Rab Puskesmas Banjarmangu 1 Terbaru Ok
Rab Puskesmas Banjarmangu 1 Terbaru Ok
HARGA
NO URAIAN PEKERJAAN Rp
1 2 3
A PEKERJAAN PERSIAPAN
I PEKERJAAN PERSIAPAN 51,687,104.52
B PEKERJAAN CUT & FILL
I PEKERJAAN TANAH 131,319,359.13
C PEKERJAAN TALUD & SALURAN
I PEKERJAAN TANAH 5,185,957.72
II PEKERJAAN PONDASI 57,129,103.93
III PEKERJAAN BESI & ALUMUNIUM 18,291,377.28
IV PEKERJAAN PLESTERAN 11,101,082.58
1 2 3 4 5 6 7
A PEKERJAAN PERSIAPAN
I PEKERJAAN PERSIAPAN
1 Papan Nama Kegiatan ls 1.00 Dihitung (a) 196,152.00 196,152.00
2 Pengukuran dan Pemasangan Bouwplank m' 294.90 1.1.d 70,017.20 20,648,072.28
3 Pembongkaran 1 m3 Dinding Tembok Bata m3 266.20 1.1.h 60,766.68 16,176,167.24
4 Keselamatan dan Kesehatan Kerja (K3)
- Alat Pelindung Diri
- Topi Pelindung (safety helmet) 1 buah buah 20.00 Dihitung (e) 38,500.00 770,000.00
- Pelindung Pernafasan dan Mulut (Masker) 1 dus dus 10.00 Dihitung (f) 27,500.00 275,000.00
- Sarung tangan (Safety Glooves) 1 set psg 20.00 Dihitung (g) 5,500.00 110,000.00
- Sepatu Keselamatan (Sepatu boot) 1 set psg 20.00 Dihitung (h) 132,000.00 2,640,000.00
- Rompi Keselamatan (Safety Vest) 1 buah buah 20.00 Dihitung (i) 38,500.00 770,000.00
- BPJS Ketenagakerjaan dan keselamatan kerja ls 1.00 Dihitung (n) 7,913,637.00 7,913,637.00
- Spanduk K3 ls 5.00 Dihitung (b) 85,615.20 428,076.00
5 Pengujian Laboratorium
- Cylinder/Cube Mould for Compressive Strength buah 27.00 Dihitung (l) 55,000.00 1,485,000.00
- Uji Mortar buah 5.00 Dihitung (m) 55,000.00 275,000.00
SUB TOTAL BAGIAN A : PEKERJAAN PERSIAPAN 51,687,104.52
B PEKERJAAN CUT & FILL
I PEKERJAAN TANAH
1 Penggalian 1 m3 Tanah Biasa Sedalam s.d. 1 m m3 807.88 1.7.1.a 67,116.50 54,222,224.84
2 Pembuangan Tanah Sejauh 40 m m3 807.88 Dihitung.1.5.5 95,431.16 77,097,134.30
SUB TOTAL BAGIAN I : PEKERJAAN TANAH 131,319,359.13
SUB TOTAL BAGIAN B : PEKERJAAN CUT & FILL 131,319,359.13
C PEKERJAAN TALUD & SALURAN
I PEKERJAAN TANAH
1 Penggalian 1 m3 Tanah Biasa Sedalam s.d. 1 m m3 77.27 1.7.1.a 67,116.50 5,185,957.72
SUB TOTAL BAGIAN I : PEKERJAAN TANAH 5,185,957.72
II PEKERJAAN PONDASI
1 Pemasangan Pondasi Batu Belah 1SP : 6 PP m3 65.99 2.1.1.d 865,749.89 57,129,103.93
SUB TOTAL BAGIAN II : PEKERJAAN PONDASI 57,129,103.93
III PEKERJAAN BESI & ALUMUNIUM
1 Pemasangan Grill Besi Lebar 40 cm Besi Siku m' 56.40 Dihitung.4.2.22 324,315.20 18,291,377.28
SUB TOTAL BAGIAN III : PEKERJAAN BESI & ALUMUNIUM 18,291,377.28
IV PEKERJAAN PLESTERAN
1 Pemasangan Plesteran 1 SP : 6 PP Tebal 15 mm m2 101.52 3.2.4.(c).a 56,291.41 5,714,703.89
2 Pemasangan Finishing Siar Pas.Batu Kali Adukan 1Pc : 2Pp m2 36.66 A.4.4.2.26 55,165.61 2,022,371.37
3 Pemasangan 1 m2 Acian m2 101.52 3.2.2.(c).b 33,136.40 3,364,007.33
SUB TOTAL BAGIAN IV : PEKERJAAN PLESTERAN 11,101,082.58
SUB TOTAL BAGIAN C : PEKERJAAN TALUD & SALURAN 91,707,521.51
D PEKERJAAN GEDUNG UTAMA A (LANTAI 1)
I PEKERJAAN TANAH
1 Penggalian 1 m3 Tanah Biasa Sedalam s.d. 1 m m3 446.68 1.7.1.a 67,116.50 29,979,863.33
2 Pengurugan Kembali 1 m3 Galian Tanah m3 194.07 1.7.2.a 16,027.00 3,110,345.07
3 Pengurugan 1m3 Dengan Pasir Urug m3 17.44 1.7.2.d 351,566.60 6,131,022.67
4 Urugan Pasir Bawah Lantai Keramik m3 30.33 1.7.2.d.a 351,566.60 10,661,331.85
SUB TOTAL BAGIAN I : PEKERJAAN TANAH 49,882,562.92
II PEKERJAAN PONDASI
1 Pemasangan Pondasi Batu Belah 1SP : 6 PP m3 120.23 2.1.1.d 865,749.89 104,085,300.32
2 Pemasang Batu Kosong/Anstamping m3 49.16 A.3.2.1.9 487,888.45 23,986,547.90
SUB TOTAL BAGIAN II : PEKERJAAN PONDASI 128,071,848.21
III PEKERJAAN BETON
1 Lantai Kerja
- Pembuatan 1 m3 Beton Mutu f’c = 7,4 Mpa (K100) m3 8.52 A.4.1.1.1 962,281.51 8,194,909.62
2 Drop Off
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 4.90 A.4.1.1.7 1,129,166.98 5,532,212.49
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 398.25 2.2.6.1.b 16,196.88 6,450,395.06
- Pemasangan 1 m2 Bekisting untuk Pondasi Telapak Beton Bangunan Gedung (volume dibagi 2 kali) m2 1.46 A.4.1.1.18 187,617.54 274,390.65
3 Footplat (FP 1)
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 57.27 A.4.1.1.7 1,129,166.98 64,667,393.11
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 7,143.27 2.2.6.1.b 16,196.88 115,698,701.07
- Pemasangan 1 m2 Bekisting untuk Pondasi Telapak Beton Bangunan Gedung (volume dibagi 2 kali) m2 133.86 A.4.1.1.18 187,617.54 25,114,483.90
4 Footplat (FP 2)
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 1.08 A.4.1.1.7 1,129,166.98 1,220,629.51
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 149.40 2.2.6.1.b 16,196.88 2,419,752.90
- Pemasangan 1 m2 Bekisting untuk Pondasi Telapak Beton Bangunan Gedung (volume dibagi 2 kali) m2 3.10 A.4.1.1.18 187,617.54 581,614.37
5 Sloof (SL 1) 20 x 25 cm
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 15.44 A.4.1.1.7 1,129,166.98 17,436,808.27
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 2,931.91 2.2.6.1.b 16,196.88 47,487,826.32
- Pemasangan 1 m2 Bekisting untuk Sloof Beton Bangunan Gedung (volume dibagi 2 kali) m2 77.88 A.4.1.1.19 201,092.54 15,661,338.38
6 Sloof (SL 2) 15 x 25 cm
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 4.35 A.4.1.1.7 1,129,166.98 4,913,358.41
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 832.46 2.2.6.1.b 16,196.88 13,483,233.28
- Pemasangan 1 m2 Bekisting untuk Sloof Beton Bangunan Gedung (volume dibagi 2 kali) m2 29.55 A.4.1.1.19 201,092.54 5,942,787.29
7 Kolom (K 1) 30 x 30 cm
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 25.57 A.4.1.1.7 1,129,166.98 28,876,751.84
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 4,440.50 2.2.6.1.b 16,196.88 71,922,208.46
- Pemasangan 1 m2 Bekisting untuk Kolom Beton Bangunan Gedung (volume dibagi 2 kali) m2 167.04 A.4.1.1.20 326,489.57 54,536,817.77
8 Kolom (K 2) 25 x 25 cm
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 0.23 A.4.1.1.7 1,129,166.98 254,062.57
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 34.95 2.2.6.1.b 16,196.88 566,051.16
- Pemasangan 1 m2 Bekisting untuk Kolom Beton Bangunan Gedung (volume dibagi 2 kali) m2 1.80 A.4.1.1.20 326,489.57 587,681.23
9 Kolom (K 3) 15 x 15 cm
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 5.19 A.4.1.1.7 1,129,166.98 5,865,034.45
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 1,134.62 2.2.6.1.b 16,196.88 18,377,251.25
- Pemasangan 1 m2 Bekisting untuk Kolom Beton Bangunan Gedung (volume dibagi 2 kali) m2 32.49 A.4.1.1.20 326,489.57 10,607,646.13
10 Balok (B 1) 20 x 40 cm
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 23.41 A.4.1.1.7 1,129,166.98 26,431,540.73
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 3,692.50 2.2.6.1.b 16,196.88 59,807,047.99
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali) m2 108.26 A.4.1.1.21 334,409.57 36,203,848.87
11 Balok (B 2) 15 x 30 cm
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 1.85 A.4.1.1.7 1,129,166.98 2,091,951.21
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 337.05 2.2.6.1.b 16,196.88 5,459,178.44
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali) m2 10.14 A.4.1.1.21 334,409.57 3,390,127.18
12 Balok Gantung (BG) 15 x 25 cm
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 1.91 A.4.1.1.7 1,129,166.98 2,154,238.88
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 369.61 2.2.6.1.b 16,196.88 5,986,594.18
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali) m2 16.54 A.4.1.1.21 334,409.57 5,531,134.29
13 Balok Latei 12 x 20 cm
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 3.67 A.4.1.1.7 1,129,166.98 4,144,946.16
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 836.73 2.2.6.1.b 16,196.88 13,552,443.94
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali) m2 30.59 A.4.1.1.21 334,409.57 10,229,588.75
14 Plat Leuvel
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 2.02 A.4.1.1.7 1,129,166.98 2,276,287.72
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 790.55 2.2.6.1.b 16,196.88 12,804,451.18
- Pemasangan 1 m2 Bekisting untuk Plat lantai Beton Bangunan Gedung m2 17.65 A.4.1.1.22 392,489.57 6,926,263.44
15 Ring Balk 15 x 20 cm
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 2.78 A.4.1.1.7 1,129,166.98 3,135,132.13
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 638.79 2.2.6.1.b 16,196.88 10,346,370.41
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali) m2 18.51 A.4.1.1.21 334,409.57 6,189,921.14
16 Plat Lantai
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 43.79 A.4.1.1.7 1,129,166.98 49,449,722.60
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 4,615.40 2.2.6.1.b 16,196.88 74,755,040.51
- Pemasangan 1 m2 Bekisting untuk Plat lantai Beton Bangunan Gedung m2 336.87 A.4.1.1.22 392,489.57 132,217,961.45
17 Saluran Air Hujan
- Pembuatan 1 m3 Beton Mutu f’c = 14,5 Mpa (K175) m3 1.89 A.4.1.1.5. 1,068,452.47 2,014,032.91
18 Pengunci Beton Terawang
- Pembuatan 1 m3 Beton Mutu f’c = 14,5 Mpa (K175) m3 0.32 A.4.1.1.5. 1,068,452.47 346,178.60
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 40.13 2.2.6.1.b 16,196.88 650,048.17
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali) m2 1.71 A.4.1.1.21 334,409.57 570,168.32
19 Tangga Utama
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 3.06 A.4.1.1.7 1,129,166.98 3,456,605.97
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 537.85 2.2.6.1.b 16,196.88 8,711,464.31
- Pemasangan 1 m2 Bekisting untuk Plat lantai Beton Bangunan Gedung m2 25.62 A.4.1.1.22 392,489.57 10,056,564.01
20 Tangga Darurat
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 1.99 A.4.1.1.7 1,129,166.98 2,247,945.63
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 326.44 2.2.6.1.b 16,196.88 5,287,258.17
- Pemasangan 1 m2 Bekisting untuk Plat lantai Beton Bangunan Gedung m2 18.30 A.4.1.1.22 392,489.57 7,184,129.09
SUB TOTAL BAGIAN III : PEKERJAAN BETON 1,040,281,525.85
IV PEKERJAAN BESI & ALUMUNIUM
1 Pemasangan 1 m Kusen Aluminium m1 1,029.98 A.4.2.1.24. 103,572.49 106,677,594.28
2 Pemasangan Pintu Allumunium Strip Lebar 8 cm m2 10.80 A.4.2.1.25 475,689.12 5,137,442.44
3 Pemasangan Pintu Kaca Rangka Allumunium m2 70.40 A.4.2.1.26 664,414.25 46,774,762.85
4 Pemasangan Jendela Kaca Rangka Allumunium m2 117.29 A.4.2.1.26.a 664,414.25 77,930,475.62
5 Pemasangan 1 m2 Rangka Besi Hollow Galvanis 40.40 mm, Modul 60 x m2 711.97 A.4.2.1.21 276,568.05 196,907,670.56
6 60 cm, untuk Plafon
Pemasangan 1 m2 Kanopy Rangka Atap Hollow Galvanis + Assesoris m2 174.17 Dihitung.4.2.6 498,115.20 86,757,073.06
7 Pemasangan 1 M2 Atap Jurai/Limasan Rangka Atap Baja Ringan (Canai Dingin) Profil C75 m2 232.94 A.4.2.1.23 290,336.71 67,630,596.79
8 Pemasangan 1 m' talang galvalum 30x30 cm, rangka hollow galvanis 3.5/3.5 cm, Jarak Rangka 60cm m1 68.75 Dihitung.4.2.7 153,540.20 10,555,888.75
9 Pemasangan Rangka Kuda-kuda Baja IWF 150.75.5.7 mm kg 633.50 A.4.2.1.1. 33,589.82 21,279,150.97
10 Klem Pengunci Seling buah 72.00 Dihitung.4.2.23 35,392.90 2,548,288.51
11 Spaner D16mm buah 8.00 Dihitung.4.2.24 92,592.90 740,743.17
12 Kawat Seling 12 mm m1 22.80 Dihitung.4.2.25 70,592.90 1,609,518.03
13 Pemasangan 1 buah Baut Angkur Ø16 buah 16.00 Dihitung.4.2.5 36,115.20 577,843.20
14 Pemasangan 1 m1 Ralling Stainlles steel m1 24.80 Dihitung.4.2.3 243,665.40 6,042,901.92
15 Pemasangan 1 m2 ACP + Rangka m2 53.45 Dihitung.4.2.17 951,336.54 50,844,181.38
16 Pasang Wenfire (Bahan Plat Galvalum) m1 46.55 Dihitung.4.2.19 57,583.35 2,680,504.94
17 Pembuatan Meja & Background Loby Ruang Pendaftaran unit 1.00 Dihitung.4.2.8 50,000,000.00 50,000,000.00
18 Meja IGD 1.00 25,000,000.00 25,000,000.00
19 Meja Bidan 1.00 25,000,000.00 25,000,000.00
SUB TOTAL BAGIAN IV : PEKERJAAN BESI & ALUMUNIUM 784,694,636.49
V PEKERJAAN PASANGAN DINDING
1 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP m2 777.01 A.4.4.1.11 132,466.69 102,928,409.02
2 Beton Terawang Tb. 4cm Motif Batik Finishing Cat m2 18.63 Dihitung.4.1.2 480,000.00 8,942,400.00
SUB TOTAL BAGIAN V : PEKERJAAN PASANGAN DINDING 111,870,809.02
VI PEKERJAAN PLESTERAN
1 Pemasangan Plesteran 1 SP : 6 PP Tebal 15 mm m2 1,112.06 3.2.4.(c).a 56,291.41 62,599,452.91
2 Pemasangan Plesteran 1 SP : 4 PP Tebal 15 mm m2 631.00 3.2.2.(c).a 58,250.96 36,756,469.56
3 Pemasangan 1 m2 Acian m2 1,743.06 3.2.2.(c).b 33,136.40 57,758,816.22
SUB TOTAL BAGIAN VI : PEKERJAAN PLESTERAN 157,114,738.70
VII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
1 Pemasangan 1m2 Lantai Keramik Ukuran 60x60 Motif Halus m2 544.59 Dihitung.4.4.4 263,996.94 143,770,553.22
2 Pemasangan 1m2 Lantai Keramik Ukuran 60x60 Motif Kasar m2 40.11 Dihitung.4.4.5 238,421.94 9,563,103.84
3 Pemasangan 1m2 Lantai Keramik Ukuran 30x30 Motif Kasar m2 21.80 Dihitung.4.4.7 202,984.65 4,425,572.83
4 Pemasangan Dinding Keramik 30x60 cm, Motif Halus m2 431.76 Dihitung.4.4.3 231,333.06 99,880,826.50
5 Pemasangan 1 m’ Radiusplint Internal Cove PVC 5x5x60cm m1 204.09 Dihitung.4.4.8 202,066.15 41,239,680.55
6 Pemasangan 1 m' stepnosing Keramik Ukuran 10x60 m' 63.85 Dihitung.4.4.6 69,277.69 4,423,380.23
SUB TOTAL BAGIAN VII : PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING 303,303,117.18
VIII PEKERJAAN LANGIT-LANGIT
1 Pemasangan 1 m2 Langit-Langit PVC. m2 700.02 Dihitung.4.5.1 188,199.00 131,743,092.21
SUB TOTAL BAGIAN VIII : PEKERJAAN LANGIT-LANGIT (PLAFON) 131,743,092.21
IX PEKERJAAN PENUTUP ATAP
1 Pemasangan 1 m2 Atap bitumen bergelombang monolayer 3mm Uk 200x95x0.30cm jarak gording dan reng m2 237.39 Dihitung.4.5.2 169,795.67 40,306,945.12
2 Pemasangan 1 m' Nok Bitumen Monolayer m1 45.40 Dihitung.4.5.3 211,621.11 9,607,598.53
3 Pemasangan 1 m2 Atap Galvalum 0.30 mm Lapis Pasir m2 67.50 Dihitung.4.5.4 75,078.74 5,067,814.95
4 Pemasangan Atap Solar Tuff m2 81.21 Dihitung.4.5.6 253,002.39 20,546,007.68
5 Pemasangan 1 m’ Lisplank GRC Lebar 40 cm m1 68.75 Dihitung.4.5.9 48,436.30 3,329,995.63
SUB TOTAL BAGIAN IX : PEKERJAAN PENUTUP ATAP 78,858,361.91
X PEKERJAAN KUNCI DAN KACA
1 Pemasangan 1 buah pintu kaca Tempered tebal 12 mm + asesories unit 2.00 Dihitung.4.6.7 14,386,152.00 28,772,304.00
2 Pemasangan 1 buah Kunci Tanam Biasa buah 29.00 A.4.6.2.2. 225,415.52 6,537,050.08
3 Pemasangan 1 buah Handle pintu stainlessteel buah 74.00 Dihitung.4.6.2 157,115.20 11,626,524.80
4 Pemasangan 1 buah Handle Slot pintu buah 22.00 Dihitung.4.6.3 74,615.20 1,641,534.40
5 Pemasangan 1 buah Engsel Pintu buah 159.00 A.4.6.2.5. 26,229.61 4,170,507.99
6 Pemasangan 1 buah Rel Pintu Geser buah 1.00 Dihitung.4.6.11 224,798.42 224,798.42
7 Pemasangan 1 Buah Grendel untuk Pintu buah 42.00 Dihitung.4.6.4 115,266.14 4,841,177.88
8 Pemasangan 1 Buah Casement buah 552.00 Dihitung.4.6.5 32,815.20 18,113,990.40
9 Pemasangan 1 buah Rambuncis buah 276.00 Dihitung.4.6.6 19,615.20 5,413,795.20
10 Pemasangan 1 m2 Stiker Sandblast m2 35.79 Dihitung.4.6.9 63,430.40 2,270,142.30
11 Pemasangan 1 m2 Kaca Es Tebal 5 mm m2 46.82 A.4.6.2.16. 200,029.61 9,364,386.19
12 Pemasangan 1 m2 Kaca Rayband Tebal 5 mm m2 76.87 Dihitung.4.6.10 169,779.61 13,051,467.96
13 Pemasangan 1 m2 Kaca Polos Tebal 5 mm m2 71.31 A.4.6.2.17. 167,359.61 11,934,581.15
SUB TOTAL BAGIAN X : PEKERJAAN KUNCI DAN KACA 117,962,260.77
XI PEKERJAAN PENGECATAN
1 Pengecatan 1 m2 Tembok Baru (1 Lapis Plamuur, 1 Lapis Cat m2 1,743.06 3.3.10.(c) 23,148.79 40,349,779.05
Dasar, 2 Lapis Cat Penutup) SUB TOTAL BAGIAN XI : PEKERJAAN PENGECATAN 40,349,779.05
XII PEKERJAAN ELEKTRIKAL
1 Pemasangan 1 Watt UJL listrik Baru + Test Comisioning watt 27,000.00 Dihitung.6.1.6 2,090.00 56,430,000.00
2 Box panel Lengkap (MCCB 2bh, MCB 5 bh, Ampere Meter 1 phase, Volt Meter 1 phase, CT, Pilot Lamp 3 bh, unit 1.00 Dihitung.6.1.33 8,525,000.00 8,525,000.00
3 Exhause fan Ceiling Plafond + instalasi pipa (Spek Disesuaikan Dengan Gambar) buah 3.00 Dihitung.6.1.24 581,152.00 1,743,456.00
4 Pemasangan 1 buah Titik Lampu buah 114.00 A.6.2.1.1 211,860.00 24,152,040.00
5 Pemasangan 1 buah Stop Kontak buah 102.00 Dihitung.6.1.15 262,724.00 26,797,848.00
6 Stop kontak Dinding AC buah 15.00 Dihitung.6.1.27 63,615.20 954,228.00
7 Pemasangan 1 buah Saklar buah 38.00 Dihitung.6.1.29 36,115.20 1,372,377.60
8 Lampu down light Kotak LED 18 watt buah 37.00 Dihitung.6.2.1 135,115.20 4,999,262.40
9 Lampu LED TL RMI 2x9 watt + Cap Lampu buah 77.00 Dihitung.6.2.9 448,615.20 34,543,370.40
10 Logo Tinggi 1 m + Lampu unit 2.00 Dihitung.6.2.8 1,053,615.20 2,107,230.40
11 Tulisan Bahan Acrilyc 3D 60 cm + Lampu unit 21.00 Dihitung.6.2.12 1,328,615.20 27,900,919.20
SUB TOTAL BAGIAN XII : PEKERJAAN ELEKTRIKAL 189,525,732.00
XIII PEKERJAAN SANITASI DAN PERPIPAAN DALAM GEDUNG
1 Instalasi Air Bersih
- Pemasangan Pipa PVC tipe AW Ø ¾" m' 137.55 A.5.1.1.26 25,695.20 3,534,374.35
- Pemasangan Pipa PVC tipe AW Ø 1" m' 152.70 A.5.1.1.27 31,662.70 4,834,893.83
2 Instalasi Air Kotor
- Pemasangan Pipa PVC tipe AW Ø 1½" m' 78.35 A.5.1.1.28 37,370.61 2,927,987.14
- Pemasangan Pipa PVC tipe AW Ø 3" m' 146.10 A.5.1.1.31 74,973.99 10,953,699.50
- Pemasangan Pipa PVC tipe AW Ø 4" m' 52.50 A.5.1.1.32 94,534.57 4,963,065.03
3 Instalasi Air Hujan
- Pemasangan Pipa PVC tipe AW Ø 4" m' 27.75 A.5.1.1.32 94,534.57 2,623,334.37
4 Pemasangan Bak Kontrol Pas.Batu Bata 60x60 tinggi 60 cm buah 13.00 A.5.1.1.18 759,243.57 9,870,166.45
5 Pemasangan 1 buah Closet Duduk/Monoblock unit 2.00 A.5.1.1.1 3,091,258.50 6,182,517.00
6 Memasang Closet Jongkok Porselen unit 4.00 A.5.1.1.2 449,753.72 1,799,014.88
7 Pemasangan Kran Ø ½" atau Ø ¾" buah 7.00 A.5.1.1.35 72,213.02 505,491.14
8 Pemasangan Floor Drain buah 7.00 A.5.1.1.36 41,033.52 287,234.64
9 Pemasangan septictank Biotech lengkap accessoriess + Peresapan buah 2.00 Dihitung.5.1.1 3,936,152.00 7,872,304.00
10 Pemasangan 1 buah Wastafel + Pedestal + Asesories + Kran Air Stainless steel buah 18.00 Dihitung.5.1.2 2,286,152.00 41,150,736.00
11 Pasang Wastafel Beton (Spek Disesuaikan Dengan Gambar) buah 2.00 Dihitung.5.1.7 1,791,152.00 3,582,304.00
12 Pemasangan 1 buah Meja (bak cuci stainlessteel + Kran Air+ Kramik + Asesories sesusaikan dengan gambar buah 6.00 Dihitung.5.1.8 5,036,152.00 30,216,912.00
13 Pemasangan 1 buah Spoel Hoek Slop Sink + Asesories buah 1.00 Dihitung.5.1.9 10,371,152.00 10,371,152.00
14 Pembuatan Sumur Gali 50cm Kedalaman 30 m + Asesories m' 30.00 Dihitung.5.1.2.1 346,500.00 10,395,000.00
15 Pemasangan 1 buahTandon Air Kapasitas 1000 Liter (sekualitas penguin) + Asesories buah 2.00 A.5.1.1.11 2,012,618.85 4,025,237.70
SUB TOTAL BAGIAN XIII : PEKERJAAN SANITASI DAN PERPIPAAN DALAM GEDUNG 156,095,424.03
SUB TOTAL BAGIAN D : PEKERJAAN GEDUNG UTAMA (LANTAI 1) 3,289,753,888.33
E PEKERJAAN GEDUNG UTAMA A (LANTAI 2)
I PEKERJAAN BETON
1 Kolom (K 1) 30 x 30 cm
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 20.05 A.4.1.1.7 1,129,166.98 22,636,975.09
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 3,522.47 2.2.6.1.b 16,196.88 57,053,100.44
- Pemasangan 1 m2 Bekisting untuk Kolom Beton Bangunan Gedung (volume dibagi 2 kali) m2 133.65 A.4.1.1.20 326,489.57 43,635,331.03
2 Kolom (K 3) 15 x 15 cm
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 2.00 A.4.1.1.7 1,129,166.98 2,263,697.51
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 442.61 2.2.6.1.b 16,196.88 7,168,895.00
- Pemasangan 1 m2 Bekisting untuk Kolom Beton Bangunan Gedung (volume dibagi 2 kali) m2 13.36 A.4.1.1.20 326,489.57 4,363,533.10
3 Balok (B 1) 20 x 40 cm
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 0.76 A.4.1.1.7 1,129,166.98 853,650.24
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 129.77 2.2.6.1.b 16,196.88 2,101,832.41
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali) m2 3.50 A.4.1.1.21 334,409.57 1,169,263.06
4 Balok (B 2) 15 x 30 cm
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 8.56 A.4.1.1.7 1,129,166.98 9,669,621.46
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 1,548.36 2.2.6.1.b 16,196.88 25,078,638.80
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali) m2 71.36 A.4.1.1.21 334,409.57 23,864,302.94
5 Balok Gantung (BG) 15 x 25 cm
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 1.63 A.4.1.1.7 1,129,166.98 1,837,719.26
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 317.53 2.2.6.1.b 16,196.88 5,143,029.36
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali) m2 14.11 A.4.1.1.21 334,409.57 4,716,846.98
6 Balok Latei 12 x 20 cm
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 1.80 A.4.1.1.7 1,129,166.98 2,033,855.57
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 413.16 2.2.6.1.b 16,196.88 6,691,961.35
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali) m2 15.01 A.4.1.1.21 334,409.57 5,019,487.65
7 Plat Leuvel
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 0.35 A.4.1.1.7 1,129,166.98 392,950.11
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 192.37 2.2.6.1.b 16,196.88 3,115,773.75
- Pemasangan 1 m2 Bekisting untuk Plat lantai Beton Bangunan Gedung m2 2.92 A.4.1.1.22 392,489.57 1,144,107.10
8 Ring Balk 15 x 20 cm
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 0.32 A.4.1.1.7 1,129,166.98 365,850.10
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 77.08 2.2.6.1.b 16,196.88 1,248,412.02
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali) m2 2.16 A.4.1.1.21 334,409.57 722,324.67
9 Plat Lantai
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 1.08 A.4.1.1.7 1,129,166.98 1,215,435.34
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 125.43 2.2.6.1.b 16,196.88 2,031,525.35
- Pemasangan 1 m2 Bekisting untuk Plat lantai Beton Bangunan Gedung m2 8.28 A.4.1.1.22 392,489.57 3,249,813.64
10 Listplank Beton
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 0.33 A.4.1.1.7 1,129,166.98 369,745.73
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 38.26 2.2.6.1.b 16,196.88 619,692.62
- Pemasangan 1 m2 Bekisting untuk Plat lantai Beton Bangunan Gedung m2 3.72 A.4.1.1.22 392,489.57 1,458,883.73
SUB TOTAL BAGIAN I : PEKERJAAN BETON 241,236,255.41
II PEKERJAAN BESI & ALUMUNIUM
1 Pemasangan 1 m Kusen Aluminium m1 672.15 A.4.2.1.24. 103,572.49 69,616,249.83
2 Pemasangan Pintu Allumunium Strip Lebar 8 cm m2 5.40 A.4.2.1.25 475,689.12 2,568,721.22
3 Pemasangan Pintu Kaca Rangka Allumunium m2 26.80 A.4.2.1.26 664,414.25 17,806,301.77
4 Pemasangan Jendela Kaca Rangka Allumunium m2 68.45 A.4.2.1.26.a 664,414.25 45,477,494.03
