,325,000.00
2 Cat dinding dalam m2 1528.00 Rp 17,500.00 Rp 26,740,000.00
3 cat plafond multiplek + calciboard m2 1779.00 Rp 17,500.00 Rp 31,132,500.00
4 cat plafond beton m2 243.00 Rp 20,000.00 Rp 4,860,000.00
Sub jumlah Pekerjaan Pengecatan Rp 89,057,500.00
I Pekerjaan Atap
1 Rangka atap baja ringan (reng + kaso) m2 2480.00 Rp 150,000.00 Rp 372,000,000.00
2 Atap genteng metal m2 2480.00 Rp 144,343.00 Rp 357,970,640.00
3 Lap.alluminium foil + kawat ayam m2 2480.00 Rp 20,000.00 Rp 49,600,000.00
4 Nok genteng metal m2 72.00 Rp 60,000.00 Rp 4,320,000.00
5 Pas. Listplank Kayu m1 185.00 Rp 95,000.00 Rp 17,575,000.00
6 Pas.flashing metal m1 80.00 Rp 75,000.00 Rp 6,000,000.00
Sub jumlah Pekerjaan atap Rp 807,465,640.00
J Pekerjaan Lain-lain
1 Pemb. Septictank dan rembesan (Pekerjaan sipil) unit 2.00 Rp 2,000,000.00 Rp 4,000,000.00
2 Saluran terbuka bis beton U-20 cm m 170.00 Rp 75,000.00 Rp 12,750,000.00
3 Bak kontrol bh 8.00 Rp 250,000.00 Rp 2,000,000.00
4 Railling tangga m1 20.00 Rp 350,000.00 Rp 7,000,000.00
5 Raillinh balkon m1 13.50 Rp 350,000.00 Rp 4,725,000.00
6 Konsol pipa dia 2.5" unit 24.00 Rp 250,000.00 Rp 6,000,000.00
7 Waterproofing dak beton m2 97.00 Rp 50,000.00 Rp 4,850,000.00
8 Meja washtafel fin.keramik m2 4.10 Rp 500,000.00 Rp 2,050,000.00
Sub jumlah Pekerjaan Lain-lain Rp 43,375,000.00
RENCANA ANGGARAN BIAYA
PROYEK : PERENCANAAN PEMBANGUNAN GEDUNGSEKOLAH
LOKASI : BANDUNG
BANGUNAN : GEDUNG SERBAGUNA
TAHUN ANGGARAN :
Jumlah Rp 6,999,509,161.93
JUMLAH Rp 7,404,795,983.62
RENCANA ANGGARAN BIAYA
PROYEK : PERENCANAAN PEMBANGUNAN GEDUNGSEKOLAH
LOKASI : BANDUNG
BANGUNAN : LAPANG
TAHUN ANGGARAN :
Pekerjaan LAPANGAN
XX LAPANGAN BOLA.
1 Pemadatan tanah lapangan m2 3880.00 Rp 7,500.00 Rp 29,100,000.00
2 Penanaman rumput embun di area lapangan m2 2800.00 Rp 10,000.00 Rp 28,000,000.00
3 Rumput gajah area sisi lapangan m2 1335.00 Rp 5,000.00 Rp 6,675,000.00
4 Lapisan gravel di track lari t=10 cm m2 1080.00 Rp 35,000.00 Rp 37,800,000.00
5 Galian tanah pondasi m3 45.00 Rp 15,000.00 Rp 675,000.00
6 Urugan pasir m3 9.00 Rp 250,000.00 Rp 2,250,000.00
7 Pondasi batu kali tribune & turap m3 137.00 Rp 450,000.00 Rp 61,650,000.00
8 Urugan tanah tribune & turap m3 225.00 Rp 80,000.00 Rp 18,000,000.00
9 Paving block pedestrian t=6 cm m2 136.00 Rp 150,000.00 Rp 20,400,000.00
10 Saluran keliling lapangan m1 285.00 Rp 1,200,000.00 Rp 342,000,000.00
