RENCANA ANGGARAN BIAYA

( R A B)
RUMAH LANTAI 2
Luas Tanah : 210 m2
Luas Bangunan : 162.5 m2

NO. URAIAN PEKERJAAN ANALISA VOLUME SATUAN HARGA SATUAN JUMLAH HARGA
1 2 3 4 5 6
A. PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan Taksir 1.00 ls 500,000.00 500,000.00
Jumlah A 500,000.00
B. PEKERJAAN PASANGAN DINDING
1 Pas. Dinding Herbel 1 : 4 Hitung-2 411.00 m2 152,277.00 62,585,847.00
2 Plesteran 1 : 4 ,tebal 15mm A.4.4.2.5 735.00 m2 53,757.60 39,511,836.00
3 Acian A.4.4.2.27 735.00 m2 34,060.00 25,034,100.00
Jumlah B 127,131,783.00
C. PEKERJAAN BETON
1 Kolom
Beton mutu K-225 A.4.1.1.5 4.34 m3 1,156,098.02 5,017,465.41
Begesting Hitung-2 11.40 m2 154,212.00 1,758,016.80
Besi A.4.1.1.17 645.07 kg 17,000.00 10,966,190.00
2 Ring Balk
Beton mutu K-225 A.4.1.1.5 4.05 m3 1,156,098.02 4,682,196.98
Begesting Hitung-2 19.80 m2 157,553.00 3,119,549.40
Besi A.4.1.1.17 804.00 kg 17,000.00 13,668,000.00
3 Balok Latiew
Beton mutu K-225 A.4.1.1.5 1.54 m3 1,156,098.02 1,780,390.95
Begesting Hitung-2 14.18 m2 386,455.00 5,479,931.90
Besi A.4.1.1.17 513.99 kg 17,000.00 8,737,830.00
4 Plat Lantai Beton tebal 12cm
Beton mutu K-225 A.4.1.1.7 3.57 m3 1,156,098.02 4,127,269.93
Begesting Bondek Hitung-2 29.75 m2 165,321.00 4,918,299.75
Besi Wiremesh A.4.1.1.17 232.50 kg 17,000.00 3,952,500.00
5 Talang & Topian Beton
Beton mutu K-225 A.4.1.1.5 6.95 m3 1,156,098.02 8,034,881.24
Begesting Hitung-2 6.90 m2 544,094.50 3,754,252.05
Besi A.4.1.1.17 614.05 kg 17,000.00 10,438,850.00
Jumlah C 90,435,624.41
D. PEKERJAAN ATAP
1 Rangka Atap Baja Ringan Hitung-26 182.45 m2 158,360.00 28,892,782.00
2 Pas. Atap Genteng Beton A.4.5.2.32 182.45 m2 187,500.00 34,209,375.00
3 Pas. Listpank (wpc) A.4.5.2.37 45.00 m 120,050.00 5,402,250.00
4 Penutup Rangka Atap (PVC) Hitung-27 29.70 m2 260,250.00 7,729,425.00
Jumlah D 76,233,832.00
E. PEKERJAAN SANITASI
1 Pas. Kloset Duduk A.5.1.1.2 1.00 bh 1,227,881.97 1,227,881.97
2 Kran Air A.5.1.1.19 7.00 bh 69,475.00 486,325.00
3 Pipa Ø 1/2-3/4" A.5.1.1.25 86.00 m 19,910.00 1,712,260.00
4 Pipa Ø 3" A.5.1.1.31 79.00 m 56,840.00 4,490,360.00
5 Pipa Ø 4" A.5.1.1.32 18.00 m 82,554.00 1,485,972.00
Jumlah E 9,402,798.97
F. PEKERJAAN ELEKTRIKAL
1 Instalasi Listrik Hitung-17 55.00 ttk 93,900.00 5,164,500.00
2 Saklar Ganda Hitung-20 9.00 bh 34,000.00 306,000.00
3 Saklar Tunggal Hitung-19 12.00 bh 31,000.00 372,000.00
4 Stop Kontak Hitung-18 12.00 bh 29,000.00 348,000.00
5 Lampu Bulb 10 watt Hitung-21 20.00 bh 51,000.00 1,020,000.00
6 Lampu Bulb 8 watt Hitung-22 19.00 bh 46,000.00 874,000.00
7 Kabel Listrik Hitung-23 433.00 m 7,500.00 3,247,500.00
8 Pipa Kabel Listrik Hitung-23a 44.00 bh 41,000.00 1,804,000.00
9 Perbaikan MCB & box Hitung-25 2.00 bh 700,000.00 1,400,000.00
Jumlah F 14,536,000.00
G. PEKERJAAN PENGECETAN
1 Cat Tembok Baru A.4.7.1.10 735.00 m2 33,750.00 24,806,250.00
Jumlah G 24,806,250.00
JUMLAH TOTAL 343,046,288.38