5 Pemasangan 1 m2 Rangka Besi Hollow Galvanis 40.40 mm, Modul 60 x m2 472.88 A.4.2.1.21 276,568.05 130,782,427.78
6 60 cm, untuk Plafon
Pemasangan 1 M2 Atap Jurai/Limasan Rangka Atap Baja Ringan (Canai Dingin) Profil C75 m2 563.46 A.4.2.1.23 290,336.71 163,593,846.20
7 Pemasangan 1 m' talang galvalum 30x30 cm, rangka hollow galvanis 3.5/3.5 cm, Jarak Rangka 60cm m1 121.00 Dihitung.4.2.7 153,540.20 18,578,364.20
8 Pemasangan Besi CNP 2 x 200.75.20.2,3 kg 117.80 A.4.2.1.1. 33,589.82 3,956,813.62
9 Pemasangan 1 m2 ACP + Rangka m2 132.19 Dihitung.4.2.17 951,336.54 125,754,798.88
SUB TOTAL BAGIAN II : PEKERJAAN BESI & ALUMUNIUM 578,135,017.53
III PEKERJAAN PASANGAN DINDING
1 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP m2 489.49 A.4.4.1.11 132,466.69 64,840,459.39
SUB TOTAL BAGIAN III : PEKERJAAN PASANGAN DINDING 64,840,459.39
IV PEKERJAAN PLESTERAN
1 Pemasangan Plesteran 1 SP : 6 PP Tebal 15 mm m2 978.97 3.2.4.(c).a 56,291.41 55,107,601.09
2 Pemasangan Plesteran 1 SP : 4 PP Tebal 15 mm m2 339.55 3.2.2.(c).a 58,250.96 19,779,112.01
3 Pemasangan 1 m2 Acian m2 1,318.52 3.2.2.(c).b 33,136.40 43,691,006.13
SUB TOTAL BAGIAN IV : PEKERJAAN PLESTERAN 118,577,719.23
V PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
1 Pemasangan 1m2 Lantai Keramik Ukuran 60x60 Motif Halus m2 351.89 Dihitung.4.4.4 263,996.94 92,898,475.70
2 Pemasangan 1m2 Lantai Keramik Ukuran 30x30 Motif Kasar m2 14.72 Dihitung.4.4.7 202,984.65 2,986,919.12
3 Pemasangan Dinding Keramik 30x60 cm, Motif Halus m2 51.12 Dihitung.4.4.3 231,333.06 11,825,746.25
SUB TOTAL BAGIAN V : PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING 107,711,141.07
VI PEKERJAAN LANGIT-LANGIT
1 Pemasangan 1 m2 Langit-Langit PVC. m2 464.64 Dihitung.4.5.1 188,199.00 87,444,712.79
SUB TOTAL BAGIAN VI : PEKERJAAN LANGIT-LANGIT (PLAFON) 87,444,712.79
VII PEKERJAAN PENUTUP ATAP
1 Pemasangan 1 m2 Atap bitumen bergelombang monolayer 3mm Uk 200x95x0.30cm jarak gording dan reng m2 574.96 Dihitung.4.5.2 169,795.67 97,626,142.91
2 Pemasangan 1 m' Nok Bitumen Monolayer m1 94.50 Dihitung.4.5.3 211,621.11 19,998,195.18
3 Pemasangan 1 m’ Lisplank GRC Lebar 40 cm m1 121.00 Dihitung.4.5.9 48,436.30 5,860,792.30
SUB TOTAL BAGIAN VII : PEKERJAAN PENUTUP ATAP 123,485,130.39
VIII PEKERJAAN KUNCI DAN KACA
1 Pemasangan 1 buah Kunci Tanam Biasa buah 10.00 A.4.6.2.2. 225,415.52 2,254,155.20
2 Pemasangan 1 buah Handle pintu stainlessteel buah 36.00 Dihitung.4.6.2 157,115.20 5,656,147.20
3 Pemasangan 1 buah Handle Slot pintu buah 2.00 Dihitung.4.6.3 74,615.20 149,230.40
4 Pemasangan 1 buah Engsel Pintu buah 63.00 A.4.6.2.5. 26,229.61 1,652,465.43
5 Pemasangan 1 Buah Grendel untuk Pintu buah 20.00 Dihitung.4.6.4 115,266.14 2,305,322.80
6 Pemasangan 1 Buah Casement buah 300.00 Dihitung.4.6.5 32,815.20 9,844,560.00
7 Pemasangan 1 buah Rambuncis buah 150.00 Dihitung.4.6.6 19,615.20 2,942,280.00
8 Pemasangan 1 m2 Stiker Sandblast m2 29.46 Dihitung.4.6.9 63,430.40 1,868,501.01
9 Pemasangan 1 m2 Kaca Es Tebal 5 mm m2 17.88 A.4.6.2.16. 200,029.61 3,576,529.43
10 Pemasangan 1 m2 Kaca Rayband Tebal 5 mm m2 52.25 Dihitung.4.6.10 169,779.61 8,870,814.84
11 Pemasangan 1 m2 Kaca Polos Tebal 5 mm m2 73.04 A.4.6.2.17. 167,359.61 12,224,364.31
SUB TOTAL BAGIAN VIII : PEKERJAAN KUNCI DAN KACA 51,344,370.62
IX PEKERJAAN PENGECATAN
1 Pengecatan 1 m2 Tembok Baru (1 Lapis Plamuur, 1 Lapis Cat m2 1,318.52 3.3.10.(c) 23,148.79 30,522,136.00
Dasar, 2 Lapis Cat Penutup) SUB TOTAL BAGIAN IX : PEKERJAAN PENGECATAN 30,522,136.00
X PEKERJAAN ELEKTRIKAL
1 Box panel Lengkap (MCCB 2bh, MCB 5 bh, Ampere Meter 1 phase, Volt Meter 1 phase, CT, Pilot Lamp 3 bh, unit 1.00 Dihitung.6.1.33 8,525,000.00 8,525,000.00
2 Pemasangan 1 buah Titik Lampu buah 73.00 A.6.2.1.1 211,860.00 15,465,780.00
3 Pemasangan 1 buah Stop Kontak buah 64.00 Dihitung.6.1.15 262,724.00 16,814,336.00
4 Stop kontak Dinding AC buah 10.00 Dihitung.6.1.27 63,615.20 636,152.00
5 Pemasangan 1 buah Saklar buah 18.00 Dihitung.6.1.29 36,115.20 650,073.60
6 Lampu down light Kotak LED 18 watt buah 15.00 Dihitung.6.2.1 135,115.20 2,026,728.00
7 Lampu LED TL RMI 2x9 watt + Cap Lampu buah 58.00 Dihitung.6.2.9 448,615.20 26,019,681.60
SUB TOTAL BAGIAN X : PEKERJAAN ELEKTRIKAL 70,137,751.20
XI PEKERJAAN SANITASI DAN PERPIPAAN DALAM GEDUNG
1 Instalasi Air Bersih
- Pemasangan Pipa PVC tipe AW Ø ¾" m' 18.00 A.5.1.1.26 25,695.20 462,513.55
- Pemasangan Pipa PVC tipe AW Ø 1" m' 45.00 A.5.1.1.27 31,662.70 1,424,821.37
2 Instalasi Air Kotor
- Pemasangan Pipa PVC tipe AW Ø 1½" m' 53.65 A.5.1.1.28 37,370.61 2,004,933.12
- Pemasangan Pipa PVC tipe AW Ø 3" m' 18.50 A.5.1.1.31 74,973.99 1,387,018.76
- Pemasangan Pipa PVC tipe AW Ø 4" m' 14.50 A.5.1.1.32 94,534.57 1,370,751.29
3 Instalasi Air Hujan
- Pemasangan Pipa PVC tipe AW Ø 4" m' 180.00 A.5.1.1.32 94,534.57 17,016,222.96
4 Pemasangan 1 buah Closet Duduk/Monoblock unit 2.00 A.5.1.1.1 3,091,258.50 6,182,517.00
5 Pemasangan Kran Ø ½" atau Ø ¾" buah 6.00 A.5.1.1.35 72,213.02 433,278.12
6 Pemasangan Floor Drain buah 5.00 A.5.1.1.36 41,033.52 205,167.60
7 Pemasangan 1 buah Meja (bak cuci stainlessteel + Kran Air+ Kramik + Asesories sesusaikan dengan gambar buah 1.00 Dihitung.5.1.8 5,036,152.00 5,036,152.00
SUB TOTAL BAGIAN XI : PEKERJAAN SANITASI DAN PERPIPAAN DALAM GEDUNG 35,523,375.76
SUB TOTAL BAGIAN E : PEKERJAAN GEDUNG UTAMA (LANTAI 2) 1,508,958,069.39
F PEKERJAAN GEDUNG B
I PEKERJAAN TANAH
1 Penggalian 1 m3 Tanah Biasa Sedalam s.d. 1 m m3 22.53 1.7.1.a 67,116.50 1,512,336.09
2 Pengurugan Kembali 1 m3 Galian Tanah m3 7.57 1.7.2.a 16,027.00 121,260.28
3 Pengurugan 1m3 Dengan Pasir Urug m3 1.04 1.7.2.d 351,566.60 365,453.48
SUB TOTAL BAGIAN I : PEKERJAAN TANAH 1,999,049.86
II PEKERJAAN PONDASI
1 Pemasangan Pondasi Batu Belah 1SP : 6 PP m3 9.87 2.1.1.d 865,749.89 8,541,055.57
2 Pemasang Batu Kosong/Anstamping m3 4.06 A.3.2.1.9 487,888.45 1,981,802.90
SUB TOTAL BAGIAN II : PEKERJAAN PONDASI 10,522,858.46
III PEKERJAAN BETON
1 Sloof 12x20 cm
- Pembuatan 1 m3 Beton Mutu f’c = 14,5 Mpa (K175) m3 0.83 A.4.1.1.5. 1,068,452.47 884,037.57
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 264.04 2.2.6.1.b 16,196.88 4,276,586.04
- Pemasangan 1 m2 Bekisting untuk Sloof Beton Bangunan Gedung (volume dibagi 2 kali) m2 7.03 A.4.1.1.19 201,092.54 1,413,680.56
2 Kolom Praktis 15x15 cm
- Pembuatan 1 m3 Beton Mutu f’c = 14,5 Mpa (K175) m3 0.99 A.4.1.1.5. 1,068,452.47 1,062,575.98
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 220.56 2.2.6.1.b 16,196.88 3,572,369.19
- Pemasangan 1 m2 Bekisting untuk Kolom Beton Bangunan Gedung (volume dibagi 2 kali) m2 12.90 A.4.1.1.20 326,489.57 4,211,715.45
3 Balok Latei 12x20 cm
- Pembuatan 1 m3 Beton Mutu f’c = 14,5 Mpa (K175) m3 0.25 A.4.1.1.5. 1,068,452.47 270,852.70
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 80.11 2.2.6.1.b 16,196.88 1,297,556.06
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali) m2 2.15 A.4.1.1.21 334,409.57 718,980.58
4 Ring Balk 15x20 cm
- Pembuatan 1 m3 Beton Mutu f’c = 14,5 Mpa (K175) m3 0.92 A.4.1.1.5. 1,068,452.47 980,839.37
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 233.87 2.2.6.1.b 16,196.88 3,787,893.61
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali) m2 6.12 A.4.1.1.21 334,409.57 2,046,586.57
SUB TOTAL BAGIAN III : PEKERJAAN BETON 24,523,673.68
IV PEKERJAAN BESI & ALUMUNIUM
1 Pemasangan 1 m2 Rangka Besi Hollow Galvanis 40.40 mm, Modul 60 x m2 63.59 A.4.2.1.21 276,568.05 17,587,653.72
2 60 cm, untuk Plafon
Pemasangan 1 m2 Kanopy Rangka Atap Hollow Galvanis + Assesoris m2 84.92 Dihitung.4.2.6 498,115.20 42,301,188.07
3 Pemasangan 1 m' talang galvalum 30x30 cm, rangka hollow galvanis 3.5/3.5 cm, Jarak Rangka 60cm m1 28.50 Dihitung.4.2.7 153,540.20 4,375,895.70
4 Pemasangan 1 m Kusen Aluminium m1 35.90 A.4.2.1.24. 103,572.49 3,718,252.43
5 Pemasangan Pintu Kaca Rangka Allumunium m2 4.80 A.4.2.1.26 664,414.25 3,189,188.38
6 Pemasangan Jendela Kaca Rangka Allumunium m2 3.72 A.4.2.1.26.a 664,414.25 2,471,620.99
7 Pasang Wenfire (Bahan Plat Galvalum) m1 25.95 Dihitung.4.2.19 57,583.35 1,494,287.93
SUB TOTAL BAGIAN IV : PEKERJAAN BESI & ALUMUNIUM 75,138,087.22
V PEKERJAAN PASANGAN DINDING
1 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP m2 44.98 A.4.4.1.11 132,466.69 5,958,351.87
SUB TOTAL BAGIAN V : PEKERJAAN PASANGAN DINDING 5,958,351.87
VI PEKERJAAN PLESTERAN
1 Pemasangan Plesteran 1 SP : 6 PP Tebal 15 mm m2 121.02 3.2.4.(c).a 56,291.41 6,812,386.37
2 Pemasangan 1 m2 Acian m2 121.02 3.2.2.(c).b 33,136.40 4,010,167.13
SUB TOTAL BAGIAN VI : PEKERJAAN PLESTERAN 10,822,553.50
VII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
1 Pemasangan 1m2 Lantai Keramik Ukuran 60x60 Motif Kasar m2 46.43 Dihitung.4.4.5 238,421.94 11,068,738.37
SUB TOTAL BAGIAN VII : PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING 11,068,738.37
VIII PEKERJAAN LANGIT-LANGIT (PLAFON)
1 Pemasangan 1 m2 Langit-Langit PVC. m2 63.59 Dihitung.4.5.1 188,199.00 11,968,044.91
SUB TOTAL BAGIAN VIII : PEKERJAAN LANGIT-LANGIT (PLAFON) 11,968,044.91
IX PEKERJAAN PENUTUP ATAP
1 Pemasangan 1 m2 Atap Galvalum 0.30 mm Lapis Pasir m2 67.37 Dihitung.4.5.4 75,078.74 5,058,054.71
2 Pemasangan Atap Solar Tuff m2 17.55 Dihitung.4.5.6 253,002.39 4,440,824.42
3 Pemasangan 1 m’ Lisplank GRC Lebar 20 cm m1 28.50 Dihitung.4.5.8 38,747.50 1,104,303.75
SUB TOTAL BAGIAN IX : PEKERJAAN PENUTUP ATAP 10,603,182.88
X PEKERJAAN KUNCI DAN KACA
1 Pemasangan 1 buah Kunci Tanam Biasa buah 3.00 A.4.6.2.2. 225,415.52 676,246.56
2 Pemasangan 1 buah Engsel Pintu buah 9.00 A.4.6.2.5. 26,229.61 236,066.49
3 Pemasangan 1 buah Handle Slot pintu buah 6.00 Dihitung.4.6.3 74,615.20 447,691.20
4 Pemasangan 1 Buah Casement buah 20.00 Dihitung.4.6.5 32,815.20 656,304.00
5 Pemasangan 1 buah Rambuncis buah 10.00 Dihitung.4.6.6 19,615.20 196,152.00
6 Pemasangan 1 m2 Stiker Sandblast m2 1.48 Dihitung.4.6.9 63,430.40 93,623.27
7 Pemasangan 1 m2 Kaca Es Tebal 5 mm m2 1.05 A.4.6.2.16. 200,029.61 210,031.09
8 Pemasangan 1 m2 Kaca Rayband Tebal 5 mm m2 2.25 Dihitung.4.6.10 169,779.61 382,004.12
9 Pemasangan 1 m2 Kaca Polos Tebal 5 mm m2 2.60 A.4.6.2.17. 167,359.61 435,770.95
10 Pemasangan 1 Buah Grendel untuk Pintu buah 6.00 Dihitung.4.6.4 115,266.14 691,596.84
SUB TOTAL BAGIAN X : PEKERJAAN KUNCI DAN KACA 4,025,486.53
XI PEKERJAAN PENGECATAN
1 Pengecatan 1 m2 Tembok Baru (1 Lapis Plamuur, 1 Lapis Cat m2 121.02 3.3.10.(c) 23,148.79 2,801,465.96
Dasar, 2 Lapis Cat Penutup) SUB TOTAL BAGIAN XI : PEKERJAAN PENGECATAN 2,801,465.96
XII PEKERJAAN ELEKTRIKAL
1 Pemasangan 1 buah Stop Kontak buah 4.00 Dihitung.6.1.15 262,724.00 1,050,896.00
2 Pemasangan 1 buah Saklar buah 4.00 Dihitung.6.1.29 36,115.20 144,460.80
3 Pemasangan 1 buah Titik Lampu buah 12.00 A.6.2.1.1 211,860.00 2,542,320.00
4 Lampu down light Kotak LED 18 watt buah 9.00 Dihitung.6.2.1 135,115.20 1,216,036.80
5 Lampu LED Lampu Panel 18 Watt Square Slim Warm White Plafon buah 3.00 Dihitung.6.2.1.a 135,115.20 405,345.60
6 MCB 3P/ 32A Ex Schneider buah 1.00 Dihitung.6.1.4 668,615.20 668,615.20
SUB TOTAL BAGIAN XII : PEKERJAAN ELEKTRIKAL 6,027,674.40
XIII PEKERJAAN SANITASI DAN PERPIPAAN DALAM GEDUNG
1 Pemasangan 1 buah Kran Diameter ½” atau ¾ ” buah 1.00 A.5.1.1.35.a 72,213.02 72,213.02
2 Pemasangan Floor Drain buah 1.00 A.5.1.1.36 41,033.52 41,033.52
3 Pemasangan 1 buah Meja (bak cuci stainlessteel + Kran Air+ Kramik + Asesories sesusaikan dengan gambar buah 2.00 Dihitung.5.1.8 5,036,152.00 10,072,304.00
4 Pemasangan 1 buah Wastafel + Pedestal + Asesories + Kran Air Stainless steel buah 1.00 Dihitung.5.1.2 2,286,152.00 2,286,152.00
SUB TOTAL BAGIAN XIII : PEKERJAAN SANITASI DAN PERPIPAAN DALAM GEDUNG 12,471,702.54
SUB TOTAL BAGIAN F : PEKERJAAN GEDUNG B 187,930,870.16
G PEKERJAAN GEDUNG C
I PEKERJAAN TANAH
1 Penggalian 1 m3 Tanah Biasa Sedalam s.d. 1 m m3 16.63 1.7.1.a 67,116.50 1,116,080.28
2 Pengurugan Kembali 1 m3 Galian Tanah m3 2.75 1.7.2.a 16,027.00 44,138.36
3 Pengurugan 1m3 Dengan Pasir Urug m3 1.01 1.7.2.d 351,566.60 355,433.83
SUB TOTAL BAGIAN I : PEKERJAAN TANAH 1,515,652.47
II PEKERJAAN PONDASI
1 Pemasangan Pondasi Batu Belah 1SP : 6 PP m3 9.19 2.1.1.d 865,749.89 7,957,973.02
2 Pemasang Batu Kosong/Anstamping m3 3.67 A.3.2.1.9 487,888.45 1,791,526.40
SUB TOTAL BAGIAN II : PEKERJAAN PONDASI 9,749,499.41
III PEKERJAAN BETON
1 Sloof 12x20 cm
- Pembuatan 1 m3 Beton Mutu f’c = 14,5 Mpa (K175) m3 0.93 A.4.1.1.5. 1,068,452.47 989,814.37
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 278.85 2.2.6.1.b 16,196.88 4,516,426.86
- Pemasangan 1 m2 Bekisting untuk Sloof Beton Bangunan Gedung (volume dibagi 2 kali) m2 7.45 A.4.1.1.19 201,092.54 1,498,139.42
2 Kolom 15x15 cm
- Pembuatan 1 m3 Beton Mutu f’c = 14,5 Mpa (K175) m3 0.97 A.4.1.1.5. 1,068,452.47 1,033,727.77
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 214.56 2.2.6.1.b 16,196.88 3,475,231.42
- Pemasangan 1 m2 Bekisting untuk Kolom Beton Bangunan Gedung (volume dibagi 2 kali) m2 6.04 A.4.1.1.20 326,489.57 1,972,649.98
3 Balok Latei 12x20 cm
- Pembuatan 1 m3 Beton Mutu f’c = 14,5 Mpa (K175) m3 0.36 A.4.1.1.5. 1,068,452.47 387,207.18
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 105.79 2.2.6.1.b 16,196.88 1,713,395.17
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali) m2 3.02 A.4.1.1.21 334,409.57 1,009,916.90
4 Balok 15x30 cm
- Pembuatan 1 m3 Beton Mutu f’c = 14,5 Mpa (K175) m3 0.57 A.4.1.1.5. 1,068,452.47 613,024.60
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 123.30 2.2.6.1.b 16,196.88 1,997,075.80
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali) m2 3.82 A.4.1.1.21 334,409.57 1,279,116.61
5 Listplank Beton
- Pembuatan 1 m3 Beton Mutu f’c = 14,5 Mpa (K175) m3 0.18 A.4.1.1.5. 1,068,452.47 193,603.59
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 28.70 2.2.6.1.b 16,196.88 464,903.27
- Pemasangan 1 m2 Bekisting untuk Plat lantai Beton Bangunan Gedung m2 2.11 A.4.1.1.22 392,489.57 829,722.95
6 Plat Leuvel
- Pembuatan 1 m3 Beton Mutu f’c = 14,5 Mpa (K175) m3 1.24 A.4.1.1.5. 1,068,452.47 1,326,184.58
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 247.68 2.2.6.1.b 16,196.88 4,011,626.01
- Pemasangan 1 m2 Bekisting untuk Plat lantai Beton Bangunan Gedung m2 5.17 A.4.1.1.22 392,489.57 2,029,857.93
7 Ring Balk 15x20 cm
- Pembuatan 1 m3 Beton Mutu f’c = 14,5 Mpa (K175) m3 0.96 A.4.1.1.5. 1,068,452.47 1,027,317.05
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 211.63 2.2.6.1.b 16,196.88 3,427,740.96
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali) m2 6.41 A.4.1.1.21 334,409.57 2,143,565.34
SUB TOTAL BAGIAN III : PEKERJAAN BETON 35,940,247.75
IV PEKERJAAN BESI & ALUMUNIUM
1 Pemasangan 1 m2 Atap Pelana Rangka Atap Baja Ringan (Canai Dingin) profil C75 m2 40.26 A.4.2.1.22 285,000.00 11,474,100.04
2 Pemasangan 1 m Kusen Aluminium m1 43.10 A.4.2.1.24. 103,572.49 4,463,974.36
3 Pemasangan Pintu Allumunium Strip Lebar 8 cm m2 5.60 A.4.2.1.25 475,689.12 2,663,859.04
4 Pemasangan 1 m2 Pintu Folding Gate m2 5.70 Dihitung.4.2.20 908,983.68 5,181,206.98
5 Pemasangan Jendela Kaca Rangka Allumunium m2 5.58 A.4.2.1.26.a 664,414.25 3,707,431.49
6 Pemasangan 1 m2 Rangka Besi Hollow Galvanis 40.40 mm, Modul 60 x m2 35.03 A.4.2.1.21 276,568.05 9,688,870.21
60 cm, untuk Plafon SUB TOTAL BAGIAN IV : PEKERJAAN BESI & ALUMUNIUM 37,179,442.12
V PEKERJAAN PASANGAN DINDING
1 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP m2 70.86 A.4.4.1.11 132,466.69 9,385,927.56
SUB TOTAL BAGIAN V : PEKERJAAN PASANGAN DINDING 9,385,927.56
VI PEKERJAAN PLESTERAN
1 Pemasangan Plesteran 1 SP : 6 PP Tebal 15 mm m2 183.76 3.2.4.(c).a 56,291.41 10,344,109.40
2 Pemasangan 1 m2 Acian m2 183.76 3.2.2.(c).b 33,136.40 6,089,144.86
SUB TOTAL BAGIAN VI : PEKERJAAN PLESTERAN 16,433,254.26
VII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
1 Pemasangan 1m2 Lantai Keramik Ukuran 60x60 Motif Halus m2 17.74 Dihitung.4.4.4 263,996.94 4,683,965.63
2 Pemasangan 1m2 Lantai Keramik Ukuran 60x60 Motif Kasar m2 10.95 Dihitung.4.4.5 238,421.94 2,610,124.14
SUB TOTAL BAGIAN VII : PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING 7,294,089.77
VIII PEKERJAAN LANGIT-LANGIT (PLAFON)
1 Pemasangan 1 m2 Langit-Langit Papan Gipsum. Tebal 9 mm m2 35.03 A.4.5.1.7. 43,515.45 1,524,455.00
SUB TOTAL BAGIAN VIII : PEKERJAAN LANGIT-LANGIT (PLAFON) 1,524,455.00
IX PEKERJAAN PENUTUP ATAP
1 Pemasangan 1 m2 Atap Genteng Metal Lapis pasir m2 40.26 Dihitung.4.5.5 90,999.44 3,663,637.56
2 Pemasangan 1 m’ Lisplank GRC Lebar 20 cm m1 27.10 Dihitung.4.5.8 38,747.50 1,050,057.25
SUB TOTAL BAGIAN IX : PEKERJAAN PENUTUP ATAP 4,713,694.81
X PEKERJAAN KUNCI DAN KACA
1 Pemasangan 1 buah Kunci Tanam Biasa buah 2.00 A.4.6.2.2. 225,415.52 450,831.04
2 Pemasangan 1 buah Engsel Pintu buah 6.00 A.4.6.2.5. 26,229.61 157,377.66
3 Pemasangan 1 Buah Casement buah 24.00 Dihitung.4.6.5 32,815.20 787,564.80
4 Pemasangan 1 buah Rambuncis buah 12.00 Dihitung.4.6.6 19,615.20 235,382.40
5 Pemasangan 1 m2 Kaca Es Tebal 5 mm m2 1.46 A.4.6.2.16. 200,029.61 291,243.11
6 Pemasangan 1 m2 Kaca Rayband Tebal 5 mm m2 4.06 Dihitung.4.6.10 169,779.61 689,441.04
7 Pemasangan 1 Buah Grendel untuk Pintu buah 4.00 Dihitung.4.6.4 115,266.14 461,064.56
SUB TOTAL BAGIAN X : PEKERJAAN KUNCI DAN KACA 3,072,904.61
XI PEKERJAAN PENGECATAN
1 Pengecatan 1 m2 Tembok Baru (1 Lapis Plamuur, 1 Lapis Cat m2 183.76 3.3.10.(c) 23,148.79 4,253,820.73
Dasar, 2 Lapis Cat Penutup) SUB TOTAL BAGIAN XI : PEKERJAAN PENGECATAN 4,253,820.73
XII PEKERJAAN ELEKTRIKAL
1 Pemasangan 1 buah Stop Kontak buah 3.00 Dihitung.6.1.15 262,724.00 788,172.00
2 Pemasangan 1 buah Saklar buah 6.00 Dihitung.6.1.29 36,115.20 216,691.20
3 Pemasangan 1 buah Titik Lampu buah 6.00 A.6.2.1.1 211,860.00 1,271,160.00
4 Lampu down light Kotak LED 18 watt buah 3.00 Dihitung.6.2.1 135,115.20 405,345.60
5 Lampu LED Lampu Panel 18 Watt Square Slim Warm White Plafon buah 3.00 Dihitung.6.2.1.a 135,115.20 405,345.60
6 MCB 3P/ 32A Ex Schneider buah 1.00 Dihitung.6.1.4 668,615.20 668,615.20
SUB TOTAL BAGIAN XII : PEKERJAAN ELEKTRIKAL 3,755,329.60
SUB TOTAL BAGIAN G : PEKERJAAN GEDUNG C 134,818,318.09
H PEKERJAAN PAGAR
I PEKERJAAN TANAH
1 Penggalian 1 m3 Tanah Biasa Sedalam s.d. 1 m m3 51.97 1.7.1.a 67,116.50 3,487,910.27
2 Pengurugan Kembali 1 m3 Galian Tanah m3 18.54 1.7.2.a 16,027.00 297,066.46
3 Pengurugan 1m3 Dengan Pasir Urug m3 2.59 1.7.2.d 351,566.60 911,260.63
SUB TOTAL BAGIAN I : PEKERJAAN TANAH 4,696,237.35
II PEKERJAAN PONDASI
1 Pemasangan Pondasi Batu Belah 1SP : 6 PP m3 20.96 2.1.1.d 865,749.89 18,148,282.13
2 Pemasang Batu Kosong/Anstamping m3 6.99 A.3.2.1.9 487,888.45 3,409,120.56
SUB TOTAL BAGIAN II : PEKERJAAN PONDASI 21,557,402.69
III PEKERJAAN BETON
1 Lantai Kerja
- Pembuatan 1 m3 Beton Mutu f’c = 7,4 Mpa (K100) m3 0.61 A.4.1.1.1 962,281.51 585,067.16
2 Footplat
- Pembuatan 1 m3 Beton Mutu f’c = 14,5 Mpa (K175) m3 3.23 A.4.1.1.5. 1,068,452.47 3,448,563.90
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 497.78 2.2.6.1.b 16,196.88 8,062,434.64
- Pemasangan 1 m2 Bekisting untuk Pondasi Telapak Beton Bangunan Gedung (volume dibagi 2 kali) m2 12.64 A.4.1.1.18 187,617.54 2,370,547.62
3 Sloof 12x20 cm
- Pembuatan 1 m3 Beton Mutu f’c = 14,5 Mpa (K175) m3 1.47 A.4.1.1.5. 1,068,452.47 1,575,753.70
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 250.21 2.2.6.1.b 16,196.88 4,052,689.88
- Pemasangan 1 m2 Bekisting untuk Sloof Beton Bangunan Gedung (volume dibagi 2 kali) m2 12.29 A.4.1.1.19 201,092.54 2,471,427.32
4 Kolom 15x15 cm
- Pembuatan 1 m3 Beton Mutu f’c = 14,5 Mpa (K175) m3 0.64 A.4.1.1.5. 1,068,452.47 685,145.15
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 114.32 2.2.6.1.b 16,196.88 1,851,688.68
- Pemasangan 1 m2 Bekisting untuk Kolom Beton Bangunan Gedung (volume dibagi 2 kali) m2 4.27 A.4.1.1.20 326,489.57 1,395,742.91
5 Ring Balk 12x20 cm
- Pembuatan 1 m3 Beton Mutu f’c = 14,5 Mpa (K175) m3 1.47 A.4.1.1.5. 1,068,452.47 1,575,753.70
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 250.21 2.2.6.1.b 16,196.88 4,052,689.88
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali) m2 12.29 A.4.1.1.21 334,409.57 4,109,893.62
6 Pemasangan 1 buah Dinding Terawang (rooster) 12x11x24 dengan Buah 172.00 Dihitung.4.1.1 25,659.33 4,413,405.33
7 Mortar Tipe S.fc’ 12.
Beton Terawang Tb. 54cm
MpaMotif
( Setara
BatikCampuran 1SP : 3PP)
Finishing Cat m2 30.38 Dihitung.4.1.2 480,000.00 14,580,000.00
8 List Beton
- Pembuatan 1 m3 Beton Mutu f’c = 9,8 Mpa (K125) m3 0.14 A.4.1.1.2 1,001,545.81 142,720.28
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 31.61 2.2.6.1.b 16,196.88 512,050.23
- Pemasangan 1 m2 Bekisting untuk Plat lantai Beton Bangunan Gedung m2 1.72 A.4.1.1.22 392,489.57 676,063.28
SUB TOTAL BAGIAN III : PEKERJAAN BETON 56,561,637.29
IV PEKERJAAN BESI & ALUMUNIUM
1 Pemasangan 1 m2 Teralis Pintu Galvanis m2 15.00 Dihitung.4.2.16 591,615.20 8,874,228.00
2 Pemasangan 1 m2 ACP Cutting Laser m2 11.52 Dihitung.4.2.18 1,380,336.54 15,901,476.94
3 Tulisan Bahan Acrilyc 3D 30 cm + Lampu unit 21.00 Dihitung.6.2.7 668,615.20 14,040,919.20
SUB TOTAL BAGIAN IV : PEKERJAAN BESI & ALUMUNIUM 38,816,624.14
V PEKERJAAN PASANGAN DINDING
1 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP m2 33.19 A.4.4.1.11 132,466.69 4,397,231.89
SUB TOTAL BAGIAN V : PEKERJAAN PASANGAN DINDING 4,397,231.89
VI PEKERJAAN PLESTERAN
1 Pemasangan Plesteran 1 SP : 6 PP Tebal 15 mm m2 75.79 3.2.4.(c).a 56,291.41 4,266,607.38
2 Pemasangan 1 m2 Acian m2 75.79 3.2.2.(c).b 33,136.40 2,511,573.44
SUB TOTAL BAGIAN VI : PEKERJAAN PLESTERAN 6,778,180.82
VII PEKERJAAN PENGECATAN
1 Pengecatan 1 m2 Tembok Baru (1 Lapis Plamuur, 1 Lapis Cat m2 75.79 3.3.10.(c) 23,148.79 1,754,562.16
Dasar, 2 Lapis Cat Penutup) SUB TOTAL BAGIAN VII : PEKERJAAN PENGECATAN 1,754,562.16
SUB TOTAL BAGIAN H : PEKERJAAN PAGAR 134,561,876.34
I PEKERJAAN PARKIR & PAVING
I PEKERJAAN TANAH
1 Penggalian 1 m3 Tanah Biasa Sedalam s.d. 1 m m3 25.88 1.7.1.a 67,116.50 1,737,243.49
2 Pengurugan Kembali 1 m3 Galian Tanah m3 18.37 1.7.2.a 16,027.00 294,448.04
3 Pengurugan 1m3 Dengan Pasir Urug m3 2.90 1.7.2.d 351,566.60 1,020,949.41
SUB TOTAL BAGIAN I : PEKERJAAN TANAH 3,052,640.94
II PEKERJAAN BETON
1 Lantai Kerja
- Pembuatan 1 m3 Beton Mutu f’c = 7,4 Mpa (K100) m3 1.93 A.4.1.1.1 962,281.51 1,853,354.19
2 Footplat
