Simulasi
Simulasi
P L H
84 X 8.4 2.4 2 unit
API pump ok
P L H
35 X 10.8 4 1 unit
BOG kondenser ok
P L H
19 X 8 4 1 unit
Substation
P L H
35 X 15 2 1 unit 2 lantai
4
EDG
P L H
17 X 15 4 1 unit
Pot mounted
P L H
84 X 8.4 2.4 2 unit
ALAT BERAT
volume galian 86 10.4 3.05 2,727.92 m3 1 lokasi
produktifitas batu
38.97 hari 1 alat
DURASI PEKERJAAN
volume beton
LC 84.2 8.6 724.12 m2
slab 84 8.4 0.6 423.36 m3
wall 84 8.4 0.5 2.4 221.76 m3
volume besi
slab 65,439.36 kg
18.70 hari 1 grup
9.35 hari 2 grup
wall 11,975.04 kg
3.42 hari 1 grup
1.71 hari 2 grup
formwork
slab 84 8.4 0.6 110.88 m2
7.39 hari 1 grup
3.70 hari 2 grup
sabuk horizontal
wall 84 8.4
SC1 sisi 84 14 112.00 btg 1 sisi
SC1 sisi 8.4 2 16.00 btg 1 sisi
full drat sisi 84 0.5 35 140.00 m 1 sisi
sisi 8.4 0.5 4 16.00 m 1 sisi
plastikon sisi 84 2 35 560.00 m 1 sisi
sisi 8.4 2 4 64.00 m 1 sisi
wing nut sisi 84 2 35 560.00 m 1 sisi
sisi 8.4 2 4 64.00 m 1 sisi
akses kerja
vertikal 84 8.4
SC1 84 42 84.00 pcs 1 sisi
SC1 8.4 5 10.00 pcs 1 sisi
SC4 84 84 84.00 pcs 1 sisi
SC4 8.4 9 9.00 pcs 1 sisi
SC1 84 21 42.00 pcs 1 sisi
SC1 8.4 3 6.00 pcs 1 sisi
horizontal
SC1 84 14 70.00 pcs 1 sisi
SC1 8.4 2 10.00 pcs 1 sisi
asiba 564
full drat 560
jack base 1728
plastikon 2240
SC1 1400
SC3 272
SC4 644
SC5 272
wing nut 2240
SC1 6m
SC2 4m
SC3 2m
SC4 1m
SC5 3m
1 breaker
1 exca
4 DT
2 breaker
2 exca
8 DT
5 orang
10 orang 15 orang untuk satu lokasi pit pot mounted
5 orang
10 orang
4 orang 16 orang
8 orang
4 orang
8 orang
12 orang
16 orang
20 orang
282 pcs
280 m
864 pcs
1120 pcs
700 btg
136 pcs
322 pcs
136 pcs
1120 pcs
pot mounted
pot mounted
Unit pompa
P L H
3X 3 1.5 11
ALAT BERAT
volume galian 5 5 1.25 31.25 m3 1 lokasi
produktifitas batu
0.45 hari 1 alat
DURASI PEKERJAAN
volume beton
LC 3.2 3.2 10.24 m2
slab 3 3 0.6 5.40 m3
wall 2.7 2.7 0.6 0.9 3.32 m3
volume besi
slab 648.00 kg
0.19 hari 1 grup
0.09 hari 2 grup
wall 398.52 kg
0.11 hari 1 grup
0.06 hari 2 grup
formwork
slab 3 3 0.6 7.20 m2
0.48 hari 1 grup
0.24 hari 2 grup
1 breaker
1 exca
4 DT
2 breaker
2 exca
8 DT
4 orang
8 orang
12
4 orang
8 orang
12 orang
16 orang
20 orang
12
3 unit 4 x berjalan
untuk satu lokasi pit pot mounted
P L H
