Anda di halaman 1dari 8

Summer 2005 1

Summer 2 • 0 • 0 • 5

The Measurable News


The Magazine of the Project Management Institute’s College of Performance Management

CONTENTS The Project Management Sextant


The Project Management Sextant
By Steve VanArsdale.................pg 1 By Steve VanArsdale

Letter to the Editor


By Richard Nimon ................... pg 3

A Re-Examination of Project Introduction Consider:


Outcome Prediction
By Walt Lipke.........................pg 14 A reduction in a tight Schedule, by
"Triple Constraint" necessity, increases the Cost.
Applying Earned Value Metrics Earned Value
to Analyze, Forecast and Report
Schedule Performance There is a Force that binds all
by Dave Jacob .......................pg 21 projects. It is as relentless as gravity,
and equally impossible to work
against. But like gravity, one can sense
when it might hurt you. The force that
shapes projects, and careers, is known
as the Triple Constraint. (fig2)

In every project, Cost and Time


are immutably linked by the Scope. Likewise, if the Scope remains con-
stant, a reduction in Cost typically ex-
tends the Schedule.

PMI-CPM Fall
Conference
Details p. 28 S cope
C ost
(fig1)
CPM President’s Time
Statement
p.5 The law of the Triple Constraint is (fig3)
easily demonstrated.

Continued on page 6
6 Summer 2005
Continued from page 1

Moreover, an expansion in Scope will have a direct Moreover, it is not unusual to see Costs stretched a
effect on Cost or Schedule, or both. little to cover an extended Schedule…

(fig6)
(fig4)
…especially past the cut-off into the next account-
Knowledge of the Constraint, and how to use it is ing period.
the key to project success. While the link between Cost,
Schedule, and Scope is fixed, it is often flexible. Ex-
perienced project managers claim to have seen their
Schedule stretched to accommodate an expanded
Scope.

(fig7)

(fig5)


Project Management Process Design

Earned Value Management Implementation Project

Independent Data Analysis Management

Integrated Baseline Reviews Excellence

Information Systems Integration
since

Software Evaluations & Training

Operational Support
Summer 2005 7

The Triple Constraint is not "dark science". It


has been known and practiced for decades.The con- Tested. At the other extreme, there are attributes of
cept of the Triple Constraint led to the U.S. Govern- expanded Scope: super-tested deliverables, "gold-
ment's supplier Cost/Schedule Control Systems Cri- plated" deliverables, and even deliverables that evolve
teria in the 1960's. C/SCSC focused on two of the con- into "delighters" (to borrow a delightful Six Sigma
straints, Cost and Time, and led to the technique known term). But recognizing these attributes, and measur-
as Earned Value, now considered a standard of project ing the changes, is simply part of effective Scope defi-
management. However, while EV is widely practiced nition.
in government and private industry, studies show that
70% of all projects exceed cost budgets or time sched- In practice a "five-way" Constraint is totally unwork-
ules or both. Moreover, industry satisfaction surveys able; a triangle is inherently more stable. Moreover,
suggest that sponsors and stakeholders are rarely get- it's not necessary; risk and quality are always con-
ting what they expected. trolled as attributes of Scope. The project cost is How
Much, time is When, while Scope is the What and
Part of the problem is thought to be the volume of risk and quality are simply the How and How Well
tabular data in the EV calculations for a project. An- attributes of Scope.
other problem is that there is a "dark" or hidden fac-
tor, the Scope. The following paper suggests that a new
metric is needed. The benefit is that all three funda- The Elusive Earned Value
mental factors can then be controlled. Another benefit Scope Metric
is that all three Constraints are revealed, the project
snaps into sharp focus, and a simple graphic can be an Let's consider the situ-
extraordinarily effective project control and even pre- ation. The Triple Con-
dictive tool. straint concept is decep-
tively easy to understand.
It appears just as easy to
The "Big Three" master. However, master-
ing the"3C" calls for the
practice of Earned Value.
Scope, Time, and Cost are the big three factors of Earned Value is a series of calculations that measure
What, When, and How Much. From time to time there two of the three Constraints. First one calculates the
have been debates about more "constraints", notably Cost Variance, or the difference between what was
risk and quality. IMHO, in most cases these additional planned expenditure and the actual. Then one calcu-
factors are simply attributes of Scope. lates the Schedule Variance, or the difference between
the time planned and expended. Comparing the Cost
All three Constraints have unique attributes. Cost Variance and the Schedule Variance to the original plan
has attributes: fixed, variable, regular, recurring, purports to show how well the project is doing. Or
phased, and of course, the accountant's favorite, op- perhaps, how well the project managers are doing with
portunity cost. Time has even more: person-hours, the project. (see italics following)
clock-time, overtime, full-time, part-time, downtime, Volumes have been written, upon these "project
discrete, recurring, lag and slack, chargeable, billable, metrics". Yet studies have determined that most
probable, imbedded, hidden, and recorded time… not projects fail to meet their budgets, or schedules, or
to mention the schedule-rescuing "off-the-clock" time. both. Not just some projects, or even a lot of them,
So Scope also has attributes. In addition to the at- but most (70% reported in the 1995 and 1997 Standish
tributes of specified, requested, and expected, there Group CHAOS reports). This is disconcerting. Earned
are risk attributes associated with each deliverable: Value has been practiced for forty years. Yet some-
risk type, likelihood, and impact. And there are qual- thing in Earned Value has been missing. Poor per-
ity attributes for each deliverable: unit tested, beta- formance goes undetected, and worse yet, good per-
tested, integration-tested, stress-tested, and user-ac- formance can go unrecognized. Perhaps this is because
ceptance-tested… as opposed to the unfortunate Not- if and when there is a shift in the third Constraint, the
Continued on page 8
8 Summer 2005
Continued from page 7

