LAPORAN PENJADWALAN KURVA S 0% A002/T100.

80/I-2023 Pembangunan Rumah Tinggal 2 Lantai Type 200


W 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Kurva S (All) Start 1-Jan-23 B 0.06 0.02 0.02 0.04 0.03 0.06 0.06 0.06 0.05 0.05 0.02 0.02 0.08 0.04 0.04 0.07 0.03 0.11 0.07 0.06 0.01

Finish 23-May-23 % 6% 8% 10% 14% 17% 23% 29% 34% 40% 45% 46% 48% 56% 61% 65% 72% 76% 87% 94% 99% 100%

14-May-23

21-May-23
12-Mar-23

19-Mar-23

26-Mar-23

16-Apr-23

23-Apr-23

30-Apr-23
12-Feb-23

19-Feb-23

26-Feb-23

7-May-23
15-Jan-23

22-Jan-23

29-Jan-23

5-Mar-23
Tanggal

2-Apr-23

9-Apr-23
5-Feb-23
1-Jan-23

8-Jan-23
ID Bobot NAMA PEKERJAAN Mulai Selesai Durasi

99% 100% 100%


A 3.31% PEKERJAAN PERSIAPAN 1 1 1 100% 0.03
94%
B 9.36% PEKERJAAN PONDASI 1 4 4 0.02 0.02 0.02 0.02
C 3.09% PEKERJAAN SLOOF 4 5 2 0.02 0.02 87%
D 0.59% PEKERJAAN TIMBUNAN 5 5 1 0.01
E 7.35% PEKERJAAN KOLOM 5 13 9 75% 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
76%
72%
F 4.90% PEKERJAAN RINGBALOK (BALOK) 6 13 8 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
65%
G 17.24% PEKERJAAN COR PLATE BETON (DAK BETON) 6 10 5 0.03 0.03 0.03 0.03 0.03 61%
H 16.79% PEKERJAAN DINDING 13 16 4 56%
0.04 0.04 0.04 0.04
I 7.56% PEKERJAAN ATAP 16 18 3 50% 48%
0.03 0.03 0.03
- 45% 46%
J 3.87% PEKERJAAN PINTU, JENDELA DAN ACCESORIS 18 18 1 0.04
K 2.97% PEKERJAAN INST. PIPA AIR BERSIH &SANITASI 7 16 10 0.00 0.00 40%
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
34%
L 1.10% PEKERJAAN INST. LISTRIK DAN PENERANGAN 19 19 1 0.01
29%
M 8.78% PEKERJAAN KERAMIK LANTAI DAN DINDING 18 20 3 0.03 0.03 0.03
23%
N 3.27% PEKERJAAN LANGIT-LANGIT (PLAFON) 18 20 3 25% 0.01 0.01 0.01
17%
O 3.58% PEKERJAAN PENGECATAN DAN WATERPROFING 17 20 4 14% 0.01 0.01 0.01 0.01
P 2.18% PEKERJAAN TANGGA 13 13 1 10% 0.02
8%
6%
Q 1.98% PEKERJAAN PAGAR DAN TAMAN/HALAMAN 6 8 3 0.01 0.01 0.01
R 2.07% PEKERJAAN TAMBAHAN DAN LAINNYA 19 21 3 0% 0.01 0.01 0.01
(blank) 0.00%
0.00%