35 X 10.8 4 1 unit
ALAT BERAT
volume galian 37 12.8 4.65 2,202.24 m3 1 lokasi
produktifitas batu
31.46 hari 1 alat
DURASI PEKERJAAN
volume beton
LC 35.2 11 387.20 m2
slab 35 10.8 0.6 226.80 m3
wall 35 10.8 0.5 4 183.20 m3
volume besi
slab 27,216.00 kg
7.78 hari 1 grup
3.89 hari 2 grup
wall 21,984.00 kg
6.28 hari 1 grup
3.14 hari 2 grup
formwork
slab 35 10.8 0.6 54.96 m2
4.58 hari 1 grup
2.29 hari 2 grup
sabuk horizontal
wall 35 10.8
SC1 sisi 35 6 48.00 btg 1 sisi
SC1 sisi 10.8 2 16.00 btg 1 sisi
full drat sisi 35 0.5 15 105.00 m 1 sisi
sisi 10.8 0.5 5 35.00 m 1 sisi
plastikon sisi 35 2 15 420.00 pcs 1 sisi
sisi 10.8 2 5 140.00 pcs 1 sisi
wing nut sisi 35 2 15 420.00 pcs 1 sisi
sisi 10.8 2 5 140.00 pcs 1 sisi
akses kerja
vertikal 35 10.8
SC1 35 18 36.00 pcs 1 sisi
SC1 10.8 6 12.00 pcs 1 sisi
SC4 35 35 35.00 pcs 1 sisi
SC4 10.8 11 11.00 pcs 1 sisi
SC1 35 9 18.00 pcs 1 sisi
SC1 10.8 3 6.00 pcs 1 sisi
horizontal
SC1 35 6 42.00 pcs 1 sisi
SC1 10.8 2 14.00 pcs 1 sisi
asiba
full drat
jack base
plastikon
SC1
SC3
SC4
SC5
wing nut
SC1 6m
SC2 4m
SC3 2m
SC4 1m
SC5 3m
1 breaker
1 exca
4 DT
2 breaker
2 exca
8 DT
5 orang
10 orang
5 orang
10 orang
4 orang
8 orang
4 orang
8 orang
12 orang
16 orang
20 orang
288 pcs
210 m
434 pcs
840 pcs
462 pcs
78 pcs
92 pcs
78 pcs
840 pcs
compressor konsole lube oil console
compressor
9.50 5.00
1.00
galian
11.80 8.00 2.45 231.28
5.10 6.10 2.45 76.22
307.50 m3 2.00
beton
lc 10.00 6.20 62.00
4.30 4.30 18.49
80.49 m2
besi
slab 9073.20 kg
wall 2017.20 kg
FW
slab 75.84
29.52
105.36 m2
wall 24.60 m2
galian
8.20 6.00 0.75 36.90 m3
beton
lc 6.40 4.20 26.88 m2
slab
6.20 4.00 1.00 24.80 m3
besi
slab 2976.00 kg
FW
slab 20.40 m2
galian
11.50 7.00 0.75 60.38 m3
beton
lc 9.70 5.20 50.44 m2
slab
9.50 5.00 1.00 47.50 m3
besi
slab 5700.00 kg
FW
slab 29.00 m2
3.00 unit
1.00 unit
3.00 unit
galian
5.70 6.70 0.75 28.64 m3
beton
lc 3.90 4.90 19.11 m2
slab
3.70 4.70 1.00 17.39 m3
besi
slab 2086.80 kg
FW
slab 16.80 m2
galian
7.40 6.00 0.75 33.30 m3
beton
lc 5.60 4.20 23.52 m2
slab
5.40 4.00 1.00 21.60 m3
besi
slab 2592.00 kg
FW
slab 18.80 m2
BoG Kondensat
panggung
P L H panggung
19 X 8 4 1 unit
pondasi
Pedestal pondasi
1.2 0.5 1 2 6 unit