Scope, there usually is no corresponding adjustment Let's assume that a project has ten work packages,
in any of the other project metrics. each producing one deliverable. Here are the Earned
Value metrics, including the Deliverables Count met-
ric used in the Project Sextant.
Oh, to be sure, there is usually a scope document.
And sometimes a rigorous control procedure. Or The CPI and SPI are apparently both on track at
maybe even a stern scope committee, or perhaps the 100%. The DPI, or deviation in the apparent plot by
dreaded Scope Change Control Board. Yet the elusive any change in the underlying deliverables, is neutral,
Scope remains the project manager's most common so the project is exactly on course at the point of 10%
escape clause: completion, a fairly typical project status.

"Well, yes, of course, the SPI indicates that we're


behind schedule, which isn't exactly true, and the CPI Project is 10% Complete
suggests we're over-budget, although we're really not…
because we're not actually going to do all that stuff in
exactly that way."

Now there is a method to retire this lame defense.


That method is a simple calculation, depicted in an
even simpler graphic. The Project
Sextant is a precision instrument
designed to reveal a project's true
course, using the tools and tech-
niques of Earned Value within the
context of the Triple Constraint.

Earned Value rules dictate that the Cost Perform-


ance Index, or CPI, and the Schedule Performance
Index, or SPI, are calculated as percentages such that
a number larger than 1.00 is ahead of plan (desirable),
less than 1.00 is behind (bad), and an index of 1.00 is
on track. The CPI and SPI can, of course, be calcu-
lated precisely, but the result is not always meaning-
ful. For example, if the CPI is 0.90, and the SPI is
1.10, can the project be considered OK?

However, the CPI and SPI can be plotted on an X-Y


line graph. When this plot is adjusted by the DPI, or
Deliverables Performance Index, the succinct devia-
tion in the Triple Constraint is suddenly visible. Like
a ship's compass in the hands of a trained navigator, a
universal law is transformed into a manager's tool. This Sextant at the 10% Completion Point
new "triple factor" graphic shows instantly the status
of the project and the degree by which it is off-course.
For this reason, this technique is called the Project By the 20% point in the progress of the project, the
Sextant. deliverables are better understood, and are being re-
considered in the light of what is feasible. Below you
Like Earned Value versus the Triple Constraint, some find diagrams of the Sextant at the point that the project
things are better seen than described. Following is an is 20% complete.
example.
Summer 2005 9

Project is 20% Complete

Sextant at the 50% Completion Point

Here are the Earned Value Sextant metrics at the point


that the project is 50% completed.

Project at the 50% Completion Point

Sextant at the 20% Completion Point

The small blue dot represents the plot of the CPI


and SPI. It is apparently within the tolerance limit,
that is, plus or minus ten percent of 100% on track.
Note that the Cost Performance Index, CPI, and
But the larger symbol to the lower right is the actual
Schedule Performance Index, SPI, indicate the project
Sextant course, adjusted for the deviation in the
is within the tolerance limits, ahead of schedule and
deliverables.
budget, as shown by the small dot at the top center.
However, as shown by the large block to the left, when
Note that the deliverable for work package WBS-
the Deliverables Performance Index or DPI is applied,
2 is considered complete, at only 0.9 or 90% of the
the actual project course is behind schedule and over
specification. The deliverables for work packages
budget. This is borne out by close examination of the
WBS-3 has been cut back to half the original plan,
table. The work packages WBS-2 and WBS-3 are con-
perhaps for testing that is now considered unneces-
sidered complete (EV of 1.0) but the actual deliverables
sary.
were reduced to 0.9 and 0.5 respectively. These
changes may be legitimate reductions in the testing
efforts required, or elimination of specified functions.
In any case, since these changes in Scope are rarely
reflected in reduced Actual Costs (AC) nor in the Budg-
Continued on page 10
10 Summer 2005
Continued from page 9

eted Cost of Work Scheduled. There should be appro- Project Sextant will be approximately 20% over
priate consideration of the Deliverables Variance and budget and 20% behind schedule.
Deliverables Performance Index. When applied to the
CPI and SPI, the DPI clearly indicates that the project
is off-course at the mid-point of the work.