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 2.68 A.4.1.1.7 1,129,166.98 3,028,425.85
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 300.77 2.2.6.1.b 16,196.88 4,871,566.85
- Pemasangan 1 m2 Bekisting untuk Pondasi Telapak Beton Bangunan Gedung (volume dibagi 2 kali) m2 5.28 A.4.1.1.18 187,617.54 990,620.61
3 Sloof 12x20 cm
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 0.10 A.4.1.1.7 1,129,166.98 116,530.03
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 28.12 2.2.6.1.b 16,196.88 455,525.00
- Pemasangan 1 m2 Bekisting untuk Sloof Beton Bangunan Gedung (volume dibagi 2 kali) m2 0.86 A.4.1.1.19 201,092.54 172,939.58
4 Kolom 30x30 cm
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 0.38 A.4.1.1.7 1,129,166.98 426,825.12
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 59.13 2.2.6.1.b 16,196.88 957,797.55
- Pemasangan 1 m2 Bekisting untuk Kolom Beton Bangunan Gedung (volume dibagi 2 kali) m2 2.52 A.4.1.1.20 326,489.57 822,753.72
5 Lantai Beton
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225) m3 3.87 A.4.1.1.7 1,129,166.98 4,369,876.22
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip Kg 240.23 2.2.6.1.b 16,196.88 3,890,942.72
- Pemasangan 1 m2 Bekisting untuk Plat lantai Beton Bangunan Gedung m2 3.09 A.4.1.1.22 392,489.57 1,212,792.77
SUB TOTAL BAGIAN II : PEKERJAAN BETON 23,169,950.21
III PEKERJAAN BESI & ALUMUNIUM
1 Memasang Kontruksi Kuda-Kuda Pipa Baja kg 150.17 A.4.2.1.1. 33,589.82 5,044,260.76
2 Memasang Gording kg 384.90 A.4.2.1.1. 33,589.82 12,928,673.75
3 Plat landas & Plat pengaku kg 23.00 A.4.2.1.1. 33,589.82 772,582.65
4 Pengerjaan pengelasan dengan las listrik cm 167.67 3.1.3.(c) 76,547.13 12,834,344.97
5 Baud Angkur 40 cm buah 8.00 Dihitung.4.2.26 47,115.20 376,921.60
SUB TOTAL BAGIAN III : PEKERJAAN BESI & ALUMUNIUM 31,956,783.74
IV PEKERJAAN PLESTERAN
1 Pemasangan Plesteran Skoning 1 SP : 2 PP, lebar 10 mm m' 4.00 A,4,4,2.20 51,444.46 205,777.86
SUB TOTAL BAGIAN IV : PEKERJAAN PLESTERAN 205,777.86
V PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
1 Pemasangan 1 m2 Dinding Batu Paras m2 4.80 A.4.4.3.56 277,238.32 1,330,743.92
2 Pemasangan 1 m2 Paving Block Mutu K-225 (Blok Beton) Natural tebal 8 cm m2 458.06 A.4.4.3.64 212,941.63 97,540,043.04
SUB TOTAL BAGIAN V : PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING 98,870,786.96
VI PEKERJAAN PENUTUP ATAP
1 Pemasangan 1 m2 Atap Galvalum 0.30 mm m2 39.52 Dihitung.4.5.4.a 71,228.74 2,814,959.80
2 Lisplang Zincalume Lebar 20 cm m1 25.20 Dihitung.4.5.10 43,336.70 1,092,084.84
SUB TOTAL BAGIAN VI : PEKERJAAN PENUTUP ATAP 3,907,044.64
VII PEKERJAAN PENGECATAN
1 Cat Besi m2 26.71 3.3.15.(c) 54,426.63 1,453,605.15
2 Coating Batu alam clear m2 4.80 3.3.7.(c) 57,856.48 277,711.10
SUB TOTAL BAGIAN VII : PEKERJAAN PENGECATAN 1,731,316.26
SUB TOTAL BAGIAN I : PEKERJAAN PARKIR & PAVING 162,894,300.60
J PEKERJAAN LAIN-LAIN
I PEKERJAAN LAIN-LAIN
1 Pembersihan Lokasi ls 1.00 Dihitung (j) 6,983,263.44 6,983,263.44
SUB TOTAL BAGIAN XIV : PEKERJAAN LAIN-LAIN 6,983,263.44
SUB TOTAL BAGIAN J : PEKERJAAN LAIN-LAIN 6,983,263.44
JUMLAH BIAYA 5,700,614,571.52
PPN 11% 627,067,602.87
TOTAL BIAYA 6,327,682,174.39
Terbilang : Tujuh Milyar Rupiah
Banjarnegara, .................................2023
A PEKERJAAN PERSIAPAN
1 Papan Nama Kegiatan
= 1.00 = 1.00 ls 1.00 ls
2 Pengukuran dan Pemasangan Bouwplank
Panjang Jumlah
Gedung A = 40.00 x 2.00 = 80.00 m'
= 25.00 x 2.00 = 50.00
Gedung B = 13.00 x 2.00 = 26.00
= 2.00 x 2.00 = 4.00
Gedung C = 8.00 x 2.00 = 16.00
= 4.00 x 2.00 = 8.00
Pagar = 16.50 x 1.00 = 16.50
= 23.00 x 1.00 = 23.00
= 15.00 x 1.00 = 15.00
Talud = 56.40 x 1.00 = 56.40 +
Vol. Total = 294.90 m' 294.90 m'
3 Pembongkaran 1 m3 Dinding Tembok Bata
Panjang Lebar Tinggi Jumlah Sisi Jumlah Unit
= 3.30 x 0.15 x 3.50 x 2.00 x 1.00 = 3.46 m3
= 4.20 x 0.15 x 3.50 x 2.00 x 1.00 = 4.41
= 7.40 x 0.15 x 3.50 x 1.00 x 1.00 = 3.89
= 3.10 x 0.15 x 3.50 x 1.00 x 1.00 = 1.63
= 4.40 x 0.15 x 3.50 x 1.00 x 1.00 = 2.31
= 13.50 x 0.15 x 3.50 x 2.00 x 1.00 = 14.17
= 3.00 x 0.15 x 3.50 x 5.00 x 1.00 = 7.87
= 3.85 x 0.15 x 3.50 x 2.00 x 1.00 = 4.04
= 10.45 x 0.15 x 3.50 x 1.00 x 1.00 = 5.49
= 13.65 x 0.15 x 3.50 x 1.00 x 1.00 = 7.17
= 7.70 x 0.15 x 3.50 x 1.00 x 1.00 = 4.04
= 3.00 x 0.15 x 3.50 x 3.00 x 1.00 = 4.73
= 7.50 x 0.15 x 3.50 x 2.00 x 1.00 = 7.88
= 15.60 x 0.15 x 3.50 x 3.00 x 1.00 = 24.57
= 8.15 x 0.15 x 3.50 x 1.00 x 1.00 = 4.28
= 3.00 x 0.15 x 3.50 x 5.00 x 1.00 = 7.87
= 2.85 x 0.15 x 3.50 x 4.00 x 1.00 = 5.98
= 1.50 x 0.15 x 3.50 x 2.00 x 1.00 = 1.57
= 11.50 x 0.15 x 3.50 x 1.00 x 1.00 = 6.04
= 4.05 x 0.15 x 3.50 x 1.00 x 1.00 = 2.13
= 10.40 x 0.15 x 3.50 x 2.00 x 1.00 = 10.92
= 2.10 x 0.15 x 3.50 x 2.00 x 1.00 = 2.21
= 3.00 x 0.15 x 3.50 x 8.00 x 1.00 = 12.60
= 7.55 x 0.15 x 3.50 x 3.00 x 1.00 = 11.89
= 11.00 x 0.15 x 3.50 x 2.00 x 1.00 = 11.55
= 3.50 x 0.15 x 3.50 x 2.00 x 1.00 = 3.68
= 1.50 x 0.15 x 3.50 x 2.00 x 1.00 = 1.57
= 11.00 x 0.15 x 3.50 x 2.00 x 1.00 = 11.55
= 4.40 x 0.15 x 3.50 x 1.00 x 1.00 = 2.31
= 2.90 x 0.15 x 3.50 x 2.00 x 1.00 = 3.05
= 7.00 x 0.15 x 3.50 x 2.00 x 1.00 = 7.35
= 10.25 x 0.15 x 3.50 x 2.00 x 1.00 = 10.76
= 4.60 x 0.15 x 3.50 x 1.00 x 1.00 = 2.42
= 3.60 x 0.15 x 3.50 x 1.00 x 1.00 = 1.89
= 3.35 x 0.15 x 3.50 x 1.00 x 1.00 = 1.76
= 3.00 x 0.15 x 3.50 x 4.00 x 1.00 = 6.30
= 2.00 x 0.15 x 3.50 x 4.00 x 1.00 = 4.20
= 16.00 x 0.15 x 3.50 x 2.00 x 1.00 = 16.80
= 3.50 x 0.15 x 3.50 x 1.00 x 1.00 = 1.84
= 2.50 x 0.15 x 3.50 x 1.00 x 1.00 = 1.31
= 6.00 x 0.15 x 3.50 x 5.00 x 1.00 = 15.75
= 1.85 x 0.15 x 3.50 x 1.00 x 1.00 = 0.97 +
Vol. Total = 266.20 m3 266.20 m3
4 Keselamatan dan Kesehatan Kerja (K3)
- Alat Pelindung Diri
- Topi Pelindung (safety helmet) 1 buah = 20.00 = 20.00 buah 20.00 buah
- Pelindung Pernafasan dan Mulut (Masker) 1 dus = 10.00 = 10.00 dus 10.00 dus
- Sarung tangan (Safety Glooves) 1 set = 20.00 = 20.00 psg 20.00 psg
- Sepatu Keselamatan (Sepatu boot) 1 set = 20.00 = 20.00 psg 20.00 psg
- Rompi Keselamatan (Safety Vest) 1 buah = 20.00 = 20.00 buah 20.00 buah
- BPJS Ketenagakerjaan dan keselamatan kerja = 1.00 = 1.00 ls 1.00 ls
- Spanduk K3 = 5.00 = 5.00 ls 5.00 ls
5 Pengujian Laboratorium
- Cylinder/Cube Mould for Compressive Strength = 27.00 = 27.00 buah 27.00 buah
- Uji Mortar = 5.00 = 5.00 buah 5.00 buah
BACK UP VOLUME
Kegiatan : PUSKESMAS BANJARMANGU 1 Kode Bangunan : A
Pekerjaan : PUSKESMAS BANJARMANGU 1 Nomor : 1
Nomor :
Sket / Gambar Perhitungan Volume Satuan
II PEKERJAAN BETON
1 Lantai Kerja
- Pembuatan 1 m3 Beton Mutu f’c = 7,4 Mpa (K100)
Panjang Lebar Tinggi Jumlah Unit
Footplat = 1.80 x 1.80 x 0.05 x 2.00 = 0.32 m3
Lantai Parkir = 4.30 x 6.00 x 0.05 x 1.00 = 1.29
Beton Pengunci Paving = 5.90 x 0.10 x 0.30 x 1.00 = 0.18
= 3.00 x 0.10 x 0.30 x 1.00 = 0.09
= 1.50 x 0.10 x 0.30 x 1.00 = 0.05 +
Vol. Total = 1.93 m3 1.93 m3
2 Footplat
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225)
Panjang Lebar Tinggi Jumlah Sisi Jumlah Unit
Tapak = 1.80 x 1.80 x 0.35 x 1.00 x 2.00 = 2.27 m3
Kolom Tapak = 0.30 x 0.30 x 2.30 x 1.00 x 2.00 = 0.41 +
Vol. Total = 2.68 m3 2.68 m3
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip
Ø Ø Koefisien
Ø 16 = 16 x 16 x 0.006165 = 1.58 kg/m
Ø 13 = 13 x 13 x 0.006165 = 1.04 kg/m
Ø8 = 8 x 8 x 0.006165 = 0.39 kg/m
Tulangan Utama Ø 12 Panjang Koefisien Jumlah Besi Jumlah Sisi Jumlah Unit
Horizontal = 4.40 x 0.89 x 31.00 x 1.00 x 1.00 = 121.09 Kg
Vertikal = 6.10 x 0.89 x 22.00 x 1.00 x 1.00 = 119.14 +
Vol. Total = 240.23 Kg 240.23 Kg
- Pemasangan 1 m2 Bekisting untuk Plat lantai Beton Bangunan Gedung
Panjang Lebar Jumlah Sisi Jumlah Unit
= 4.30 x 0.15 x 2.00 x 1.00 = 1.29 m2
= 6.00 x 0.15 x 2.00 x 1.00 = 1.80 +
Vol. Total = 3.09 m2 3.09 m2
IV PEKERJAAN PLESTERAN
1 Pemasangan Plesteran Skoning 1 SP : 2 PP, lebar 10 mm
Panjang Jumlah Sisi Jumlah Unit
= 0.50 x 4.00 x 2.00 = 4.00 m' 4.00 m'
J PEKERJAAN LAIN-LAIN
I PEKERJAAN LAIN-LAIN
1 Pembersihan Lokasi
= 1.00 = 1.00 ls 1.00 ls
BACK UP VOLUME
Kegiatan : PUSKESMAS BANJARMANGU 1 Kode Bangunan : A
Pekerjaan : PUSKESMAS BANJARMANGU 1 Nomor : 1
Nomor :
Sket / Gambar Perhitungan Volume Satuan
II PEKERJAAN PONDASI
1 Pemasangan Pondasi Batu Belah 1SP : 6 PP
Pondasi 1 Panjang Lebar Tinggi Jumlah Sisi Jumlah Unit
2 ke 3 = 4.00 x 0.30 x 0.60 x 1.00 x 1.00 = 0.72 m3
4 = 4.50 x 0.30 x 0.60 x 1.00 x 1.00 = 0.81
5 = 4.00 x 0.30 x 0.60 x 1.00 x 1.00 = 0.72
6 = 3.00 x 0.30 x 0.60 x 1.00 x 1.00 = 0.54
7 = 10.00 x 0.30 x 0.60 x 1.00 x 1.00 = 1.80
8 = 10.00 x 0.30 x 0.60 x 1.00 x 1.00 = 1.80
9 = 12.55 x 0.30 x 0.60 x 1.00 x 1.00 = 2.26
10 = 5.55 x 0.30 x 0.60 x 1.00 x 1.00 = 1.00
11 = 5.50 x 0.30 x 0.60 x 1.00 x 1.00 = 0.99
12 = 3.00 x 0.30 x 0.60 x 1.00 x 1.00 = 0.54
13 = 3.00 x 0.30 x 0.60 x 1.00 x 1.00 = 0.54
A = 8.00 x 0.30 x 0.60 x 1.00 x 1.00 = 1.44
A ke B = 2.20 x 0.30 x 0.60 x 1.00 x 1.00 = 0.40
C = 14.00 x 0.30 x 0.60 x 1.00 x 1.00 = 2.52
D = 8.00 x 0.30 x 0.60 x 1.00 x 1.00 = 1.44
E = 5.00 x 0.30 x 0.60 x 1.00 x 1.00 = 0.90
F = 2.50 x 0.30 x 0.60 x 1.00 x 1.00 = 0.45
G = 6.00 x 0.30 x 0.60 x 1.00 x 1.00 = 1.08
Tangga Darurat
Vertikal = 6.17 x 0.30 x 0.60 x 1.00 x 1.00 = 1.11
Horizontal = 7.45 x 0.30 x 0.60 x 1.00 x 1.00 = 1.34
Pondasi 2
1 = 8.20 x 0.50 x 0.60 x 1.00 x 1.00 = 2.46
2 = 9.70 x 0.50 x 0.60 x 1.00 x 1.00 = 2.91
2 ke 3 = 3.70 x 0.50 x 0.60 x 1.00 x 1.00 = 1.11
3 = 20.70 x 0.50 x 0.60 x 1.00 x 1.00 = 6.21
3 ke 4 = 12.10 x 0.50 x 0.60 x 1.00 x 1.00 = 3.63
4 = 2.70 x 0.50 x 0.60 x 1.00 x 1.00 = 0.81
4 ke 5 = 3.70 x 0.50 x 0.60 x 1.00 x 1.00 = 1.11
5 = 9.70 x 0.50 x 0.60 x 1.00 x 1.00 = 2.91
6 = 18.40 x 0.50 x 0.60 x 1.00 x 1.00 = 5.52
7 = 4.70 x 0.50 x 0.60 x 1.00 x 1.00 = 1.41
8 = 11.40 x 0.50 x 0.60 x 1.00 x 1.00 = 3.42
9 = 11.40 x 0.50 x 0.60 x 1.00 x 1.00 = 3.42
10 = 18.40 x 0.50 x 0.60 x 1.00 x 1.00 = 5.52
10 ke 11 = 3.70 x 0.50 x 0.60 x 1.00 x 1.00 = 1.11
11 = 16.60 x 0.50 x 0.60 x 1.00 x 1.00 = 4.98
11 ke 12 = 3.20 x 0.50 x 0.60 x 1.00 x 1.00 = 0.96
12 = 5.20 x 0.50 x 0.60 x 1.00 x 1.00 = 1.56
13 = 5.20 x 0.50 x 0.60 x 1.00 x 1.00 = 1.56
14 = 8.20 x 0.50 x 0.60 x 1.00 x 1.00 = 2.46
B = 38.70 x 0.50 x 0.60 x 1.00 x 1.00 = 11.61
C = 26.10 x 0.50 x 0.60 x 1.00 x 1.00 = 7.83
C ke D = 7.40 x 0.50 x 0.60 x 1.00 x 1.00 = 2.22
D = 30.80 x 0.50 x 0.60 x 1.00 x 1.00 = 9.24
D ke E = 2.70 x 0.50 x 0.60 x 1.00 x 1.00 = 0.81
E = 17.60 x 0.50 x 0.60 x 1.00 x 1.00 = 5.28
E ke F = 4.20 x 0.50 x 0.60 x 1.00 x 1.00 = 1.26
F = 28.40 x 0.50 x 0.60 x 1.00 x 1.00 = 8.52
G = 19.90 x 0.50 x 0.60 x 1.00 x 1.00 = 5.97
G ke H = 7.90 x 0.50 x 0.60 x 1.00 x 1.00 = 2.37
H = 23.20 x 0.50 x 0.60 x 1.00 x 1.00 = 6.96
Pengurang
Silangan Pondasi 2 = 0.50 x 0.50 x 0.60 x 1.00 x 83.00 = (12.45)
Silangan Kolom K 1 Antar Pondasi 1 = 0.30 x 0.30 x 0.60 x 1.00 x 28.00 = (1.51)
Silangan Kolom K 1 Antar Pondasi 2 = 0.30 x 0.30 x 0.60 x 1.00 x 62.00 = (3.35) +
Vol. Total = 120.23 m3 120.23 m3
2 Pemasang Batu Kosong/Anstamping
Pondasi 2 Panjang Lebar Tinggi Jumlah Sisi Jumlah Unit
1 = 8.20 x 0.80 x 0.20 x 1.00 x 1.00 = 1.31 m3
2 = 9.70 x 0.80 x 0.20 x 1.00 x 1.00 = 1.55
2 ke 3 = 3.70 x 0.80 x 0.20 x 1.00 x 1.00 = 0.59
3 = 20.70 x 0.80 x 0.20 x 1.00 x 1.00 = 3.31
3 ke 4 = 12.10 x 0.80 x 0.20 x 1.00 x 1.00 = 1.94
4 = 2.70 x 0.80 x 0.20 x 1.00 x 1.00 = 0.43
4 ke 5 = 3.70 x 0.80 x 0.20 x 1.00 x 1.00 = 0.59
5 = 9.70 x 0.80 x 0.20 x 1.00 x 1.00 = 1.55
6 = 18.40 x 0.80 x 0.20 x 1.00 x 1.00 = 2.94
7 = 4.70 x 0.80 x 0.20 x 1.00 x 1.00 = 0.75
8 = 11.40 x 0.80 x 0.20 x 1.00 x 1.00 = 1.82
9 = 11.40 x 0.80 x 0.20 x 1.00 x 1.00 = 1.82
10 = 18.40 x 0.80 x 0.20 x 1.00 x 1.00 = 2.94
10 ke 11 = 3.70 x 0.80 x 0.20 x 1.00 x 1.00 = 0.59
11 = 16.60 x 0.80 x 0.20 x 1.00 x 1.00 = 2.66
11 ke 12 = 3.20 x 0.80 x 0.20 x 1.00 x 1.00 = 0.51
12 = 5.20 x 0.80 x 0.20 x 1.00 x 1.00 = 0.83
13 = 5.20 x 0.80 x 0.20 x 1.00 x 1.00 = 0.83
14 = 8.20 x 0.80 x 0.20 x 1.00 x 1.00 = 1.31
B = 38.70 x 0.80 x 0.20 x 1.00 x 1.00 = 6.19
C = 26.10 x 0.80 x 0.20 x 1.00 x 1.00 = 4.18
C ke D = 7.40 x 0.80 x 0.20 x 1.00 x 1.00 = 1.18
D = 30.80 x 0.80 x 0.20 x 1.00 x 1.00 = 4.93
D ke E = 2.70 x 0.80 x 0.20 x 1.00 x 1.00 = 0.43
E = 17.60 x 0.80 x 0.20 x 1.00 x 1.00 = 2.82
E ke F = 4.20 x 0.80 x 0.20 x 1.00 x 1.00 = 0.67
F = 28.40 x 0.80 x 0.20 x 1.00 x 1.00 = 4.54
G = 19.90 x 0.80 x 0.20 x 1.00 x 1.00 = 3.18
G ke H = 7.90 x 0.80 x 0.20 x 1.00 x 1.00 = 1.26
H = 23.20 x 0.80 x 0.20 x 1.00 x 1.00 = 3.71
Pengurang
Silangan Pondasi 2 = 0.80 x 0.80 x 0.20 x 1.00 x 83.00 = (10.62)
Silangan Kolom K 1 Antar Pondasi 1 = 0.30 x 0.30 x 0.20 x 1.00 x 28.00 = (0.50)
Silangan Kolom K 1 Antar Pondasi 2 = 0.30 x 0.30 x 0.20 x 1.00 x 62.00 = (1.12) +
Vol. Total = 49.16 m3 49.16 m3
Tulangan Utama Ø 12 Panjang Koefisien Jumlah Besi Jumlah Sisi Jumlah Unit
2 ke 3 = 4.10 x 0.89 x 6.00 x 1.00 x 1.00 = 21.84 Kg
3 = 6.60 x 0.89 x 6.00 x 1.00 x 1.00 = 35.16
4 = 6.60 x 0.89 x 6.00 x 1.00 x 1.00 = 35.16
5 = 4.10 x 0.89 x 6.00 x 1.00 x 1.00 = 21.84
6 = 20.10 x 0.89 x 6.00 x 1.00 x 1.00 = 107.06
7 = 14.10 x 0.89 x 6.00 x 1.00 x 1.00 = 75.10
8 = 20.10 x 0.89 x 6.00 x 1.00 x 1.00 = 107.06
9 = 20.10 x 0.89 x 6.00 x 1.00 x 1.00 = 107.06
10 = 20.10 x 0.89 x 6.00 x 1.00 x 1.00 = 107.06
10 ke 11 = 4.60 x 0.89 x 6.00 x 1.00 x 1.00 = 24.50
11 = 20.10 x 0.89 x 6.00 x 1.00 x 1.00 = 107.06
11 ke 12 = 2.60 x 0.89 x 6.00 x 1.00 x 1.00 = 13.85
12 = 7.60 x 0.89 x 6.00 x 1.00 x 1.00 = 40.48
13 = 7.60 x 0.89 x 6.00 x 1.00 x 1.00 = 40.48
14 = 7.60 x 0.89 x 6.00 x 1.00 x 1.00 = 40.48
A = 8.10 x 0.89 x 6.00 x 1.00 x 1.00 = 43.15
B = 38.10 x 0.89 x 6.00 x 1.00 x 1.00 = 202.94
C = 23.60 x 0.89 x 6.00 x 1.00 x 1.00 = 125.71
D = 23.60 x 0.89 x 6.00 x 1.00 x 1.00 = 125.71
E = 15.10 x 0.89 x 6.00 x 1.00 x 1.00 = 80.43
F = 24.60 x 0.89 x 6.00 x 1.00 x 1.00 = 131.03
G = 24.60 x 0.89 x 6.00 x 1.00 x 1.00 = 131.03
H = 22.60 x 0.89 x 6.00 x 1.00 x 1.00 = 120.38
Tulangan Utama Ø 10
2 ke 3 = 4.10 x 0.62 x 2.00 x 1.00 x 1.00 = 5.06
3 = 6.60 x 0.62 x 2.00 x 1.00 x 1.00 = 8.14
4 = 6.60 x 0.62 x 2.00 x 1.00 x 1.00 = 8.14
5 = 4.10 x 0.62 x 2.00 x 1.00 x 1.00 = 5.06
6 = 20.10 x 0.62 x 2.00 x 1.00 x 1.00 = 24.78
7 = 14.10 x 0.62 x 2.00 x 1.00 x 1.00 = 17.39
8 = 20.10 x 0.62 x 2.00 x 1.00 x 1.00 = 24.78
9 = 20.10 x 0.62 x 2.00 x 1.00 x 1.00 = 24.78
10 = 20.10 x 0.62 x 2.00 x 1.00 x 1.00 = 24.78
10 ke 11 = 4.60 x 0.62 x 2.00 x 1.00 x 1.00 = 5.67
11 = 20.10 x 0.62 x 2.00 x 1.00 x 1.00 = 24.78
11 ke 12 = 2.60 x 0.62 x 2.00 x 1.00 x 1.00 = 3.21
12 = 7.60 x 0.62 x 2.00 x 1.00 x 1.00 = 9.37
13 = 7.60 x 0.62 x 2.00 x 1.00 x 1.00 = 9.37
14 = 7.60 x 0.62 x 2.00 x 1.00 x 1.00 = 9.37
A = 8.10 x 0.62 x 2.00 x 1.00 x 1.00 = 9.99
B = 38.10 x 0.62 x 2.00 x 1.00 x 1.00 = 46.98
C = 23.60 x 0.62 x 2.00 x 1.00 x 1.00 = 29.10
D = 23.60 x 0.62 x 2.00 x 1.00 x 1.00 = 29.10
E = 15.10 x 0.62 x 2.00 x 1.00 x 1.00 = 18.62
F = 24.60 x 0.62 x 2.00 x 1.00 x 1.00 = 30.33
G = 24.60 x 0.62 x 2.00 x 1.00 x 1.00 = 30.33
H = 22.60 x 0.62 x 2.00 x 1.00 x 1.00 = 27.87
Tulangan Sengkang Ø 8
2 ke 3 = 0.80 x 0.39 x 25.00 x 1.00 x 1.00 = 7.89
3 = 0.80 x 0.39 x 40.00 x 1.00 x 1.00 = 12.63
4 = 0.80 x 0.39 x 40.00 x 1.00 x 1.00 = 12.63
5 = 0.80 x 0.39 x 25.00 x 1.00 x 1.00 = 7.89
6 = 0.80 x 0.39 x 122.00 x 1.00 x 1.00 = 38.51
7 = 0.80 x 0.39 x 86.00 x 1.00 x 1.00 = 27.15
8 = 0.80 x 0.39 x 122.00 x 1.00 x 1.00 = 38.51
9 = 0.80 x 0.39 x 122.00 x 1.00 x 1.00 = 38.51
10 = 0.80 x 0.39 x 122.00 x 1.00 x 1.00 = 38.51
10 ke 11 = 0.80 x 0.39 x 30.00 x 1.00 x 1.00 = 9.47
11 = 0.80 x 0.39 x 122.00 x 1.00 x 1.00 = 38.51
11 ke 12 = 0.80 x 0.39 x 15.00 x 1.00 x 1.00 = 4.73
12 = 0.80 x 0.39 x 47.00 x 1.00 x 1.00 = 14.84
13 = 0.80 x 0.39 x 47.00 x 1.00 x 1.00 = 14.84
14 = 0.80 x 0.39 x 47.00 x 1.00 x 1.00 = 14.84
A = 0.80 x 0.39 x 48.00 x 1.00 x 1.00 = 15.15
B = 0.80 x 0.39 x 226.00 x 1.00 x 1.00 = 71.34
C = 0.80 x 0.39 x 141.00 x 1.00 x 1.00 = 44.51
D = 0.80 x 0.39 x 141.00 x 1.00 x 1.00 = 44.51
E = 0.80 x 0.39 x 91.00 x 1.00 x 1.00 = 28.72
F = 0.80 x 0.39 x 148.00 x 1.00 x 1.00 = 46.72
G = 0.80 x 0.39 x 148.00 x 1.00 x 1.00 = 46.72
H = 0.80 x 0.39 x 137.00 x 1.00 x 1.00 = 43.24 +
Vol. Total = 2,931.91 Kg 2,931.91 Kg
- Pemasangan 1 m2 Bekisting untuk Sloof Beton Bangunan Gedung (volume dibagi 2 kali)
Panjang Lebar Jumlah Sisi Jumlah Unit
2 ke 3 = 3.70 x 0.25 x 2.00 x 1.00 = 1.85 m2
3 = 5.90 x 0.25 x 2.00 x 1.00 = 2.95
4 = 5.90 x 0.25 x 2.00 x 1.00 = 2.95
5 = 3.70 x 0.25 x 2.00 x 1.00 = 1.85
6 = 18.20 x 0.25 x 2.00 x 1.00 = 9.10
7 = 12.80 x 0.25 x 2.00 x 1.00 = 6.40
8 = 18.20 x 0.25 x 2.00 x 1.00 = 9.10
9 = 18.20 x 0.25 x 2.00 x 1.00 = 9.10
10 = 18.20 x 0.25 x 2.00 x 1.00 = 9.10
10 ke 11 = 4.43 x 0.25 x 2.00 x 1.00 = 2.21
11 = 18.20 x 0.25 x 2.00 x 1.00 = 9.10
11 ke 12 = 2.20 x 0.25 x 2.00 x 1.00 = 1.10
12 = 6.90 x 0.25 x 2.00 x 1.00 = 3.45
13 = 6.90 x 0.25 x 2.00 x 1.00 = 3.45
14 = 6.90 x 0.25 x 2.00 x 1.00 = 3.45
A = 7.10 x 0.25 x 2.00 x 1.00 = 3.55
B = 33.80 x 0.25 x 2.00 x 1.00 = 16.90
C = 21.10 x 0.25 x 2.00 x 1.00 = 10.55
D = 21.10 x 0.25 x 2.00 x 1.00 = 10.55
E = 13.50 x 0.25 x 2.00 x 1.00 = 6.75
F = 22.10 x 0.25 x 2.00 x 1.00 = 11.05
G = 22.10 x 0.25 x 2.00 x 1.00 = 11.05
H = 20.40 x 0.25 x 2.00 x 1.00 = 10.20 +
Vol. Total = 155.76 m2
Dipakai 2 kali = 77.88 m2 77.88 m2
6 Sloof (SL 2) 15 x 25 cm
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225)
Panjang Lebar Tinggi Panjang Lebar Tinggi Jumlah Kolom
1 = 7.50 x 0.15 x 0.25 - 0.30 x 0.15 x 0.25 x 0.50 = 0.28 m3
0.15 x 0.15 x 0.25 x 3.50 = (0.02)
2 = 9.00 x 0.15 x 0.25 - 0.15 x 0.15 x 0.25 x 4.00 = 0.31
2 ke 3 = 3.00 x 0.15 x 0.25 - 0.15 x 0.15 x 0.25 x 2.00 = 0.10
3 = 13.50 x 0.15 x 0.25 - 0.30 x 0.15 x 0.25 x 1.00 = 0.50
0.15 x 0.15 x 0.25 x 4.00 = (0.02)
3 ke 4 = 10.00 x 0.15 x 0.25 - 0.15 x 0.15 x 0.25 x 4.00 = 0.35
4 ke 5 = 3.00 x 0.15 x 0.25 - 0.15 x 0.15 x 0.25 x 2.00 = 0.10
5 = 9.00 x 0.15 x 0.25 - 0.15 x 0.15 x 0.25 x 5.00 = 0.31
10 ke 11 = 3.00 x 0.15 x 0.25 - 0.15 x 0.15 x 0.25 x 2.00 = 0.10
C = 14.50 x 0.15 x 0.25 - 0.30 x 0.15 x 0.25 x 0.50 = 0.54
0.15 x 0.15 x 0.25 x 5.50 = (0.03)
C ke D = 6.00 x 0.15 x 0.25 - 0.15 x 0.15 x 0.25 x 3.00 = 0.21
D = 12.50 x 0.15 x 0.25 - 0.15 x 0.15 x 0.25 x 6.00 = 0.44
D ke E = 2.00 x 0.15 x 0.25 - 0.15 x 0.15 x 0.25 x 1.00 = 0.07
E = 5.50 x 0.15 x 0.25 - 0.15 x 0.15 x 0.25 x 3.00 = 0.19
E ke F = 3.50 x 0.15 x 0.25 - 0.15 x 0.15 x 0.25 x 2.00 = 0.12
F = 5.00 x 0.15 x 0.25 - 0.30 x 0.15 x 0.25 x 0.50 = 0.18
0.15 x 0.15 x 0.25 x 1.50 = (0.01)
G ke H = 6.50 x 0.15 x 0.25 - 0.15 x 0.15 x 0.25 x 4.00 = 0.22
Tangga Darurat
Vertikal = 0.60 x 0.15 x 0.25 = 0.02
= 0.90 x 0.15 x 0.25 = 0.03
= 1.11 x 0.15 x 0.25 = 0.04
= 1.07 x 0.15 x 0.25 = 0.04
= 1.15 x 0.15 x 0.25 = 0.04
Horizontal = 1.58 x 0.15 x 0.25 = 0.06
= 0.38 x 0.15 x 0.25 = 0.01
= 0.70 x 0.15 x 0.25 = 0.03
= 1.20 x 0.15 x 0.25 = 0.05
= 1.20 x 0.15 x 0.25 = 0.05
= 1.27 x 0.15 x 0.25 = 0.05 +
Vol. Total = 4.35 m3 4.35 m3
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip
Ø Ø Koefisien
Ø 12 = 12 x 12 x 0.006165 = 0.89 kg/m
Ø 10 = 10 x 10 x 0.006165 = 0.62 kg/m
Ø8 = 8 x 8 x 0.006165 = 0.39 kg/m
Tulangan Utama Ø 12 Panjang Koefisien Jumlah Besi Jumlah Sisi Jumlah Unit
1 = 7.60 x 0.89 x 4.00 x 1.00 x 1.00 = 26.99 Kg
2 = 9.10 x 0.89 x 4.00 x 1.00 x 1.00 = 32.31
2 ke 3 = 3.10 x 0.89 x 4.00 x 1.00 x 1.00 = 11.01
3 = 13.60 x 0.89 x 4.00 x 1.00 x 1.00 = 48.29
3 ke 4 = 10.10 x 0.89 x 4.00 x 1.00 x 1.00 = 35.87
4 ke 5 = 3.10 x 0.89 x 4.00 x 1.00 x 1.00 = 11.01
5 = 9.10 x 0.89 x 4.00 x 1.00 x 1.00 = 32.31
10 ke 11 = 3.10 x 0.89 x 4.00 x 1.00 x 1.00 = 11.01
C = 14.60 x 0.89 x 4.00 x 1.00 x 1.00 = 51.85
C ke D = 6.10 x 0.89 x 4.00 x 1.00 x 1.00 = 21.66
D = 12.60 x 0.89 x 4.00 x 1.00 x 1.00 = 44.74
D ke E = 2.10 x 0.89 x 4.00 x 1.00 x 1.00 = 7.46
E = 5.60 x 0.89 x 4.00 x 1.00 x 1.00 = 19.89
E ke F = 3.60 x 0.89 x 4.00 x 1.00 x 1.00 = 12.78
F = 5.10 x 0.89 x 4.00 x 1.00 x 1.00 = 18.11
G ke H = 6.60 x 0.89 x 4.00 x 1.00 x 1.00 = 23.44
Tangga Darurat
Vertikal = 0.70 x 0.89 x 4.00 x 1.00 x 1.00 = 2.49
= 1.00 x 0.89 x 4.00 x 1.00 x 1.00 = 3.55
= 1.21 x 0.89 x 4.00 x 1.00 x 1.00 = 4.30
= 1.17 x 0.89 x 4.00 x 1.00 x 1.00 = 4.15
= 1.25 x 0.89 x 4.00 x 1.00 x 1.00 = 4.44
Horizontal = 1.68 x 0.89 x 4.00 x 1.00 x 1.00 = 5.97
= 0.48 x 0.89 x 4.00 x 1.00 x 1.00 = 1.70
= 0.80 x 0.89 x 4.00 x 1.00 x 1.00 = 2.84
= 1.30 x 0.89 x 4.00 x 1.00 x 1.00 = 4.62
= 1.30 x 0.89 x 4.00 x 1.00 x 1.00 = 4.62
= 1.37 x 0.89 x 4.00 x 1.00 x 1.00 = 4.86
Tulangan Utama Ø 10
1 = 7.60 x 0.62 x 2.00 x 1.00 x 1.00 = 9.37
2 = 9.10 x 0.62 x 2.00 x 1.00 x 1.00 = 11.22
2 ke 3 = 3.10 x 0.62 x 2.00 x 1.00 x 1.00 = 3.82
3 = 13.60 x 0.62 x 2.00 x 1.00 x 1.00 = 16.77
3 ke 4 = 10.10 x 0.62 x 2.00 x 1.00 x 1.00 = 12.45
4 ke 5 = 3.10 x 0.62 x 2.00 x 1.00 x 1.00 = 3.82
5 = 9.10 x 0.62 x 2.00 x 1.00 x 1.00 = 11.22
10 ke 11 = 3.10 x 0.62 x 2.00 x 1.00 x 1.00 = 3.82
C = 14.60 x 0.62 x 2.00 x 1.00 x 1.00 = 18.00
C ke D = 6.10 x 0.62 x 2.00 x 1.00 x 1.00 = 7.52
D = 12.60 x 0.62 x 2.00 x 1.00 x 1.00 = 15.54
D ke E = 2.10 x 0.62 x 2.00 x 1.00 x 1.00 = 2.59
E = 5.60 x 0.62 x 2.00 x 1.00 x 1.00 = 6.90
E ke F = 3.60 x 0.62 x 2.00 x 1.00 x 1.00 = 4.44
F = 5.10 x 0.62 x 2.00 x 1.00 x 1.00 = 6.29
G ke H = 6.60 x 0.62 x 2.00 x 1.00 x 1.00 = 8.14
Tangga Darurat
Vertikal = 0.70 x 0.62 x 2.00 x 1.00 x 1.00 = 0.86
= 1.00 x 0.62 x 2.00 x 1.00 x 1.00 = 1.23
= 1.21 x 0.62 x 2.00 x 1.00 x 1.00 = 1.49
= 1.17 x 0.62 x 2.00 x 1.00 x 1.00 = 1.44
= 1.25 x 0.62 x 2.00 x 1.00 x 1.00 = 1.54
Horizontal = 1.68 x 0.62 x 2.00 x 1.00 x 1.00 = 2.07
= 0.48 x 0.62 x 2.00 x 1.00 x 1.00 = 0.59
= 0.80 x 0.62 x 2.00 x 1.00 x 1.00 = 0.99
= 1.30 x 0.62 x 2.00 x 1.00 x 1.00 = 1.60
= 1.30 x 0.62 x 2.00 x 1.00 x 1.00 = 1.60
= 1.37 x 0.62 x 2.00 x 1.00 x 1.00 = 1.69
Tulangan Utama Ø 8
1 = 0.70 x 0.39 x 50.00 x 1.00 x 1.00 = 13.81
2 = 0.70 x 0.39 x 57.00 x 1.00 x 1.00 = 15.74
2 ke 3 = 0.70 x 0.39 x 19.00 x 1.00 x 1.00 = 5.25
3 = 0.70 x 0.39 x 89.00 x 1.00 x 1.00 = 24.58
3 ke 4 = 0.70 x 0.39 x 63.00 x 1.00 x 1.00 = 17.40
4 ke 5 = 0.70 x 0.39 x 19.00 x 1.00 x 1.00 = 5.25
5 = 0.70 x 0.39 x 56.00 x 1.00 x 1.00 = 15.47
10 ke 11 = 0.70 x 0.39 x 19.00 x 1.00 x 1.00 = 5.25
C = 0.70 x 0.39 x 96.00 x 1.00 x 1.00 = 26.51
C ke D = 0.70 x 0.39 x 38.00 x 1.00 x 1.00 = 10.50
D = 0.70 x 0.39 x 78.00 x 1.00 x 1.00 = 21.54
D ke E = 0.70 x 0.39 x 13.00 x 1.00 x 1.00 = 3.59
E = 0.70 x 0.39 x 34.00 x 1.00 x 1.00 = 9.39
E ke F = 0.70 x 0.39 x 22.00 x 1.00 x 1.00 = 6.08