slab
3.6 5.4 0.5 1 6 unit
1 Unit PONDASI
ALAT BERAT
volume galian 5.6 7.4 0.8 1 33.15 m3 1 lokasi
produktifitas batu
0.47 hari 1 alat
DURASI PEKERJAAN
volume beton
LC 3.8 5.6 1 21.28 m2
slab 3.6 5.4 0.5 1 9.72 m3
wall 1.2 0.5 1 2 2.40 m3
volume besi
slab 1,166.40 kg
0.33 hari 1 grup
wall 288.00 kg
0.08 hari 1 grup
formwork
slab 3.6 5.4 0.5 1 9.00 m2
0.60 hari 1 grup
sabuk horizontal
wall 1.2 0.5
SC4 sisi 1.2 1 8.00 btg 1 sisi
SC4 sisi 0.5 1 8.00 btg 1 sisi
full drat sisi 1.2 0.5 1 2.00 m 1 sisi
sisi 0.5 0.5 1 - m 1 sisi
plastikon sisi 1.2 2 1 8.00 m 1 sisi
sisi 0.5 2 1 - m 1 sisi
wing nut sisi 1.2 2 1 8.00 m 1 sisi
sisi 0.5 2 1 - m 1 sisi
full drat
jack base
plastikon
SC4
wing nut
SC1 6m
SC2 4m
SC3 2m
SC4 1m
SC5 3m
1 breaker
1 exca
4 DT
5 orang
5 orang
5 orang
5 orang
72.00 pcs 2 sisi 3 set
108.00 pcs 2 sisi 3 set
12 m
216 pcs
48 pcs
132 pcs
48 pcs
BoG Kondensat
panggung
P L H panggung
19 X 8 4 1 unit
pondasi
Pedestal pondasi
1.2 0.5 1 2 6 unit
slab
3.6 5.4 0.5 1 6 unit
1 Unit Mezanine
ALAT BERAT
volume galian 135 m2 0.8 1 108.00 m3 1 lokasi
produktifitas batu
1.54 hari 1 alat
DURASI PEKERJAAN
volume beton
LC 73.02 m2
slab 4.84 8 38.72
tie beam 1 3.99 4 15.96
tie beam 2 3.057 6 18.34
slab 2 2 0.5 8 16.00 m3
tie beam 1 2.75 0.5 4 5.50 m3
tie beam 2 2.1 0.5 6 6.30 m3
kolom 0.25 4.3 8 8.60 m3
beam 1 3.5 0.5 10 17.50 m3
beam 2 2.833 0.5 12 17.00 m3
top slab 152 0.3 1 45.60 m3
volume besi
slab 1,920.00 kg 0.96
tie beam 1 660.00 kg 0.33
tie beam 2 756.00 kg 0.38
kolom 1,032.00 kg 0.52
beam 1 2,100.00 kg 1.05
beam 2 2,039.76 kg 1.02
top slab 5,472.00 kg 2.74
formwork
slab 8 0.5 8 32.00 m2 3.20
tie beam 1 15 0.5 4 30.00 m2 3.00
tie beam 2 12.33 0.5 6 36.99 m2 3.70
kolom 2 4.3 8 68.80 m2 6.88
beam 1 15 0.5 10 75.00 m2 7.50
beam 2 12.33 0.5 12 73.98 m2 7.40
top slab 152 1 152.00 m2 15.20
top slab 54 0.5 27.00 m2 2.70
kolom
support vertikal
SC1 1 4 4.00 pcs
SC5 1 4 4.00 pcs
SC3 1 4 4.00 pcs
support horizontal
SC4 4.3 4 2 32.00 pcs 4 sisi
akses
akses kerja
vertikal 19 8
SC1 19 10 20.00 pcs 1 sisi
SC1 8 4 8.00 pcs 1 sisi
SC4 19 19 19.00 pcs 1 sisi
SC4 8 8 8.00 pcs 1 sisi
SC1 19 5 10.00 pcs 1 sisi
SC1 8 2 4.00 pcs 1 sisi
horizontal