11 Tiang gawang unit 2.00 Rp 1,500,000.00 Rp 3,000,000.00
12 Plesteran tribune m2 257.00 Rp 79,000.00 Rp 20,303,000.00
13 Garis line lapangan m1 546.00 Rp 15,000.00 Rp 8,190,000.00
14 Saluran galian tanah sekeliling lapangan m1 350.00 Rp 25,000.00 Rp 8,750,000.00
Jumlah Pekerjaan lap.bola Rp 586,793,000.00
Lapangan-67
RENCANA ANGGARAN BIAYA
PROYEK : PERENCANAAN PEMBANGUNAN GEDUNGSEKOLAH
LOKASI : BANDUNG
BANGUNAN : TOILET
TAHUN ANGGARAN :
TOILET BERSAMA
A Pekerjaan pondasi
1 Pengukuran dan pasang bouwplank m1 60.00 Rp 45,000.00 Rp 2,700,000.00
2 Galian tanah pondasi m3 32.45 Rp 108,904.50 Rp 3,534,386.64
3 Urugan pasir urug dibawah pondasi m3 6.29 Rp 295,561.00 Rp 1,857,699.41
4 Beton lantai kerja m2 17.20 Rp 50,781.00 Rp 873,433.20
5 Pondasi batu kali 1Pc:5Ps m3 7.53 Rp 3,888,147.00 Rp 29,277,746.91
6 Beton sloof m3 2.20 Rp 3,144,314.00 Rp 6,917,490.80
7 Urugan kembali m3 11.19 Rp 44,311.00 Rp 495,751.47
8 Buang tanah bekas galian m3 21.27 Rp 81,663.00 Rp 1,736,645.36
Sub jumlah pek pondasi Rp 47,393,153.78
B Pekerjaan Dinding
1 Pas. Dining bata 1Pc:3Ps m2 80.71 Rp 168,596.00 Rp 13,607,383.16
2 Pas. Dining bata 1Pc:5Ps m2 26.40 Rp 164,096.00 Rp 4,332,134.40
3 Plesteran dinding 1Pc:3Ps m2 161.42 Rp 98,311.00 Rp 15,869,361.62
4 Plesteran dinding 1Pc:5Ps m2 52.80 Rp 93,083.00 Rp 4,914,782.40
5 Beton kolom praktis m1 205.00 Rp 78,316.00 Rp 16,054,780.00
6 Beton balok praktis m1 139.00 Rp 78,316.00 Rp 10,885,924.00
7 Pasang dinding keramik 20x25 cm m2 60.10 Rp 1,029,270.00 Rp 61,859,127.00
8 Plesteran kamprotan beralur m2 24.50 Rp 45,000.00 Rp 1,102,500.00
9 Banbanan m1 33.00 Rp 25,000.00 Rp 825,000.00
Sub Jumlah Pekerjaan dinding Rp 129,450,992.58
C Pekerjaan Lantai
1 Urugan pasir dibawah lantai dasar m3 11.85 Rp 295,561.00 Rp 3,502,397.85
2 Lantai keramik 30x30 cm ex roman m2 61.84 Rp 258,869.00 Rp 16,008,458.96
3 Lantai keramik 30x30 cm km. mandi unpolish m2 56.36 Rp 350,000.00 Rp 19,726,000.00
4 Plint keramik 10x30 cm m1 4.10 Rp 46,355.00 Rp 190,055.50
5 Plint keramik 10x40 cm m1 42.70 Rp 46,355.00 Rp 1,979,358.50
6 Lantai rabat beton m2 38.00 Rp 75,000.00 Rp 2,850,000.00
7 Beton lantai dasar (work floor) m2 20.50 Rp 50,781.00 Rp 1,041,010.50
Sub Jumlah pek lantai Rp 45,297,281.31
D Pekerjaan Plafond
1 Plafond calcyboard rk.metal furing m2 73.60 Rp 175,778.00 Rp 12,937,260.80
2 Plafond calcyboard rk.metal furing (toilet dan empe m2 66.45 Rp 175,778.00 Rp 11,680,448.10