F = 0.70 x 0.39 x 33.00 x 1.00 x 1.00 = 9.11
G ke H = 0.70 x 0.39 x 40.00 x 1.00 x 1.00 = 11.05
Tangga Darurat
Vertikal = 0.70 x 0.39 x 5.00 x 1.00 x 1.00 = 1.38
= 0.70 x 0.39 x 7.00 x 1.00 x 1.00 = 1.93
= 0.70 x 0.39 x 8.00 x 1.00 x 1.00 = 2.21
= 0.70 x 0.39 x 8.00 x 1.00 x 1.00 = 2.21
= 0.70 x 0.39 x 8.00 x 1.00 x 1.00 = 2.21
Horizontal = 0.70 x 0.39 x 11.00 x 1.00 x 1.00 = 3.04
= 0.70 x 0.39 x 3.00 x 1.00 x 1.00 = 0.83
= 0.70 x 0.39 x 5.00 x 1.00 x 1.00 = 1.38
= 0.70 x 0.39 x 9.00 x 1.00 x 1.00 = 2.49
= 0.70 x 0.39 x 9.00 x 1.00 x 1.00 = 2.49
= 0.70 x 0.39 x 9.00 x 1.00 x 1.00 = 2.49 +
Vol. Total = 832.46 Kg 832.46 Kg
- Pemasangan 1 m2 Bekisting untuk Sloof Beton Bangunan Gedung (volume dibagi 2 kali)
Panjang Lebar Jumlah Sisi Jumlah Unit
1 = 7.35 x 0.25 x 2.00 x 1.00 = 3.68 m2
2 = 8.40 x 0.25 x 2.00 x 1.00 = 4.20
2 ke 3 = 2.70 x 0.25 x 2.00 x 1.00 = 1.35
3 = 13.20 x 0.25 x 2.00 x 1.00 = 6.60
3 ke 4 = 9.40 x 0.25 x 2.00 x 1.00 = 4.70
4 ke 5 = 2.70 x 0.25 x 2.00 x 1.00 = 1.35
5 = 8.25 x 0.25 x 2.00 x 1.00 = 4.13
10 ke 11 = 2.70 x 0.25 x 2.00 x 1.00 = 1.35
C = 14.35 x 0.25 x 2.00 x 1.00 = 7.18
C ke D = 5.55 x 0.25 x 2.00 x 1.00 = 2.78
D = 11.60 x 0.25 x 2.00 x 1.00 = 5.80
D ke E = 1.85 x 0.25 x 2.00 x 1.00 = 0.93
E = 5.05 x 0.25 x 2.00 x 1.00 = 2.53
E ke F = 3.20 x 0.25 x 2.00 x 1.00 = 1.60
F = 4.85 x 0.25 x 2.00 x 1.00 = 2.43
G ke H = 5.90 x 0.25 x 2.00 x 1.00 = 2.95
Tangga Darurat
Vertikal = 0.60 x 0.25 x 2.00 x 1.00 = 0.30
= 0.90 x 0.25 x 2.00 x 1.00 = 0.45
= 1.11 x 0.25 x 2.00 x 1.00 = 0.56
= 1.07 x 0.25 x 2.00 x 1.00 = 0.54
= 1.15 x 0.25 x 2.00 x 1.00 = 0.58
Horizontal = 1.58 x 0.25 x 2.00 x 1.00 = 0.79
= 0.38 x 0.25 x 2.00 x 1.00 = 0.19
= 0.70 x 0.25 x 2.00 x 1.00 = 0.35
= 1.20 x 0.25 x 2.00 x 1.00 = 0.60
= 1.20 x 0.25 x 2.00 x 1.00 = 0.60
= 1.27 x 0.25 x 2.00 x 1.00 = 0.64 +
Vol. Total = 59.10 m2
Dipakai 2 kali = 29.55 m2 29.55 m2
7 Kolom (K 1) 30 x 30 cm
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225)
Panjang Lebar Tinggi Jumlah Sisi Jumlah Unit
= 0.30 x 0.30 x 4.05 x 1.00 x 69.00 = 25.15 m3
Tangga Darurat
= 0.30 x 0.30 x 1.85 x 1.00 x 1.00 = 0.17
= 0.30 x 0.30 x 2.85 x 1.00 x 1.00 = 0.26 +
Vol. Total = 25.57 m3 25.57 m3
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip
Ø Ø Koefisien
Ø 16 = 16 x 16 x 0.006165 = 1.58 kg/m
Ø8 = 8 x 8 x 0.006165 = 0.39 kg/m
Tulangan Utama Ø 13 Panjang Koefisien Jumlah Besi Jumlah Sisi Jumlah Unit
Balok (B 1) 20 x 40 cm Elevasi +3.55
B = 14.60 x 1.04 x 6.00 x 1.00 x 1.00 = 91.27 Kg
Balok (B 1) 20 x 40 cm Elevasi +4.00
3 = 6.60 x 1.04 x 6.00 x 1.00 x 1.00 = 41.26
4 = 6.60 x 1.04 x 6.00 x 1.00 x 1.00 = 41.26
6 = 10.60 x 1.04 x 6.00 x 1.00 x 1.00 = 66.26
= 6.60 x 1.04 x 6.00 x 1.00 x 1.00 = 41.26
7 = 10.60 x 1.04 x 6.00 x 1.00 x 1.00 = 66.26
= 6.60 x 1.04 x 6.00 x 1.00 x 1.00 = 41.26
8 = 20.10 x 1.04 x 6.00 x 1.00 x 1.00 = 125.65
9 = 20.10 x 1.04 x 6.00 x 1.00 x 1.00 = 125.65
10 = 20.10 x 1.04 x 6.00 x 1.00 x 1.00 = 125.65
11 = 20.10 x 1.04 x 6.00 x 1.00 x 1.00 = 125.65
11 ke 12 = 2.60 x 1.04 x 6.00 x 1.00 x 1.00 = 16.25
12 = 7.60 x 1.04 x 6.00 x 1.00 x 1.00 = 47.51
13 = 7.60 x 1.04 x 6.00 x 1.00 x 1.00 = 47.51
14 = 7.60 x 1.04 x 6.00 x 1.00 x 1.00 = 47.51
B = 23.60 x 1.04 x 6.00 x 1.00 x 1.00 = 147.53
C = 23.60 x 1.04 x 6.00 x 1.00 x 1.00 = 147.53
D = 23.60 x 1.04 x 6.00 x 1.00 x 1.00 = 147.53
E = 15.10 x 1.04 x 6.00 x 1.00 x 1.00 = 94.39
F = 24.60 x 1.04 x 6.00 x 1.00 x 1.00 = 153.78
G = 24.60 x 1.04 x 6.00 x 1.00 x 1.00 = 153.78
H = 22.60 x 1.04 x 6.00 x 1.00 x 1.00 = 141.28
Tulangan Utama Ø 10
Balok (B 1) 20 x 40 cm Elevasi +3.55
B = 14.60 x 0.62 x 4.00 x 1.00 x 1.00 = 36.00
Balok (B 1) 20 x 40 cm Elevasi +4.00
3 = 6.60 x 0.62 x 4.00 x 1.00 x 1.00 = 16.28
4 = 6.60 x 0.62 x 4.00 x 1.00 x 1.00 = 16.28
6 = 10.60 x 0.62 x 4.00 x 1.00 x 1.00 = 26.14
= 6.60 x 0.62 x 4.00 x 1.00 x 1.00 = 16.28
7 = 10.60 x 0.62 x 4.00 x 1.00 x 1.00 = 26.14
= 6.60 x 0.62 x 4.00 x 1.00 x 1.00 = 16.28
8 = 20.10 x 0.62 x 4.00 x 1.00 x 1.00 = 49.57
9 = 20.10 x 0.62 x 4.00 x 1.00 x 1.00 = 49.57
10 = 20.10 x 0.62 x 4.00 x 1.00 x 1.00 = 49.57
11 = 20.10 x 0.62 x 4.00 x 1.00 x 1.00 = 49.57
11 ke 12 = 2.60 x 0.62 x 4.00 x 1.00 x 1.00 = 6.41
12 = 7.60 x 0.62 x 4.00 x 1.00 x 1.00 = 18.74
13 = 7.60 x 0.62 x 4.00 x 1.00 x 1.00 = 18.74
14 = 7.60 x 0.62 x 4.00 x 1.00 x 1.00 = 18.74
B = 23.60 x 0.62 x 4.00 x 1.00 x 1.00 = 58.20
C = 23.60 x 0.62 x 4.00 x 1.00 x 1.00 = 58.20
D = 23.60 x 0.62 x 4.00 x 1.00 x 1.00 = 58.20
E = 15.10 x 0.62 x 4.00 x 1.00 x 1.00 = 37.24
F = 24.60 x 0.62 x 4.00 x 1.00 x 1.00 = 60.66
G = 24.60 x 0.62 x 4.00 x 1.00 x 1.00 = 60.66
H = 22.60 x 0.62 x 4.00 x 1.00 x 1.00 = 55.73
Tulangan Sengkang Ø 8
Balok (B 1) 20 x 40 cm Elevasi +3.55
B = 1.10 x 0.39 x 85.00 x 1.00 x 1.00 = 36.89
Balok (B 1) 20 x 40 cm Elevasi +4.00
3 = 1.10 x 0.39 x 40.00 x 1.00 x 1.00 = 17.36
4 = 1.10 x 0.39 x 40.00 x 1.00 x 1.00 = 17.36
6 = 1.10 x 0.39 x 65.00 x 1.00 x 1.00 = 28.21
= 1.10 x 0.39 x 40.00 x 1.00 x 1.00 = 17.36
7 = 1.10 x 0.39 x 65.00 x 1.00 x 1.00 = 28.21
= 1.10 x 0.39 x 40.00 x 1.00 x 1.00 = 17.36
8 = 1.10 x 0.39 x 122.00 x 1.00 x 1.00 = 52.95
9 = 1.10 x 0.39 x 122.00 x 1.00 x 1.00 = 52.95
10 = 1.10 x 0.39 x 122.00 x 1.00 x 1.00 = 52.95
11 = 1.10 x 0.39 x 122.00 x 1.00 x 1.00 = 52.95
11 ke 12 = 1.10 x 0.39 x 15.00 x 1.00 x 1.00 = 6.51
12 = 1.10 x 0.39 x 47.00 x 1.00 x 1.00 = 20.40
13 = 1.10 x 0.39 x 47.00 x 1.00 x 1.00 = 20.40
14 = 1.10 x 0.39 x 47.00 x 1.00 x 1.00 = 20.40
B = 1.10 x 0.39 x 141.00 x 1.00 x 1.00 = 61.20
C = 1.10 x 0.39 x 141.00 x 1.00 x 1.00 = 61.20
D = 1.10 x 0.39 x 141.00 x 1.00 x 1.00 = 61.20
E = 1.10 x 0.39 x 91.00 x 1.00 x 1.00 = 39.50
F = 1.10 x 0.39 x 148.00 x 1.00 x 1.00 = 64.23
G = 1.10 x 0.39 x 148.00 x 1.00 x 1.00 = 64.23
H = 1.10 x 0.39 x 137.00 x 1.00 x 1.00 = 59.46 +
Vol. Total = 3,692.50 Kg 3,692.50 Kg
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali)
Panjang Lebar Jumlah Sisi Jumlah Unit
Balok (B 1) 20 x 40 cm Elevasi +3.55
B = 12.70 x 0.74 x 1.00 x 1.00 = 9.40 m2
Balok (B 1) 20 x 40 cm Elevasi +4.00
3 = 5.90 x 0.74 x 1.00 x 1.00 = 4.37
4 = 5.90 x 0.74 x 1.00 x 1.00 = 4.37
6 = 9.60 x 0.74 x 1.00 x 1.00 = 7.10
= 5.90 x 0.74 x 1.00 x 1.00 = 4.37
7 = 9.60 x 0.74 x 1.00 x 1.00 = 7.10
= 5.90 x 0.74 x 1.00 x 1.00 = 4.37
8 = 18.20 x 0.74 x 1.00 x 1.00 = 13.47
9 = 18.20 x 0.74 x 1.00 x 1.00 = 13.47
10 = 18.20 x 0.74 x 1.00 x 1.00 = 13.47
11 = 18.20 x 0.74 x 1.00 x 1.00 = 13.47
11 ke 12 = 2.20 x 0.74 x 1.00 x 1.00 = 1.63
12 = 6.90 x 0.74 x 1.00 x 1.00 = 5.11
13 = 6.90 x 0.74 x 1.00 x 1.00 = 5.11
14 = 6.90 x 0.74 x 1.00 x 1.00 = 5.11
B = 21.10 x 0.74 x 1.00 x 1.00 = 15.61
C = 21.10 x 0.74 x 1.00 x 1.00 = 15.61
D = 21.10 x 0.74 x 1.00 x 1.00 = 15.61
E = 13.50 x 0.74 x 1.00 x 1.00 = 9.99
F = 22.10 x 0.74 x 1.00 x 1.00 = 16.35
G = 22.10 x 0.74 x 1.00 x 1.00 = 16.35
H = 20.40 x 0.74 x 1.00 x 1.00 = 15.10 +
Vol. Total = 216.52 m2
Dipakai 2 kali = 108.26 m2 108.26 m2
11 Balok (B 2) 15 x 30 cm
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225)
Panjang Lebar Tinggi Panjang Lebar Tinggi Jumlah Silangan
Balok (B 2) 15 x 30 cm Elevasi +3.55
B = 23.50 x 0.15 x 0.30 - 0.30 x 0.15 x 0.30 x 8.00 = 0.95 m3
Balok (B 2) 15 x 30 cm Elevasi +4.00
3 ke 4 = 4.00 x 0.15 x 0.30 - 0.20 x 0.15 x 0.30 x 1.00 = 0.17
= - 0.15 x 0.15 x 0.30 x 1.00 = (0.01)
10 ke 11 = 3.00 x 0.15 x 0.30 - 0.20 x 0.15 x 0.30 x 1.00 = 0.13
= - 0.15 x 0.15 x 0.30 x 1.00 = (0.01)
E ke F = 3.50 x 0.15 x 0.30 - 0.20 x 0.15 x 0.30 x 1.00 = 0.15
G ke H = 3.00 x 0.15 x 0.30 - 0.20 x 0.15 x 0.30 x 1.00 = 0.13
= 3.50 x 0.15 x 0.30 - 0.20 x 0.15 x 0.30 x 1.00 = 0.15
Tangga Darurat
Balok (B 2) 15 x 30 cm Elevasi +1.00 = 0.70 x 0.15 x 0.30 = 0.03
Balok (B 2) 15 x 30 cm Elevasi +1.45 = 1.20 x 0.15 x 0.30 = 0.05
Balok (B 2) 15 x 30 cm Elevasi +2.85 = 1.20 x 0.15 x 0.30 = 0.05
Balok (B 2) 15 x 30 cm Elevasi +4.00 = 1.27 x 0.15 x 0.30 = 0.06 +
Vol. Total = 1.85 m3 1.85 m3
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip
Ø Ø Koefisien
Ø 13 = 13 x 13 x 0.006165 = 1.04 kg/m
Ø 10 = 10 x 10 x 0.006165 = 0.62 kg/m
Ø8 = 8 x 8 x 0.006165 = 0.39 kg/m
Tulangan Utama Ø 13 Panjang Koefisien Jumlah Besi Jumlah Sisi Jumlah Unit
Balok (B 2) 15 x 30 cm Elevasi +3.55
B = 23.60 x 1.04 x 4.00 x 1.00 x 1.00 = 98.35 Kg
Balok (B 2) 15 x 30 cm Elevasi +4.00
3 ke 4 = 4.10 x 1.04 x 4.00 x 1.00 x 1.00 = 17.09
10 ke 11 = 3.10 x 1.04 x 4.00 x 1.00 x 1.00 = 12.92
E ke F = 3.60 x 1.04 x 4.00 x 1.00 x 1.00 = 15.00
G ke H = 3.10 x 1.04 x 4.00 x 1.00 x 1.00 = 12.92
= 3.60 x 1.04 x 4.00 x 1.00 x 1.00 = 15.00
Tangga Darurat
Balok (B 2) 15 x 30 cm Elevasi +1.00 = 0.80 x 1.04 x 4.00 x 1.00 x 1.00 = 3.33
Balok (B 2) 15 x 30 cm Elevasi +1.45 = 1.30 x 1.04 x 4.00 x 1.00 x 1.00 = 5.42
Balok (B 2) 15 x 30 cm Elevasi +2.85 = 1.30 x 1.04 x 4.00 x 1.00 x 1.00 = 5.42
Balok (B 2) 15 x 30 cm Elevasi +4.00 = 1.37 x 1.04 x 4.00 x 1.00 x 1.00 = 5.71
Tulangan Utama Ø 10
Balok (B 2) 15 x 30 cm Elevasi +3.55
B = 23.60 x 0.62 x 2.00 x 1.00 x 1.00 = 29.10
Balok (B 2) 15 x 30 cm Elevasi +4.00
3 ke 4 = 4.10 x 0.62 x 2.00 x 1.00 x 1.00 = 5.06
10 ke 11 = 3.10 x 0.62 x 2.00 x 1.00 x 1.00 = 3.82
E ke F = 3.60 x 0.62 x 2.00 x 1.00 x 1.00 = 4.44
G ke H = 3.10 x 0.62 x 2.00 x 1.00 x 1.00 = 3.82
= 3.60 x 0.62 x 2.00 x 1.00 x 1.00 = 4.44
Tangga Darurat
Balok (B 2) 15 x 30 cm Elevasi +1.00 = 0.80 x 0.62 x 2.00 x 1.00 x 1.00 = 0.99
Balok (B 2) 15 x 30 cm Elevasi +1.45 = 1.30 x 0.62 x 2.00 x 1.00 x 1.00 = 1.60
Balok (B 2) 15 x 30 cm Elevasi +2.85 = 1.30 x 0.62 x 2.00 x 1.00 x 1.00 = 1.60
Balok (B 2) 15 x 30 cm Elevasi +4.00 = 1.37 x 0.62 x 2.00 x 1.00 x 1.00 = 1.69
Tulangan Sengkang Ø 8
Balok (B 2) 15 x 30 cm Elevasi +3.55
B = 0.80 x 0.39 x 141.00 x 1.00 x 1.00 = 44.51
Balok (B 2) 15 x 30 cm Elevasi +4.00
3 ke 4 = 0.80 x 0.39 x 26.00 x 1.00 x 1.00 = 8.21
10 ke 11 = 0.80 x 0.39 x 19.00 x 1.00 x 1.00 = 6.00
E ke F = 0.80 x 0.39 x 23.00 x 1.00 x 1.00 = 7.26
G ke H = 0.80 x 0.39 x 19.00 x 1.00 x 1.00 = 6.00
= 0.80 x 0.39 x 23.00 x 1.00 x 1.00 = 7.26
Tangga Darurat
Balok (B 2) 15 x 30 cm Elevasi +1.00 = 0.80 x 0.39 x 5.00 x 1.00 x 1.00 = 1.58
Balok (B 2) 15 x 30 cm Elevasi +1.45 = 0.80 x 0.39 x 9.00 x 1.00 x 1.00 = 2.84
Balok (B 2) 15 x 30 cm Elevasi +2.85 = 0.80 x 0.39 x 9.00 x 1.00 x 1.00 = 2.84
Balok (B 2) 15 x 30 cm Elevasi +4.00 = 0.80 x 0.39 x 9.00 x 1.00 x 1.00 = 2.84 +
Vol. Total = 337.05 Kg 337.05 Kg
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali)
Panjang Lebar Jumlah Sisi Jumlah Unit
Balok (B 2) 15 x 30 cm Elevasi +3.55
B = 21.10 x 0.49 x 1.00 x 1.00 = 10.34 m2
Balok (B 2) 15 x 30 cm Elevasi +4.00
3 ke 4 = 3.80 x 0.49 x 1.00 x 1.00 = 1.86
= 0.15 x 0.15 x 1.00 x 1.00 = (0.02)
10 ke 11 = 2.80 x 0.49 x 1.00 x 1.00 = 1.37
= 0.15 x 0.15 x 1.00 x 1.00 = (0.02)
E ke F = 3.30 x 0.49 x 1.00 x 1.00 = 1.62
G ke H = 2.80 x 0.49 x 1.00 x 1.00 = 1.37
= 3.30 x 0.49 x 1.00 x 1.00 = 1.62
Tangga Darurat
Balok (B 2) 15 x 30 cm Elevasi +1.00 = 0.70 x 0.49 x 1.00 x 1.00 = 0.34
Balok (B 2) 15 x 30 cm Elevasi +1.45 = 1.20 x 0.49 x 1.00 x 1.00 = 0.59
Balok (B 2) 15 x 30 cm Elevasi +2.85 = 1.20 x 0.49 x 1.00 x 1.00 = 0.59
Balok (B 2) 15 x 30 cm Elevasi +4.00 = 1.27 x 0.49 x 1.00 x 1.00 = 0.62 +
Vol. Total = 20.28 m2
Dipakai 2 kali = 10.14 m2 10.14 m2
12 Balok Gantung (BG) 15 x 25 cm
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225)
Panjang Lebar Tinggi Panjang Lebar Tinggi Jumlah Silangan
Balok Gantung (BG) 15 x 25 cm Elevasi +2.70
B = 2.50 x 0.15 x 0.25 - 0.30 x 0.15 x 0.25 x 1.00 = 0.08 m3
= 2.50 x 0.15 x 0.25 - 0.30 x 0.15 x 0.25 x 1.00 = 0.08
Balok Gantung (BG) 15 x 25 cm Elevasi +2.85
B = 7.00 x 0.15 x 0.25 - 0.30 x 0.15 x 0.25 x 3.00 = 0.23
= 14.00 x 0.15 x 0.25 - 0.30 x 0.15 x 0.25 x 5.00 = 0.47
= 12.00 x 0.15 x 0.25 - 0.30 x 0.15 x 0.25 x 4.00 = 0.40
Balok Gantung (BG) 15 x 25 cm Elevasi +3.35
F = 8.00 x 0.15 x 0.25 - 0.30 x 0.15 x 0.25 x 2.50 = 0.27
= - 0.15 x 0.15 x 0.25 x 0.50 = (0.00)
Balok Gantung (BG) 15 x 25 cm Elevasi +4.00
C = 2.50 x 0.15 x 0.25 - 0.15 x 0.15 x 0.25 x 1.00 = 0.09
D = 5.50 x 0.15 x 0.25 - 0.15 x 0.15 x 0.25 x 2.00 = 0.19
E = 2.50 x 0.15 x 0.25 - 0.15 x 0.15 x 0.25 x 1.00 = 0.09 +
Vol. Total = 1.91 m3 1.91 m3
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip
Ø Ø Koefisien
Ø 12 = 12 x 12 x 0.006165 = 0.89 kg/m
Ø 10 = 10 x 10 x 0.006165 = 0.62 kg/m
Ø8 = 8 x 8 x 0.006165 = 0.39 kg/m
Tulangan Utama Ø 12 Panjang Koefisien Jumlah Besi Jumlah Sisi Jumlah Unit
Balok Gantung (BG) 15 x 25 cm Elevasi +2.70
B = 2.60 x 0.89 x 4.00 x 1.00 x 1.00 = 9.23 Kg
= 2.60 x 0.89 x 4.00 x 1.00 x 1.00 = 9.23
Balok Gantung (BG) 15 x 25 cm Elevasi +2.85
B = 7.10 x 0.89 x 4.00 x 1.00 x 1.00 = 25.21
= 14.10 x 0.89 x 4.00 x 1.00 x 1.00 = 50.07
= 12.10 x 0.89 x 4.00 x 1.00 x 1.00 = 42.97
Balok Gantung (BG) 15 x 25 cm Elevasi +3.35
F = 8.10 x 0.89 x 4.00 x 1.00 x 1.00 = 28.76
Balok Gantung (BG) 15 x 25 cm Elevasi +4.00
C = 2.60 x 0.89 x 4.00 x 1.00 x 1.00 = 9.23
D = 5.60 x 0.89 x 4.00 x 1.00 x 1.00 = 19.89
E = 2.60 x 0.89 x 4.00 x 1.00 x 1.00 = 9.23
Tulangan Utama Ø 10
Balok Gantung (BG) 15 x 25 cm Elevasi +2.70
B = 2.60 x 0.62 x 2.00 x 1.00 x 1.00 = 3.21
= 2.60 x 0.62 x 2.00 x 1.00 x 1.00 = 3.21
Balok Gantung (BG) 15 x 25 cm Elevasi +2.85
B = 7.10 x 0.62 x 2.00 x 1.00 x 1.00 = 8.75
= 14.10 x 0.62 x 2.00 x 1.00 x 1.00 = 17.39
= 12.10 x 0.62 x 2.00 x 1.00 x 1.00 = 14.92
Balok Gantung (BG) 15 x 25 cm Elevasi +3.35
F = 8.10 x 0.62 x 2.00 x 1.00 x 1.00 = 9.99
Balok Gantung (BG) 15 x 25 cm Elevasi +4.00
C = 2.60 x 0.62 x 2.00 x 1.00 x 1.00 = 3.21
D = 5.60 x 0.62 x 2.00 x 1.00 x 1.00 = 6.90
E = 2.60 x 0.62 x 2.00 x 1.00 x 1.00 = 3.21
Tulangan Sengkang Ø 8
Balok Gantung (BG) 15 x 25 cm Elevasi +2.70
B = 0.70 x 0.39 x 15.00 x 1.00 x 1.00 = 4.14
= 0.70 x 0.39 x 15.00 x 1.00 x 1.00 = 4.14
Balok Gantung (BG) 15 x 25 cm Elevasi +2.85
B = 0.70 x 0.39 x 41.00 x 1.00 x 1.00 = 11.32
= 0.70 x 0.39 x 84.00 x 1.00 x 1.00 = 23.20
= 0.70 x 0.39 x 73.00 x 1.00 x 1.00 = 20.16
Balok Gantung (BG) 15 x 25 cm Elevasi +3.35
F = 0.70 x 0.39 x 49.00 x 1.00 x 1.00 = 13.53
Balok Gantung (BG) 15 x 25 cm Elevasi +4.00
C = 0.70 x 0.39 x 16.00 x 1.00 x 1.00 = 4.42
D = 0.70 x 0.39 x 35.00 x 1.00 x 1.00 = 9.67
E = 0.70 x 0.39 x 16.00 x 1.00 x 1.00 = 4.42 +
Vol. Total = 369.61 Kg 369.61 Kg
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali)
Panjang Lebar Jumlah Sisi Jumlah Unit
Balok Gantung (BG) 15 x 25 cm Elevasi +2.70
B = 2.20 x 0.65 x 1.00 x 1.00 = 1.43 m2
= 2.20 x 0.65 x 1.00 x 1.00 = 1.43
Balok Gantung (BG) 15 x 25 cm Elevasi +2.85
B = 6.10 x 0.65 x 1.00 x 1.00 = 3.97
= 12.50 x 0.65 x 1.00 x 1.00 = 8.13
= 10.80 x 0.65 x 1.00 x 1.00 = 7.02
Balok Gantung (BG) 15 x 25 cm Elevasi +3.35
F = 7.25 x 0.65 x 1.00 x 1.00 = 4.71
= 0.15 x 0.25 x 1.00 x 1.00 = (0.04)
Balok Gantung (BG) 15 x 25 cm Elevasi +4.00
C = 2.35 x 0.65 x 1.00 x 1.00 = 1.53
D = 5.20 x 0.65 x 1.00 x 1.00 = 3.38
E = 2.35 x 0.65 x 1.00 x 1.00 = 1.53 +
Vol. Total = 33.08 m2
Dipakai 2 kali = 16.54 m2 16.54 m2
13 Balok Latei 12 x 20 cm
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225)
Panjang Lebar Tinggi Panjang Lebar Tinggi Jumlah Silangan
Balok Latei 12 x 20 cm Elevasi +2.00
2 = 1.50 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 1.00 = 0.03 m3
Balok Latei 12 x 20 cm Elevasi +2.20
C ke D = 2.00 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 1.00 = 0.04
Balok Latei 12 x 20 cm Elevasi +2.75
3 ke 4 = 2.00 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 1.00 = 0.04
10 ke 11 = 3.00 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 2.00 = 0.06
D = 2.00 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 1.00 = 0.04
E = 2.00 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 1.00 = 0.04
G = 1.50 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 1.00 = 0.03
Balok Latei 12 x 20 cm Elevasi +2.80
10 = 3.00 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 2.00 = 0.06
Balok Latei 12 x 20 cm Elevasi +3.30
1 = 7.50 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 4.00 = 0.17
2 = 6.00 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 2.00 = 0.14
= 1.50 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 1.00 = 0.03
2 ke 3 = 1.50 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 1.00 = 0.03
3 = 2.25 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 1.00 = 0.05
= 3.00 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 1.00 = 0.07
= 4.50 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 2.00 = 0.10
3 ke 4 = 3.00 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 1.00 = 0.07
= 3.00 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 1.00 = 0.07
5 = 7.50 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 4.00 = 0.17
6 = 2.25 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 1.00 = 0.05
= 2.50 x 0.12 x 0.20 - 0.30 x 0.12 x 0.20 x 1.00 = 0.05
8 = 3.00 x 0.12 x 0.20 - 0.30 x 0.12 x 0.20 x 1.00 = 0.06
9 = 3.00 x 0.12 x 0.20 - 0.30 x 0.12 x 0.20 x 1.00 = 0.06
10 = 2.50 x 0.12 x 0.20 - 0.30 x 0.12 x 0.20 x 1.00 = 0.05
= 2.50 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 1.00 = 0.06
11 = 6.00 x 0.12 x 0.20 - 0.30 x 0.12 x 0.20 x 3.00 = 0.12
= 4.00 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 2.00 = 0.09
11 ke 12 = 2.50 x 0.12 x 0.20 - 0.30 x 0.12 x 0.20 x 1.00 = 0.05
14 = 5.25 x 0.12 x 0.20 - 0.30 x 0.12 x 0.20 x 2.00 = 0.11
C = 2.00 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 1.00 = 0.04
= 2.00 x 0.12 x 0.20 - 0.30 x 0.12 x 0.20 x 1.00 = 0.04
= 1.75 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 1.00 = 0.04
= 8.50 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 3.00 = 0.19
C ke D = 2.00 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 1.00 = 0.04
D = 3.00 x 0.12 x 0.20 - 0.30 x 0.12 x 0.20 x 1.00 = 0.06
= 3.00 x 0.12 x 0.20 - 0.30 x 0.12 x 0.20 x 1.00 = 0.06
= 12.00 x 0.12 x 0.20 - 0.30 x 0.12 x 0.20 x 4.00 = 0.26
E = 9.00 x 0.12 x 0.20 - 0.30 x 0.12 x 0.20 x 3.00 = 0.19
F = 2.50 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 1.00 = 0.06
G = 4.00 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 1.00 = 0.09
= 9.00 x 0.12 x 0.20 - 0.30 x 0.12 x 0.20 x 4.00 = 0.19
H = 1.50 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 2.00 = 0.03
= 17.75 x 0.12 x 0.20 - 0.30 x 0.12 x 0.20 x 6.00 = 0.38 +
Vol. Total = 3.67 m3 3.67 m3
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip
Ø Ø Koefisien
Ø 12 = 12 x 12 x 0.006165 = 0.89 kg/m
Ø8 = 8 x 8 x 0.006165 = 0.39 kg/m
Tulangan Utama Ø 12 Panjang Koefisien Jumlah Besi Jumlah Sisi Jumlah Unit
Balok Latei 12 x 20 cm Elevasi +2.00
2 = 1.60 x 0.89 x 4.00 x 1.00 x 1.00 = 5.68 Kg
Balok Latei 12 x 20 cm Elevasi +2.20
C ke D = 2.10 x 0.89 x 4.00 x 1.00 x 1.00 = 7.46
Balok Latei 12 x 20 cm Elevasi +2.75
3 ke 4 = 2.10 x 0.89 x 4.00 x 1.00 x 1.00 = 7.46
10 ke 11 = 3.10 x 0.89 x 4.00 x 1.00 x 1.00 = 11.01
D = 2.10 x 0.89 x 4.00 x 1.00 x 1.00 = 7.46
E = 2.10 x 0.89 x 4.00 x 1.00 x 1.00 = 7.46
G = 1.60 x 0.89 x 4.00 x 1.00 x 1.00 = 5.68
Balok Latei 12 x 20 cm Elevasi +2.80
10 = 3.10 x 0.89 x 4.00 x 1.00 x 1.00 = 11.01
Balok Latei 12 x 20 cm Elevasi +3.30
1 = 7.60 x 0.89 x 4.00 x 1.00 x 1.00 = 26.99
2 = 6.10 x 0.89 x 4.00 x 1.00 x 1.00 = 21.66
= 1.60 x 0.89 x 4.00 x 1.00 x 1.00 = 5.68
2 ke 3 = 1.60 x 0.89 x 4.00 x 1.00 x 1.00 = 5.68
3 = 2.35 x 0.89 x 4.00 x 1.00 x 1.00 = 8.34
= 3.10 x 0.89 x 4.00 x 1.00 x 1.00 = 11.01
= 4.60 x 0.89 x 4.00 x 1.00 x 1.00 = 16.33
3 ke 4 = 3.10 x 0.89 x 4.00 x 1.00 x 1.00 = 11.01
= 3.10 x 0.89 x 4.00 x 1.00 x 1.00 = 11.01
5 = 7.60 x 0.89 x 4.00 x 1.00 x 1.00 = 26.99
6 = 2.35 x 0.89 x 4.00 x 1.00 x 1.00 = 8.34
= 2.60 x 0.89 x 4.00 x 1.00 x 1.00 = 9.23
8 = 3.10 x 0.89 x 4.00 x 1.00 x 1.00 = 11.01
9 = 3.10 x 0.89 x 4.00 x 1.00 x 1.00 = 11.01
10 = 2.60 x 0.89 x 4.00 x 1.00 x 1.00 = 9.23
= 2.60 x 0.89 x 4.00 x 1.00 x 1.00 = 9.23
11 = 6.10 x 0.89 x 4.00 x 1.00 x 1.00 = 21.66
= 4.10 x 0.89 x 4.00 x 1.00 x 1.00 = 14.56
11 ke 12 = 2.60 x 0.89 x 4.00 x 1.00 x 1.00 = 9.23
14 = 5.35 x 0.89 x 4.00 x 1.00 x 1.00 = 19.00
C = 2.10 x 0.89 x 4.00 x 1.00 x 1.00 = 7.46
= 2.10 x 0.89 x 4.00 x 1.00 x 1.00 = 7.46
= 1.85 x 0.89 x 4.00 x 1.00 x 1.00 = 6.57
= 8.60 x 0.89 x 4.00 x 1.00 x 1.00 = 30.54
C ke D = 2.10 x 0.89 x 4.00 x 1.00 x 1.00 = 7.46
D = 3.10 x 0.89 x 4.00 x 1.00 x 1.00 = 11.01
= 3.10 x 0.89 x 4.00 x 1.00 x 1.00 = 11.01
= 12.10 x 0.89 x 4.00 x 1.00 x 1.00 = 42.97
E = 9.10 x 0.89 x 4.00 x 1.00 x 1.00 = 32.31
F = 2.60 x 0.89 x 4.00 x 1.00 x 1.00 = 9.23
G = 4.10 x 0.89 x 4.00 x 1.00 x 1.00 = 14.56
= 9.10 x 0.89 x 4.00 x 1.00 x 1.00 = 32.31
H = 1.60 x 0.89 x 4.00 x 1.00 x 1.00 = 5.68
= 17.85 x 0.89 x 4.00 x 1.00 x 1.00 = 63.39
Tulangan Sengkang Ø 8
Balok Latei 12 x 20 cm Elevasi +2.00
2 = 0.54 x 0.39 x 10.00 x 1.00 x 1.00 = 2.13
Balok Latei 12 x 20 cm Elevasi +2.20
C ke D = 0.54 x 0.39 x 13.00 x 1.00 x 1.00 = 2.77
Balok Latei 12 x 20 cm Elevasi +2.75
3 ke 4 = 0.54 x 0.39 x 13.00 x 1.00 x 1.00 = 2.77
10 ke 11 = 0.54 x 0.39 x 19.00 x 1.00 x 1.00 = 4.05
D = 0.54 x 0.39 x 13.00 x 1.00 x 1.00 = 2.77
E = 0.54 x 0.39 x 13.00 x 1.00 x 1.00 = 2.77
G = 0.54 x 0.39 x 10.00 x 1.00 x 1.00 = 2.13
Balok Latei 12 x 20 cm Elevasi +2.80
10 = 0.54 x 0.39 x 19.00 x 1.00 x 1.00 = 4.05
Balok Latei 12 x 20 cm Elevasi +3.30
1 = 0.54 x 0.39 x 47.00 x 1.00 x 1.00 = 10.01
2 = 0.54 x 0.39 x 39.00 x 1.00 x 1.00 = 8.31
= 0.54 x 0.39 x 10.00 x 1.00 x 1.00 = 2.13
2 ke 3 = 0.54 x 0.39 x 10.00 x 1.00 x 1.00 = 2.13
3 = 0.54 x 0.39 x 15.00 x 1.00 x 1.00 = 3.20
= 0.54 x 0.39 x 20.00 x 1.00 x 1.00 = 4.26
= 0.54 x 0.39 x 29.00 x 1.00 x 1.00 = 6.18
3 ke 4 = 0.54 x 0.39 x 20.00 x 1.00 x 1.00 = 4.26
= 0.54 x 0.39 x 20.00 x 1.00 x 1.00 = 4.26
5 = 0.54 x 0.39 x 47.00 x 1.00 x 1.00 = 10.01
6 = 0.54 x 0.39 x 15.00 x 1.00 x 1.00 = 3.20
= 0.54 x 0.39 x 15.00 x 1.00 x 1.00 = 3.20
8 = 0.54 x 0.39 x 19.00 x 1.00 x 1.00 = 4.05
9 = 0.54 x 0.39 x 19.00 x 1.00 x 1.00 = 4.05
10 = 0.54 x 0.39 x 15.00 x 1.00 x 1.00 = 3.20
= 0.54 x 0.39 x 16.00 x 1.00 x 1.00 = 3.41
11 = 0.54 x 0.39 x 35.00 x 1.00 x 1.00 = 7.46
= 0.54 x 0.39 x 25.00 x 1.00 x 1.00 = 5.33
11 ke 12 = 0.54 x 0.39 x 15.00 x 1.00 x 1.00 = 3.20
14 = 0.54 x 0.39 x 32.00 x 1.00 x 1.00 = 6.82
C = 0.54 x 0.39 x 13.00 x 1.00 x 1.00 = 2.77
= 0.54 x 0.39 x 12.00 x 1.00 x 1.00 = 2.56
= 0.54 x 0.39 x 11.00 x 1.00 x 1.00 = 2.34
= 0.54 x 0.39 x 54.00 x 1.00 x 1.00 = 11.51
C ke D = 0.54 x 0.39 x 13.00 x 1.00 x 1.00 = 2.77
D = 0.54 x 0.39 x 19.00 x 1.00 x 1.00 = 4.05