SC1 19 4 28.00 pcs 1 sisi
SC1 8 2 14.00 pcs 1 sisi
deck mezanine
vertikal
19 32
8 14
jack base 448.00 pcs 1 sisi
SC2 448.00 pcs
horizontal
SC1 19 11 4 44.00 pcs 1 tingkat
SC1 8 5 2 10.00 pcs 1 tingkat
asiba
jack base
SC1
SC2
SC3
SC4
SC5
SC1 6m
SC2 4m
SC3 2m
SC4 1m
SC5 3m
1 breaker
1 exca
4 DT
2 6 orang
2 6 orang
2 6 orang
2 6 orang
4 6 orang
4 6 orang
5 6 orang
3 1 grup 5 orang
3 1 grup 5 orang
4 1 grup 5 orang
7 1 grup 5 orang
8 1 grup 5 orang
8 1 grup 5 orang
15 1 grup 5 orang
3 1 grup 5 orang
168 pcs
1340 pcs
362 pcs
448 pcs
32 pcs
310 pcs
32 pcs
substatiun building
P L H
35 X 15 3
1.8
pondasi
slab
37 17 0.4
kolom
0.5 0.5 1.8 32
panggung
tie beam
0.5 0.5 14.5 8
0.5 0.5 34.5 4
slab
35 15 0.25
dek
kolom
0.5 0.5 3 32
tie beam
0.5 0.5 14.5 8
0.5 0.5 34.5 4
dek
35 15 0.25
1 Unit Mezanine
ALAT BERAT
volume galian 39 19 0.85 1 33.15 m3 1 lokasi
produktifitas batu
0.47 hari 1 alat
DURASI PEKERJAAN
volume beton
LC 37.2 17.2 1 37.20 m2
pondasi
slab 37 17 0.4 251.60 m3
kolom 0.5 0.5 1.8 32 14.40 m3
panggung
tie beam 0.5 0.5 14.5 8 29.00 m3
tie beam 0.5 0.5 34.5 4 34.50 m3
slab 35 15 0.25 131.25 m3
dek
kolom 0.5 0.5 3 32 24.00 m3
tie beam 0.5 0.5 14.5 8 29.00 m3
tie beam 0.5 0.5 34.5 4 34.50 m3
slab 35 15 0.25 131.25 m3
volume besi
pondasi
slab 30,192.00 kg 10.06
kolom 1,728.00 kg 0.86
panggung - -
tie beam 3,480.00 kg 1.74
tie beam 4,140.00 kg 2.07
slab 15,750.00 kg 5.25
dek - -
kolom 2,880.00 kg 1.44
tie beam 3,480.00 kg 1.74
tie beam 4,140.00 kg 2.07
slab 15,750.00 kg 5.25
formwork
pondasi
slab 43.20 m2 4.32
kolom 115.20 m2 7.20
panggung
tie beam 174.00 m2 8.70
tie beam 207.00 m2 10.35
slab 550.00 m2 13.75
dek
kolom 192.00 m2 12.00
tie beam 174.00 m2 8.70
tie beam 207.00 m2 10.35
slab 550.00 m2 13.75
pondasi
slab 37 17
jack base sisi 37 124.00 pcs 1 sisi
jack base sisi 17 57.00 pcs 1 sisi
kolom
support vertikal
SC3 1 4 4.00 pcs
SC4 1 4 4.00 pcs
SC4 1 4 4.00 pcs
support horizontal
SC4 3 3 2 24.00 pcs 4 sisi
akses
akses kerja
vertikal 35 15
SC1 35 18 36.00 pcs 1 sisi
SC1 15 8 16.00 pcs 1 sisi
SC4 35 35 35.00 pcs 1 sisi
SC4 15 15 15.00 pcs 1 sisi
SC1 35 9 18.00 pcs 1 sisi
SC1 15 4 8.00 pcs 1 sisi
horizontal
SC1 35 6 42.00 pcs 1 sisi