3 List plafon gypsum m1 129.60 Rp 25,000.00 Rp 3,240,000.00
4 list plafon calcyboard m1 118.50 Rp 20,000.00 Rp 2,370,000.00
Sub jumlah Pekerjaan plafond Rp 30,227,708.90
Toilet-67
RENCANA ANGGARAN BIAYA
PROYEK : PERENCANAAN PEMBANGUNAN GEDUNGSEKOLAH
LOKASI : BANDUNG
BANGUNAN : TOILET
TAHUN ANGGARAN :
G Pekerjaan pengecatan
1 Cat dinding luar m2 111.85 Rp 22,500.00 Rp 2,516,625.00
2 Cat dinding dalam m2 42.27 Rp 17,500.00 Rp 739,725.00
3 Cat plafond gypsum m2 140.05 Rp 17,500.00 Rp 2,450,875.00
Sub jumlah Pekerjaan Pengecatan Rp 5,707,225.00
H Pekerjaan Atap
1 Rangka atap baja ringan m2 99.00 Rp 170,000.00 Rp 16,830,000.00
2 Atap genteng metal m2 99.00 Rp 144,343.00 Rp 14,289,957.00
3 Pas.alluminium foil + kawat ayam m2 99.00 Rp 20,000.00 Rp 1,980,000.00
4 Pas.Nok ujung bh 2.00 Rp 35,000.00 Rp 70,000.00
5 Pas.flashing genteng m1 20.00 Rp 35,000.00 Rp 700,000.00
6 Nok genteng metal m1 8.50 Rp 40,000.00 Rp 340,000.00
7 Pas. Listplank kayu m1 42.00 Rp 95,000.00 Rp 3,990,000.00
Sub jumlah Pekerjaan atap Rp 38,199,957.00
I Pekerjaan Lain-lain
1 Pemb. SeptictanK dan rembesan (Pekerjaan sipil) unit 1.00 Rp 2,500,000.00 Rp 2,500,000.00
2 Saluran terbuka bis beton U-20 cm m 30.00 Rp 75,000.00 Rp 2,250,000.00
3 Bak kontrol bh 3.00 Rp 250,000.00 Rp 750,000.00
Sub jumlah Pekerjaan Lain-lain Rp 5,500,000.00
Toilet-67
RENCANA ANGGARAN BIAYA
PROYEK : PERENCANAAN PEMBANGUNAN GEDUNGSEKOLAH
LOKASI : BANDUNG
BANGUNAN : TOILET
TAHUN ANGGARAN :
Jumlah Rp 362,322,238.57
JUMLAH Rp 424,704,125.75
Toilet-67
DAFTAR ANALISA HARGA SATUAN
Jumlah 78,317
Dibulatkan 78,316
21 1 M2 Plafond gypsum
Rangka metal m2 1.000 55,000 55,000
Gypsum t=9 mm m2 1.000 29,757 29,757
Coumpond m2 1.000 8,500 8,500
Pekerja hr 0.150 139,376 20906.4
tukang kayu hr 0.080 167,251 13,380
Kepala tukang hr 0.008 174,900 1,399
Mandor hr 0.008 174,900 1,399
Jumlah 130,342
Dibulatkan 130,341
22 1 M2 Plafond calcyboard
Rangka metal furing m2 1.000 55,000 55,000
Kalciboard m2 1.000 35,000 35,000
Pekerja hr 0.180 139,376 25,088
tukang kayu hr 0.320 167,251 53,520
Kepala tukang hr 0.032 174,900 5,597
Mandor hr 0.009 174,900 1,574
Jumlah 175,779
Dibulatkan 175,778
23 1 M2 Lantai keramik 30x30 cm (tangga) dan teras (unpolish)
Keramik 30x30 cm m2 1.050 65,000 68,250
Cement sak 0.280 75,000 21,000
Pasir pasang m3 0.042 257,143 10,800
Pengisi nat kg 0.250 10,000 2,500
Pekerja hr 0.620 139,376 86,413
Tukang batu hr 0.350 167,251 58,538