= 0.54 x 0.39 x 19.00 x 1.00 x 1.00 = 4.05
= 0.54 x 0.39 x 73.00 x 1.00 x 1.00 = 15.55
E = 0.54 x 0.39 x 55.00 x 1.00 x 1.00 = 11.72
F = 0.54 x 0.39 x 16.00 x 1.00 x 1.00 = 3.41
G = 0.54 x 0.39 x 26.00 x 1.00 x 1.00 = 5.54
= 0.54 x 0.39 x 53.00 x 1.00 x 1.00 = 11.29
H = 0.54 x 0.39 x 9.00 x 1.00 x 1.00 = 1.92
= 0.54 x 0.39 x 107.00 x 1.00 x 1.00 = 22.80 +
Vol. Total = 836.73 Kg 836.73 Kg
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali)
Panjang Lebar Jumlah Sisi Jumlah Unit
Balok Latei 12 x 20 cm Elevasi +2.00
2 = 1.35 x 0.20 x 2.00 x 1.00 = 0.54 m2
Balok Latei 12 x 20 cm Elevasi +2.20
C ke D = 1.85 x 0.20 x 2.00 x 1.00 = 0.74
Balok Latei 12 x 20 cm Elevasi +2.75
3 ke 4 = 1.85 x 0.20 x 2.00 x 1.00 = 0.74
10 ke 11 = 2.70 x 0.20 x 2.00 x 1.00 = 1.08
D = 1.85 x 0.20 x 2.00 x 1.00 = 0.74
E = 1.85 x 0.20 x 2.00 x 1.00 = 0.74
G = 1.35 x 0.20 x 2.00 x 1.00 = 0.54
Balok Latei 12 x 20 cm Elevasi +2.80
10 = 2.70 x 0.20 x 2.00 x 1.00 = 1.08
Balok Latei 12 x 20 cm Elevasi +3.30
1 = 6.90 x 0.20 x 2.00 x 1.00 = 2.76
2 = 5.70 x 0.20 x 2.00 x 1.00 = 2.28
= 1.35 x 0.20 x 2.00 x 1.00 = 0.54
2 ke 3 = 1.35 x 0.20 x 2.00 x 1.00 = 0.54
3 = 2.10 x 0.20 x 2.00 x 1.00 = 0.84
= 2.85 x 0.20 x 2.00 x 1.00 = 1.14
= 4.20 x 0.20 x 2.00 x 1.00 = 1.68
3 ke 4 = 2.85 x 0.20 x 2.00 x 1.00 = 1.14
= 2.85 x 0.20 x 2.00 x 1.00 = 1.14
5 = 6.90 x 0.20 x 2.00 x 1.00 = 2.76
6 = 2.10 x 0.20 x 2.00 x 1.00 = 0.84
= 2.20 x 0.20 x 2.00 x 1.00 = 0.88
8 = 2.70 x 0.20 x 2.00 x 1.00 = 1.08
9 = 2.70 x 0.20 x 2.00 x 1.00 = 1.08
10 = 2.20 x 0.20 x 2.00 x 1.00 = 0.88
= 2.35 x 0.20 x 2.00 x 1.00 = 0.94
11 = 5.10 x 0.20 x 2.00 x 1.00 = 2.04
= 3.70 x 0.20 x 2.00 x 1.00 = 1.48
11 ke 12 = 2.20 x 0.20 x 2.00 x 1.00 = 0.88
14 = 4.65 x 0.20 x 2.00 x 1.00 = 1.86
C = 1.85 x 0.20 x 2.00 x 1.00 = 0.74
= 1.70 x 0.20 x 2.00 x 1.00 = 0.68
= 1.60 x 0.20 x 2.00 x 1.00 = 0.64
= 8.05 x 0.20 x 2.00 x 1.00 = 3.22
C ke D = 1.85 x 0.20 x 2.00 x 1.00 = 0.74
D = 2.70 x 0.20 x 2.00 x 1.00 = 1.08
= 2.70 x 0.20 x 2.00 x 1.00 = 1.08
= 10.80 x 0.20 x 2.00 x 1.00 = 4.32
E = 8.10 x 0.20 x 2.00 x 1.00 = 3.24
F = 2.35 x 0.20 x 2.00 x 1.00 = 0.94
G = 3.85 x 0.20 x 2.00 x 1.00 = 1.54
= 7.80 x 0.20 x 2.00 x 1.00 = 3.12
H = 1.20 x 0.20 x 2.00 x 1.00 = 0.48
= 15.95 x 0.20 x 2.00 x 1.00 = 6.38 +
Vol. Total = 61.18 m2
Dipakai 2 kali = 30.59 m2 30.59 m2
14 Plat Leuvel
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225)
Panjang Lebar Tinggi Jumlah Sisi Jumlah Unit
Plat Leuvel 1 Elevasi +3.30
Memanjang = 2.35 x 0.50 x 0.08 x 1.00 x 1.00 = 0.09 m3
Melintang = 0.37 x 0.50 x 0.08 x 2.00 x 1.00 = 0.03
Plat Leuvel 2 Elevasi +3.30
Memanjang = 1.05 x 0.50 x 0.08 x 1.00 x 4.00 = 0.17
Melintang = 0.37 x 0.50 x 0.08 x 2.00 x 4.00 = 0.12
Plat Leuvel 3 Elevasi +3.30
Memanjang = 1.70 x 0.50 x 0.08 x 1.00 x 8.00 = 0.54
Melintang = 0.37 x 0.50 x 0.08 x 2.00 x 8.00 = 0.24
Plat Leuvel 4 Elevasi +3.30
Memanjang = 7.85 x 0.50 x 0.08 x 1.00 x 1.00 = 0.31
Melintang = 0.37 x 0.50 x 0.08 x 2.00 x 1.00 = 0.03
Plat Leuvel 5 Elevasi +3.30
Memanjang = 6.70 x 0.15 x 0.10 x 1.00 x 1.00 = 0.10
= 13.70 x 0.15 x 0.10 x 1.00 x 1.00 = 0.21
= 11.70 x 0.15 x 0.10 x 1.00 x 1.00 = 0.18 +
Vol. Total = 2.02 m3 2.02 m3
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip
Ø Ø Koefisien
Ø 12 = 12 x 12 x 0.006165 = 0.89 kg/m
Tulangan Utama Ø 12 Panjang Koefisien Jumlah Besi Jumlah Sisi Jumlah Unit
Plat Leuvel 1 Elevasi +3.30
Memanjang = 3.20 x 0.89 x 6.00 x 1.00 x 1.00 = 17.04 Kg
Melintang = 0.86 x 0.89 x 33.00 x 1.00 x 1.00 = 25.19
Plat Leuvel 2 Elevasi +3.30
Memanjang = 1.90 x 0.89 x 6.00 x 1.00 x 4.00 = 40.48
Melintang = 0.86 x 0.89 x 20.00 x 1.00 x 4.00 = 61.08
Plat Leuvel 3 Elevasi +3.30
Memanjang = 2.55 x 0.89 x 6.00 x 1.00 x 8.00 = 108.66
Melintang = 0.86 x 0.89 x 26.00 x 1.00 x 8.00 = 158.80
Plat Leuvel 4 Elevasi +3.30
Memanjang = 8.59 x 0.89 x 6.00 x 1.00 x 1.00 = 45.76
= 0.50 x 0.89 x 6.00 x 1.00 x 1.00 = 2.66
Melintang = 0.86 x 0.89 x 79.00 x 1.00 x 1.00 = 60.31
= 0.86 x 0.89 x 4.00 x 1.00 x 1.00 = 3.05
Plat Leuvel 5 Elevasi +3.30
Memanjang = 6.80 x 0.89 x 3.00 x 1.00 x 1.00 = 18.11
= 13.80 x 0.89 x 3.00 x 1.00 x 1.00 = 36.75
= 11.80 x 0.89 x 3.00 x 1.00 x 1.00 = 31.43
Melintang = 0.63 x 0.89 x 68.00 x 1.00 x 1.00 = 38.03
= 0.63 x 0.89 x 138.00 x 1.00 x 1.00 = 77.18
= 0.63 x 0.89 x 118.00 x 1.00 x 1.00 = 66.00 +
Vol. Total = 790.55 Kg 790.55 Kg
- Pemasangan 1 m2 Bekisting untuk Plat lantai Beton Bangunan Gedung
Panjang Lebar Jumlah Sisi Jumlah Unit
Plat Leuvel 1 Elevasi +3.30
Memanjang = 2.19 x 0.50 x 1.00 x 1.00 = 1.10 m2
= 2.19 x 0.08 x 1.00 x 1.00 = 0.18
Melintang = 0.90 x 0.50 x 2.00 x 1.00 = 0.90
= 0.15 x 0.08 x 2.00 x 1.00 = 0.02
Plat Leuvel 2 Elevasi +3.30
Memanjang = 0.89 x 0.50 x 1.00 x 4.00 = 1.78
= 0.89 x 0.08 x 1.00 x 4.00 = 0.28
Melintang = 0.90 x 0.50 x 2.00 x 4.00 = 3.60
= 0.15 x 0.08 x 2.00 x 4.00 = 0.10
Plat Leuvel 3 Elevasi +3.30
Memanjang = 1.54 x 0.50 x 1.00 x 8.00 = 6.16
= 1.54 x 0.08 x 1.00 x 8.00 = 0.99
Melintang = 0.90 x 0.50 x 2.00 x 8.00 = 7.20
= 0.15 x 0.08 x 2.00 x 8.00 = 0.19
Plat Leuvel 4 Elevasi +3.30
Memanjang = 7.68 x 0.50 x 1.00 x 1.00 = 3.84
= 7.68 x 0.08 x 1.00 x 1.00 = 0.61
Melintang = 0.82 x 0.50 x 2.00 x 1.00 = 0.82
= 0.45 x 0.08 x 2.00 x 1.00 = 0.07
Plat Leuvel 5 Elevasi +3.30
Memanjang = 6.70 x 0.15 x 1.00 x 1.00 = 1.01
= 7.00 x 0.08 x 1.00 x 1.00 = 0.56
= 13.70 x 0.15 x 1.00 x 1.00 = 2.05
= 14.00 x 0.08 x 1.00 x 1.00 = 1.12
= 11.70 x 0.15 x 1.00 x 1.00 = 1.76
= 12.00 x 0.08 x 1.00 x 1.00 = 0.96 +
Vol. Total = 35.29 m2
Dipakai 2 kali = 17.65 m2 17.65 m2
15 Ring Balk 15 x 20 cm
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225)
Panjang Lebar Tinggi Panjang Lebar Tinggi Jumlah Silangan
1 = 7.50 x 0.15 x 0.20 - 0.15 x 0.15 x 0.20 x 4.00 = 0.21 m3
2 = 9.00 x 0.15 x 0.20 - 0.15 x 0.15 x 0.20 x 4.00 = 0.25
2 ke 3 = 3.00 x 0.15 x 0.20 - 0.15 x 0.15 x 0.20 x 2.00 = 0.08
3 = 13.50 x 0.15 x 0.20 - 0.15 x 0.15 x 0.20 x 5.00 = 0.38
3 ke 4 = 3.00 x 0.15 x 0.20 - 0.15 x 0.15 x 0.20 x 1.00 = 0.09
= 3.00 x 0.15 x 0.20 - 0.15 x 0.15 x 0.20 x 1.00 = 0.09
4 ke 5 = 3.00 x 0.15 x 0.20 - 0.15 x 0.15 x 0.20 x 2.00 = 0.08
5 = 9.00 x 0.15 x 0.20 - 0.15 x 0.15 x 0.20 x 5.00 = 0.25
B = 14.50 x 0.15 x 0.20 - 0.30 x 0.15 x 0.20 x 6.00 = 0.38
C = 7.00 x 0.15 x 0.20 - 0.15 x 0.15 x 0.20 x 3.00 = 0.20
= 5.00 x 0.15 x 0.20 - 0.15 x 0.15 x 0.20 x 2.00 = 0.14
C ke D = 4.00 x 0.15 x 0.20 - 0.15 x 0.15 x 0.20 x 2.00 = 0.11
= 2.00 x 0.15 x 0.20 - 0.15 x 0.15 x 0.20 x 1.00 = 0.06
D = 4.00 x 0.15 x 0.20 - 0.15 x 0.15 x 0.20 x 2.00 = 0.11
= 3.00 x 0.15 x 0.20 - 0.15 x 0.15 x 0.20 x 2.00 = 0.08
D ke E = 2.00 x 0.15 x 0.20 - 0.15 x 0.15 x 0.20 x 1.00 = 0.06
E = 3.00 x 0.15 x 0.20 - 0.15 x 0.15 x 0.20 x 2.00 = 0.08
F = 5.00 x 0.15 x 0.20 - 0.15 x 0.15 x 0.20 x 2.00 = 0.14 +
Vol. Total = 2.78 m3 2.78 m3
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip
Ø Ø Koefisien
Ø 12 = 12 x 12 x 0.006165 = 0.89 kg/m
Ø 10 = 10 x 10 x 0.006165 = 0.62 kg/m
Ø8 = 8 x 8 x 0.006165 = 0.39 kg/m
Tulangan Utama Ø 12 Panjang Koefisien Jumlah Besi Jumlah Sisi Jumlah Unit
1 = 7.60 x 0.89 x 4.00 x 1.00 x 1.00 = 26.99 Kg
2 = 9.10 x 0.89 x 4.00 x 1.00 x 1.00 = 32.31
2 ke 3 = 3.10 x 0.89 x 4.00 x 1.00 x 1.00 = 11.01
3 = 13.60 x 0.89 x 4.00 x 1.00 x 1.00 = 48.29
3 ke 4 = 3.10 x 0.89 x 4.00 x 1.00 x 1.00 = 11.01
= 3.10 x 0.89 x 4.00 x 1.00 x 1.00 = 11.01
4 ke 5 = 3.10 x 0.89 x 4.00 x 1.00 x 1.00 = 11.01
5 = 9.10 x 0.89 x 4.00 x 1.00 x 1.00 = 32.31
B = 14.60 x 0.89 x 4.00 x 1.00 x 1.00 = 51.85
C = 7.10 x 0.89 x 4.00 x 1.00 x 1.00 = 25.21
= 5.10 x 0.89 x 4.00 x 1.00 x 1.00 = 18.11
C ke D = 4.10 x 0.89 x 4.00 x 1.00 x 1.00 = 14.56
= 2.10 x 0.89 x 4.00 x 1.00 x 1.00 = 7.46
D = 4.10 x 0.89 x 4.00 x 1.00 x 1.00 = 14.56
= 3.10 x 0.89 x 4.00 x 1.00 x 1.00 = 11.01
D ke E = 2.10 x 0.89 x 4.00 x 1.00 x 1.00 = 7.46
E = 3.10 x 0.89 x 4.00 x 1.00 x 1.00 = 11.01
F = 5.10 x 0.89 x 4.00 x 1.00 x 1.00 = 18.11
Tulangan Utama Ø 10
1 = 7.60 x 0.62 x 2.00 x 1.00 x 1.00 = 9.37
2 = 9.10 x 0.62 x 2.00 x 1.00 x 1.00 = 11.22
2 ke 3 = 3.10 x 0.62 x 2.00 x 1.00 x 1.00 = 3.82
3 = 13.60 x 0.62 x 2.00 x 1.00 x 1.00 = 16.77
3 ke 4 = 3.10 x 0.62 x 2.00 x 1.00 x 1.00 = 3.82
= 3.10 x 0.62 x 2.00 x 1.00 x 1.00 = 3.82
4 ke 5 = 3.10 x 0.62 x 2.00 x 1.00 x 1.00 = 3.82
5 = 9.10 x 0.62 x 2.00 x 1.00 x 1.00 = 11.22
B = 14.60 x 0.62 x 2.00 x 1.00 x 1.00 = 18.00
C = 7.10 x 0.62 x 2.00 x 1.00 x 1.00 = 8.75
= 5.10 x 0.62 x 2.00 x 1.00 x 1.00 = 6.29
C ke D = 4.10 x 0.62 x 2.00 x 1.00 x 1.00 = 5.06
= 2.10 x 0.62 x 2.00 x 1.00 x 1.00 = 2.59
D = 4.10 x 0.62 x 2.00 x 1.00 x 1.00 = 5.06
= 3.10 x 0.62 x 2.00 x 1.00 x 1.00 = 3.82
D ke E = 2.10 x 0.62 x 2.00 x 1.00 x 1.00 = 2.59
E = 3.10 x 0.62 x 2.00 x 1.00 x 1.00 = 3.82
F = 5.10 x 0.62 x 2.00 x 1.00 x 1.00 = 6.29
Tulangan Sengkang Ø 8
1 = 0.60 x 0.39 x 47.00 x 1.00 x 1.00 = 11.13
2 = 0.60 x 0.39 x 57.00 x 1.00 x 1.00 = 13.49
2 ke 3 = 0.60 x 0.39 x 19.00 x 1.00 x 1.00 = 4.50
3 = 0.60 x 0.39 x 86.00 x 1.00 x 1.00 = 20.36
3 ke 4 = 0.60 x 0.39 x 20.00 x 1.00 x 1.00 = 4.73
= 0.60 x 0.39 x 20.00 x 1.00 x 1.00 = 4.73
4 ke 5 = 0.60 x 0.39 x 19.00 x 1.00 x 1.00 = 4.50
5 = 0.60 x 0.39 x 56.00 x 1.00 x 1.00 = 13.26
B = 0.60 x 0.39 x 85.00 x 1.00 x 1.00 = 20.12
C = 0.60 x 0.39 x 44.00 x 1.00 x 1.00 = 10.42
= 0.60 x 0.39 x 32.00 x 1.00 x 1.00 = 7.58
C ke D = 0.60 x 0.39 x 25.00 x 1.00 x 1.00 = 5.92
= 0.60 x 0.39 x 13.00 x 1.00 x 1.00 = 3.08
D = 0.60 x 0.39 x 25.00 x 1.00 x 1.00 = 5.92
= 0.60 x 0.39 x 19.00 x 1.00 x 1.00 = 4.50
D ke E = 0.60 x 0.39 x 13.00 x 1.00 x 1.00 = 3.08
E = 0.60 x 0.39 x 19.00 x 1.00 x 1.00 = 4.50
F = 0.60 x 0.39 x 32.00 x 1.00 x 1.00 = 7.58 +
Vol. Total = 638.79 Kg 638.79 Kg
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali)
Panjang Lebar Jumlah Sisi Jumlah Unit
1 = 6.90 x 0.20 x 2.00 x 1.00 = 2.76 m2
2 = 8.40 x 0.20 x 2.00 x 1.00 = 3.36
2 ke 3 = 2.70 x 0.20 x 2.00 x 1.00 = 1.08
3 = 12.75 x 0.20 x 2.00 x 1.00 = 5.10
3 ke 4 = 2.85 x 0.20 x 2.00 x 1.00 = 1.14
= 2.85 x 0.20 x 2.00 x 1.00 = 1.14
4 ke 5 = 2.70 x 0.20 x 2.00 x 1.00 = 1.08
5 = 8.25 x 0.20 x 2.00 x 1.00 = 3.30
B = 12.70 x 0.20 x 2.00 x 1.00 = 5.08
C = 6.55 x 0.20 x 2.00 x 1.00 = 2.62
= 4.70 x 0.20 x 2.00 x 1.00 = 1.88
C ke D = 3.70 x 0.20 x 2.00 x 1.00 = 1.48
= 1.85 x 0.20 x 2.00 x 1.00 = 0.74
D = 3.70 x 0.20 x 2.00 x 1.00 = 1.48
= 2.70 x 0.20 x 2.00 x 1.00 = 1.08
D ke E = 1.85 x 0.20 x 2.00 x 1.00 = 0.74
E = 2.70 x 0.20 x 2.00 x 1.00 = 1.08
F = 4.70 x 0.20 x 2.00 x 1.00 = 1.88 +
Vol. Total = 37.02 m2
Dipakai 2 kali = 18.51 m2 18.51 m2
16 Plat Lantai
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225)
Panjang Lebar Tinggi Jumlah Sisi Jumlah Unit
Area A (3 x 4.50 m) = 4.30 x 2.80 x 0.13 x 1.00 x 5.00 = 7.83 m3
Area B (2.50 x 4.50 m) = 4.30 x 2.30 x 0.13 x 1.00 x 3.00 = 3.86
Area C (3 x 3 m) = 2.80 x 2.80 x 0.13 x 1.00 x 9.00 = 9.17
Area D (2.50 x 3 m) = 2.80 x 2.30 x 0.13 x 1.00 x 8.00 = 6.70
Area E (3.50 x 3 m) = 3.30 x 2.80 x 0.13 x 1.00 x 3.00 = 3.60
Area F (2.50 x 2.50 m) = 2.30 x 2.30 x 0.13 x 1.00 x 1.00 = 0.69
Area G (3.50 x 2.50 m) = 3.30 x 2.30 x 0.13 x 1.00 x 1.00 = 0.99
Area H (2 x 2.50 m) = 2.30 x 1.80 x 0.13 x 1.00 x 1.00 = 0.54
Area I (3 x 4 m) = 3.80 x 2.80 x 0.13 x 1.00 x 4.00 = 5.53
Area J (4.50 x 4 m) = 4.30 x 3.80 x 0.13 x 1.00 x 1.00 = 2.12
Area K (2.50 x 4 m) = 3.80 x 2.30 x 0.13 x 1.00 x 1.00 = 1.14
Area L (3.50 x 4 m) = 3.80 x 3.30 x 0.13 x 1.00 x 1.00 = 1.63 +
Vol. Total = 43.79 m3 43.79 m3
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip
Ø Ø Koefisien
Ø 10 = 10 x 10 x 0.006165 = 0.62 kg/m
VI PEKERJAAN PLESTERAN
1 Pemasangan Plesteran 1 SP : 6 PP Tebal 15 mm
Volume Jumlah Sisi
Vol. Pasangan Dinding = 777.01 x 2.00 = 1,554.03 m2
Pengurang
Keramik Dinding = 431.76 x 1.00 = (431.76)
Radius Plint = 204.09 x 0.05 = (10.20) +
Vol. Total = 1,112.06 m2 1,112.06 m2
2 Pemasangan Plesteran 1 SP : 4 PP Tebal 15 mm
Panjang Lebar Jumlah Sisi Jumlah Unit
Kolom 1 = 3.85 x 0.44 x 2.00 x 69.00 = 233.77 m2
Kolom 3 = 3.85 x 0.15 x 2.00 x 57.00 = 65.84
Balok 1 = 292.60 x 0.32 x 2.00 x 1.00 = 187.26
Balok 2 = 37.40 x 0.17 x 2.00 x 1.00 = 12.72
Balok Latei = 152.95 x 0.20 x 2.00 x 1.00 = 61.18
Balok Gantung = 51.10 x 0.65 x 1.00 x 1.00 = 33.22
Ring Balok = 92.55 x 0.20 x 2.00 x 1.00 = 37.02 +
Vol. Total = 631.00 m2 631.00 m2
3 Pemasangan 1 m2 Acian
Vol. Plesteran 1 SP : 6 PP = 1,112.06 = 1,112.06 m2
Vol. Plesteran 1 SP : 4 PP = 631.00 = 631.00 +
Vol. Total = 1,743.06 m2 1,743.06 m2
XI PEKERJAAN PENGECATAN
Pengecatan 1 m2 Tembok Baru (1 Lapis Plamuur, 1 Lapis Cat
1
Dasar, 2 Lapis Cat Penutup)
Vol. Acian = 1,743.06 = 1,743.06 m2 1,743.06 m2
### Err:509
### Err:509
### Err:509
### Err:509
### Err:509
4 Pemasangan Bak Kontrol Pas.Batu Bata 60x60 tinggi 60 cm
Jumlah
Bak Kontrol 1 = 11.00 = 11.00 buah
Bak Kontrol 2 = 2.00 = 2.00 +
Vol. Total = 13.00 buah 13.00 buah
5 Pemasangan 1 buah Closet Duduk/Monoblock
Jumlah
= 2.00 = 2.00 unit 2.00 unit
6 Memasang Closet Jongkok Porselen
Jumlah
= 4.00 = 4.00 unit 4.00 unit
7 Pemasangan Kran Ø ½" atau Ø ¾"
Jumlah
= 7.00 = 7.00 buah 7.00 buah
8 Pemasangan Floor Drain
Jumlah
= 7.00 = 7.00 buah 7.00 buah
9 Pemasangan septictank Biotech lengkap accessoriess + Peresapan
Jumlah
= 2.00 = 2.00 buah 2.00 buah
10 Pemasangan 1 buah Wastafel + Pedestal + Asesories + Kran Air Stainless steel
Jumlah
= 18.00 = 18.00 buah 18.00 buah
11 Pasang Wastafel Beton (Spek Disesuaikan Dengan Gambar)
Jumlah
= 2.00 = 2.00 buah 2.00 buah
12 Pemasangan 1 buah Meja (bak cuci stainlessteel + Kran Air+ Kramik + Asesories sesusaikan dengan gambar)
Jumlah
= 6.00 = 6.00 buah 6.00 buah
13 Pemasangan 1 buah Spoel Hoek Slop Sink + Asesories
Jumlah
= 1.00 = 1.00 buah 1.00 buah
14 Pembuatan Sumur Gali 50cm Kedalaman 30 m + Asesories
Panjang
= 30.00 = 30.00 m' 30.00 m'
15 Pemasangan 1 buahTandon Air Kapasitas 1000 Liter (sekualitas penguin) + Asesories
Jumlah
= 2.00 = 2.00 buah 2.00 buah
BACK UP VOLUME
Kegiatan : PUSKESMAS BANJARMANGU 1 Kode Bangunan : A
Pekerjaan : PUSKESMAS BANJARMANGU 1 Nomor : 1
Nomor :
Sket / Gambar Perhitungan Volume Satuan
Tulangan Utama Ø 13 Panjang Koefisien Jumlah Besi Jumlah Sisi Jumlah Unit
Balok (B 1) 20 x 40 cm Elevasi +7.50
F = 2.70 x 1.04 x 6.00 x 1.00 x 1.00 = 16.88 Kg
G = 2.70 x 1.04 x 6.00 x 1.00 x 1.00 = 16.88
11 = 2.60 x 1.04 x 6.00 x 1.00 x 1.00 = 16.25
11 ke 12 = 3.65 x 1.04 x 6.00 x 1.00 x 1.00 = 22.82
Tulangan Utama Ø 10
Balok (B 1) 20 x 40 cm Elevasi +7.50
F = 2.70 x 0.62 x 4.00 x 1.00 x 1.00 = 6.66
G = 2.70 x 0.62 x 4.00 x 1.00 x 1.00 = 6.66
11 = 2.60 x 0.62 x 4.00 x 1.00 x 1.00 = 6.41
11 ke 12 = 3.65 x 0.62 x 4.00 x 1.00 x 1.00 = 9.00
Tulangan Sengkang Ø 8
Balok (B 1) 20 x 40 cm Elevasi +7.50
F = 1.10 x 0.39 x 15.00 x 1.00 x 1.00 = 6.51
G = 1.10 x 0.39 x 15.00 x 1.00 x 1.00 = 6.51
11 = 1.10 x 0.39 x 15.00 x 1.00 x 1.00 = 6.51
11 ke 12 = 1.10 x 0.39 x 20.00 x 1.00 x 1.00 = 8.68 +
Vol. Total = 129.77 Kg 129.77 Kg
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali)
Panjang Lebar Jumlah Sisi Jumlah Unit
Balok (B 1) 20 x 40 cm Elevasi +7.50
F = 2.15 x 0.74 x 1.00 x 1.00 = 1.59 m2
G = 2.15 x 0.74 x 1.00 x 1.00 = 1.59
11 = 2.20 x 0.74 x 1.00 x 1.00 = 1.63
11 ke 12 = 2.95 x 0.74 x 1.00 x 1.00 = 2.18 +
Vol. Total = 6.99 m2
Dipakai 2 kali = 3.50 m2 3.50 m2
4 Balok (B 2) 15 x 30 cm
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225)
Panjang Lebar Tinggi Panjang Lebar Tinggi Jumlah Silangan
Balok (B 2) 15 x 30 cm Elevasi +8.00
B = 23.50 x 0.15 x 0.30 - 0.30 x 0.15 x 0.30 x 8.00 = 0.95 m3
C = 8.50 x 0.15 x 0.30 - 0.30 x 0.15 x 0.30 x 3.00 = 0.34
D = 12.00 x 0.15 x 0.30 - 0.30 x 0.15 x 0.30 x 4.00 = 0.49
E = 9.00 x 0.15 x 0.30 - 0.30 x 0.15 x 0.30 x 3.00 = 0.36
= 3.50 x 0.15 x 0.30 - 0.30 x 0.15 x 0.30 x 1.00 = 0.14
F = 16.50 x 0.15 x 0.30 - 0.30 x 0.15 x 0.30 x 5.00 = 0.68
= 3.50 x 0.15 x 0.30 - 0.30 x 0.15 x 0.30 x 1.00 = 0.14
G = 22.50 x 0.15 x 0.30 - 0.30 x 0.15 x 0.30 x 7.00 = 0.92
H = 22.50 x 0.15 x 0.30 - 0.30 x 0.15 x 0.30 x 7.00 = 0.92
3 = 6.50 x 0.15 x 0.30 - 0.30 x 0.15 x 0.30 x 2.00 = 0.27
4 = 4.00 x 0.15 x 0.30 - 0.30 x 0.15 x 0.30 x 1.00 = 0.17
6 = 10.50 x 0.15 x 0.30 - 0.30 x 0.15 x 0.30 x 3.00 = 0.43
= 4.00 x 0.15 x 0.30 - 0.30 x 0.15 x 0.30 x 1.00 = 0.17
8 = 3.00 x 0.15 x 0.30 - 0.30 x 0.15 x 0.30 x 1.00 = 0.12
9 = 13.50 x 0.15 x 0.30 - 0.30 x 0.15 x 0.30 x 4.00 = 0.55
= 4.00 x 0.15 x 0.30 - 0.30 x 0.15 x 0.30 x 1.00 = 0.17
10 = 13.50 x 0.15 x 0.30 - 0.30 x 0.15 x 0.30 x 4.00 = 0.55
11 = 4.50 x 0.15 x 0.30 - 0.30 x 0.15 x 0.30 x 1.00 = 0.19
= 12.50 x 0.15 x 0.30 - 0.30 x 0.15 x 0.30 x 4.00 = 0.51
12 = 4.50 x 0.15 x 0.30 - 0.30 x 0.15 x 0.30 x 1.00 = 0.19
14 = 7.50 x 0.15 x 0.30 - 0.30 x 0.15 x 0.30 x 2.00 = 0.31 +
Vol. Total = 8.56 m3 8.56 m3
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip
Ø Ø Koefisien
Ø 13 = 13 x 13 x 0.006165 = 1.04 kg/m
Ø 10 = 10 x 10 x 0.006165 = 0.62 kg/m
Ø8 = 8 x 8 x 0.006165 = 0.39 kg/m
Tulangan Utama Ø 13 Panjang Koefisien Jumlah Besi Jumlah Sisi Jumlah Unit
Balok (B 2) 15 x 30 cm Elevasi +8.00
B = 23.60 x 1.04 x 4.00 x 1.00 x 1.00 = 98.35 Kg
C = 8.60 x 1.04 x 4.00 x 1.00 x 1.00 = 35.84
D = 12.10 x 1.04 x 4.00 x 1.00 x 1.00 = 50.43
E = 9.10 x 1.04 x 4.00 x 1.00 x 1.00 = 37.92
= 3.60 x 1.04 x 4.00 x 1.00 x 1.00 = 15.00
F = 16.60 x 1.04 x 4.00 x 1.00 x 1.00 = 69.18
= 3.60 x 1.04 x 4.00 x 1.00 x 1.00 = 15.00
G = 22.60 x 1.04 x 4.00 x 1.00 x 1.00 = 94.19
H = 22.60 x 1.04 x 4.00 x 1.00 x 1.00 = 94.19
3 = 6.60 x 1.04 x 4.00 x 1.00 x 1.00 = 27.51
4 = 4.10 x 1.04 x 4.00 x 1.00 x 1.00 = 17.09
6 = 10.60 x 1.04 x 4.00 x 1.00 x 1.00 = 44.18
= 4.10 x 1.04 x 4.00 x 1.00 x 1.00 = 17.09
8 = 3.10 x 1.04 x 4.00 x 1.00 x 1.00 = 12.92
9 = 13.60 x 1.04 x 4.00 x 1.00 x 1.00 = 56.68
= 4.10 x 1.04 x 4.00 x 1.00 x 1.00 = 17.09
10 = 13.60 x 1.04 x 4.00 x 1.00 x 1.00 = 56.68
11 = 4.60 x 1.04 x 4.00 x 1.00 x 1.00 = 19.17
= 12.60 x 1.04 x 4.00 x 1.00 x 1.00 = 52.51
12 = 4.60 x 1.04 x 4.00 x 1.00 x 1.00 = 19.17
14 = 7.60 x 1.04 x 4.00 x 1.00 x 1.00 = 31.67
Tulangan Utama Ø 10
Balok (B 2) 15 x 30 cm Elevasi +8.00
B = 23.60 x 0.62 x 2.00 x 1.00 x 1.00 = 29.10
C = 8.60 x 0.62 x 2.00 x 1.00 x 1.00 = 10.60
D = 12.10 x 0.62 x 2.00 x 1.00 x 1.00 = 14.92
E = 9.10 x 0.62 x 2.00 x 1.00 x 1.00 = 11.22
= 3.60 x 0.62 x 2.00 x 1.00 x 1.00 = 4.44
F = 16.60 x 0.62 x 2.00 x 1.00 x 1.00 = 20.47
= 3.60 x 0.62 x 2.00 x 1.00 x 1.00 = 4.44
G = 22.60 x 0.62 x 2.00 x 1.00 x 1.00 = 27.87
H = 22.60 x 0.62 x 2.00 x 1.00 x 1.00 = 27.87
3 = 6.60 x 0.62 x 2.00 x 1.00 x 1.00 = 8.14
4 = 4.10 x 0.62 x 2.00 x 1.00 x 1.00 = 5.06
6 = 10.60 x 0.62 x 2.00 x 1.00 x 1.00 = 13.07
= 4.10 x 0.62 x 2.00 x 1.00 x 1.00 = 5.06
8 = 3.10 x 0.62 x 2.00 x 1.00 x 1.00 = 3.82
9 = 13.60 x 0.62 x 2.00 x 1.00 x 1.00 = 16.77
= 4.10 x 0.62 x 2.00 x 1.00 x 1.00 = 5.06
10 = 13.60 x 0.62 x 2.00 x 1.00 x 1.00 = 16.77
11 = 4.60 x 0.62 x 2.00 x 1.00 x 1.00 = 5.67
= 12.60 x 0.62 x 2.00 x 1.00 x 1.00 = 15.54
12 = 4.60 x 0.62 x 2.00 x 1.00 x 1.00 = 5.67
14 = 7.60 x 0.62 x 2.00 x 1.00 x 1.00 = 9.37
Tulangan Sengkang Ø 8
Balok (B 2) 15 x 30 cm Elevasi +8.00
B = 0.80 x 0.39 x 141.00 x 1.00 x 1.00 = 44.51
C = 0.80 x 0.39 x 51.00 x 1.00 x 1.00 = 16.10
D = 0.80 x 0.39 x 73.00 x 1.00 x 1.00 = 23.04
E = 0.80 x 0.39 x 55.00 x 1.00 x 1.00 = 17.36
= 0.80 x 0.39 x 22.00 x 1.00 x 1.00 = 6.94
F = 0.80 x 0.39 x 101.00 x 1.00 x 1.00 = 31.88
= 0.80 x 0.39 x 22.00 x 1.00 x 1.00 = 6.94
G = 0.80 x 0.39 x 137.00 x 1.00 x 1.00 = 43.24
H = 0.80 x 0.39 x 137.00 x 1.00 x 1.00 = 43.24
3 = 0.80 x 0.39 x 40.00 x 1.00 x 1.00 = 12.63
4 = 0.80 x 0.39 x 25.00 x 1.00 x 1.00 = 7.89
6 = 0.80 x 0.39 x 65.00 x 1.00 x 1.00 = 20.52
= 0.80 x 0.39 x 25.00 x 1.00 x 1.00 = 7.89
8 = 0.80 x 0.39 x 19.00 x 1.00 x 1.00 = 6.00
9 = 0.80 x 0.39 x 83.00 x 1.00 x 1.00 = 26.20
= 0.80 x 0.39 x 25.00 x 1.00 x 1.00 = 7.89
10 = 0.80 x 0.39 x 83.00 x 1.00 x 1.00 = 26.20
11 = 0.80 x 0.39 x 29.00 x 1.00 x 1.00 = 9.15
= 0.80 x 0.39 x 76.00 x 1.00 x 1.00 = 23.99
12 = 0.80 x 0.39 x 29.00 x 1.00 x 1.00 = 9.15
14 = 0.80 x 0.39 x 47.00 x 1.00 x 1.00 = 14.84 +
Vol. Total = 1,548.36 Kg 1,548.36 Kg
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali)
Panjang Lebar Jumlah Sisi Jumlah Unit
Balok (B 2) 15 x 30 cm Elevasi +8.00
B = 21.10 x 0.75 x 1.00 x 1.00 = 15.83 m2
C = 7.60 x 0.75 x 1.00 x 1.00 = 5.70
D = 10.80 x 0.75 x 1.00 x 1.00 = 8.10
E = 8.10 x 0.75 x 1.00 x 1.00 = 6.07
= 3.20 x 0.75 x 1.00 x 1.00 = 2.40
F = 15.00 x 0.75 x 1.00 x 1.00 = 11.25
= 3.20 x 0.75 x 1.00 x 1.00 = 2.40
G = 20.40 x 0.75 x 1.00 x 1.00 = 15.30
H = 20.40 x 0.75 x 1.00 x 1.00 = 15.30
3 = 5.90 x 0.75 x 1.00 x 1.00 = 4.43
4 = 3.70 x 0.75 x 1.00 x 1.00 = 2.78
6 = 9.60 x 0.75 x 1.00 x 1.00 = 7.20
= 3.70 x 0.75 x 1.00 x 1.00 = 2.78
8 = 2.70 x 0.75 x 1.00 x 1.00 = 2.03
9 = 12.30 x 0.75 x 1.00 x 1.00 = 9.23
= 3.70 x 0.75 x 1.00 x 1.00 = 2.78
10 = 12.30 x 0.75 x 1.00 x 1.00 = 9.23
11 = 4.20 x 0.75 x 1.00 x 1.00 = 3.15
= 11.30 x 0.75 x 1.00 x 1.00 = 8.48
12 = 4.20 x 0.75 x 1.00 x 1.00 = 3.15
14 = 6.90 x 0.75 x 1.00 x 1.00 = 5.18 +
Vol. Total = 142.73 m2
Dipakai 2 kali = 71.36 m2 71.36 m2
5 Balok Gantung (BG) 15 x 25 cm
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225)
Panjang Lebar Tinggi Panjang Lebar Tinggi Jumlah Silangan
Balok Gantung (BG) 15 x 25 cm Elevasi +7.30
B = 23.50 x 0.15 x 0.25 - 0.30 x 0.15 x 0.25 x 8.00 = 0.79 m3
Balok Gantung (BG) 15 x 25 cm Elevasi +7.35
8 = 3.00 x 0.15 x 0.25 - 0.30 x 0.15 x 0.25 x 1.00 = 0.10
F = 6.00 x 0.15 x 0.25 - 0.30 x 0.15 x 0.25 x 2.00 = 0.20
Balok Gantung (BG) 15 x 25 cm Elevasi +8.00
C = 3.50 x 0.15 x 0.25 - 0.30 x 0.15 x 0.25 x 1.00 = 0.12
E = 2.50 x 0.15 x 0.25 - 0.30 x 0.15 x 0.25 x 1.00 = 0.08
F = 2.50 x 0.15 x 0.25 - 0.30 x 0.15 x 0.25 x 1.00 = 0.08
4 = 2.50 x 0.15 x 0.25 - 0.30 x 0.15 x 0.25 x 1.00 = 0.08
6 = 2.50 x 0.15 x 0.25 - 0.30 x 0.15 x 0.25 x 1.00 = 0.08
9 = 2.50 x 0.15 x 0.25 - 0.30 x 0.15 x 0.25 x 1.00 = 0.08 +
Vol. Total = 1.63 m3 1.63 m3
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip
Ø Ø Koefisien
Ø 12 = 12 x 12 x 0.006165 = 0.89 kg/m
Ø 10 = 10 x 10 x 0.006165 = 0.62 kg/m
Ø8 = 8 x 8 x 0.006165 = 0.39 kg/m
Tulangan Utama Ø 12 Panjang Koefisien Jumlah Besi Jumlah Sisi Jumlah Unit
Balok Gantung (BG) 15 x 25 cm Elevasi +7.30
B = 23.60 x 0.89 x 4.00 x 1.00 x 1.00 = 83.80 Kg
Balok Gantung (BG) 15 x 25 cm Elevasi +7.35
8 = 3.10 x 0.89 x 4.00 x 1.00 x 1.00 = 11.01
F = 6.10 x 0.89 x 4.00 x 1.00 x 1.00 = 21.66
Balok Gantung (BG) 15 x 25 cm Elevasi +8.00