SC1 15 3 21.00 pcs 1 sisi
deck mezanine
vertikal
35 59
15 25
jack base 1,475.00 pcs 1 sisi
SC2 1,475.00 pcs
horizontal
SC1 35 20 6 120.00 pcs 1 tingkat
SC1 15 9 3 27.00 pcs 1 tingkat
asiba
jack base
SC1
SC2
SC3
SC4
SC5
SC1 6m
SC2 4m
SC3 2m
SC4 1m
SC5 3m
1 breaker
1 exca
4 DT
6 12 orang
4 8 orang
4 8 orang
4 8 orang
6 12 orang
4 8 orang
4 8 orang
4 8 orang
6 12 orang
5 5 orang
8 8 orang
10 10 orang
10 10 orang
20 20 orang
8 8 orang
10 10 orang
10 10 orang
20 20 orang
64.00 pcs 16
64.00 pcs 16
64.00 pcs 16
384.00 pcs 16
1 set saja
1 set saja
312 pcs
3312 pcs
723 pcs
1475 pcs
64 pcs
612 pcs
0 pcs
substatiun building
P L H
17 X 15 3
1.8
pondasi
slab
19 17 0.4
kolom
0.5 0.5 1.8 16
panggung
tie beam
0.5 0.5 14.5 4
0.5 0.5 16.5 4
slab
17 15 0.25
dek
kolom
0.5 0.5 3 16
tie beam
0.5 0.5 14.5 4
0.5 0.5 34.5 4
dek
17 15 0.25
1 Unit Mezanine
ALAT BERAT
volume galian 21 19 0.85 1 17.85 m3 1 lokasi
produktifitas batu
0.26 hari 1 alat
DURASI PEKERJAAN
volume beton
LC 19.2 17.2 1 19.20 m2
pondasi
slab 19 17 0.4 129.20 m3
kolom 0.5 0.5 1.8 16 7.20 m3
panggung
tie beam 0.5 0.5 14.5 4 14.50 m3
tie beam 0.5 0.5 16.5 4 16.50 m3
slab 17 15 0.25 63.75 m3
dek
kolom 0.5 0.5 3 16 12.00 m3
tie beam 0.5 0.5 14.5 4 14.50 m3
tie beam 0.5 0.5 34.5 4 34.50 m3
slab 17 15 0.25 63.75 m3
volume besi
pondasi
slab 15,504.00 kg 5.17
kolom 864.00 kg 0.43
panggung - -
tie beam 1,740.00 kg 0.87
tie beam 1,980.00 kg 0.99
slab 7,650.00 kg 2.55
dek - -
kolom 1,440.00 kg 0.72
tie beam 1,740.00 kg 0.87
tie beam 4,140.00 kg 2.07
slab 7,650.00 kg 2.55
formwork
pondasi
slab 28.80 m2 2.88
kolom 57.60 m2 3.60
panggung
tie beam 87.00 m2 4.35
tie beam 99.00 m2 4.95
slab 271.00 m2 6.78
dek
kolom 96.00 m2 6.00
tie beam 87.00 m2 4.35
tie beam 207.00 m2 10.35
slab 271.00 m2 6.78
pondasi
slab 19 17
jack base sisi 19 64.00 pcs 1 sisi
jack base sisi 17 57.00 pcs 1 sisi
kolom
support vertikal
SC3 1 4 4.00 pcs
SC4 1 4 4.00 pcs
SC4 1 4 4.00 pcs
support horizontal
SC4 3 3 2 24.00 pcs 4 sisi
akses
akses kerja
vertikal 17 15
SC1 17 9 18.00 pcs 1 sisi
SC1 15 8 16.00 pcs 1 sisi
SC4 17 17 17.00 pcs 1 sisi
SC4 15 15 15.00 pcs 1 sisi
SC1 17 5 10.00 pcs 1 sisi
SC1 15 4 8.00 pcs 1 sisi
horizontal
