Summer 2 • 0 • 0 • 5
PMI-CPM Fall
Conference
Details p. 28 S cope
C ost
(fig1)
CPM President’s Time
Statement
p.5 The law of the Triple Constraint is (fig3)
easily demonstrated.
Continued on page 6
6 Summer 2005
Continued from page 1
Moreover, an expansion in Scope will have a direct Moreover, it is not unusual to see Costs stretched a
effect on Cost or Schedule, or both. little to cover an extended Schedule…
(fig6)
(fig4)
…especially past the cut-off into the next account-
Knowledge of the Constraint, and how to use it is ing period.
the key to project success. While the link between Cost,
Schedule, and Scope is fixed, it is often flexible. Ex-
perienced project managers claim to have seen their
Schedule stretched to accommodate an expanded
Scope.
(fig7)
(fig5)
●
Project Management Process Design
●
Earned Value Management Implementation Project
●
Independent Data Analysis Management
●
Integrated Baseline Reviews Excellence
●
Information Systems Integration
since
●
Software Evaluations & Training
●
Operational Support
Summer 2005 7
Scope, there usually is no corresponding adjustment Let's assume that a project has ten work packages,
in any of the other project metrics. each producing one deliverable. Here are the Earned
Value metrics, including the Deliverables Count met-
ric used in the Project Sextant.
Oh, to be sure, there is usually a scope document.
And sometimes a rigorous control procedure. Or The CPI and SPI are apparently both on track at
maybe even a stern scope committee, or perhaps the 100%. The DPI, or deviation in the apparent plot by
dreaded Scope Change Control Board. Yet the elusive any change in the underlying deliverables, is neutral,
Scope remains the project manager's most common so the project is exactly on course at the point of 10%
escape clause: completion, a fairly typical project status.
eted Cost of Work Scheduled. There should be appro- Project Sextant will be approximately 20% over
priate consideration of the Deliverables Variance and budget and 20% behind schedule.
Deliverables Performance Index. When applied to the
CPI and SPI, the DPI clearly indicates that the project
is off-course at the mid-point of the work.
Summary:
Few of us have the luxury of working on projects
with a budget of "whatever it takes". Instead we plan
every penny, predict every deliverable, and answer to
every sponsor and investor. The real benefit of the
Sextant approach is more than "tweaking" Earned
Value. It is the simple underlying logic. The Triple
Constraint is well known, and respected in virtually
every business discipline. The Deliverables Variance
and Deliverables Performance Index is a simple ex-
tension of widely accepted Earned Value methods.
Together with the CPI and SPI, the DPI reduces com-
plex Earned Value calculation spreadsheets to a sim-
ple picture with the intuitive Triple Constraint per-
spective. So the Project Sextant is an instantly-recog-
nizable method for identifying, and demonstrating, a
project's status. Moreover, a series of Sextant plots
presents an unmistakable projection of the project's
true course. Finally, with a sufficient history of
projects plotted with the Sextant, an organization can
At this point we can predict that given the project's develop an indicative and even predictive tool for
twenty-percent course and performance, the final project performance within the organization's own
Summer 2005 11
unique constraints, as shown in the two isolated SPI As a project manager's tool, the Project Sextant ap-
vertical and CPI horizontal perspectives of the three- proach is effective at the activity level. It is equally
dimensional series example on the following page. effective for the savvy business manager, at the pro-
gram level, spotting characteristic behaviors affect-
Note the path of the Schedule Performance Index at ing dozens of projects.
the top, looking downward on the 3D history of the
project. Note the path of the Cost Performance Index About the Author
at the bottom, as seen by looking at the course of the
project directly from the front. This is representative Steve VanArsdale is a contract senior manager for IBM,
of the course of most good projects with a mid-project Unisys, and now Computer Associates, with success-
funding gate. There is often a sudden shift in the cost ful projects in 23 three states and seven countries. Mr.
reporting just before the funding gate, followed by a VanArsdale personally managed major complex
slight "sigh-of-relief" schedule slippage. Then near projects for industry leaders Allstate, Bank of America,
the end of the project there is often a flurry of rework Sears, Marriott, and TetraPak Lavel. He has also served
that is visible in the SPI, and an accumulation of small as a project program portfolio director, PMO manager,
unanticipated costs affecting the CPI. In each project and OPM3 mentor, and has worked in several strate-
organization, the Sextant course plots for major gic projects in partnership with major consulting firms
projects will often show a distinct pattern correspond- such as McKinney and Booz Allen Hamilton. Cur-
ing to the organization's standards, policies, and prac- rently, Mr. VanArsdale is working in IT auditing for
tices. Knowing this pattern is the means for recogniz- project process improvement, using CAAT tools such
ing when a project team has improved upon standard as continuous Earned Value. He is a graduate of Ohio
practice instead of just fudging the numbers. State University, a PMI Project Management Profes-
sional, AICPA Certified Public Accountant, and a 2005
(Chart Shown on page 12) candidate for ISACA Certified Information Systems
Auditor.
Continued on page 12