C = 3.60 x 0.89 x 4.00 x 1.00 x 1.00 = 12.78
E = 2.60 x 0.89 x 4.00 x 1.00 x 1.00 = 9.23
F = 2.60 x 0.89 x 4.00 x 1.00 x 1.00 = 9.23
4 = 2.60 x 0.89 x 4.00 x 1.00 x 1.00 = 9.23
6 = 2.60 x 0.89 x 4.00 x 1.00 x 1.00 = 9.23
9 = 2.60 x 0.89 x 4.00 x 1.00 x 1.00 = 9.23
Tulangan Utama Ø 10
Balok Gantung (BG) 15 x 25 cm Elevasi +7.30
B = 23.60 x 0.62 x 2.00 x 1.00 x 1.00 = 29.10
Balok Gantung (BG) 15 x 25 cm Elevasi +7.35
8 = 3.10 x 0.62 x 2.00 x 1.00 x 1.00 = 3.82
F = 6.10 x 0.62 x 2.00 x 1.00 x 1.00 = 7.52
Balok Gantung (BG) 15 x 25 cm Elevasi +8.00
C = 3.60 x 0.62 x 2.00 x 1.00 x 1.00 = 4.44
E = 2.60 x 0.62 x 2.00 x 1.00 x 1.00 = 3.21
F = 2.60 x 0.62 x 2.00 x 1.00 x 1.00 = 3.21
4 = 2.60 x 0.62 x 2.00 x 1.00 x 1.00 = 3.21
6 = 2.60 x 0.62 x 2.00 x 1.00 x 1.00 = 3.21
9 = 2.60 x 0.62 x 2.00 x 1.00 x 1.00 = 3.21
Tulangan Sengkang Ø 8
Balok Gantung (BG) 15 x 25 cm Elevasi +7.30
B = 0.70 x 0.39 x 141.00 x 1.00 x 1.00 = 38.94
Balok Gantung (BG) 15 x 25 cm Elevasi +7.35
8 = 0.70 x 0.39 x 19.00 x 1.00 x 1.00 = 5.25
F = 0.70 x 0.39 x 37.00 x 1.00 x 1.00 = 10.22
Balok Gantung (BG) 15 x 25 cm Elevasi +8.00
C = 0.70 x 0.39 x 22.00 x 1.00 x 1.00 = 6.08
E = 0.70 x 0.39 x 15.00 x 1.00 x 1.00 = 4.14
F = 0.70 x 0.39 x 15.00 x 1.00 x 1.00 = 4.14
4 = 0.70 x 0.39 x 15.00 x 1.00 x 1.00 = 4.14
6 = 0.70 x 0.39 x 15.00 x 1.00 x 1.00 = 4.14
9 = 0.70 x 0.39 x 15.00 x 1.00 x 1.00 = 4.14 +
Vol. Total = 317.53 Kg 317.53 Kg
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali)
Panjang Lebar Jumlah Sisi Jumlah Unit
Balok Gantung (BG) 15 x 25 cm Elevasi +7.30
B = 21.10 x 0.65 x 1.00 x 1.00 = 13.72 m2
Balok Gantung (BG) 15 x 25 cm Elevasi +7.35
8 = 2.70 x 0.65 x 1.00 x 1.00 = 1.76
F = 5.40 x 0.65 x 1.00 x 1.00 = 3.51
Balok Gantung (BG) 15 x 25 cm Elevasi +8.00
C = 3.20 x 0.65 x 1.00 x 1.00 = 2.08
E = 2.20 x 0.65 x 1.00 x 1.00 = 1.43
F = 2.20 x 0.65 x 1.00 x 1.00 = 1.43
4 = 2.20 x 0.65 x 1.00 x 1.00 = 1.43
6 = 2.20 x 0.65 x 1.00 x 1.00 = 1.43
9 = 2.20 x 0.65 x 1.00 x 1.00 = 1.43 +
Vol. Total = 28.21 m2
Dipakai 2 kali = 14.11 m2 14.11 m2
6 Balok Latei 12 x 20 cm
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225)
Panjang Lebar Tinggi Panjang Lebar Tinggi Jumlah Silangan
Balok Latei 12 x 20 cm Elevasi +6.78
10 ke 11 = 3.00 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 2.00 = 0.06 m3
G ke H = 1.50 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 1.00 = 0.03
Balok Latei 12 x 20 cm Elevasi +6.80
3 ke 4 = 2.00 x 0.12 x 0.20 - 0.15 x 0.12 x 0.20 x 1.00 = 0.04
9 = 3.00 x 0.12 x 0.20 - 0.30 x 0.12 x 0.20 x 1.00 = 0.06
10 = 3.00 x 0.12 x 0.20 - 0.30 x 0.12 x 0.20 x 1.00 = 0.06
Balok Latei 12 x 20 cm Elevasi +7.30
C = 6.00 x 0.12 x 0.20 - 0.30 x 0.12 x 0.20 x 2.00 = 0.13
D = 8.50 x 0.12 x 0.20 - 0.30 x 0.12 x 0.20 x 3.00 = 0.18
G = 5.50 x 0.12 x 0.20 - 0.30 x 0.12 x 0.20 x 2.00 = 0.12
= 2.50 x 0.12 x 0.20 - 0.30 x 0.12 x 0.20 x 1.00 = 0.05
H = 19.50 x 0.12 x 0.20 - 0.30 x 0.12 x 0.20 x 6.00 = 0.42
= 1.50 x 0.12 x 0.20 - 0.30 x 0.12 x 0.20 x 1.00 = 0.03
3 = 4.50 x 0.12 x 0.20 - 0.30 x 0.12 x 0.20 x 2.00 = 0.09
6 = 3.00 x 0.12 x 0.20 - 0.30 x 0.12 x 0.20 x 1.00 = 0.06
9 = 3.00 x 0.12 x 0.20 - 0.30 x 0.12 x 0.20 x 1.00 = 0.06
10 = 6.00 x 0.12 x 0.20 - 0.30 x 0.12 x 0.20 x 2.00 = 0.13
11 = 6.00 x 0.12 x 0.20 - 0.30 x 0.12 x 0.20 x 2.00 = 0.13
14 = 5.25 x 0.12 x 0.20 - 0.30 x 0.12 x 0.20 x 2.00 = 0.11 +
Vol. Total = 1.80 m3 1.80 m3
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip
Ø Ø Koefisien
Ø 12 = 12 x 12 x 0.006165 = 0.89 kg/m
Ø8 = 8 x 8 x 0.006165 = 0.39 kg/m
Tulangan Utama Ø 12 Panjang Koefisien Jumlah Besi Jumlah Sisi Jumlah Unit
Balok Latei 12 x 20 cm Elevasi +6.78
10 ke 11 = 3.10 x 0.89 x 4.00 x 1.00 x 1.00 = 11.01 Kg
G ke H = 1.60 x 0.89 x 4.00 x 1.00 x 1.00 = 5.68
Balok Latei 12 x 20 cm Elevasi +6.80
3 ke 4 = 2.10 x 0.89 x 4.00 x 1.00 x 1.00 = 7.46
9 = 3.10 x 0.89 x 4.00 x 1.00 x 1.00 = 11.01
10 = 3.10 x 0.89 x 4.00 x 1.00 x 1.00 = 11.01
Balok Latei 12 x 20 cm Elevasi +7.30
C = 6.10 x 0.89 x 4.00 x 1.00 x 1.00 = 21.66
D = 8.60 x 0.89 x 4.00 x 1.00 x 1.00 = 30.54
G = 5.60 x 0.89 x 4.00 x 1.00 x 1.00 = 19.89
= 2.60 x 0.89 x 4.00 x 1.00 x 1.00 = 9.23
H = 19.60 x 0.89 x 4.00 x 1.00 x 1.00 = 69.60
= 1.60 x 0.89 x 4.00 x 1.00 x 1.00 = 5.68
3 = 4.60 x 0.89 x 4.00 x 1.00 x 1.00 = 16.33
6 = 3.10 x 0.89 x 4.00 x 1.00 x 1.00 = 11.01
9 = 3.10 x 0.89 x 4.00 x 1.00 x 1.00 = 11.01
10 = 6.10 x 0.89 x 4.00 x 1.00 x 1.00 = 21.66
11 = 6.10 x 0.89 x 4.00 x 1.00 x 1.00 = 21.66
14 = 5.35 x 0.89 x 4.00 x 1.00 x 1.00 = 19.00
Tulangan Sengkang Ø 8
Balok Latei 12 x 20 cm Elevasi +6.78
10 ke 11 = 0.54 x 0.39 x 19.00 x 1.00 x 1.00 = 4.05
G ke H = 0.54 x 0.39 x 10.00 x 1.00 x 1.00 = 2.13
Balok Latei 12 x 20 cm Elevasi +6.80
3 ke 4 = 0.54 x 0.39 x 13.00 x 1.00 x 1.00 = 2.77
9 = 0.54 x 0.39 x 19.00 x 1.00 x 1.00 = 4.05
10 = 0.54 x 0.39 x 19.00 x 1.00 x 1.00 = 4.05
Balok Latei 12 x 20 cm Elevasi +7.30
C = 0.54 x 0.39 x 37.00 x 1.00 x 1.00 = 7.88
D = 0.54 x 0.39 x 51.00 x 1.00 x 1.00 = 10.87
G = 0.54 x 0.39 x 33.00 x 1.00 x 1.00 = 7.03
= 0.54 x 0.39 x 15.00 x 1.00 x 1.00 = 3.20
H = 0.54 x 0.39 x 119.00 x 1.00 x 1.00 = 25.35
= 0.54 x 0.39 x 9.00 x 1.00 x 1.00 = 1.92
3 = 0.54 x 0.39 x 27.00 x 1.00 x 1.00 = 5.75
6 = 0.54 x 0.39 x 19.00 x 1.00 x 1.00 = 4.05
9 = 0.54 x 0.39 x 19.00 x 1.00 x 1.00 = 4.05
10 = 0.54 x 0.39 x 37.00 x 1.00 x 1.00 = 7.88
11 = 0.54 x 0.39 x 37.00 x 1.00 x 1.00 = 7.88
14 = 0.54 x 0.39 x 32.00 x 1.00 x 1.00 = 6.82 +
Vol. Total = 413.16 Kg 413.16 Kg
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali)
Panjang Lebar Jumlah Sisi Jumlah Unit
Balok Latei 12 x 20 cm Elevasi +6.78
10 ke 11 = 2.70 x 0.20 x 2.00 x 1.00 = 1.08 m2
G ke H = 1.35 x 0.20 x 2.00 x 1.00 = 0.54
Balok Latei 12 x 20 cm Elevasi +6.80
3 ke 4 = 1.85 x 0.20 x 2.00 x 1.00 = 0.74
9 = 2.70 x 0.20 x 2.00 x 1.00 = 1.08
10 = 2.70 x 0.20 x 2.00 x 1.00 = 1.08
Balok Latei 12 x 20 cm Elevasi +7.30
C = 5.40 x 0.20 x 2.00 x 1.00 = 2.16
D = 7.60 x 0.20 x 2.00 x 1.00 = 3.04
G = 4.90 x 0.20 x 2.00 x 1.00 = 1.96
= 2.20 x 0.20 x 2.00 x 1.00 = 0.88
H = 17.70 x 0.20 x 2.00 x 1.00 = 7.08
= 1.20 x 0.20 x 2.00 x 1.00 = 0.48
3 = 3.90 x 0.20 x 2.00 x 1.00 = 1.56
6 = 2.70 x 0.20 x 2.00 x 1.00 = 1.08
9 = 2.70 x 0.20 x 2.00 x 1.00 = 1.08
10 = 5.40 x 0.20 x 2.00 x 1.00 = 2.16
11 = 5.40 x 0.20 x 2.00 x 1.00 = 2.16
14 = 4.65 x 0.20 x 2.00 x 1.00 = 1.86 +
Vol. Total = 30.02 m2
Dipakai 2 kali = 15.01 m2 15.01 m2
7 Plat Leuvel
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225)
Panjang Lebar Tinggi Jumlah Sisi Jumlah Unit
Plat Leuvel 5 Elevasi +7.15
Memanjang = 23.20 x 0.15 x 0.10 x 1.00 x 1.00 = 0.35 m3 0.35 m3
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip
Ø Ø Koefisien
Ø 12 = 12 x 12 x 0.006165 = 0.89 kg/m
Tulangan Utama Ø 12 Panjang Koefisien Jumlah Besi Jumlah Sisi Jumlah Unit
Plat Leuvel 5 Elevasi +7.15
Memanjang = 23.30 x 0.89 x 3.00 x 1.00 x 1.00 = 62.05 Kg
Melintang = 0.63 x 0.89 x 233.00 x 1.00 x 1.00 = 130.31 +
Vol. Total = 192.37 Kg 192.37 Kg
- Pemasangan 1 m2 Bekisting untuk Plat lantai Beton Bangunan Gedung
Panjang Lebar Jumlah Sisi Jumlah Unit
Plat Leuvel 5 Elevasi +7.15
= 23.20 x 0.15 x 1.00 x 1.00 = 3.48 m2
= 23.50 x 0.10 x 1.00 x 1.00 = 2.35 +
Vol. Total = 5.83 m2
Dipakai 2 kali = 2.92 m2 2.92 m2
8 Ring Balk 15 x 20 cm
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225)
Panjang Lebar Tinggi Panjang Lebar Tinggi Jumlah Silangan
3 ke 4 = 4.00 x 0.15 x 0.20 - 0.15 x 0.15 x 0.20 x 2.00 = 0.11 m3
10 ke 11 = 3.00 x 0.15 x 0.20 - 0.15 x 0.15 x 0.20 x 2.00 = 0.08
E ke F = 3.50 x 0.15 x 0.20 - 0.15 x 0.15 x 0.20 x 2.00 = 0.10
G ke H = 1.50 x 0.15 x 0.20 - 0.15 x 0.15 x 0.20 x 2.00 = 0.04 +
Vol. Total = 0.32 m3 0.32 m3
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip
Ø Ø Koefisien
Ø 12 = 12 x 12 x 0.006165 = 0.89 kg/m
Ø 10 = 10 x 10 x 0.006165 = 0.62 kg/m
Ø8 = 8 x 8 x 0.006165 = 0.39 kg/m
Tulangan Utama Ø 12 Panjang Koefisien Jumlah Besi Jumlah Sisi Jumlah Unit
3 ke 4 = 4.10 x 0.89 x 4.00 x 1.00 x 1.00 = 14.56 Kg
10 ke 11 = 3.10 x 0.89 x 4.00 x 1.00 x 1.00 = 11.01
E ke F = 3.60 x 0.89 x 4.00 x 1.00 x 1.00 = 12.78
G ke H = 1.60 x 0.89 x 4.00 x 1.00 x 1.00 = 5.68
Tulangan Utama Ø 10
3 ke 4 = 4.10 x 0.62 x 2.00 x 1.00 x 1.00 = 5.06
10 ke 11 = 3.10 x 0.62 x 2.00 x 1.00 x 1.00 = 3.82
E ke F = 3.60 x 0.62 x 2.00 x 1.00 x 1.00 = 4.44
G ke H = 1.60 x 0.62 x 2.00 x 1.00 x 1.00 = 1.97
Tulangan Utama Ø 8
3 ke 4 = 0.60 x 0.39 x 25.00 x 1.00 x 1.00 = 5.92
10 ke 11 = 0.60 x 0.39 x 19.00 x 1.00 x 1.00 = 4.50
E ke F = 0.60 x 0.39 x 22.00 x 1.00 x 1.00 = 5.21
G ke H = 0.60 x 0.39 x 9.00 x 1.00 x 1.00 = 2.13 +
Vol. Total = 77.08 Kg 77.08 Kg
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali)
Panjang Lebar Jumlah Sisi Jumlah Unit
3 ke 4 = 3.70 x 0.20 x 2.00 x 1.00 = 1.48 m2
10 ke 11 = 2.70 x 0.20 x 2.00 x 1.00 = 1.08
E ke F = 3.20 x 0.20 x 2.00 x 1.00 = 1.28
G ke H = 1.20 x 0.20 x 2.00 x 1.00 = 0.48 +
Vol. Total = 4.32 m2
Dipakai 2 kali = 2.16 m2 2.16 m2
9 Plat Lantai
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225)
Panjang Lebar Tinggi Jumlah Sisi Jumlah Unit
Torn (2 x 2.50 m) = 1.85 x 2.35 x 0.13 x 1.00 x 1.00 = 0.57 m3
= 1.85 x 0.55 x 0.13 x 1.00 x 2.00 = 0.26
= 0.55 x 2.35 x 0.13 x 1.00 x 1.00 = 0.17
= 0.55 x 0.55 x 0.13 x 1.00 x 2.00 = 0.08 +
Vol. Total = 1.08 m3 1.08 m3
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip
Ø Ø Koefisien
Ø 10 = 10 x 10 x 0.006165 = 0.62 kg/m
Horizontal
Lajur Bawah Ø 10 - 300 = 2.00 x 0.62 x 2.00 x 1.00 x 2.00 = 4.93
Lajur Atas Ø 10 - 150 = 2.00 x 0.62 x 4.00 x 1.00 x 2.00 = 9.86
Vertikal
Lajur Bawah Ø 10 - 300 = 0.70 x 0.62 x 7.00 x 1.00 x 2.00 = 6.04
Lajur Atas Ø 10 - 150 = 0.70 x 0.62 x 13.00 x 1.00 x 2.00 = 11.22
Horizontal
Lajur Bawah Ø 10 - 300 = 0.70 x 0.62 x 8.00 x 1.00 x 1.00 = 3.45
Lajur Atas Ø 10 - 150 = 0.70 x 0.62 x 16.00 x 1.00 x 1.00 = 6.90
Vertikal
Lajur Bawah Ø 10 - 300 = 2.50 x 0.62 x 2.00 x 1.00 x 1.00 = 3.08
Lajur Atas Ø 10 - 150 = 2.50 x 0.62 x 4.00 x 1.00 x 1.00 = 6.17
Horizontal
Lajur Bawah Ø 10 - 300 = 0.70 x 0.62 x 2.00 x 1.00 x 2.00 = 1.73
Lajur Atas Ø 10 - 150 = 0.70 x 0.62 x 4.00 x 1.00 x 2.00 = 3.45
Vertikal
Lajur Bawah Ø 10 - 300 = 0.70 x 0.62 x 2.00 x 1.00 x 2.00 = 1.73
Lajur Atas Ø 10 - 150 = 0.70 x 0.62 x 4.00 x 1.00 x 2.00 = 3.45 +
Vol. Total = 125.43 Kg 125.43 Kg
- Pemasangan 1 m2 Bekisting untuk Plat lantai Beton Bangunan Gedung
Panjang Lebar Jumlah Sisi Jumlah Unit
Torn (2 x 2.50 m) = 1.85 x 2.35 x 1.00 x 1.00 = 4.35 m2
= 1.85 x 0.55 x 1.00 x 2.00 = 2.04
= 0.55 x 2.35 x 1.00 x 1.00 = 1.29
= 0.55 x 0.55 x 1.00 x 2.00 = 0.61 +
Vol. Total = 8.28 m2 8.28 m2
10 Listplank Beton
- Pembuatan 1 m3 Beton Mutu f’c = 19,3 Mpa (K225)
Panjang Lebar Tinggi Jumlah Sisi Jumlah Unit
= 3.75 x 0.10 x 0.37 x 1.00 x 1.00 = 0.14 m3
= 2.55 x 0.10 x 0.37 x 1.00 x 2.00 = 0.19 +
Vol. Total = 0.33 m3 0.33 m3
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip
Ø Ø Koefisien
Ø 10 = 10 x 10 x 0.006165 = 0.62 kg/m
IV PEKERJAAN PLESTERAN
1 Pemasangan Plesteran 1 SP : 6 PP Tebal 15 mm
Volume Jumlah
Vol. Pasangan Dinding = 489.49 x 2.00 = 978.97 m2
Pengurang
Keramik Dinding = 0.00 x 1.00 = - +
Vol. Total = 978.97 m2 978.97 m2
2 Pemasangan Plesteran 1 SP : 4 PP Tebal 15 mm
Panjang Lebar Jumlah Sisi Jumlah Unit
Kolom 1 = 3.75 x 0.44 x 2.00 x 55.00 = 181.50 m2
Kolom 3 = 3.75 x 0.15 x 2.00 x 22.00 = 24.75
Balok 1 = 9.45 x 0.32 x 2.00 x 1.00 = 6.05
Balok 2 = 190.30 x 0.17 x 2.00 x 1.00 = 64.70
Balok Latei = 75.05 x 0.20 x 2.00 x 1.00 = 30.02
Balok Gantung = 43.40 x 0.65 x 1.00 x 1.00 = 28.21
Ring Balok = 10.80 x 0.20 x 2.00 x 1.00 = 4.32 +
Vol. Total = 339.55 m2 339.55 m2
3 Pemasangan 1 m2 Acian
Vol. Plesteran 1 SP : 6 PP = 978.97 = 978.97 m2
Vol. Plesteran 1 SP : 4 PP = 339.55 = 339.55 +
Vol. Total = 1,318.52 m2 1,318.52 m2
VI PEKERJAAN LANGIT-LANGIT
Panjang Lebar Jumlah Unit
Aula = 10.45 x 8.85 x 1.00 = 92.48
Musholla = 2.85 x 2.85 x 1.00 = 8.12
Selasar depan Aula = 13.55 x 2.35 x 1.00 = 31.84
R. Arsip = 3.35 x 2.85 x 1.00 = 9.55
Selasar depan R. Dokter = 11.85 x 2.85 x 1.00 = 33.77
Atas Tangga Utama = 4.58 x 3.35 x 1.00 = 15.34
R. Konsultasi Gizi = 4.45 x 2.85 x 1.00 = 12.68
R. Dokter / UKP = 5.35 x 4.45 x 1.00 = 23.81
Selasar depan R. UKM = 22.35 x 2.35 x 1.00 = 52.52
R. Tata Usaha = 5.85 x 3.85 x 1.00 = 22.52
R. UKM = 8.85 x 3.85 x 1.00 = 34.07
R. Kepala Puskesmas = 5.85 x 3.85 x 1.00 = 22.52
Kamar Mandi = 1.85 x 1.35 x 3.00 = 7.49
Lavatory = 1.85 x 1.35 x 1.00 = 2.50
T. Wudhu = 1.50 x 1.35 x 2.00 = 4.05
Pengurang
Kolom = 0.30 x 0.08 x 46.00 = (1.04)
= 0.08 x 0.08 x 47.00 = (0.26)
Lampu Downlight 18 watt = 0.15 x 0.15 x 17.00 = (0.38)
Lampu TL RMI = 0.21 x 0.68 x 55.00 = (7.85) +
Vol. Total = 363.74 m2 363.74 m2
1 Pemasangan 1 m2 Langit-Langit PVC.
Panjang Lebar Jumlah Unit
Tritisan samping R. Dokter = 8.75 x 1.00 x 1.00 = 8.75 m2
Atas Tangga Darurat = 8.50 x 1.00 x 1.00 = 8.50
Atas Tangga Darurat = 12.50 x 1.00 x 1.00 = 12.50
Belakang = 23.65 x 1.00 x 1.00 = 23.65
Belakang samping = 7.65 x 1.00 x 1.00 = 7.65
Depan Selasar Belakang = 12.50 x 1.00 x 1.00 = 12.50
Samping Musholla = 2.85 x 1.00 x 1.00 = 2.85
Belakang Aula = 6.00 x 1.00 x 1.00 = 6.00
Samping Aula = 10.75 x 1.00 x 1.00 = 10.75
Selasar tangga darurat = 2.35 x 1.85 x 1.00 = 4.35
= 2.45 x 0.45 x 2.00 = 2.21
= 2.65 x 0.45 x 1.00 = 1.19 +
Vol. Total = 100.89 m2 100.89 m2
464.64
VII PEKERJAAN PENUTUP ATAP
1 Pemasangan 1 m2 Atap bitumen bergelombang monolayer 3mm Uk 200x95x0.30cm jarak gording dan reng max 45 cm
Panjang Tinggi Jumlah Sisi Jumlah Unit
Sisi D Samping = 6.13 x 7.10 x 1.00 x 1.00 = 43.49 m2
Sisi D Depan = 10.63 x 7.10 x 1.00 x 1.00 = 75.44
Sisi D Belakang = 6.00 x 6.15 x 1.00 x 1.00 = 36.90
= 5.25 x 1.05 x 1.00 x 1.00 = 5.51
Sisi E Samping = 4.63 x 5.35 x 1.00 x 1.00 = 24.74
Sisi E Depan-Belakang = 8.50 x 5.35 x 2.00 x 1.00 = 90.95
Sisi F Kanan = 3.00 x 5.35 x 1.00 x 1.00 = 16.05
= 1.50 x 1.85 x 1.00 x 1.00 = 2.78
= 9.50 x 6.15 x 1.00 x 1.00 = 58.43
Sisi F Kiri = 9.50 x 1.50 x 1.00 x 1.00 = 14.25
= 5.38 x 4.75 x 1.00 x 1.00 = 25.53
Sisi G Samping kiri = 4.13 x 4.75 x 1.00 x 1.00 = 19.59
Sisi G Depan-Belakang = 13.50 x 4.75 x 2.00 x 1.00 = 128.25
= 5.38 x 6.15 x 1.00 x 1.00 = 33.06 +
Vol. Total = 574.96 m2 574.96 m2
2 Pemasangan 1 m' Nok Bitumen Monolayer
Panjang
= 94.50 = 94.50 m1 94.50 m1
3 Pemasangan 1 m’ Lisplank GRC Lebar 40 cm
Panjang
= 121.00 = 121.00 m1 121.00 m1
X PEKERJAAN ELEKTRIKAL
1 Box panel Lengkap (MCCB 2bh, MCB 5 bh, Ampere Meter 1 phase, Volt Meter 1 phase, CT, Pilot Lamp 3 bh, Sikring 3 bh)
Jumlah
= 1.00 = 1.00 unit 1.00 unit
2 Pemasangan 1 buah Titik Lampu
Jumlah
Lampu down light Kotak LED 18 watt = 15.00 = 15.00 buah
Lampu LED TL RMI 2x9 watt + Cap Lampu = 58.00 = 58.00 +
Vol. Total = 73.00 buah 73.00 buah
3 Pemasangan 1 buah Stop Kontak
Jumlah
= 64.00 = 64.00 buah 64.00 buah
4 Stop kontak Dinding AC
Jumlah
= 10.00 = 10.00 buah 10.00 buah
5 Pemasangan 1 buah Saklar
Jumlah
Saklar Tunggal = 3.00 = 3.00 buah
Saklar Ganda = 15.00 = 15.00 +
Vol. Total = 18.00 buah 18.00 buah
6 Lampu down light Kotak LED 18 watt
Jumlah
= 15.00 = 15.00 buah 15.00 buah
7 Lampu LED TL RMI 2x9 watt + Cap Lampu
Jumlah
= 58.00 = 58.00 buah 58.00 buah
1 A.4.1.2.8 Pemasangan dan Membuka Cetakan 1 buah Komponen Pelat Beton Pracetak M2 6,681.25
2 A.4.1.2.9 Pemasangan dan Membuka Cetakan 1 buah Komponen Balok Beton Pracetak M2 10,859.18
3 A.4.1.2.10 Pemasangan dan Membuka Cetakan 1 buah Komponen Kolom Beton Pracetak M2 8,770.21
4 A.4.1.2.11 Penuangan/Menebar Beton 1 m3 untuk Pelat Beton Pracetak M3 49,594.69
5 A.4.1.2.12 Penuangan/Menebar Beton 1 m3 untuk Balok Beton Pracetak M3 51,288.55
6 A.4.1.2.13 Penuangan/Menebar Beton 1 m3 untuk Kolom Beton Pracetak M3 46,133.78
Pemasangan 1 buah Dinding Terawang (rooster) 12x11x24 dengan
Dihitung.4.1.1 Buah 25,659.33
Mortar Tipe S.fc’ 12. 5 Mpa ( Setara Campuran 1SP : 3PP)
Dihitung.4.1.2 Beton Terawang Tb. 4cm Motif Batik Finishing Cat m2 480,000.00
Dihitung.4.1.3 Membuat Saluran Beton U m' 150,000.00
1 A.4.4.1.1. Pemasangan 1 m² Dinding Bata Merah ( 5 x 11 x 22 ) sm Tebal 1 Batu dengan Mortar tipe M, Fc 17,2 m2 300,851.15
2 A.4.4.1.2. Pemasangan 1 m² Dinding Bata Merah ( 5 x 11 x 22 ) sm Tebal 1 Batu dengan Mortar tipe S, Fc 12,5 m2 287,803.63
3 A.4.4.1.3. Pemasangan 1 m² Dinding Bata Merah ( 5 x 11 x 22 ) sm Tebal 1 Batu dengan Mortar tipe N, Fc 5,2 M m2 278,627.96
4 A.4.4.1.4. Pemasangan 1 m² Dinding Bata Merah ( 5 x 11 x 22 ) sm Tebal 1 Batu dengan Mortar tipe O, Fc 2,4 M m2 274,452.51
5 A.4.4.1.5 Pemasangan 1 m² Dinding Bata Merah ( 5 x 11 x 22 ) cm Tebal 1 batu Campuran 1 SP : 6PP m2 274,231.15
6 A.4.4.1.7 Pemasangan 1 m² Dinding Bata Merah ( 5 x 11 x 22 ) sm Tebal 1/2 Batu dengan Mortar tipe M, Fc 17, m2 145,635.65
7 A.4.4.1.8 Pemasangan 1 m² Dinding Bata Merah ( 5 x 11 x 22 ) sm Tebal 1/2 Batu dengan Mortar tipe S, Fc 12,5 m2 139,222.74
8 A.4.4.1.9 Pemasangan 1 m² Dinding Bata Merah ( 5 x 11 x 22 ) sm Tebal 1/2 Batu dengan Mortar tipe N, Fc 5,2 m2 135,675.36
9 A.4.4.1.10 Pemasangan 1 m² Dinding Bata Merah ( 5 x 11 x 22 ) sm Tebal 1/2 Batu dengan Mortar tipe O, Fc 2,4 m2 133,452.13
10 A.4.4.1.11 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP m2 132,466.69
11 A.4.4.1.12 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 8PP m2 129,973.70
12 A.4.4.1.13 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3KP : 10PP m2 129,446.69
13 A.4.4.1.14 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 1SM : 1PP m2 114,541.53
14 A.4.4.1.15 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1KP : 1SM : 2PP m2 116,557.55
15 A.4.4.1.16 Pemasangan 1 m² Dinding Conblock HB20 dengan Mortar Tipe S, Fc 12,5 Mpa ( Setara campuran 1 Sp m2 323,272.88
16 A.4.4.1.17 Pemasangan 1 m² Dinding Conblock HB20 dengan Mortar Tipe N, Fc 5,2 Mpa ( Setara campuran 1 Sp : m2 325,943.32
17 A.4.4.1.18 Pemasangan 1 m² Dinding Conblock HB15 dengan Mortar Tipe S, Fc 12,5 Mpa ( Setara campuran 1 Sp m2 262,280.21
18 A.4.4.1.19 Pemasangan 1 m² Dinding Conblock HB15 dengan Mortar Tipe N, Fc 5,2 Mpa ( Setara campuran 1 Sp : m2 264,020.87
19 A.4.4.1.20 Pemasangan 1 m² Dinding Conblock HB10 dengan Mortar Tipe s, Fc 12,5 Mpa ( Setara campuran 1 Sp m2 196,780.61
20 A.4.4.1.21 Pemasangan 1 m² Dinding Conblock HB10 dengan Mortar Tipe N, Fc 5,2 Mpa ( Setara campuran 1 Sp : m2 198,655.36
21 A.4.4.1.22 Pemasangan 1m² Dinding Terawang ( rooster ) 12 x 11 x 24 dengan mortar type S, Fc 12,5 Mpa ( Seta m2 393,458.27
22 A.4.4.1.23 Pemasangan 1m² Dinding Terawang ( rooster ) 12 x 11 x 24 dengan mortar type N, Fc 5,2 Mpa ( Setara m2 393,458.27
23 A.4.4.1.24 Pemasangan 1m² Dinding bata berongga Ekspose 12 x 11 x 24 dengan Mortar tipe S, Fc 12,5 ( Setara m2 -
24 A.4.4.1.25 Pemasangan 1 m² Dinding bata ringan tebal 7,5 cm dengan mortar siap pakai m2 -
25 A.4.4.1.26 Pemasangan 1 m² Dinding bata ringan tebal 10 cm dengan mortar siap pakai m2 -
URAIAN PEKERJAAN HARGA SATUAN PEKERJAAN
NO. KODE SAT HARGA
(Rp)
1 A.4.4.3.1 Pemasangan 1m2 lantai ubin PC Abu-abu Ukuran 40cm x40cm m2 35,353.73
2 A.4.4.3.2 Pemasangan lantai Ubin PC Abu-abu Uk. 30 x 30 cm m2 -
3 A.4.4.3.3 Pemasangan lantai Ubin PC Abu-abu Uk. 20 x 20 cm m2 -
4 A.4.4.3.5 Pemasangan 1m2 Lantai ubin Warna Ukuran 30cm x 30cm m2 -
5 A.4.4.3.6 Pemasangan lantai Ubin PC Warna Uk. 20 x 20 cm m2 -
6 A.4.4.3.7 Pemasangan 1m2 Lantai Ubin Teraso Ukuran 40cm x 40cm m' -
7 A.4.4.3.8 Pemasangan 1m2 Lantai Ubin Granit Ukuran 30cm x 30cm m2 -
8 A.4.4.3.9 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm m2 -
9 A.4.4.3.12 Pemasangan 1m2 Lantai Ubin Teralux Ukuran 30cm x30cm m2 -
10 A.4.4.3.13 Pemasangan 1m2 Lantai Ubin Teralux Marmer Ukuran 60cm x60cm m2 -
11 A.4.4.3.16 Pemasangan 1 m’ Plint Ubin PC Abu-abu Ukuran 20 s.d. <30 cm m' -
12 A.4.4.3.19 Pemasangan 1 m’ Plint Ubin Warna Ukuran 20 s.d. <30cm m' -
13 A.4.4.3.32 Pemasangan 1m2 Lantai Keramik Artistik 10 s.d. <20cm m2 -
14 A.4.4.3.33 Pemasangan 1m2 Lantai Keramik Artistik Ukuran 20 s.d. <30 cm m2 -
15 A.4.4.3.36 Pemasangan 1m2 Lantai Keramik Ukuran 30 s.d. <40cm m2 166,866.94
16 A.4.4.3.39 Pemasangan 1 m’ Plint Keramik Ukuran 10 s.d. <20cm m1 58,567.69
17 A.4.4.3.42 Pemasangan 1 m2 Lantai Marmer Ukuran 100cm x 100cm m2 -
18 A.4.4.3.43 Pemasangan 1 m2 Lantai Karpet m2 -
19 A.4.4.3.44 Pemasangan 1 m2 Underlayer (Pelapis Bawah Karpet) m2 -
20 A.4.4.3.45 Pemasangan 1 m2 Lantai Parquet Kayu Solid m2 -
21 A.4.4.3.47 Pemasangan Dinding Porselen 11 x 11 cm m2 -
22 A.4.4.3.52 Pemasangan Dinding Keramik 10x20 cm, m2 -
23 A.4.4.3.53 Pemasangan Dinding Keramik 20x20 cm, m2 249,208.06
24 Dihitung.4.4.3 Pemasangan Dinding Keramik 30x60 cm, Motif Halus m2 231,333.06
25 Dihitung.4.4.4 Pemasangan 1m2 Lantai Keramik Ukuran 60x60 Motif Halus m2 263,996.94
26 Dihitung.4.4.5 Pemasangan 1m2 Lantai Keramik Ukuran 60x60 Motif Kasar m2 238,421.94
27 Dihitung.4.4.6 Pemasangan 1 m' stepnosing Keramik Ukuran 10x60 m' 69,277.69
Dihitung.4.4.7 Pemasangan 1m2 Lantai Keramik Ukuran 30x30 Motif Kasar m2 202,984.65
Dihitung.4.4.8 Pemasangan 1 m’ Radiusplint Internal Cove PVC 5x5x60cm m1 202,066.15
28 A.4.4.3.54 Pemasangan Dinding Marmer Ukuran 1.00x1.00 cm m2 -
29 A.4.4.3.56 Pemasangan 1 m2 Dinding Batu Paras m2 277,238.32
30 A.4.4.3.57 Pemasangan 1 m2 Dinding Batu Tempel Hitam m2 307,488.32
31 A.4.4.3.58 Pemasangan Lantai Vynil uk.30 x 30 cm m2 -
32 A.4.4.3.59 Pemasangan 1 m2 Wallpaper lebar 50 cm m2 -
33 A.4.4.3.60 Pemasangan 1m2 Floor Harderner m2 -
34 A.4.4.3.62 Pemasangan 1 m’ Plint Kayu Tebal 2 cm Lebar 10 cm m' 78,179.64
35 A.4.4.3.63 Pemasangan 1 m2 Paving Block (Blok Beton) Natural tebal 6cm m2 168,072.63
36 A.4.4.3.64 Pemasangan 1 m2 Paving Block Mutu K-225 (Blok Beton) Natural tebal 8 cm m2 212,941.63
URAIAN PEKERJAAN HARGA SATUAN PEKERJAAN
NO. KODE SAT HARGA
(Rp)
Dihitung.4.5.2 Pemasangan 1 m2 Atap bitumen bergelombang monolayer 3mm Uk 200x95x0.30cm jarak gording dan m2 169,795.67
Dihitung.4.5.3 Pemasangan 1 m' Nok Bitumen Monolayer m1 211,621.11
Dihitung.4.5.4 Pemasangan 1 m2 Atap Galvalum 0.30 mm Lapis Pasir m2 75,078.74
Dihitung.4.5.4.a Pemasangan 1 m2 Atap Galvalum 0.30 mm m2 71,228.74
Dihitung.4.5.5 Pemasangan 1 m2 Atap Genteng Metal Lapis pasir m2 90,999.44
Dihitung.4.5.6 Pemasangan Atap Solar Tuff m2 253,002.39
Dihitung.4.5.7 Pemasangan 1 m Nok Galvalum m1 #N/A
Dihitung.4.5.8 Pemasangan 1 m’ Lisplank GRC Lebar 20 cm m1 38,747.50