SC1 17 3 21.00 pcs 1 sisi
SC1 15 3 21.00 pcs 1 sisi
deck mezanine
vertikal
17 29
15 25
jack base 725.00 pcs 1 sisi
SC2 725.00 pcs
horizontal
SC1 17 10 3 30.00 pcs 1 tingkat
SC1 15 9 3 27.00 pcs 1 tingkat
asiba
jack base
SC1
SC2
SC3
SC4
SC5
SC1 6m
SC2 4m
SC3 2m
SC4 1m
SC5 3m
1 breaker
1 exca
4 DT
6 12 orang
4 8 orang
4 8 orang
4 8 orang
6 12 orang
4 8 orang
4 8 orang
4 8 orang
6 12 orang
5 5 orang
8 8 orang
10 10 orang
10 10 orang
20 20 orang
8 8 orang
10 10 orang
10 10 orang
20 20 orang
64.00 pcs 16
64.00 pcs 16
64.00 pcs 16
384.00 pcs 16
1 set saja
1 set saja
204 pcs
1692 pcs
359 pcs
725 pcs
64 pcs
576 pcs
0 pcs
asiba
full drat
jack base
plastikon
SC1
SC3
SC4
SC5
wing nut
asiba
full drat
jack base
plastikon
SC1
SC3
SC4
SC5
wing nut
full drat
jack base
plastikon
SC4
wing nut
asiba
jack base
SC1
SC2
SC3
SC4
SC5
asiba
jack base
SC1
SC2
SC3
SC4
SC5
asiba
jack base
SC1
SC2
SC3
SC4
SC5
resume darat
asiba
jack base
SC1
SC2
SC3
SC4
SC5
wing nut
full drat
plastikon
klem
SC1
SC2
SC3
SC4
SC5
jack base
klem
asiba
Resume Total
asiba
full drat
jack base
klem
plastikon
SC1
SC2
SC3
SC4
SC5
wing nut
564 pcs
560 m
1728 pcs
2240 pcs
1400 btg
272 pcs
644 pcs
272 pcs
2240 pcs
288 pcs
210 m
434 pcs
840 pcs
462 pcs
78 pcs
92 pcs
78 pcs
840 pcs
12 m
216 pcs
48 pcs
132 pcs
48 pcs
168 pcs
1340 pcs
362 pcs
448 pcs
32 pcs
310 pcs
32 pcs
312 pcs
3312 pcs
723 pcs
1475 pcs
64 pcs
612 pcs
0 pcs
204 pcs
1692 pcs
359 pcs
725 pcs
64 pcs
576 pcs
0 pcs
1536 pcs
8722 pcs
3306 pcs
2648 pcs
510 pcs
2366 pcs
382 pcs
3128 pcs
782 m
3128 pcs
18424 pcs
19,167 pcs
9,888 pcs
3,456 pcs
10,896 pcs
4,968 pcs
17,484 pcs
26,448 pcs
648 pcs
2,184 pcs
782 m
26,206 pcs
44,872 pcs
3,128 pcs
22,473 pcs
12,536 pcs
3,966 pcs
13,262 pcs
5,350 pcs
3,128 pcs
Remarks
Jam Kerja 8.00 jam Asumsi Jam Kerja (08.00-17.00)
ACCESS BRIDGE
PREPARED FOR BOREPILE
Asumsi Durasi untuk persiapan Sebelum pekerjaan Bore Pile Asumsi penimbunan, peralihan jalur air laut dan juga
90.00 hari
dimulai pemasangan gorong2 akses temporary
Asumsi Volume mengikuti Durasi, berdasarkan produktifitas
Volume Tanah Timbunan for access & etc 32,561.70 m3 Excavator PC200 dan Juga ketersediaan tanah timbunan by PT.
