Anda di halaman 1dari 3

URAIAN PEKERJAAN SOSORAN GUDANG 1 LAMONGAN

TOTAL TOTAL CONVERT BERAT BERAT WIRE MESH CONVERT


NO URAIAN PEKERJAAN P L T VOL SAT SAT SAT SAT
TITIK VOL BTG WF/12M WF/M1 M8/LBR/KG KG
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
I PEKERJAAN TANAH
1 Galian plat setempat 0.8 0.8 1.2 0.768 M3 7 5.376 m3
2 Galian sloof 65.2 0.55 0.3 10.758 m3
3 Urukan tanah kembali 11.526 m3

II PEKERJAAN BETON
1 Lantai kerja
-Pondasi Plat setempat(80x80x30CM) 7 unit
-Sloof (25X30) 65.2 0.25 0.3 4.89 m3

2 Concrete K300 plat lantai 1 0.15 34.2225 M3


Plastik cor 228 m2
Begesting 61.815 m2
Wiremesh M-8(1 Lapis) 35.18518519 m2 61.79 2174.09 kg
Trowel finishing 228 m2

III PEKERJAAN KONTRUKSI BAJA


1 Kolom wf 200X100X5,5X8 42.597 42.597 m1 m1 3.54975 btg 255.6 21.3 907.3161 kg
2 Balok WF 200X100X5,5X8 45.2 45.2 m1 m1 3.766667 btg 255.6 21.3 962.76 kg
3 Haunch wf 250,125,6,9(1/2wf) 0.2 4.26 kg 14 59.64 kg
4 Plat 16 mm(base plate) 300 200 16 7.536 kg 7 52.752 kg
5 Plat 12 mm conektor colom ke balok 400 100 12 3.768 kg 14 52.752 kg
6 Plat 10mm(Stiffener) 184 47 10 0.339434 kg 28 9.504152 kg
7 Trekstang Ø 10 mm 59.237 m1 4.936417 btg 7.4 0.616667 36.5294833333333 kg
8 Ikat angin Ø 16 mm 41.034 m1 3.4195 btg 18.96 1.58 64.83372 kg
9 Ongkos fabrikasi,erection&cat dasar +cat warna +tranportasi 2044.724252 kg
10 Angkur Ø19~750 + 2 mur 4 bh 7 28 bh
11 Kawat las,angin,dll 288 m2
12 Sewa Crane 1 ls

IV PEKERJAAN ATAP SOSORAN


1 Gording CNP 125.50.20.2,3 197.772 m1 32.962 btg 27.1 4.516667 893.2702 kg
2 Gording double/buat dudukan talang 41.22 m1 6.87 btg 27.1 4.516667 186.177 kg
3 CNP 125.50.20.2,3 regel (DOUBLE)regel atas & bawah 82.244 m1 13.70733 btg 27.1 4.516667 371.468733333333 kg
4 Atap zincalum 236.845 m2
5 Ongkos pasang atap + drilling SDS 236.845 m2
6 Talang galvalum 0.4mm 20.561 m1
7 Roof insulation bubble 4mm 236.845 m2
RAB SOSORAN GUDANG 1 LAMONGAN

PEKERJAAN : SOSORAN GUDANG 1


PROYEK : PT.BUIYET INDONESIA LAMONGAN JAWA TIMUR

HARGA JUMLAH HARGA


NO URAIAN PEKERJAAN VOLUME SAT SATUAN HARGA
(RP) (RP)
1 2 3 4 5 6
I PEKERJAAN TANAH
1 Galian plat setempat 5.376 m3 Rp97,750 Rp525,504
2 Galian sloof 10.758 m3 Rp97,750 Rp1,051,595
3 Urukan tanah kembali 11.526 M3 Rp45,000 Rp518,670
SUB TOTAL 1 : Rp2,095,769
II PEKERJAAN BETON
1 Lantai kerja
-Pondasi Plat setempat(80x80x30CM) 7 unit Rp3,500,000 Rp24,500,000
-Sloof (25X30) 4.89 m3 Rp665,750 Rp3,255,518