Kepala tukang hr 0.035 174,900 6,122
Mandor hr 0.030 174,900 5,247
Jumlah 258,869
28 1 M2 Plafon multiplek t= 5 mm
Rangka kayu Meranti m3 0.019 3,350,000.00 63,650.00
Plywoo t=5 mm lbr 0.390 70,000.00 27,300.00
Paku kg 0.060 13,500.00 810.00
Pekerja hr 0.270 139,376.00 37,631.52
Tukan kayu hr 0.400 167,251.00 66,900.40
Kepala tukang hr 0.040 174,900.00 6,996.00
Manor hr 0.014 174,900.00 2,361.15
Jumlah 205,649.07
Dibulatkan 205,649.00
29 1 M2 Beton lantai kerja 1Pc:3Ps:5Ps
Cement sak 0.250 75,000.00 18,750.00
Pasir beton m3 0.026 265,000.00 6,890.00
Kerikil m3 0.044 281,117.00 12,369.15
Pekerja hr 0.058 139,376 8,028
Tukang batu hr 0.020 167,251 3,345
Kepala tukang hr 0.002 174,900 350
Mandor hr 0.006 174,900 1,049
Jumlah 50,781.43
Dibulatkan 50,781.00
30 1 Kg. besi beton
Besi beton kg 1.050 13,500.00 14,175.00
Bindrat kg 0.015 15,000.00 225.00
Pekerja hr 0.007 139,376 976
Tukang besi hr 0.007 167,251 1,171
Kepala tukang hr 0.001 174,900 122
Mandor hr 0.000 174,900 52
Jumlah 16,721.29
Dibulatkan 16,721.00
31 1 M2Bekisting plywood (kolom)
Kayu rangka (3xpakai) m3 0.013 2,100,000.00 27,930.00
Plywood t=12mm (3xpakai) lbr 0.125 161,250.00 20,156.25
Paku rata2 kg 0.200 13,500.00 2,700.00
Beton deking bh 4.000 500.00 2,000.00
Minyak bekisting m2 1.000 2,500.00 2,500.00
Pekerja hr 0.320 139,376.00 44,600.32
Tukan kayu hr 0.330 167,251.00 55,192.83
Kepala tukang hr 0.033 174,900.00 5,771.70
Manor hr 0.006 174,900.00 1,049.40
Jumlah 161,900.50
Dibulatkan 161,900.00
32 1 M2Bekisting plywood (balok dan plat)
Kayu rangka (2xpakai) m3 0.020 2,100,000.00 42,000.00
Plywood t=12mm (2xpakai) lbr 0.175 161,250.00 28,218.75
Paku rata2 kg 0.200 13,500.00 2,700.00
Beton deking bh 4.000 500.00 2,000.00
DAFTAR ANALISA HARGA SATUAN
ASRAMA PA/PI
1 M3 Beton foot plat ( 113 kg/m3 )
Beton K.300 m3 1.030 890,000.00 916,700.00
Besi beton kg 113.000 16,721.00 1,889,473.00
Bekisting m2 2.100 108,435.00 227,713.50
Upah cor m3 1.000 25,000.00 25,000.00
Jumlah 3,058,886.50
Jumlah 3,058,886.00
MASJID
1 M3 Beton foot plat ( 110 kg/m3 )
Beton K.300 m3 1.030 890,000.00 916,700.00
Besi beton kg 110.000 16,721.00 1,839,310.00
Bekisting m2 2.199 108,435.00 238,408.74
Upah cor m3 1.000 25,000.00 25,000.00
Jumlah 3,019,418.74
Jumlah 3,019,418.00
GUEST HOUSE
1 M3 Beton foot plat ( 112 kg/m3 )
Beton K.300 m3 1.030 890,000.00 916,700.00
Besi beton kg 112.000 16,721.00 1,872,752.00
DAFTAR ANALISA HARGA SATUAN
SEKOLAH / LAB.