Nursejatin Andika
Luas Area 32,561.70 m2
1 Excavator PC 200
Volume excavation 32,561.70 m3
Bucket Capacity 0.93 m3
Faktor Bucket 1.00
Faktor efesiensi Alat 0.70 Alat lebih dari 5 tahun kerja
Condition of work 0.90 Kondisi site dengan curah hujan tinggi
Swell 0.90
Swing and depth 0.90 Kondisi pengambilan material normal
Equipment management 0.90 management equipment baik
Laoding time 0.25 menit
Swing 0.12 menit
Unloading time 0.08 menit
Siklus Time 0.57 menit
Cycle Per Hour 105.88 cycle/jam
Produktifitas per hour 45.22 m3/jam
Unit Exca PC 200 2.00 Unit
durasi pekerjaan 41.00 hari
Loading Time
- Hauling Capacity : 4.65 m3 (Dump Truck 5 T)
- Number of Bucket : 5 Bucket (Excavator PC 200)
- Swing Duration per bucket : 0.57 minute (Excavator PC 200) 34 detik dari siklus time atau 0.57menit
- Loading Duration : 2.83 minute
Cycle Time:
Hauling (empty) 0.750 Hour = 45.0 minute
Manuver Loading 0.008 Hour = 0.5 minute 30 detik
Loading 0.047 Hour = 2.8 minute
Hauling (loaded) 1.000 Hour = 60 minute
Manuver Dumping 0.008 Hour = 0.5 minute 30 detik
Dumping 0.008 Hour = 0.5 minute 30 detik
Total Cycle Time 1.822 Hour = 109.3 minute
SITE FILLING
Volume Soil B1 32,561.70 M3
Durasi 40.00 hari
1 Excavator PC 200
Loading Time
- Hauling Capacity : 4.65 m3 (Dump Truck 20 T)
- Number of Bucket : 5 Bucket (Excavator PC 200)
- Swing Duration per bucket : 0.57 minute (Excavator PC 200) 34 detik dari siklus time atau 0.57menit
- Loading Duration : 2.83 minute
Cycle Time:
Hauling (empty) 0.750 Hour = 45.0 minute
Manuver Loading 0.008 Hour = 0.5 minute 30 detik
Loading 0.047 Hour = 2.8 minute
Hauling (loaded) 1.000 Hour = 60 minute
Manuver Dumping 0.008 Hour = 0.5 minute 30 detik
Dumping 0.008 Hour = 0.5 minute 30 detik
Total Cycle Time 1.822 Hour = 109.3 minute
3 Perataan By Dozzer
Streppid distance 30.00 m
Lebar area kerja 15.00 m
Faktor Blade 0.80
Faktor Efisiensi alat 0.90
Blade grade 0.70
Lebar Blade 3.98 m
Tinggi Blade 1.55 m
Work efisiensi 0.67
Push Time 0.60 Menit
Reverse Time 0.45 Menit
Manuver Time 0.10 Menit
Waktu Siklus 1.15 menit
Push Speed 3.00 km/jam
Reverse Speed 4.00 km/jam
Faktor Kemiringan pisau grade 1.00
Lebar overlap 0.30 m
Jumlah stripping passes 3.00
Jumlah lane 3.00
Lebar Efektif 10.00 m
Produktifitas per jam 268.44 m2/jam
Produktifitas per Hari 2,147.50 m2/day
Kebutuhan Alat 1.00 Alat
Durasi 11.00 Hari
Produktifitas 1 alat perhari per team 2.00 Titik/Hari Berdasarkan produktifitas aktual di site tuban dengan resources
dan equipment yang tersedia 1 team =
team 1.00 Team
Durasi 24.00 Hari Durasi tidak include PDA Test dan CSL
INSTALL DIAFRAGMA
SLAB INSITU
8 orang
8 Orang
11
11 Orang
11
11 Orang
11
11