2 Concrete K300 plat lantai 1 34.2225 m3 Rp1,400,000 Rp47,911,500


Plastik cor 228 m2 Rp5,000 Rp1,140,000
Begesting 61.815 m2 Rp280,000 Rp17,308,200
Wiremesh M-8(1 Lapis) 2174.09 kg Rp19,000 Rp41,307,759
Trowel finishing 228 m2 Rp15,000 Rp3,420,000
SUB TOTAL 2 : Rp138,842,977
III PEKERJAAN KONTRUKSI BAJA
1 Kolom wf 200X100X5,5X8 907.3161 kg Rp19,500 Rp17,692,664
2 Balok WF 200X100X5,5X8 962.76 kg Rp19,500 Rp18,773,820
3 Haunch wf 250,125,6,9(1/2wf) 59.64 kg Rp19,500 Rp1,162,980
4 Plat 16 mm(base plate) 52.752 kg Rp17,500 Rp923,160
5 Plat 12 mm conektor colom ke balok 52.752 kg Rp17,500 Rp923,160
6 Plat 10mm(Stiffener) 9.504152 kg Rp17,500 Rp166,323
7 Trekstang Ø 10 mm 36.5294833333 kg Rp11,500 Rp420,089
8 Ikat angin Ø 16 mm 64.83372 kg Rp11,500 Rp745,588
9 Ongkos fabrikasi,erection&cat dasar +cat warna +tranportasi 2044.724252 kg Rp16,500 Rp33,737,950
10 Angkur Ø19~750 + 2 mur 28 bh Rp85,000 Rp2,380,000
11 Kawat las,angin,dll 288 M2 Rp55,000 Rp15,840,000
12 Sewa Crane 1 ls Rp10,000,000 Rp10,000,000
SUB TOTAL 3 : Rp102,765,734
IV PEKERJAAN ATAP SOSORAN
1 Gording CNP 125.50.20.2,3 893.2702 kg Rp21,000 Rp18.758.674
2 Gording double/buat dudukan talang 186.177 kg Rp21,000 Rp3.909.717
3 CNP 125.50.20.2,3 regel (DOUBLE)regel atas & bawah 371.468733333 kg Rp21,000 Rp7.800.843
4 Atap zincalum 236.845 m2 Rp102,350 Rp24.241.086
5 Ongkos pasang atap + drilling SDS 236.845 m2 Rp95,750 Rp22.677.909
6 Talang galvalum 0.4mm 20.561 M1 Rp67,850 Rp1.395.064
7 Roof insulation bubble 4mm 236.845 m2 Rp45,000 Rp10.658.025
SUB TOTAL 4 : Rp89,441,318
BIYAYAH PROYEK
VI Total Biyayah Pekerjaan Rp 333,145,796.82
Pajak PPN 11% Rp 36,646,037.65
GRAND TOTAL (RP) : Rp 369,791,834.47
REKAPITULASI
SOSORAN GUDANG 1 LAMONGAN

PEKERJAAN : TAMBAHAN SOSORAN GUDANG 1


PROYEK : PT. BUILDYET INDONESIA, LAMONGAN, JAWA TIMUR

JUMLAH TOTAL.
NO. URAIAN PEKERJAAN
(Rp) (Rp).
1 2 3 4
I PEKERJAAN TANAH 2,095,768.50
II PEKERJAAN BETON 138,842,976.76
III PEKERJAAN KONTRUKSI BAJA 102,765,733.61
IV PEKERJAAN ATAP SOSORAN 89,441,317.95

JUMLAH : 333,145,796.82
OVERHEAD & MANAGEMENT FEE 5% : 16,657,289.84

Harga/m2: 1,476,928 TOTAL Rp. 349,803,086.66


Luasan : 237 PPn 11 % Rp. 38,478,339.53

GRAND TOTAL Rp. 388,281,426.19