Even at this early stage the Project Sextant shows a


clear and lethal deviation for this project. According to
David Christensen and Scott Heise in the National
Contract Management Association Journal in 1993, a
project's final CPI will not typically change by more
than 10% from the value at the 20% project comple-
tion point.

Given the DPI, a calculation of Estimate at Comple-


tion (BAC divided by the Sextant-corrected CPI) indi-
cates this project will be at least 16% over budget.
Moreover, it is known that this simple EAC calcula-
tion tends to understate the actual total project cost
overrun, if the factors such as rework that caused the While the small dot at the center representing CPI
deviation from the baseline plan are expected to con- and SPI seems to be on track, the Sextant reveals that
tinue. this project will end up considerably off its course.
Management can be forewarned, for example, that if
Now, plotting the Sextant in series can be useful. this is a million-dollar effort, there will need to be an
Simple line/slope extrapolation from the 20% and 50% additional $160,000 allocated to complete all the
points produces a Sextant for this project that looks deliverables of this project. If this project is a space
like this. shuttle mission, it will miss the launch window by 16
days. In either case, a "course change" is needed
immediately, before careers are at stake.

Summary:
Few of us have the luxury of working on projects
with a budget of "whatever it takes". Instead we plan
every penny, predict every deliverable, and answer to
every sponsor and investor. The real benefit of the
Sextant approach is more than "tweaking" Earned
Value. It is the simple underlying logic. The Triple
Constraint is well known, and respected in virtually
every business discipline. The Deliverables Variance
and Deliverables Performance Index is a simple ex-
tension of widely accepted Earned Value methods.
Together with the CPI and SPI, the DPI reduces com-
plex Earned Value calculation spreadsheets to a sim-
ple picture with the intuitive Triple Constraint per-
spective. So the Project Sextant is an instantly-recog-
nizable method for identifying, and demonstrating, a
project's status. Moreover, a series of Sextant plots
presents an unmistakable projection of the project's
true course. Finally, with a sufficient history of
projects plotted with the Sextant, an organization can
At this point we can predict that given the project's develop an indicative and even predictive tool for
twenty-percent course and performance, the final project performance within the organization's own
Summer 2005 11

unique constraints, as shown in the two isolated SPI As a project manager's tool, the Project Sextant ap-
vertical and CPI horizontal perspectives of the three- proach is effective at the activity level. It is equally
dimensional series example on the following page. effective for the savvy business manager, at the pro-
gram level, spotting characteristic behaviors affect-
Note the path of the Schedule Performance Index at ing dozens of projects.
the top, looking downward on the 3D history of the
project. Note the path of the Cost Performance Index About the Author
at the bottom, as seen by looking at the course of the
project directly from the front. This is representative Steve VanArsdale is a contract senior manager for IBM,
of the course of most good projects with a mid-project Unisys, and now Computer Associates, with success-
funding gate. There is often a sudden shift in the cost ful projects in 23 three states and seven countries. Mr.
reporting just before the funding gate, followed by a VanArsdale personally managed major complex
slight "sigh-of-relief" schedule slippage. Then near projects for industry leaders Allstate, Bank of America,
the end of the project there is often a flurry of rework Sears, Marriott, and TetraPak Lavel. He has also served
that is visible in the SPI, and an accumulation of small as a project program portfolio director, PMO manager,
unanticipated costs affecting the CPI. In each project and OPM3 mentor, and has worked in several strate-
organization, the Sextant course plots for major gic projects in partnership with major consulting firms
projects will often show a distinct pattern correspond- such as McKinney and Booz Allen Hamilton. Cur-
ing to the organization's standards, policies, and prac- rently, Mr. VanArsdale is working in IT auditing for
tices. Knowing this pattern is the means for recogniz- project process improvement, using CAAT tools such
ing when a project team has improved upon standard as continuous Earned Value. He is a graduate of Ohio
practice instead of just fudging the numbers. State University, a PMI Project Management Profes-
sional, AICPA Certified Public Accountant, and a 2005
(Chart Shown on page 12) candidate for ISACA Certified Information Systems
Auditor.
Continued on page 12

Our 17th Annual


International Integrated Program
Management Conference
From Nov. 7-9 2005
at the
SHERATON PREMIER HOTEL
For
Information and Registration Form
See Pg. 28 & 29
12 Summer 2005
Continued from page 11

Anda mungkin juga menyukai