Dihitung.4.5.9 Pemasangan 1 m’ Lisplank GRC Lebar 40 cm m1 48,436.30
Dihitung.4.5.10 Lisplang Zincalume Lebar 20 cm m1 43,336.70
21 Dihitung.9 Pemasangan 1 Watt UJL listrik Baru + Test Comisioning watt 2,090.00
22 Dihitung.10 Kabel Oper Spaneng NYY 4X16 mm. m' 180,000.00
Box panel Lengkap
23 Dihitung.11 (MCCB 2buah, MCB 16 buah, Ampere Meter 3 phase, Volt Meter 3 phase, CT, Pilot Lamp 3 buah, unit 6,000,000.00
sikring 3 buah)
Box Panel Induk
24 Dihitung.12 unit 6,500,000.00
(Push Bar,MCCB, Pilot Lamp, Stop Kontak)
25 A.6.2.1.1 Pemasangan 1 buah Titik Lampu buah 211,860.00
26 Dihitung.13 Pemasangan 1 buah Stop Kontak buah 262,724.00
27 Dihitung.14 Stop kontak Dinding AC buah 63,615.20
28 Dihitung.15 Lampu LED TL RMI 2x9 watt + Cap Lampu buah 448,615.20
29 Dihitung.16 Lampu down light Kotak LED 18 watt buah 135,470.50
30 Dihitung.17 Lampu down light Kotak LED 6 watt buah 25,470.50
31 Dihitung.18 Lampu down light Kotak LED 9 watt buah 58,470.50
32 Dihitung.19 Pemasangan 1 buah Saklar Hotel buah 36,470.50
33 Dihitung.20 Exhause fan Ceiling Plafond + instalasi pipa (Spek Disesuaikan Dengan Gambar) buah 584,705.00
34 Dihitung.29 Meja Dapur (Spek & Ukuran disesuaikan dengan gambar) unit 10,287,236.40
35 Dihitung.30 Grille FAG uk. 40 x 20 cm buah 438,735.00
36 Dihitung.31 Pemasangan 1 buah pintu kaca Tempered tebal 12 mm + asesories + Stiker Loago Perpusda unit 15,015,000.00
37 Dihitung.32 Pemasangan 1 buah pintu kaca Tempered tebal 12 mm m2 1,226,255.86
38 Dihitung.33 Pemasangan 1 m2 ACP m2 950,746.50
39 Dihitung.34 Tulisan Bahan Acrilyc 3D 70 cm buah 624,970.50
40 Dihitung.35 Tulisan Bahan Acrilyc 3D 40 cm buah 360,970.50
41 Dihitung.36 Logo Tinggi 1 m buah 1,548,970.50
42 Dihitung.37 Pekerjaan 1 buah Meja Loby buah 25,000,000.00
43 Dihitung.38 Pembersihan Lokasi ls 6,983,263.44
44 Dihitung.39 Pemasangan 1 m' Nok Bitumen Monolayer m' 211,208.09
45 Dihitung.40 Pemasangan 1 m2 Atap bitumen bergelombang monolayer 3mm Uk 200x95x0.30cm jarak gording dan m2 169,107.29
46 Dihitung.41 Pemasangan 1 m’ Lisplank GRC m' 38,255.80
47 Dihitung.42 Pemasangan 1 Unit Pintu Rangka Aluminium + Grendel dan Engsel (kamar Mandi) unit 1,931,380.00
48 Dihitung.43 Pemasangan 1 m2 Langit-Langit PVC. m2 164,301.50
49 Dihitung.44 Pemasangan 1 m2 Atap UPVC Double Layer m2 241,759.10
50 Dihitung.45 Pemasangan 1 m' Talang UPVC m' 119,591.12
51 Dihitung.46 Pasang rangka Talang hollow galvanis 3.5/3.5 cm, Jarak Rangka 60cm m' 217,800.00
52 Dihitung.47 Logo Tinggi 2 m buah 3088123.5
53 Dihitung.48 Pemasangan 1 buah AC buah 4,290,000.00
54 Dihitung.49 jdih.pu.go.id buah -
55 Dihitung.50 Pembuatan 1 m Sumur Gali + Pondasi Silinder + Penutup m' 323,752.00
56 Dihitung.51 Pompa transfer (pengisian Bak) kapasitas 30 liter/ menit (Voltage/Hz : 220 V/50 Hz, Output : 500 W, unit 4,146,252.00
57 Dihitung.52 Pompa Transfer (JET PUMP OTOMATIS Type PC-503 BIT Daya Hisap: 50 Meter (25 m permukaan air) unit 4,267,252.00
Mengetahui
Kepala Dinas Pekerjaan Umum
Dan Penataan Ruang
H PEKERJAAN PAGAR
I PEKERJAAN TANAH
1 Penggalian 1 m3 Tanah Biasa Sedalam s.d. 1 m
Panjang Lebar Tinggi Jumlah Sisi Jumlah Unit
Fp = 0.80 x 0.80 x 1.50 x 1.00 x 19.00 = 18.24 m3
Pondasi 1 = 64.80 x 0.80 x 0.85 x 1.00 x 1.00 = 44.06
Pengurang
Silangan Pondasi 1 = 0.80 x 0.80 x 0.85 x 1.00 x 19.00 = (10.34) +
Vol. Total = 51.97 m3 51.97 m3
2 Pengurugan Kembali 1 m3 Galian Tanah
Vol. Galian Vol. Pasir UrugVol. Aanstamping Vol. Pondasi Vol. Lc Vol. Fp Vol. Timb. Taman
= 51.97 - 2.59 - 6.99 - 20.96 - 0.61 - 3.23 + 0.95 = 18.54 m3 18.54 m3
3 Pengurugan 1m3 Dengan Pasir Urug
Panjang Lebar Tinggi Jumlah Sisi Jumlah Unit
Fp = 0.80 x 0.80 x 0.05 x 1.00 x 19.00 = 0.61 m3
Pondasi 1 = 64.80 x 0.80 x 0.05 x 1.00 x 1.00 = 2.59
Pengurang
Silangan Pondasi 1 = 0.80 x 0.80 x 0.05 x 1.00 x 19.00 = (0.61) +
Vol. Total = 2.59 m3 2.59 m3
II PEKERJAAN PONDASI
1 Pemasangan Pondasi Batu Belah 1SP : 6 PP
Panjang Lebar Tinggi Jumlah Sisi Jumlah Unit
Pondasi 1 = 64.30 x 0.55 x 0.60 x 1.00 x 1.00 = 21.22 m3
Pengurang
Silangan Pondasi 1 = 0.15 x 0.15 x 0.60 x 1.00 x 19.00 = (0.26) +
Vol. Total = 20.96 m3 20.96 m3
2 Pemasang Batu Kosong/Anstamping
Panjang Lebar Tinggi Jumlah Sisi Jumlah Unit
Pondasi 1 = 64.30 x 0.55 x 0.20 x 1.00 x 1.00 = 7.07 m3
Pengurang
Silangan Pondasi 1 = 0.15 x 0.15 x 0.20 x 1.00 x 19.00 = (0.09) +
Vol. Total = 6.99 m3 6.99 m3
VI PEKERJAAN PLESTERAN
1 Pemasangan Plesteran 1 SP : 6 PP Tebal 15 mm
Panjang Lebar Jumlah Sisi Jumlah Unit
Pagar = 2.70 x 0.35 x 2.00 x 15.00 = 28.35 m2
Taman = 9.90 x 0.40 x 2.00 x 1.00 = 7.92
= 9.90 x 0.15 x 1.00 x 1.00 = 1.49
= 8.70 x 0.20 x 2.00 x 1.00 = 3.48
Sloof = 2.70 x 0.20 x 2.00 x 16.00 = 17.28
Ring Balk = 2.70 x 0.20 x 2.00 x 16.00 = 17.28 +
Vol. Total = 75.79 m2 75.79 m2
2 Pemasangan 1 m2 Acian
Vol. Plesteran = 75.79 = 75.79 m2 75.79 m2
G PEKERJAAN GEDUNG C
I PEKERJAAN TANAH
1 Penggalian 1 m3 Tanah Biasa Sedalam s.d. 1 m
Pondasi 1 Panjang Lebar Tinggi Jml Sisi Jml Unit
A = 4.55 x 0.60 x 0.85 x 1.00 x 1.00 = 2.32 m3
B = 4.55 x 0.60 x 0.85 x 1.00 x 1.00 = 2.32
C = 4.55 x 0.60 x 0.85 x 1.00 x 1.00 = 2.32
D = 4.55 x 0.60 x 0.85 x 1.00 x 1.00 = 2.32
2 = 8.60 x 0.60 x 0.85 x 1.00 x 1.00 = 4.39
3 = 8.60 x 0.60 x 0.85 x 1.00 x 1.00 = 4.39
Pondasi 2
1 = 1.90 x 0.30 x 0.55 x 1.00 x 2.00 = 0.63
= 2.40 x 0.30 x 0.55 x 1.00 x 1.00 = 0.40
Pengurang
Silangan Pondasi 1 = 0.60 x 0.60 x 0.85 x 1.00 x 8.00 = (2.45) +
Vol. Total = 16.63 m3 16.63 m3
2 Pengurugan Kembali 1 m3 Galian Tanah
Vol. Galian Vol. Pasir Urug Vol. Aanstamping Vol. Pondasi
= 16.63 - 1.01 - 3.67 - 9.19 = 2.75 m3 2.75 m3
3 Pengurugan 1m3 Dengan Pasir Urug
Pondasi 1 Panjang Lebar Tinggi Jml Sisi Jml Unit
A = 4.55 x 0.60 x 0.05 x 1.00 x 1.00 = 0.14 m3
B = 4.55 x 0.60 x 0.05 x 1.00 x 1.00 = 0.14
C = 4.55 x 0.60 x 0.05 x 1.00 x 1.00 = 0.14
D = 4.55 x 0.60 x 0.05 x 1.00 x 1.00 = 0.14
2 = 8.60 x 0.60 x 0.05 x 1.00 x 1.00 = 0.26
3 = 8.60 x 0.60 x 0.05 x 1.00 x 1.00 = 0.26
Pondasi 2
1 = 1.90 x 0.30 x 0.05 x 1.00 x 2.00 = 0.06
= 2.40 x 0.30 x 0.05 x 1.00 x 1.00 = 0.04
Pengurang
Silangan Pondasi 1 = 0.60 x 0.60 x 0.05 x 1.00 x 8.00 = (0.14) +
Vol. Total = 1.01 m3 1.01 m3
II PEKERJAAN PONDASI
1 Pemasangan Pondasi Batu Belah 1SP : 6 PP
Pondasi 1 Panjang Lebar Tinggi Jml Sisi Jml Unit
A = 4.55 x 0.45 x 0.60 x 1.00 x 1.00 = 1.23 m3
B = 4.55 x 0.45 x 0.60 x 1.00 x 1.00 = 1.23
C = 4.55 x 0.45 x 0.60 x 1.00 x 1.00 = 1.23
D = 4.55 x 0.45 x 0.60 x 1.00 x 1.00 = 1.23
2 = 8.60 x 0.45 x 0.60 x 1.00 x 1.00 = 2.32
3 = 8.60 x 0.45 x 0.60 x 1.00 x 1.00 = 2.32
Pondasi 2
1 = 1.90 x 0.30 x 0.50 x 1.00 x 2.00 = 0.57
= 2.40 x 0.30 x 0.50 x 1.00 x 1.00 = 0.36
Pengurang
Silangan Pondasi 1 = 0.60 x 0.45 x 0.60 x 1.00 x 8.00 = (1.30) +
Vol. Total = 9.19 m3 9.19 m3
2 Pemasang Batu Kosong/Anstamping
Pondasi 1 Panjang Lebar Tinggi Jml Sisi Jml Unit
A = 4.55 x 0.60 x 0.20 x 1.00 x 1.00 = 0.55 m3
B = 4.55 x 0.60 x 0.20 x 1.00 x 1.00 = 0.55
C = 4.55 x 0.60 x 0.20 x 1.00 x 1.00 = 0.55
D = 4.55 x 0.60 x 0.20 x 1.00 x 1.00 = 0.55
2 = 8.60 x 0.60 x 0.20 x 1.00 x 1.00 = 1.03
3 = 8.60 x 0.60 x 0.20 x 1.00 x 1.00 = 1.03
Pengurang
Silangan Pondasi 1 = 0.60 x 0.60 x 0.20 x 1.00 x 8.00 = (0.58) +
Vol. Total = 3.67 m3 3.67 m3
Tulangan Utama Panjang Koefisien Jumlah Besi Jumlah Sisi Jumlah Unit
A = 4.20 x 0.89 x 6.00 x 1.00 x 1.00 = 22.37 Kg
B = 4.20 x 0.89 x 6.00 x 1.00 x 1.00 = 22.37
C = 4.20 x 0.89 x 6.00 x 1.00 x 1.00 = 22.37
D = 4.20 x 0.89 x 6.00 x 1.00 x 1.00 = 22.37
1 = 8.25 x 0.89 x 6.00 x 1.00 x 1.00 = 43.94
2 = 8.25 x 0.89 x 6.00 x 1.00 x 1.00 = 43.94
3 = 8.25 x 0.89 x 6.00 x 1.00 x 1.00 = 43.94
Tulangan Sengkang
A = 0.54 x 0.39 x 27.00 x 1.00 x 1.00 = 5.75
B = 0.54 x 0.39 x 27.00 x 1.00 x 1.00 = 5.75
C = 0.54 x 0.39 x 27.00 x 1.00 x 1.00 = 5.75
D = 0.54 x 0.39 x 27.00 x 1.00 x 1.00 = 5.75
1 = 0.54 x 0.39 x 54.00 x 1.00 x 1.00 = 11.51
2 = 0.54 x 0.39 x 54.00 x 1.00 x 1.00 = 11.51
3 = 0.54 x 0.39 x 54.00 x 1.00 x 1.00 = 11.51 +
Vol. Total = 278.85 Kg 278.85 Kg
- Pemasangan 1 m2 Bekisting untuk Sloof Beton Bangunan Gedung (volume dibagi 2 kali)
Panjang Lebar Jumlah Sisi Jumlah Unit
A = 4.10 x 0.20 x 2.00 x 1.00 = 1.64 m2
B = 4.10 x 0.20 x 2.00 x 1.00 = 1.64
C = 4.10 x 0.20 x 2.00 x 1.00 = 1.64
D = 4.10 x 0.20 x 2.00 x 1.00 = 1.64
1 = 8.15 x 0.20 x 2.00 x 1.00 = 3.26
2 = 8.15 x 0.20 x 2.00 x 1.00 = 3.26
3 = 8.15 x 0.20 x 2.00 x 1.00 = 3.26
Pengurang
Silangan Sloof = 0.15 x 0.20 x 2.00 x 24.00 = (1.44) +
Vol. Total = 14.90 m2
Dipakai 2 kali = 7.45 m2 7.45 m2
2 Kolom 15x15 cm
- Pembuatan 1 m3 Beton Mutu f’c = 14,5 Mpa (K175)
Panjang Lebar Tinggi Jumlah Sisi Jumlah Unit
= 0.15 x 0.15 x 3.55 x 1.00 x 4.00 = 0.32 m3
= 0.15 x 0.15 x 4.45 x 1.00 x 4.00 = 0.40
= 0.15 x 0.15 x 2.75 x 1.00 x 4.00 = 0.25 +
Vol. Total = 0.97 m3 0.97 m3
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip
Ø Ø Koefisien
Ø 12 = 12 x 12 x 0.006165 = 0.89 kg/m
Ø8 = 8 x 8 x 0.006165 = 0.39 kg/m
Tulangan Utama Panjang Koefisien Jumlah Besi Jumlah Sisi Jumlah Unit
2 = 2.45 x 0.89 x 6.00 x 1.00 x 2.00 = 26.10 Kg
= 2.95 x 0.89 x 6.00 x 1.00 x 1.00 = 15.71
3 = 2.45 x 0.89 x 6.00 x 1.00 x 2.00 = 26.10
= 2.95 x 0.89 x 6.00 x 1.00 x 1.00 = 15.71
Tulangan Sengkang
2 = 0.54 x 0.39 x 16.00 x 1.00 x 2.00 = 6.82
= 0.54 x 0.39 x 20.00 x 1.00 x 1.00 = 4.26
3 = 0.54 x 0.39 x 16.00 x 1.00 x 2.00 = 6.82
= 0.54 x 0.39 x 20.00 x 1.00 x 1.00 = 4.26 +
Vol. Total = 105.79 Kg 105.79 Kg
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali)
Panjang Lebar Jumlah Sisi Jumlah Unit
2 = 2.35 x 0.20 x 2.00 x 2.00 = 1.88 m2
= 2.85 x 0.20 x 2.00 x 1.00 = 1.14
3 = 2.35 x 0.20 x 2.00 x 2.00 = 1.88
= 2.85 x 0.20 x 2.00 x 1.00 = 1.14 +
Vol. Total = 6.04 m2
Dipakai 2 Kali = 3.02 m2 3.02 m2
4 Balok 15x30 cm
- Pembuatan 1 m3 Beton Mutu f’c = 14,5 Mpa (K175)
Panjang Lebar Tinggi Jumlah Sisi Jumlah Unit
A = 1.30 x 0.15 x 0.30 x 1.00 x 1.00 = 0.06 m3
B = 1.30 x 0.15 x 0.30 x 1.00 x 1.00 = 0.06
C = 1.30 x 0.15 x 0.30 x 1.00 x 1.00 = 0.06
D = 1.30 x 0.15 x 0.30 x 1.00 x 1.00 = 0.06
2 = 2.35 x 0.15 x 0.30 x 1.00 x 2.00 = 0.21
= 2.85 x 0.15 x 0.30 x 1.00 x 1.00 = 0.13 +
Vol. Total = 0.57 m3 0.57 m3
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip
Ø Ø Koefisien
Ø 12 = 12 x 12 x 0.006165 = 0.89 kg/m
Ø8 = 8 x 8 x 0.006165 = 0.39 kg/m
Tulangan Utama Panjang Koefisien Jumlah Besi Jumlah Sisi Jumlah Unit
A = 1.40 x 0.89 x 8.00 x 1.00 x 1.00 = 9.94 Kg
B = 1.40 x 0.89 x 8.00 x 1.00 x 1.00 = 9.94
C = 1.40 x 0.89 x 8.00 x 1.00 x 1.00 = 9.94
D = 1.40 x 0.89 x 8.00 x 1.00 x 1.00 = 9.94
2 = 2.45 x 0.89 x 8.00 x 1.00 x 2.00 = 34.80
= 2.95 x 0.89 x 8.00 x 1.00 x 1.00 = 20.95
Tulangan Sengkang
A = 0.80 x 0.39 x 9.00 x 1.00 x 1.00 = 2.84
B = 0.80 x 0.39 x 9.00 x 1.00 x 1.00 = 2.84
C = 0.80 x 0.39 x 9.00 x 1.00 x 1.00 = 2.84
D = 0.80 x 0.39 x 9.00 x 1.00 x 1.00 = 2.84
2 = 0.80 x 0.39 x 16.00 x 1.00 x 2.00 = 10.10
= 0.80 x 0.39 x 20.00 x 1.00 x 1.00 = 6.31 +
Vol. Total = 123.30 Kg 123.30 Kg
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali)
Panjang Lebar Jumlah Sisi Jumlah Unit
A = 1.30 x 0.30 x 2.00 x 1.00 = 0.78 m2
B = 1.30 x 0.30 x 2.00 x 1.00 = 0.78
C = 1.30 x 0.30 x 2.00 x 1.00 = 0.78
D = 1.30 x 0.30 x 2.00 x 1.00 = 0.78
2 = 2.35 x 0.30 x 2.00 x 2.00 = 2.82
= 2.85 x 0.30 x 2.00 x 1.00 = 1.71 +
Vol. Total = 7.65 m2
Dipakai 2 Kali = 3.82 m2 3.82 m2
5 Listplank Beton
- Pembuatan 1 m3 Beton Mutu f’c = 14,5 Mpa (K175)
Panjang Lebar Tinggi Jumlah Sisi Jumlah Unit
1 = 2.35 x 0.08 x 0.30 x 1.00 x 2.00 = 0.11 m3
= 2.85 x 0.08 x 0.30 x 1.00 x 1.00 = 0.07 +
Vol. Total = 0.18 m3 0.18 m3
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip
Ø Ø Koefisien
Ø 12 = 12 x 12 x 0.006165 = 0.89 kg/m
Ø8 = 8 x 8 x 0.006165 = 0.39 kg/m
Vertikal
Lajur Bawah Ø 10 - 250 = 1.70 x 0.62 x 11.00 x 1.00 x 2.00 = 23.06
Portal Ø 10 - 250 = 1.85 x 0.62 x 5.00 x 2.00 x 2.00 = 22.81
Lajur Atas Ø 10 - 125 = 1.70 x 0.62 x 7.00 x 2.00 x 2.00 = 29.35
Ekstra Ø 10 - 250 = 0.60 x 0.62 x 5.00 x 2.00 x 2.00 = 7.40
Tulangan Utama Ø 12
Ring Balk Elv. +3.30 Panjang Koefisien Jumlah Besi Jumlah Sisi Jumlah Unit
A = 2.45 x 0.89 x 4.00 x 1.00 x 1.00 = 8.70 Kg
B = 2.45 x 0.89 x 4.00 x 1.00 x 1.00 = 8.70
C = 2.45 x 0.89 x 4.00 x 1.00 x 1.00 = 8.70
D = 2.45 x 0.89 x 4.00 x 1.00 x 1.00 = 8.70
2 = 2.45 x 0.89 x 4.00 x 1.00 x 2.00 = 17.40
= 2.95 x 0.89 x 4.00 x 1.00 x 1.00 = 10.48
3 = 2.45 x 0.89 x 4.00 x 1.00 x 2.00 = 17.40
= 2.95 x 0.89 x 4.00 x 1.00 x 1.00 = 10.48
Ring Balk Elv. +4.20
2 = 2.45 x 0.89 x 4.00 x 1.00 x 2.00 = 17.40
= 2.95 x 0.89 x 4.00 x 1.00 x 1.00 = 10.48
Tulangan Utama Ø 10
Ring Balk Elv. +3.30
A = 2.45 x 0.62 x 2.00 x 1.00 x 1.00 = 3.02
B = 2.45 x 0.62 x 2.00 x 1.00 x 1.00 = 3.02
C = 2.45 x 0.62 x 2.00 x 1.00 x 1.00 = 3.02
D = 2.45 x 0.62 x 2.00 x 1.00 x 1.00 = 3.02
2 = 2.45 x 0.62 x 2.00 x 1.00 x 2.00 = 6.04
= 2.95 x 0.62 x 2.00 x 1.00 x 1.00 = 3.64
3 = 2.45 x 0.62 x 2.00 x 1.00 x 2.00 = 6.04
= 2.95 x 0.62 x 2.00 x 1.00 x 1.00 = 3.64
Ring Balk Elv. +4.20
2 = 2.45 x 0.62 x 2.00 x 1.00 x 2.00 = 6.04
= 2.95 x 0.62 x 2.00 x 1.00 x 1.00 = 3.64
Tulangan Sengkang
Ring Balk Elv. +3.30
A = 0.60 x 0.39 x 16.00 x 1.00 x 1.00 = 3.79
B = 0.60 x 0.39 x 16.00 x 1.00 x 1.00 = 3.79
C = 0.60 x 0.39 x 16.00 x 1.00 x 1.00 = 3.79
D = 0.60 x 0.39 x 16.00 x 1.00 x 1.00 = 3.79
2 = 0.60 x 0.39 x 16.00 x 1.00 x 2.00 = 7.58
= 0.60 x 0.39 x 20.00 x 1.00 x 1.00 = 4.73
3 = 0.60 x 0.39 x 16.00 x 1.00 x 2.00 = 7.58
= 0.60 x 0.39 x 20.00 x 1.00 x 1.00 = 4.73
Ring Balk Elv. +4.20
2 = 0.60 x 0.39 x 16.00 x 1.00 x 2.00 = 7.58
= 0.60 x 0.39 x 20.00 x 1.00 x 1.00 = 4.73 +
Vol. Total = 211.63 Kg 211.63 Kg
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali)
Ring Balk Elv. +3.30 Panjang Lebar Jumlah Sisi Jumlah Unit
A = 2.35 x 0.20 x 2.00 x 1.00 = 0.94 m2
B = 2.35 x 0.20 x 2.00 x 1.00 = 0.94
C = 2.35 x 0.20 x 2.00 x 1.00 = 0.94
D = 2.35 x 0.20 x 2.00 x 1.00 = 0.94
2 = 2.35 x 0.20 x 2.00 x 2.00 = 1.88
= 2.85 x 0.20 x 2.00 x 1.00 = 1.14
3 = 2.35 x 0.20 x 2.00 x 2.00 = 1.88
= 2.85 x 0.20 x 2.00 x 1.00 = 1.14
Ring Balk Elv. +4.20
2 = 2.35 x 0.20 x 2.00 x 2.00 = 1.88
= 2.85 x 0.20 x 2.00 x 1.00 = 1.14 +
Vol. Total = 12.82 m2
Dipakai 2 Kali = 6.41 m2 6.41 m2
VI PEKERJAAN PLESTERAN
1 Pemasangan Plesteran 1 SP : 6 PP Tebal 15 mm
Panjang Tinggi Jumlah Sisi Jumlah Unit
Kolom 1 = 0.15 x 3.55 x 2.00 x 3.00 = 3.20 m2
= 0.15 x 4.45 x 2.00 x 3.00 = 4.01
= 0.15 x 4.00 x 2.00 x 4.00 = 4.80
= 0.15 x 2.95 x 2.00 x 4.00 = 3.54
Balok Latei
2 = 2.35 x 0.20 x 2.00 x 2.00 = 1.88
= 2.85 x 0.20 x 2.00 x 1.00 = 1.14
3 = 2.35 x 0.20 x 2.00 x 2.00 = 1.88
= 2.85 x 0.20 x 2.00 x 1.00 = 1.14
Balok B1
A = 1.30 x 0.30 x 2.00 x 1.00 = 0.78
B = 1.30 x 0.30 x 2.00 x 1.00 = 0.78
C = 1.30 x 0.30 x 2.00 x 1.00 = 0.78
D = 1.30 x 0.30 x 2.00 x 1.00 = 0.78
2 = 2.35 x 0.30 x 2.00 x 2.00 = 2.82
= 2.85 x 0.30 x 2.00 x 1.00 = 1.71
Ring Balk
Ring Balk Elv. +3.30
A = 2.35 x 0.20 x 2.00 x 1.00 = 0.94
B = 2.35 x 0.20 x 2.00 x 1.00 = 0.94
C = 2.35 x 0.20 x 2.00 x 1.00 = 0.94
D = 2.35 x 0.20 x 2.00 x 1.00 = 0.94
2 = 2.35 x 0.20 x 2.00 x 2.00 = 1.88
= 2.85 x 0.20 x 2.00 x 1.00 = 1.14
3 = 2.35 x 0.20 x 2.00 x 2.00 = 1.88
= 2.85 x 0.20 x 2.00 x 1.00 = 1.14
Ring Balk Elv. +4.20
2 = 2.35 x 0.20 x 2.00 x 2.00 = 1.88
= 2.85 x 0.20 x 2.00 x 1.00 = 1.14
Vol. Pasangan Dinding = 70.86 x 2.00 = 141.71 +
Vol. Total = 183.76 m2 183.76 m2
2 Pemasangan 1 m2 Acian
Vol. Plesteran = 183.76 = 183.76 m2 183.76 m2
XI PEKERJAAN PENGECATAN
Pengecatan 1 m2 Tembok Baru (1 Lapis Plamuur, 1 Lapis Cat
1
Dasar, 2 Lapis Cat Penutup)
Vol. Acian = 183.76 = 183.76 m2 183.76 m2
5 Lampu LED Lampu Panel 18 Watt Square Slim Warm White Plafon
Jumlah
Kuning = 3.00 = 3.00 buah 3.00 buah
6 MCB 3P/ 32A Ex Schneider
Jumlah
= 1.00 = 1.00 buah 1.00 buah
BACK UP VOLUME
Kegiatan : PUSKESMAS BANJARMANGU 1 Kode Bangunan : A
Pekerjaan : PUSKESMAS BANJARMANGU 1 Nomor : 1
Nomor :
Sket / Gambar Perhitungan Volume Satuan
F PEKERJAAN GEDUNG B
I PEKERJAAN TANAH
1 Penggalian 1 m3 Tanah Biasa Sedalam s.d. 1 m
Pondasi 1 Panjang Lebar Tinggi Jml Sisi Jml Unit
A = 2.60 x 0.60 x 1.10 x 1.00 x 1.00 = 1.72 m3
B = 2.60 x 0.60 x 1.10 x 1.00 x 1.00 = 1.72
C = 2.60 x 0.60 x 1.10 x 1.00 x 1.00 = 1.72
D = 2.60 x 0.60 x 1.10 x 1.00 x 1.00 = 1.72
E = 2.10 x 0.60 x 1.10 x 1.00 x 1.00 = 1.39
F = 2.10 x 0.60 x 1.10 x 1.00 x 1.00 = 1.39
1 = 12.60 x 0.60 x 1.10 x 1.00 x 1.00 = 8.32
1 ke 2 = 4.25 x 0.60 x 1.10 x 1.00 x 1.00 = 2.81
2 = 9.60 x 0.60 x 1.10 x 1.00 x 1.00 = 6.34
Pondasi 2 = 1.60 x 0.30 x 0.40 x 1.00 x 1.00 = 0.19
Pengurang
Silangan Pondasi 1 = 0.60 x 0.60 x 1.10 x 1.00 x 12.00 = (4.75) +
Vol. Total = 22.53 m3 22.53 m3
2 Pengurugan Kembali 1 m3 Galian Tanah
Vol. Galian Vol. Pasir Urug Vol. Aanstamping Vol. Pondasi
= 22.53 - 1.04 - 4.06 - 9.87 = 7.57 m3 7.57 m3
3 Pengurugan 1m3 Dengan Pasir Urug
Pondasi 1 Panjang Lebar Tinggi Jml Sisi Jml Unit
A = 2.60 x 0.60 x 0.05 x 1.00 x 1.00 = 0.08 m3
B = 2.60 x 0.60 x 0.05 x 1.00 x 1.00 = 0.08
C = 2.60 x 0.60 x 0.05 x 1.00 x 1.00 = 0.08
D = 2.60 x 0.60 x 0.05 x 1.00 x 1.00 = 0.08
E = 2.10 x 0.60 x 0.05 x 1.00 x 1.00 = 0.06
F = 2.10 x 0.60 x 0.05 x 1.00 x 1.00 = 0.06
1 = 12.60 x 0.60 x 0.05 x 1.00 x 1.00 = 0.38
1 ke 2 = 4.25 x 0.60 x 0.05 x 1.00 x 1.00 = 0.13
2 = 9.60 x 0.60 x 0.05 x 1.00 x 1.00 = 0.29
Pondasi 2 = 1.60 x 0.30 x 0.05 x 1.00 x 1.00 = 0.02
Pengurang
Silangan Pondasi 1 = 0.60 x 0.60 x 0.05 x 1.00 x 12.00 = (0.22) +
Vol. Total = 1.04 m3 1.04 m3
II PEKERJAAN PONDASI
1 Pemasangan Pondasi Batu Belah 1SP : 6 PP
Pondasi 1 Panjang Lebar Tinggi Jml Sisi Jml Unit
A = 2.60 x 0.45 x 0.60 x 1.00 x 1.00 = 0.70 m3
B = 2.60 x 0.45 x 0.60 x 1.00 x 1.00 = 0.70
C = 2.60 x 0.45 x 0.60 x 1.00 x 1.00 = 0.70
D = 2.60 x 0.45 x 0.60 x 1.00 x 1.00 = 0.70
E = 2.10 x 0.45 x 0.60 x 1.00 x 1.00 = 0.57
F = 2.10 x 0.45 x 0.60 x 1.00 x 1.00 = 0.57
1 = 12.60 x 0.45 x 0.60 x 1.00 x 1.00 = 3.40
1 ke 2 = 4.25 x 0.45 x 0.60 x 1.00 x 1.00 = 1.15
2 = 9.60 x 0.45 x 0.60 x 1.00 x 1.00 = 2.59
Pondasi 2 = 1.60 x 0.30 x 0.50 x 1.00 x 1.00 = 0.24
Pengurang
Silangan Pondasi 1 = 0.45 x 0.45 x 0.60 x 1.00 x 12.00 = (1.46) +
Vol. Total = 9.87 m3 9.87 m3
2 Pemasang Batu Kosong/Anstamping
Pondasi 1 Panjang Lebar Tinggi Jml Sisi Jml Unit
A = 2.60 x 0.60 x 0.20 x 1.00 x 1.00 = 0.31 m3
B = 2.60 x 0.60 x 0.20 x 1.00 x 1.00 = 0.31
C = 2.60 x 0.60 x 0.20 x 1.00 x 1.00 = 0.31
D = 2.60 x 0.60 x 0.20 x 1.00 x 1.00 = 0.31
E = 2.10 x 0.60 x 0.20 x 1.00 x 1.00 = 0.25
F = 2.10 x 0.60 x 0.20 x 1.00 x 1.00 = 0.25
1 = 12.60 x 0.60 x 0.20 x 1.00 x 1.00 = 1.51
1 ke 2 = 4.25 x 0.60 x 0.20 x 1.00 x 1.00 = 0.51
2 = 9.60 x 0.60 x 0.20 x 1.00 x 1.00 = 1.15
Pengurang
Silangan Pondasi 1 = 0.60 x 0.60 x 0.20 x 1.00 x 12.00 = (0.86) +
Vol. Total = 4.06 m3 4.06 m3
Tulangan Utama Panjang Koefisien Jumlah Besi Jumlah Sisi Jumlah Unit
A = 2.10 x 0.89 x 6.00 x 1.00 x 1.00 = 11.19 Kg
= 2.10 x 0.89 x 6.00 x 1.00 x 1.00 = 11.19
B = 2.10 x 0.89 x 6.00 x 1.00 x 1.00 = 11.19
C = 2.10 x 0.89 x 6.00 x 1.00 x 1.00 = 11.19
D = 2.10 x 0.89 x 6.00 x 1.00 x 1.00 = 11.19
E = 1.60 x 0.89 x 6.00 x 1.00 x 1.00 = 8.52
F = 1.60 x 0.89 x 6.00 x 1.00 x 1.00 = 8.52
1 = 4.10 x 0.89 x 6.00 x 1.00 x 1.00 = 21.84
= 2.10 x 0.89 x 6.00 x 1.00 x 1.00 = 11.19
= 3.10 x 0.89 x 6.00 x 1.00 x 1.00 = 16.51
= 1.60 x 0.89 x 6.00 x 1.00 x 1.00 = 8.52
= 1.60 x 0.89 x 6.00 x 1.00 x 1.00 = 8.52
1 ke 2 = 1.60 x 0.89 x 6.00 x 1.00 x 1.00 = 8.52
= 1.60 x 0.89 x 6.00 x 1.00 x 1.00 = 8.52
= 0.95 x 0.89 x 6.00 x 1.00 x 1.00 = 5.06
2 = 4.10 x 0.89 x 6.00 x 1.00 x 1.00 = 21.84
= 2.10 x 0.89 x 6.00 x 1.00 x 1.00 = 11.19
= 3.10 x 0.89 x 6.00 x 1.00 x 1.00 = 16.51
Tulangan Sengkang
A = 0.54 x 0.39 x 13.00 x 1.00 x 1.00 = 2.77
= 0.54 x 0.39 x 13.00 x 1.00 x 1.00 = 2.77
B = 0.54 x 0.39 x 13.00 x 1.00 x 1.00 = 2.77
C = 0.54 x 0.39 x 13.00 x 1.00 x 1.00 = 2.77
D = 0.54 x 0.39 x 13.00 x 1.00 x 1.00 = 2.77
E = 0.54 x 0.39 x 10.00 x 1.00 x 1.00 = 2.13
F = 0.54 x 0.39 x 10.00 x 1.00 x 1.00 = 2.13
1 = 0.54 x 0.39 x 26.00 x 1.00 x 1.00 = 5.54
= 0.54 x 0.39 x 13.00 x 1.00 x 1.00 = 2.77
= 0.54 x 0.39 x 20.00 x 1.00 x 1.00 = 4.26
= 0.54 x 0.39 x 10.00 x 1.00 x 1.00 = 2.13
= 0.54 x 0.39 x 10.00 x 1.00 x 1.00 = 2.13
1 ke 2 = 0.54 x 0.39 x 10.00 x 1.00 x 1.00 = 2.13
= 0.54 x 0.39 x 10.00 x 1.00 x 1.00 = 2.13
= 0.54 x 0.39 x 5.00 x 1.00 x 1.00 = 1.07
2 = 0.54 x 0.39 x 26.00 x 1.00 x 1.00 = 5.54
= 0.54 x 0.39 x 13.00 x 1.00 x 1.00 = 2.77
= 0.54 x 0.39 x 20.00 x 1.00 x 1.00 = 4.26 +
Vol. Total = 264.04 Kg 264.04 Kg
- Pemasangan 1 m2 Bekisting untuk Sloof Beton Bangunan Gedung (volume dibagi 2 kali)
Panjang Lebar Jumlah Sisi Jumlah Unit
A = 1.85 x 0.20 x 2.00 x 1.00 = 0.74 m2
= 1.85 x 0.20 x 2.00 x 1.00 = 0.74
B = 1.85 x 0.20 x 2.00 x 1.00 = 0.74
C = 1.85 x 0.20 x 2.00 x 1.00 = 0.74
D = 1.85 x 0.20 x 2.00 x 1.00 = 0.74
E = 1.35 x 0.20 x 2.00 x 1.00 = 0.54
F = 1.35 x 0.20 x 2.00 x 1.00 = 0.54
1 = 3.85 x 0.20 x 2.00 x 1.00 = 1.54
= 1.85 x 0.20 x 2.00 x 1.00 = 0.74
= 2.85 x 0.20 x 2.00 x 1.00 = 1.14
= 1.35 x 0.20 x 2.00 x 1.00 = 0.54
= 1.35 x 0.20 x 2.00 x 1.00 = 0.54
1 ke 2 = 1.35 x 0.20 x 2.00 x 1.00 = 0.54
= 1.35 x 0.20 x 2.00 x 1.00 = 0.54
= 0.70 x 0.20 x 2.00 x 1.00 = 0.28
2 = 3.85 x 0.20 x 2.00 x 1.00 = 1.54
= 1.85 x 0.20 x 2.00 x 1.00 = 0.74
= 2.85 x 0.20 x 2.00 x 1.00 = 1.14 +
Vol. Total = 14.06 m2
Dipakai 2 Kali = 7.03 m2 7.03 m2
2 Kolom Praktis 15x15 cm
- Pembuatan 1 m3 Beton Mutu f’c = 14,5 Mpa (K175)
Panjang Lebar Tinggi Jumlah Sisi Jumlah Unit
= 0.15 x 0.15 x 3.40 x 1.00 x 13.00 = 0.99 m3 0.99 m3
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip
Ø Ø Koefisien
Ø 12 = 12 x 12 x 0.006165 = 0.89 kg/m
Ø8 = 8 x 8 x 0.006165 = 0.39 kg/m
Tulangan Utama Panjang Koefisien Jumlah Besi Jumlah Sisi Jumlah Unit
1 = 2.10 x 0.89 x 6.00 x 1.00 x 1.00 = 11.19 Kg
= 3.10 x 0.89 x 6.00 x 1.00 x 1.00 = 16.51
= 1.60 x 0.89 x 6.00 x 1.00 x 1.00 = 8.52
2 = 2.10 x 0.89 x 6.00 x 1.00 x 1.00 = 11.19
= 3.10 x 0.89 x 6.00 x 1.00 x 1.00 = 16.51
Tulangan Sengkang
1 = 0.54 x 0.39 x 13.00 x 1.00 x 1.00 = 2.77
= 0.54 x 0.39 x 20.00 x 1.00 x 1.00 = 4.26
= 0.54 x 0.39 x 10.00 x 1.00 x 1.00 = 2.13
2 = 0.54 x 0.39 x 13.00 x 1.00 x 1.00 = 2.77
= 0.54 x 0.39 x 20.00 x 1.00 x 1.00 = 4.26 +
Vol. Total = 80.11 Kg 80.11 Kg
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali)
Panjang Lebar Jumlah Sisi Jumlah Unit
1 = 1.85 x 0.20 x 2.00 x 1.00 = 0.74 m2
= 2.85 x 0.20 x 2.00 x 1.00 = 1.14
= 1.35 x 0.20 x 2.00 x 1.00 = 0.54
2 = 1.85 x 0.20 x 2.00 x 1.00 = 0.74
= 2.85 x 0.20 x 2.00 x 1.00 = 1.14 +
