Naad 5 mm
Naad 5 mm Naad 5 mm
Plint Lantai
Lantai kerja
Trasraam
20 ±0.00 20 ±0.00
Sloop 15/20
4Ø10, Sk. Ø8-15
25 25
C C Tanah urug Tanah urug
140 140
KP KP K1
4 80 Pondasi Batu 80 Pondasi Batu
Kali 1pc : 3ps Kali 1pc : 3ps
1200
B
K1
3250
K1
15 Aanstamping 15 Aanstamping
KP KP A Lantai kerja Lantai kerja
5 5
3100
KP KP KP 70 20 20 80 20
3 KP NO. TANGGAL CATATAN DAN REVISI
POTONGAN A POTONGAN B
1500
REVISI
SKALA 1 : 25 SKALA 1 : 25
KP KP KP KP KP
2
1000
15 15
500
A
KP
2500
1000
B K1
-0.20 -0.20
K1
1000
K1
500
25 20
Tanah urug Tanah urug
100 60
120 80 Pondasi Batu Pondasi Batu
Kali 1pc : 3ps Kali 1pc : 3ps
5500
15 Aanstamping
5 Lantai kerja
15 Aanstamping
D 5 Lantai kerja 40 20
RUMAH TINGGAL
60 20 JL. ADELIA 1 NO. 6
POTONGAN C POTONGAN D
SKALA 1 : 25 SKALA 1 : 25 DENAH PONDASI DAN
DETAIL
3950 3000 1000
1:100
7950
15
15 A3
15
A B 4Ø10
4Ø12
4Ø10
20 25
Sk. Ø8-15 Sk. Ø8-15 15 Sk. Ø8-15
DENAH PONDASI
SKALA 1 : 50 DET. SLOOP DET. KOLOM K1 DET. KOLOM KP
SKALA 1 : 25 SKALA 1 : 25 SKALA 1 : 25
STR-001 15-02-2018
TENDER