1 M3 Beton foot plat ( 160 kg/m3 )
Beton K.300 m3 1.030 890,000.00 916,700.00
Besi beton kg 160.000 16,721.00 2,675,360.00
Bekisting m2 2.500 108,435.00 271,087.50
Upah cor m3 1.000 25,000.00 25,000.00
Jumlah 3,888,147.50
Dibulatkan 3,888,147.00
1 M3 Beton Tie beam ( 340Kg/m3 )
Beton K.300 m3 1.030 890,000.00 916,700.00
DAFTAR ANALISA HARGA SATUAN
SERBA GUNA
1 M3 Beton foot plat ( 75 kg/m3 )
Beton K.300 m3 1.030 890,000.00 916,700.00
Besi beton kg 75.000 16,721.00 1,254,075.00
Bekisting m2 3.066 108,435.00 332,485.57
Upah cor m3 1.000 25,000.00 25,000.00
Jumlah 2,528,260.57
Dibulatkan 2,528,260.00
1 M3 Beton Tie beam ( 222Kg/m3 )
Beton K.300 m3 1.030 890,000.00 916,700.00
Besi beton kg 222.000 16,721.00 3,712,062.00
Bekisting m2 8.629 108,435.00 935,640.53
Upah cor m3 1.000 25,000.00 25,000.00
DAFTAR ANALISA HARGA SATUAN
R.MAKAN
1 M3 Beton foot plat ( 112 kg/m3 )
Beton K.300 m3 1.030 890,000.00 916,700.00
Besi beton kg 112.000 16,721.00 1,872,752.00
Bekisting m2 2.650 108,435.00 287,310.83
Upah cor m3 1.000 25,000.00 25,000.00
Jumlah 3,101,762.83
Dibulatkan 3,101,762.00
1 M3 Beton Tie beam ( 188Kg/m3 )
Beton K.300 m3 1.030 890,000.00 916,700.00
Besi beton kg 188.000 16,721.00 3,143,548.00
Bekisting m2 6.798 108,435.00 737,148.31
Upah cor m3 1.000 25,000.00 25,000.00
Jumlah 4,822,396.31
Dibulatkan 4,822,396.00
1 M3 Beton Kolom ( 236Kg/m3 ) It.1
Beton K.300 m3 1.030 890,000.00 916,700.00
Besi beton kg 236.000 16,721.00 3,946,156.00
Bekisting m2 13.333 108,435.00 1,445,800.00
Upah cor m3 1.000 35,000.00 35,000.00
Jumlah 6,343,656.00
Dibulatkan 6,343,656.00
1 M3 Beton Balok ( 150Kg/m3 ) Lt.1
Beton K.300 m3 1.030 890,000.00 916,700.00
Besi beton kg 150.000 16,721.00 2,508,150.00
DAFTAR ANALISA HARGA SATUAN
PERPUSTAKAAN
1 M3 Beton foot plat ( 130 kg/m3 )
Beton K.300 m3 1.030 890,000.00 916,700.00
Besi beton kg 130.000 16,721.00 2,173,730.00
Bekisting m2 1.200 108,435.00 130,122.00
Upah cor m3 1.000 25,000.00 25,000.00
Jumlah 3,245,552.00
Dibulatkan 3,245,552.00
1 M3 Beton Tie beam ( 285Kg/m3 )
Beton K.300 m3 1.030 890,000.00 916,700.00
Besi beton kg 285.000 16,721.00 4,765,485.00
Bekisting m2 10.000 108,435.00 1,084,350.00
Upah cor m3 1.000 25,000.00 25,000.00
Jumlah 6,791,535.00
Dibulatkan 6,791,535.00
1 M3 Beton Kolom ( 280Kg/m3 ) It.1
Beton K.300 m3 1.030 890,000.00 916,700.00
Besi beton kg 280.000 16,721.00 4,681,880.00
Bekisting m2 8.889 108,435.00 963,866.67
Upah cor m3 1.000 35,000.00 35,000.00
Jumlah 6,597,446.67
Dibulatkan 6,597,446.00
1 M3 Beton Balok ( 188Kg/m3 ) Lt.1
Beton K.300 m3 1.030 890,000.00 916,700.00
Besi beton kg 188.000 16,721.00 3,143,548.00
Bekisting m2 7.822 206,557.00 1,615,716.98
Upah cor m3 1.000 25,000.00 25,000.00
Jumlah 5,700,964.98
Dibulatkan 5,700,964.00
1 M3 Beton Plat ( 120Kg/m3 ) It.2
Beton K.300 m3 1.030 890,000.00 916,700.00
Besi beton kg 120.000 16,721.00 2,006,520.00
Bekisting m2 7.070 206,557.00 1,460,357.99
Upah cor m3 1.000 35,000.00 35,000.00
Jumlah 4,418,577.99
Dibulatkan 4,418,577.00
STUDENT CENTER
1 M3 Beton foot plat ( 85 kg/m3 )
Beton K.300 m3 1.030 890,000.00 916,700.00
Besi beton kg 85.000 16,721.00 1,421,285.00
Bekisting m2 2.800 108,435.00 303,618.00
Upah cor m3 1.000 25,000.00 25,000.00
Jumlah 2,666,603.00
Dibulatkan 2,666,603.00
1 M3 Beton Tie beam ( 226Kg/m3 )
Beton K.300 m3 1.030 890,000.00 916,700.00
Besi beton kg 226.000 16,721.00 3,778,946.00
Bekisting m2 8.840 108,435.00 958,565.40
Upah cor m3 1.000 25,000.00 25,000.00
Jumlah 5,679,211.40
Dibulatkan 5,679,211.00
1 M3 Beton Kolom ( 242Kg/m3 ) It.1
Beton K.300 m3 1.030 890,000.00 916,700.00
Besi beton kg 242.000 16,721.00 4,046,482.00
Bekisting m2 19.000 108,435.00 2,060,265.00
Upah cor m3 1.000 35,000.00 35,000.00
Jumlah 7,058,447.00
Dibulatkan 7,058,447.00
1 M3 Beton Pond.jalur ( 103Kg/m3 )
Beton K.300 m3 1.030 890,000.00 916,700.00
Besi beton kg 103.000 16,721.00 1,722,263.00
Bekisting m2 2.570 108,435.00 278,677.95
Upah cor m3 1.000 25,000.00 25,000.00
Jumlah 2,942,640.95
Dibulatkan 2,942,640.00
1 M3 Beton Plat ( 83Kg/m3 ) It.dasar
Beton K.300 m3 1.030 890,000.00 916,700.00
Besi beton kg 83.000 16,721.00 1,387,843.00
Bekisting m2 1.250 206,557.00 258,196.25
Upah cor m3 1.000 35,000.00 35,000.00
Jumlah 2,597,739.25
Dibulatkan 2,597,739.00
MINARET
1 M3 Beton POER (215 kg/m3 )
Beton K.300 m3 1.030 890,000.00 916,700.00
Besi beton kg 215.000 16,721.00 3,595,015.00
Bekisting m2 1.300 108,435.00 140,965.50
Upah cor m3 1.000 25,000.00 25,000.00
Jumlah 4,677,680.50
Dibulatkan 4,677,680.00
ASRAMA
1 Unit Pintu Utama P.1
Kosen alluminium m1 6.864 85,000.00 583,440.00
d.pintu t.wood m2 3.596 708,504.60 2,547,428.29
Kunci bh 1.000 300,000.00 300,000.00
handel pintu set 2.000 500,000.00 1,000,000.00
Engsel bh 6.000 22,500.00 135,000.00
silen m1 13.728 4,000.00 54,912.00
Pasang unit 1.000 200,000.00 200,000.00
Finishing daun pintu m2 7.191 75,000.00 539,325.00
Jumlah 5,360,105.29
Dibulatkan 5,360,105.00
RUMAH KEP.SEKOLAH
54 1 Unit pintu type P.1
Kosen alluminium m1 6.490 85,000.00 551,650.00
Daun pintu panel kayu m2 3.655 919,973.50 3,362,503.14
Kunci pintu lengkap bh 1.000 500,000.00 500,000.00
Engsel pintu bh 3.000 25,000.00 75,000.00
Finis. Daun pintu m2 7.310 75,000.00 548,250.00
Silen m1 12.980 4,000.00 51,920.00
Pemasangan unit 1.000 150,000.00 150,000.00
Jumlah 5,239,323.14
Dibulatkan 5,239,000.00
RUMAH GURU
1 Unit Pintu type PJ.1
Kosen alluminium m1 13.090 85,000.00 1,112,650.00
Pintu panel m2 1.763 919,973.50 1,621,913.28
Daun jendela alluminium m1 11.400 80,000.00 912,000.00
Kaca clear t= 5 mm m2 1.800 80,000.00 144,000.00
Engsel jendela bh 6.000 30,000.00 180,000.00
Hak angin bh 3.000 25,000.00 75,000.00
Grendel jendela bh 3.000 35,000.00 105,000.00
Silen m1 52.360 4,000.00 209,440.00
Upah pemasangan unit 1.000 150,000.00 150,000.00
Jumlah 4,510,003.28
Dibulatkan 4,510,003.00
MASJID
1 Unit Pintu type P.1
Kosen alluminium m1 5.000 85,000.00 425,000.00
Daun pintu alluminium m1 5.800 95,000.00 551,000.00
Kaca t=6 mm m2 1.400 125,000.00 175,000.00
Kunci pintu bh 1.000 350,000.00 350,000.00
Engsel pintu bh 3.000 35,000.00 105,000.00
Silen m1 20.000 4,000.00 80,000.00
Upah pemasangan unit 1.000 100,000.00 100,000.00
Jumlah 1,786,000.00
Dibulatkan 1,786,000.00
SEKOLAH
1 Unit Pintu type PD.1
Kosen alluminium m1 6.820 85,000.00 579,700.00
Daun pintu dobel teakwood m2 3.360 708,504.60 2,380,575.46
Kaca t=5 mm m2 0.176 125,000.00 22,000.00
Kunci pintu bh 1.000 350,000.00 350,000.00
Engsel pintu bh 6.000 35,000.00 210,000.00
grendel tanam bh 1.000 75,000.00 75,000.00
Silen m1 13.640 4,000.00 54,560.00
Melamik daun pintu m2 6.720 75,000.00 504,000.00
Upah pemasangan unit 1.000 150,000.00 150,000.00
Jumlah 4,325,835.46
Dibulatkan 4,325,000.00
ADMINISTRASI
1 Unit Pintu type PU (Utama)
Kosen alluminium m1 19.184 85,000.00 1,630,640.00
Daun pintu kaca rk.kayu kmpr m2 3.840 400,000.00 1,536,000.00
Kaca t=6 mm u.pintu m2 2.925 125,000.00 365,625.00
Kunci pintu bh 1.000 350,000.00 350,000.00
Engsel pintu bh 6.000 35,000.00 210,000.00
grendel tanam bh 1.000 75,000.00 75,000.00
Handel pintu ps 2.000 250,000.00 500,000.00
Floor hing ps 2.000 750,000.00 1,500,000.00
Daun jendela alluminium m1 7.700 80,000.00 616,000.00
Kaca jendela t=5 mm m2 3.280 80,000.00 262,400.00
Engsel jendela bh 4.000 22,500.00 90,000.00
Grendel jendela bh 2.000 25,000.00 50,000.00
Hak angin bh 2.000 25,000.00 50,000.00
Silen m1 76.736 4,000.00 306,944.00
Melamik rangkadaun pintu m2 3.840 75,000.00 288,000.00
Upah pemasangan unit 1.000 200,000.00 200,000.00
Jumlah 8,030,609.00
Dibulatkan 8,030,609.00
1 Unit Pintu type PD
Kosen alluminium m1 6.490 85,000.00 551,650.00
Daun pintu dobel teakwood m2 3.570 708,504.60 2,529,361.42
Kunci pintu bh 1.000 350,000.00 350,000.00
Engsel pintu bh 6.000 35,000.00 210,000.00
Hanedel pintu ps 2.000 500,000.00 1,000,000.00
Silen m1 12.980 4,000.00 51,920.00
Melamik daun pintu m2 7.140 75,000.00 535,500.00
Upah pemasangan unit 1.000 150,000.00 150,000.00
Jumlah 5,378,431.42
Dibulatkan 5,378,431.00
1 Unit pintu type P.1
Kosen alluminium m1 5.610 85,000.00 476,850.00
Daun pintu teakwood m2 1.935 708,504.60 1,370,956.40
DAFTAR ANALISA HARGA SATUAN
STUDENT CENTER
1 Unit Pintu type PD.1
Kosen alluminium m1 7.150 85,000.00 607,750.00
Daun pintu dobel teakwood m2 4.080 708,504.60 2,890,698.77
Kunci pintu bh 1.000 350,000.00 350,000.00
Engsel pintu ps 3.000 35,000.00 105,000.00
Handel pintu ps 2.000 250,000.00 500,000.00
Silen m1 14.300 4,000.00 57,200.00
Melamik rangkadaun pintu m2 8.160 75,000.00 612,000.00
Upah pemasangan unit 1.000 100,000.00 100,000.00
Jumlah 5,222,648.77
Dibulatkan 5,222,648.00
1 Unit pintu type P.1
Kosen alluminium m1 6.490 85,000.00 551,650.00
Daun pintu teakwood m2 2.400 708,504.60 1,700,411.04
Kunci pintu lengkap bh 1.000 350,000.00 350,000.00
Engsel pintu ps 1.500 35,000.00 52,500.00
Finis. Daun pintu m2 4.800 75,000.00 360,000.00
Silen m1 12.980 4,000.00 51,920.00
Pemasangan unit 1.000 50,000.00 50,000.00
Jumlah 3,116,481.04
Dibulatkan 3,116,481.00
LABORATORIUM
1 Unit Pintu type PD.1
Kosen alluminium m1 7.260 85,000.00 617,100.00
Daun pintu kaca rk. Alluminium m1 13.040 80,000.00 1,043,200.00
kaca t=8 mm m2 3.450 250,000.00 862,500.00
Kunci pintu bh 1.000 350,000.00 350,000.00
Engsel pintu ps 3.000 35,000.00 105,000.00
Handel pintu ps 2.000 350,000.00 700,000.00
Silen m1 29.040 4,000.00 116,160.00
Upah pemasangan unit 1.000 150,000.00 150,000.00
Jumlah 3,943,960.00
Dibulatkan 3,943,960.00
SERBA GUNA
1 Unit Pintu type P.1
Kosen alluminium m1 12.760 85,000.00 1,084,600.00
Daun pintu dobel teakwood m2 3.360 708,504.60 2,380,575.46
Kunci pintu bh 1.000 350,000.00 350,000.00
Engsel pintu ps 3.000 35,000.00 105,000.00
Daun jendela alluminium m1 8.800 80,000.00 704,000.00
Kaca jendela t=5 mm m2 1.650 80,000.00 132,000.00
Engsel jendela ps 2.000 22,500.00 45,000.00
Grendel jendela bh 2.000 25,000.00 50,000.00
Hak angin bh 2.000 25,000.00 50,000.00
Silen m1 43.120 4,000.00 172,480.00
Melamik rangkadaun pintu m2 6.720 75,000.00 504,000.00
Upah pemasangan unit 1.000 100,000.00 100,000.00
Jumlah 5,677,655.46
DAFTAR ANALISA HARGA SATUAN
R.MAKAN
1 Unit Pintu type PD.1
Kosen alluminium m1 7.260 85,000.00 617,100.00
Daun pintu teakwood m1 4.320 708,504.60 3,060,739.87
kaca t=5 mm m2 0.250 80,000.00 20,000.00
Kunci pintu bh 1.000 350,000.00 350,000.00
Engsel pintu ps 3.000 35,000.00 105,000.00
Handel pintu ps 2.000 350,000.00 700,000.00
Silen m1 14.520 4,000.00 58,080.00
Finis. Daun pintu m2 8.640 75,000.00 648,000.00
Upah pemasangan unit 1.000 150,000.00 150,000.00
Jumlah 5,708,919.87
Dibulatkan 5,708,919.00
GUEST HOUSE
1 Unit Pintu type PJ.1
Kosen alluminium m1 19.855 85,000.00 1,687,675.00
Daun pintu dobel teakwood m2 3.150 708,504.60 2,231,789.49
Kunci pintu bh 1.000 350,000.00 350,000.00
Engsel pintu ps 3.000 35,000.00 105,000.00
Daun jendela alluminium m1 20.000 80,000.00 1,600,000.00
Kaca jendela t=5 mm m2 3.960 80,000.00 316,800.00
Engsel jendela ps 4.000 22,500.00 90,000.00
Grendel jendela bh 4.000 25,000.00 100,000.00
Hak angin bh 4.000 25,000.00 100,000.00
Silen m1 79.710 4,000.00 318,840.00
Melamik rangkadaun pintu m2 6.300 75,000.00 472,500.00
Upah pemasangan unit 1.000 200,000.00 200,000.00
Jumlah 7,572,604.49
Dibulatkan 7,572,604.00
1 Unit pintu type PJ.2 & PJ.2b
Kosen alluminium m1 11.880 85,000.00 1,009,800.00
Daun pintu teakwood m2 1.890 708,504.60 1,339,073.69
Kunci pintu lengkap bh 1.000 350,000.00 350,000.00
Engsel pintu ps 1.500 35,000.00 52,500.00
Kaca jendela t=5 mm m2 1.980 80,000.00 158,400.00
Finis. Daun pintu m2 3.780 75,000.00 283,500.00
Silen m1 47.520 4,000.00 190,080.00
Pemasangan unit 1.000 100,000.00 100,000.00
Jumlah 3,483,353.69
Dibulatkan 3,483,353.00
1 Unit pintu type PJ.3
Kosen alluminium m1 9.350 85,000.00 794,750.00
Daun pintu teakwood m2 1.890 708,504.60 1,339,073.69
DAFTAR ANALISA HARGA SATUAN