Vol. Total = 4.30 m2
Dipakai 2 Kali = 2.15 m2 2.15 m2
4 Ring Balk 15x20 cm
- Pembuatan 1 m3 Beton Mutu f’c = 14,5 Mpa (K175)
Grid Panjang Lebar Tinggi Jumlah Sisi Jumlah Unit
A = 2.00 x 0.15 x 0.20 x 1.00 x 1.00 = 0.06 m3
B = 2.00 x 0.15 x 0.20 x 1.00 x 1.00 = 0.06
C = 2.00 x 0.15 x 0.20 x 1.00 x 1.00 = 0.06
D = 2.00 x 0.15 x 0.20 x 1.00 x 1.00 = 0.06
E = 1.50 x 0.15 x 0.20 x 1.00 x 1.00 = 0.05
F = 1.50 x 0.15 x 0.20 x 1.00 x 1.00 = 0.05
1 = 4.00 x 0.15 x 0.20 x 1.00 x 1.00 = 0.12
= 2.00 x 0.15 x 0.20 x 1.00 x 1.00 = 0.06
= 3.00 x 0.15 x 0.20 x 1.00 x 1.00 = 0.09
= 1.50 x 0.15 x 0.20 x 1.00 x 1.00 = 0.05
1 ke 2 = 1.50 x 0.15 x 0.20 x 1.00 x 1.00 = 0.05
= 0.85 x 0.15 x 0.20 x 1.00 x 1.00 = 0.03
2 = 4.00 x 0.15 x 0.20 x 1.00 x 1.00 = 0.12
= 2.00 x 0.15 x 0.20 x 1.00 x 1.00 = 0.06
= 3.00 x 0.15 x 0.20 x 1.00 x 1.00 = 0.09
Pengurang
Kolom 1 = 0.15 x 0.15 x 0.20 x 1.00 x 15.00 = (0.07) +
Vol. Total = 0.92 m3 0.92 m3
- Penulangan 1 kg dengan Besi Polos atau Besi Sirip
Ø Ø Koefisien
Ø 12 = 12 x 12 x 0.006165 = 0.89 kg/m
Ø8 = 8 x 8 x 0.006165 = 0.39 kg/m
Tulangan Utama Panjang Koefisien Jumlah Besi Jumlah Sisi Jumlah Unit
A = 2.10 x 0.89 x 6.00 x 1.00 x 1.00 = 11.19 Kg
B = 2.10 x 0.89 x 6.00 x 1.00 x 1.00 = 11.19
C = 2.10 x 0.89 x 6.00 x 1.00 x 1.00 = 11.19
D = 2.10 x 0.89 x 6.00 x 1.00 x 1.00 = 11.19
E = 1.60 x 0.89 x 6.00 x 1.00 x 1.00 = 8.52
F = 1.60 x 0.89 x 6.00 x 1.00 x 1.00 = 8.52
1 = 4.10 x 0.89 x 6.00 x 1.00 x 1.00 = 21.84
= 2.10 x 0.89 x 6.00 x 1.00 x 1.00 = 11.19
= 3.10 x 0.89 x 6.00 x 1.00 x 1.00 = 16.51
= 1.60 x 0.89 x 6.00 x 1.00 x 1.00 = 8.52
1 ke 2 = 1.60 x 0.89 x 6.00 x 1.00 x 1.00 = 8.52
= 0.95 x 0.89 x 6.00 x 1.00 x 1.00 = 5.06
2 = 4.10 x 0.89 x 6.00 x 1.00 x 1.00 = 21.84
= 2.10 x 0.89 x 6.00 x 1.00 x 1.00 = 11.19
= 3.10 x 0.89 x 6.00 x 1.00 x 1.00 = 16.51
Tulangan Sengkang
A = 0.60 x 0.39 x 13.00 x 1.00 x 1.00 = 3.08
B = 0.60 x 0.39 x 13.00 x 1.00 x 1.00 = 3.08
C = 0.60 x 0.39 x 13.00 x 1.00 x 1.00 = 3.08
D = 0.60 x 0.39 x 13.00 x 1.00 x 1.00 = 3.08
E = 0.60 x 0.39 x 10.00 x 1.00 x 1.00 = 2.37
F = 0.60 x 0.39 x 10.00 x 1.00 x 1.00 = 2.37
1 = 0.60 x 0.39 x 26.00 x 1.00 x 1.00 = 6.16
= 0.60 x 0.39 x 13.00 x 1.00 x 1.00 = 3.08
= 0.60 x 0.39 x 20.00 x 1.00 x 1.00 = 4.73
= 0.60 x 0.39 x 10.00 x 1.00 x 1.00 = 2.37
1 ke 2 = 0.60 x 0.39 x 10.00 x 1.00 x 1.00 = 2.37
= 0.60 x 0.39 x 5.00 x 1.00 x 1.00 = 1.18
2 = 0.60 x 0.39 x 26.00 x 1.00 x 1.00 = 6.16
= 0.60 x 0.39 x 13.00 x 1.00 x 1.00 = 3.08
= 0.60 x 0.39 x 20.00 x 1.00 x 1.00 = 4.73 +
Vol. Total = 233.87 Kg 233.87 Kg
- Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (volume dibagi 2 kali)
Panjang Lebar Jumlah Sisi Jumlah Unit
A = 1.85 x 0.20 x 2.00 x 1.00 = 0.74 m2
B = 1.85 x 0.20 x 2.00 x 1.00 = 0.74
C = 1.85 x 0.20 x 2.00 x 1.00 = 0.74
D = 1.85 x 0.20 x 2.00 x 1.00 = 0.74
E = 1.35 x 0.20 x 2.00 x 1.00 = 0.54
F = 1.35 x 0.20 x 2.00 x 1.00 = 0.54
1.00 = 3.85 x 0.20 x 2.00 x 1.00 = 1.54
= 1.85 x 0.20 x 2.00 x 1.00 = 0.74
= 2.85 x 0.20 x 2.00 x 1.00 = 1.14
= 1.35 x 0.20 x 2.00 x 1.00 = 0.54
1 ke 2 = 1.35 x 0.20 x 2.00 x 1.00 = 0.54
= 0.70 x 0.20 x 2.00 x 1.00 = 0.28
2.00 = 3.85 x 0.20 x 2.00 x 1.00 = 1.54
= 1.85 x 0.20 x 2.00 x 1.00 = 0.74
= 2.85 x 0.20 x 2.00 x 1.00 = 1.14 +
Vol. Total = 12.24 m2
Dipakai 2 Kali = 6.12 m2 6.12 m2
IV PEKERJAAN BESI & ALUMUNIUM
Pemasangan 1 m2 Rangka Besi Hollow Galvanis 40.40 mm, Modul 60 x
1
60 cm, untuk Plafon
Panjang Lebar Jumlah Sisi Jumlah Unit
Laundry = 1.85 x 1.85 x 1.00 x 1.00 = 3.42 m2
Dapur = 2.85 x 1.85 x 1.00 x 1.00 = 5.27
Selasar = 13.00 x 1.85 x 1.00 x 1.00 = 24.05
= 2.30 x 9.60 x 1.00 x 1.00 = 22.08
= 4.18 x 2.10 x 1.00 x 1.00 = 8.77 +
Vol. Total = 63.59 m2 63.59 m2
2 Pemasangan 1 m2 Kanopy Rangka Atap Hollow Galvanis + Assesoris
Panjang Lebar Jumlah Sisi Jumlah Unit
= 11.60 x 4.20 x 1.00 x 1.00 = 48.72 m2
= 3.82 x 1.40 x 1.00 x 1.00 = 5.35
= 2.30 x 9.60 x 1.00 x 1.00 = 22.08
= 4.18 x 2.10 x 1.00 x 1.00 = 8.77 +
Vol. Total = 84.92 m2 84.92 m2
3 Pemasangan 1 m' talang galvalum 30x30 cm, rangka hollow galvanis 3.5/3.5 cm, Jarak Rangka 60cm
Panjang Jumlah
= 11.60 x 1.00 = 11.60 m1
= 10.15 x 1.00 = 10.15
= 2.65 x 1.00 = 2.65
= 4.10 x 1.00 = 4.10 +
Vol. Total = 28.50 m1 28.50 m1
4 Pemasangan 1 m Kusen Aluminium
Panjang Jumlah Sisi Jumlah Unit
Pintu 1 = 2.60 x 2.00 x 2.00 = 10.40 m1
= 0.80 x 2.00 x 2.00 = 3.20
Pintu 2 = 2.05 x 2.00 x 1.00 = 4.10
= 0.80 x 1.00 x 1.00 = 0.80
Jendela 1 = 1.70 x 3.00 x 2.00 = 10.20
= 0.60 x 6.00 x 2.00 = 7.20 +
Vol. Total = 35.90 m1 35.90 m1
5 Pemasangan Pintu Kaca Rangka Allumunium
Panjang Lebar Jumlah Unit
Pintu 1 = 2.00 x 0.80 x 2.00 = 3.20 m2
Pintu 2 = 2.00 x 0.80 x 1.00 = 1.60 +
Vol. Total = 4.80 m2 4.80 m2
6 Pemasangan Jendela Kaca Rangka Allumunium
Panjang Lebar Jumlah Sisi Jumlah Unit
Jendela 1 = 1.05 x 0.60 x 2.00 x 2.00 = 2.52 m2
= 0.50 x 0.60 x 2.00 x 2.00 = 1.20 +
Vol. Total = 3.72 m2 3.72 m2
7 Pasang Wenfire (Bahan Plat Galvalum)
Panjang
= 25.95 = 25.95 m1 25.95 m1
VI PEKERJAAN PLESTERAN
1 Pemasangan Plesteran 1 SP : 6 PP Tebal 15 mm
Panjang Tinggi Jumlah Sisi Jumlah Unit
Kolom 1 = 0.15 x 0.75 x 2.00 x 2.00 = 0.45 m2
= 0.15 x 3.40 x 2.00 x 3.00 = 3.06
= 0.15 x 3.00 x 2.00 x 6.00 = 5.40
Balok Latei = 11.50 x 0.20 x 2.00 x 1.00 = 4.60
Ring Balk = 32.85 x 0.20 x 2.00 x 1.00 = 13.14
Openingan Pintu 1 = 0.90 x 0.15 x 1.00 x 2.00 = 0.27
= 2.60 x 0.15 x 2.00 x 2.00 = 1.56
Openingan Pintu 2 = 0.90 x 0.15 x 1.00 x 1.00 = 0.14
= 2.05 x 0.15 x 2.00 x 1.00 = 0.61
Openingan Jendela = 1.35 x 0.15 x 2.00 x 2.00 = 0.81
= 1.70 x 0.15 x 2.00 x 2.00 = 1.02
Vol. Pasangan Dinding = 44.98 x 2.00 = 89.96 +
Vol. Total = 121.02 m2 121.02 m2
2 Pemasangan 1 m2 Acian
Vol. Plesteran = 121.02 = 121.02 m2 121.02 m2
XI PEKERJAAN PENGECATAN
Pengecatan 1 m2 Tembok Baru (1 Lapis Plamuur, 1 Lapis Cat
1
Dasar, 2 Lapis Cat Penutup)
Vol. Acian = 121.02 = 121.02 m2 121.02 m2
5 Lampu LED Lampu Panel 18 Watt Square Slim Warm White Plafon
Jumlah
Kuning = 3.00 = 3.00 buah 3.00 buah
6 MCB 3P/ 32A Ex Schneider
Jumlah
= 1.00 = 1.00 buah 1.00 buah
3 Pemasangan 1 buah Meja (bak cuci stainlessteel + Kran Air+ Kramik + Asesories sesusaikan dengan gambar)
Jumlah
Ruang Dapur = 1.00 = 1.00 buah
Pojok Dahag = 1.00 = 1.00 +
Vol. Total = 2.00 buah 2.00 buah
4 Pemasangan 1 buah Wastafel + Pedestal + Asesories + Kran Air Stainless steel
Jumlah
Ruang Dapur = 1.00 = 1.00 buah 1.00 buah
BACK UP VOLUME
Kegiatan : PUSKESMAS BANJARMANGU 1 Kode Bangunan : A
Pekerjaan : PUSKESMAS BANJARMANGU 1 Nomor : 1
Nomor :
Sket / Gambar Perhitungan Volume Satuan
II PEKERJAAN PONDASI
1 Pemasangan Pondasi Batu Belah 1SP : 6 PP
Panjang Lebar Tinggi Jumlah Sisi
Koperan Talud = 56.40 x 0.60 x 0.70 x 1.00 = 23.69 m3
Dinding Talud = 56.40 x 0.60 x 0.65 x 1.00 = 22.00
Lantai Saluran = 56.40 x 0.80 x 0.20 x 1.00 = 9.02
= 56.40 x 0.50 x 0.20 x 2.00 = 11.28 +
Vol. Total = 65.99 m3 65.99 m3
IV PEKERJAAN PLESTERAN
1 Pemasangan Plesteran 1 SP : 6 PP Tebal 15 mm
Panjang Lebar Jumlah Sisi
Lantai Saluran = 56.40 x 0.40 x 1.00 = 22.56 m2
Dinding Saluran = 56.40 x 0.70 x 2.00 = 78.96 +
Vol. Total = 101.52 m2 101.52 m2
2 Pemasangan Finishing Siar Pas.Batu Kali Adukan 1Pc : 2Pp
Panjang Lebar Jumlah Sisi
Dinding Talud = 56.40 x 0.65 x 1.00 = 36.66 m2 36.66 m2
3 Pemasangan 1 m2 Acian
Panjang Lebar Jumlah Sisi
Lantai Saluran = 56.40 x 0.40 x 1.00 = 22.56 m2
Dinding Saluran = 56.40 x 0.70 x 2.00 = 78.96 +
Vol. Total = 101.52 m2 101.52 m2
DAFTAR UPAH PEKERJA
KECAMATAN : BANJARNEGARA
HARGA
NO. JENIS BAHAN SATUAN KET.
(Rp)
1 Pekerja OH 78,320
2 Mandor OH 91,000
10 T u k a n g c a t OH 81,550
11 K e p . t k . c a t OH 91,000
12 T u k a n g p l i t u r OH 81,550
13 T u k a n g j a l a n OH 81,550
14 T u k a n g g a l i OH 81,550
16 T k . l e i d e n g OH 81,550
17 M a s i n i s OH 81,550
18 P e m b . M a s i n i s OH 73,850
19 P e n j a g a a p i OH 81,550
20 P e n j a g a m a l a m OH 81,550
21 Sopir OH 73,850
HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)
I BAHAN DASAR
1 BATU KALI Bulat Utuh m3 214,285.71 *
Bulat Belah *
Pecah 10/15 m3 246,428.57 *
Pecah 5/7 m3 286,000.00 *
Pecah 3/5 m3 291,000.00
2 KERIKIL Sirtu m3 214,285.71
Beton 0,5/1 m3 238,000.00
Beton ,1/2 m3 314,285.71
Beton ,2/3 m3 296,666.67
Biasa m3
3 BATU BATA ex lokal bh 900.00
5 ASBES GELOMBANG
. 180 cm X 80 cm X 5 mm lbr 35,500.00 Djabesmen
. 210 cm X 80 cm X 5 mm lbr 41,500.00 Djabesmen
. 240 cm X 80 cm X 5 mm lbr 47,400.00 Djabesmen
. 300 cm X 80 cm X 5 mm lbr 63,000.00 Djabesmen
Asbes Gelombang Kecil
. 150 cm X 105 cm X 4 mm lbr 44,800.00 Djabesmen
. 180 cm X 105 cm X 4 mm lbr 53,300.00 Djabesmen
. 210 cm X 105 cm X 4 mm lbr 62,250.00 Djabesmen
. 240 cm X 105 cm X 4 mm lbr 71,200.00 Djabesmen
. 270 cm X 105 cm X 4 mm lbr 81,500.00 Djabesmen
. 300 cm X 105 cm X 4 mm lbr 95,000.00 Djabesmen
HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)
6 ASBES PLAT
. 100cm X 100 cm X 2,7 mm bh 14,000.00 Karsirata
8 SENG PLAT
BJLS 0,20 lebar 55 cm m' 23,000.00 Fumira
BJLS 0,30 lebar 55 cm m' 29,000.00
9 SENG GELOMBANG
BJLS 0,2 panjang 180 cm lbr 65,000.00 Fumira
BJLS 0,20 panjang 210 cm lbr 75,900.00 Fumira
BJLS 0,20 panjang 240 cm lbr 86,700.00 Fumira
BJLS 0,20 panjang 300 cm lbr 108,400.00 Fumira
III . B A H A N K A Y U
1 JATI Papan m3 Ö
Balok/pesagen m3 Ö
4 MERANTI Papan m3 Ö
Balok/pesagen m3 Ö
7 Parquet Jati m2
8 Batu Paros m2
10 Keramik Homogen 40 x 40 cm m2
30 x 30 cm m2
11 Marmer m2 Ö
HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)
V.BAHAN CETAK
1 BUIS BETON Ø 10 cm - 100 cm bh 24,790.00
Ø 20 cm - 100 cm bh 47,190.00
Ø 30 cm - 100 cm bh 83,960.00
Ø 50 cm - 100 cm bh 99,660.00
Ø 60 cm - 100 cm bh 115,450.00
Ø 70 cm - 100 cm bh 164,870.00
U 10 cm - 100 cm bh 15,450.00
U 15 cm - 100 cm bh 20,000.00
U 20 cm - 100 cm bh 27,270.00
U 30 cm - 100 cm bh 41,980.00
VI . B A H A N B E S I
1 BESI BETON besi beton polos kg 12,600.00
besi beton ulir kg 12,600.00
VII . B A H A N P I P A
1 Pipa PVC SII SCJ , S - 12,5 (10 bar)
Pipa PVC DN 20 ( ½" ) AW JIS m1
Pipa PVC DN 25 ( ¾" ) AW JIS m1
Pipa PVC DN 32 ( 1" ) AW JIS m1
Pipa PVC DN 40 ( 1½" ) m1
Pipa PVC DN 63 ( 2" ) m1
Pipa PVC DN 90 ( 3" ) m1
Pipa PVC DN 110 ( 4" ) m1
Pipa PVC DN 160 ( 6" ) m1
Pipa PVC DN 200 ( 8" ) m1
3 Pipa PVC AW
Pipa PVC AW 1/2" m1 7,125.00 Rucika
Pipa PVC AW 3/4" m1 9,625.00 Rucika
Pipa PVC AW 1" m1 13,125.00 Rucika
Pipa PVC AW 1 1/4" m1 19,500.00 Rucika
Pipa PVC D 1 1/2" m1 13,750.00 Rucika
Pipa PVC D 2" m1 17,750.00 Rucika
Pipa PVC D 2 1/2" m1 24,000.00 Rucika
Pipa PVC D 3" m1 31,750.00 Rucika
Pipa PVC D 4" m1 50,000.00 Rucika
\
VIII . B A H A N L A N G I T - L A N G I T
1 AKUSTIK-uk : 60 X 60 lbr 135,000.00
60 X 120 lbr 125,000.00
List Kayu Profil m' 10,000.00
2 SOFT BOARD-uk: 4'X 8'
Gypsum tebal 9 mm lbr 65,000.00 jayaboard
3 HARD BOARD-uk: 4'X 8'
Indostar Board tebal 4 mm lbr 58,000.00 GRC
Nusaboard tebal 4 mm lbr 41,000.00 3,5 MM
4 PLY WOOD
Teak wood
90 X 210 X 3 mm lbr 83,000.00
. 120 X 240 X 3 mm lbr 94,000.00
. 90 X 210 X 4 mm lbr
. 90 X 210 X 9 mm lbr
. 90 X 210 X 12 mm lbr
. 90 X 210 X 15 mm lbr
. 90 X 210 X 18 mm lbr 365,000.00 120 X 240
Tripleks
. 120 X 240 X 3 mm lbr 45,000.00
. 120 X 240 X 4 mm lbr 60,000.00
. 120 X 240 X 6 mm lbr 75,000.00
. 120 X 240 X 8 mm lbr 100,000.00
Multipleks
. 120 X 240 X 9 mm lbr 114,000.00
. 120 X 240 X 12 mm lbr 150,000.00
. 120 X 240 X 15 mm lbr 186,000.00
. 120 X 240 X 18 mm lbr 225,000.00
Formika ukuran pintu lbr 75,000.00
IX . B A H A N F I N I S H I N G
1 KAYU
Menie kg 35,800.00 ALTEC
Dempul plamur kg 35,800.00 ALTEC
Ambril/amplas lbr 5,500.00 -
Lem Kayu kg 20,500.00 FOX
. Avian kg 59,800.00 -
. Spiritus ltr - -
. Plitur jadi ltr 61,000.00 SUNFLOWER
2 TEMBOK
Plamur kg 36,300.00
Cat Tembok (Decolith) kg 30,383.09
Catylac 5 kg 137,000.00
Mowilex/Dulux/Jotun 5 kg
3 BESI
Menie kg 35,800.00
Cat mengkilat kg 62,000.00
Cat kg
Thinner A ltr 29,650.00
Minyak cat ltr -
Residu (teer/aspal) kg 56,803.17
Kuas Cat bh 19,000.00
Rol Kuas bh 35,000.00
HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)
X.BAHAN KACA
1 POLOS 3 mm m2 82,000.00
5 mm m2 123,000.00
2 ES KABUR 3 mm m2 100,000.00
5 mm m2 150,000.00
1 KABEL LISTRIK
NYA : . 1 X 1 1/2 mm2 m' 2,760.00 Kitani
SPLN LMK 1 X 2 1/2 mm2 m' 4,420.00 Kitani
NYM :. 2 X 1 1/2 mm2 m' 7,500.00 Kitani
PRIMA 2 X 2 1/2 mm2 m' 11,800.00 Kitani
3 X 1 1/2 mm2 m' 10,480.00 Kitani
3 X 2 1/2 mm2 m' 14,660.00 Kitani
2 SKAKELAR
Out bauw . Seri bh 15,000.00 Broco
. Engkel bh 11,000.00 Broco
In bauw . Seri bh 14,500.00 Broco
. Engkel bh 12,000.00 Broco
XV . POMPA AIR.
2 POMPA AIR LISTRIK
Sanyo 125 Watt ( non otomatis ) bh 450,000.00
Fuji 250 watt bh
Shimizu 125 Watt ( non otomatis ) bh 422,000.00
. 90 watt bh
Dab . 125 watt bh 435,000.00
. 175 watt bh 525,000.00
10 K A C A
Cermin tebal 5 mm m2 235,000.00
0.07
0.05
4.00
1,000,000.00 0.01 71.43
1.00
DEPOToko DEPOsandoz ud subur UD ANUGRAH mega baja ingin jaya Langgeng MAX
- -
- -
- -
### ### - -
### - -
- -
### - -
- -
### - -
- -
- -
### ### ### - -
### ### - -
### ### - -
### ### - -
- -
- -
- -
Bangkirai - -
### balok 6/15 - -
### Papan 4/25 - -
### - -
- -
Kamper Medan - -
### Balok 6/15 - -
- -
- -
### - -
### - -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
#DIV/0!
#DIV/0!
#DIV/0!
### ### #DIV/0!
- #DIV/0!
### ### #DIV/0!
### ### #DIV/0!
### #DIV/0!
### ### #DIV/0!
### ### #DIV/0!
### #DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
DEPOToko DEPOsandoz ud subur UD ANUGRAH mega baja ingin jaya Langgeng MAX
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
### #DIV/0!
#DIV/0!
#DIV/0!
besi 8 ### 10,713.73 9,754.86 9,727.17 11,660.23 10,464.00
Besi ### #DIV/0!
besi ### #DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
### #DIV/0!
### #DIV/0!
### #DIV/0!
### #DIV/0!
### #DIV/0!
### #DIV/0!
### 11,660.23 11,660.23
### 1,665.75 1,665.75
- #DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
### ### #DIV/0!
#DIV/0!
### #DIV/0!
### #DIV/0!
### #DIV/0!
### #DIV/0!
### #DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
DEPOToko DEPOsandoz ud subur UD ANUGRAH mega baja ingin jaya Langgeng MAX
#DIV/0!
#DIV/0!
### ### ### #DIV/0!
### ### ### #DIV/0!
### ### ### #DIV/0!
### ### ### #DIV/0!
### ### ### #DIV/0!
### ### ### #DIV/0!
### ### ### #DIV/0!
### ### ### #DIV/0!
### ### ### #DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
### ### #DIV/0!
#DIV/0!
### #DIV/0!
### #DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
### #DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
### #DIV/0!
#DIV/0!
### ### ### #DIV/0!
### ### ### 60,000.00 60,000.00
### ### ### 75,000.00 75,000.00
### ### ### 100,000.00 100,000.00
#DIV/0!
### ### ### #DIV/0!
### ### ### 150,000.00 150,000.00
### ### ### #DIV/0!
### ### ### #DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
### ### ### 10,401.02 10,401.02
### ### ### 10,259.28 10,259.28
### 24000 ### 8,619.73 8,619.73
### ### ### 10,861.92 10,861.92
### ### ### #DIV/0!
### ### - 10,035.49 10,035.49
### ### ### #DIV/0!
#DIV/0!
#DIV/0!
### ### ### #DIV/0!
### ### ### #DIV/0!
### ### ### #DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
### ### ### #DIV/0!
### ### #DIV/0!
#DIV/0!
### ### #DIV/0!
### - #DIV/0!
### ### #DIV/0!
### ### ### #DIV/0!
### #DIV/0!
#DIV/0!
DEPOToko DEPOsandoz ud subur UD ANUGRAH mega baja ingin jaya Langgeng MAX
#DIV/0!
### #DIV/0!
### #DIV/0!
#DIV/0!
### #DIV/0!
### #DIV/0!
#DIV/0!
### #DIV/0!
### #DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
### #DIV/0!
### #DIV/0!
### #DIV/0!
### #DIV/0!
### #DIV/0!
### #DIV/0!
#DIV/0!
#DIV/0!
### #DIV/0!
### #DIV/0!
### #DIV/0!
### #DIV/0!
#DIV/0!
### #DIV/0!
### #DIV/0!
### #DIV/0!
### #DIV/0!
#DIV/0!
### #DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
### ### #DIV/0!
### ### #DIV/0!
#DIV/0!
#DIV/0!
### ### #DIV/0!
### ### #DIV/0!
### ### #DIV/0!
### #DIV/0!
#DIV/0!
#DIV/0!
### #DIV/0!
### #DIV/0!
#DIV/0!
### ### ### #DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
### 35000 ( japex 1/2 #DIV/0!
### ### #DIV/0!
### #DIV/0!
#DIV/0!
### ### #DIV/0!
### ### #DIV/0!
#DIV/0!
DEPOToko DEPOsandoz ud subur UD ANUGRAH mega baja ingin jaya Langgeng MAX
#DIV/0!
### ### 18,500.00 18,500.00
### ### #DIV/0!
### ### #DIV/0!
### ### #DIV/0!
### ### ### #DIV/0!
### #DIV/0!
### #DIV/0!
### #DIV/0!
### #DIV/0!
### #DIV/0!
### #DIV/0!
### #DIV/0!
### #DIV/0!
### #DIV/0!
#DIV/0!
#DIV/0!
### #DIV/0!
### #DIV/0!
### ### #DIV/0!
### #DIV/0!
### ### #DIV/0!
### #DIV/0!
### ### #DIV/0!
### #DIV/0!
### ### #DIV/0!
### #DIV/0!
### #DIV/0!
#DIV/0!
### ### #DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
### ### #DIV/0!
#DIV/0!
### ### #DIV/0!
#DIV/0!
### #DIV/0!
### #DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
DEPOToko DEPOsandoz ud subur UD ANUGRAH mega baja ingin jaya Langgeng MAX
#DIV/0!
#DIV/0!
#DIV/0!
### #DIV/0!
### #DIV/0!
### #DIV/0!
#DIV/0!
#DIV/0!
### #DIV/0!
#DIV/0!
### #DIV/0!
### #DIV/0!
### #DIV/0!
#DIV/0!
#DIV/0!
### #DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
DEPOToko DEPOsandoz ud subur UD ANUGRAH mega baja ingin jaya Langgeng MAX
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
HARGA HARGA
(Rp) (Rp)
2,017.00 2,019.00
1.00 150,000.00 165,000.00 -
1.00 150,000.00 165,000.00 339,000.00
1.00 165,000.00 181,500.00 433,000.00
- 200,000.00 220,000.00 447,181.82
- 218,000.00 239,800.00 425,818.18
1.00 150,000.00 165,000.00 432,181.82
- 256,000.00 281,600.00 577,363.64
1.00 240,000.00 264,000.00 541,545.45
1.00 225,000.00 247,500.00 458,181.82
1.00 225,000.00 247,500.00 458,181.82
- 725.00 797.50 1,029.55
1.00 -
1.00 150,000.00 165,000.00 411,636.36
1.00 184,200.00 202,620.00 666,727.27
1.00 202,600.00 222,860.00 679,818.18
- 165,000.00 181,500.00 406,272.73
1.00 165,000.00 181,500.00 -
- 250,000.00 275,000.00 167,272.73
1.00 -
1.00 64,000.00 70,400.00 136,363.64
- 113,200.00 124,520.00 124,909.09
- 2,830.00 3,113.00 124,909.09
1.00 -
1.00 -
1.00 -
1.00 - - -
1.00 -
- 8,000.00 8,800.00 8,090.91
- 9,000.00 9,900.00 9,545.45
1.00 -
1.00 1,080.00 1,188.00 1,090.91
- 2,200.00 2,420.00 2,718.18
- 2,500.00 2,750.00 3,072.73
- 4,200.00 4,620.00 4,254.55
- 4,300.00 4,730.00 4,363.64
- 5,000.00 5,500.00 7,090.91
- 5,000.00 5,500.00 7,090.91
1.00 -
- 13,000.00 14,300.00 13,000.00
- 11,000.00 12,100.00 11,000.00
1.00 -
1.00 -
- 44,200.00 48,620.00 44,672.73
- 55,600.00 61,160.00 56,181.82
- 1.02 64,000.00 70,400.00 64,727.27
- 0.92 81,800.00 89,980.00 83,618.18
1.00 -
- 30,250.00 33,275.00 -
- 33,000.00 36,300.00 -
- 38,500.00 42,350.00 -
- 44,000.00 48,400.00 -
- 49,500.00 54,450.00 -
- 1.05 66,000.00 72,600.00 -
HARGA HARGA
(Rp) (Rp)
1.00 -
1.00 -
- 35,950.00 39,545.00 39,545.45
- 42,970.00 47,267.00 47,272.73
1.00 -
1.00 -
- 12,500.00 13,750.00 -
1.00 -
- 26,030.00 28,633.00 28,636.36
- 28,920.00 31,812.00 28,920.00
1.00 -
- 46,000.00 50,600.00 66,027.27
- 53,000.00 58,300.00 -
- 61,000.00 67,100.00 -
- 76,000.00 83,600.00 -
1.00 -
1.00 - - -
1.00 - - -
1.00 -
- 8,400,000.00 9,240,000.00 -
- 8,000,000.00 8,800,000.00 -
1.00 -
- 8,269,690.00 9,096,659.00 9,096,663.64
- 7,613,090.00 8,374,399.00 8,374,402.73
1.00 -
1.00 6,500,000.00 7,150,000.00 -
1.00 6,000,000.00 6,600,000.00 -
1.00 -
- 1,500,000.00 1,650,000.00 3,204,545.45
- 1,715,000.00 1,886,500.00 2,649,350.65
1.00 - -
- 15,539,050.00 17,092,955.00 17,092,963.64
- 13,977,140.00 15,374,854.00 15,374,863.64
1.00 -
1.00 2,913,220.00 3,204,542.00 -
1.00 123,960.00 136,356.00 235,909.09
- 13,460.00 14,806.00 14,809.09
1.00 -
1.00 -
- 4,000.00 4,400.00 -
#DIV/0! 10,000.00 11,000.00 -
#DIV/0! 15,000.00 16,500.00 -
#DIV/0! -
#DIV/0! 60,160.00 66,176.00 50,909.09
#DIV/0! 61,000.00 67,100.00 53,000.00
#DIV/0! 63,810.00 70,191.00 54,000.00
#DIV/0! 64,000.00 70,400.00 59,090.91
#DIV/0! 51,730.00 56,903.00 55,000.00
#DIV/0! 54,290.00 59,719.00 59,636.36
#DIV/0! 68,330.00 75,163.00 59,727.27
#DIV/0! 83,000.00 91,300.00 -
#DIV/0! -
#DIV/0! - - -
#DIV/0! -
#DIV/0! - - -
#DIV/0! -
#DIV/0! 158,470.00 174,317.00 -
#DIV/0! -
#DIV/0! 273,300.00 300,630.00 300,636.36
#DIV/0! 227,760.00 250,536.00 250,545.45
#DIV/0! -
#DIV/0! 440,000.00 484,000.00 -
HARGA HARGA
(Rp) (Rp)
#DIV/0! -
#DIV/0! -
#DIV/0! 24,790.00 27,269.00 27,272.73
#DIV/0! 47,190.00 51,909.00 51,909.09
#DIV/0! 83,960.00 92,356.00 92,363.64
#DIV/0! 99,660.00 109,626.00 109,636.36
#DIV/0! 115,450.00 126,995.00 127,000.00
#DIV/0! 164,870.00 181,357.00 181,363.64
#DIV/0! 15,450.00 16,995.00 17,000.00
#DIV/0! 20,000.00 22,000.00 22,000.00
#DIV/0! 27,270.00 29,997.00 30,000.00
#DIV/0! 41,980.00 46,178.00 46,181.82
#DIV/0! -
#DIV/0! -
#DIV/0! 8,000.00 8,800.00 -
#DIV/0! 16,000.00 17,600.00 -
#DIV/0! 10,000.00 11,000.00 -
#DIV/0! -
#DIV/0! mega ingin subur langgeng -
- dia 6 10,150.38 10,902.26 11,278.20 12,030.08 10,560.00 11,616.00 18,000.00
#DIV/0! dia8 9,071.73 9,282.70 10,548.52 10,548.52 11,060.00 12,166.00 20,272.73
#DIV/0! DIA 10 9,189.19 9,324.32 10,405.41 10,810.81 -
#DIV/0! dia 12 9,287.05 9,474.67 10,787.99 11,726.08 19,000.00 20,900.00 21,818.18
#DIV/0! dia 16 11,075.95 9,651.90 10,548.52 13,185.65 -
#DIV/0! 9,754.86 9,727.17 10,713.73 11,660.23 9,000.00 9,900.00 21,818.18
#DIV/0! 12,100.00 13,310.00 33,000.00
#DIV/0! 11,115.51
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
- -
- -
#DIV/0! 10,560.00 11,616.00 -
#DIV/0! 24,170.00 26,587.00 -
#DIV/0! 118,800.00 130,680.00 -
#DIV/0! 191,700.00 210,870.00 -
#DIV/0! 275,400.00 302,940.00 -
#DIV/0! -
#DIV/0! 23,620.00 25,982.00 -
#DIV/0! - - -
#DIV/0! 20,000.00 22,000.00 24,818.18
#DIV/0! 12,000.00 13,200.00 -
#DIV/0! 15,000.00 16,500.00 -
#DIV/0! - - -
#DIV/0! 24,170.00 26,587.00 35,363.64
#DIV/0! -
#DIV/0! -
#DIV/0! -
#DIV/0! 8,420.00 9,262.00 -
#DIV/0! 11,730.00 12,903.00 -
#DIV/0! 15,610.00 17,171.00 -
#DIV/0! 25,780.00 28,358.00 -
#DIV/0! 30,570.00 33,627.00 -
#DIV/0! 61,980.00 68,178.00 -
#DIV/0! 95,040.00 104,544.00 -
#DIV/0! 194,210.00 213,631.00 -
#DIV/0! 305,780.00 336,358.00 -
#DIV/0! -
#DIV/0! -
#DIV/0! 21,650.00 23,815.00 -
#DIV/0! 32,970.00 36,267.00 -
#DIV/0! 47,680.00 52,448.00 -
#DIV/0! 75,450.00 82,995.00 -
#DIV/0! 80,660.00 88,726.00 -
#DIV/0! 114,540.00 125,994.00 -
#DIV/0! 132,720.00 145,992.00 -
#DIV/0! 178,760.00 196,636.00 -
HARGA HARGA
(Rp) (Rp)
#DIV/0!
#DIV/0! -
#DIV/0! 21,650.00 23,815.00 -
#DIV/0! 32,970.00 36,267.00 -
#DIV/0! 47,680.00 52,448.00 -
#DIV/0! 75,450.00 82,995.00 -
#DIV/0! 80,660.00 88,726.00 -
#DIV/0! 114,540.00 125,994.00 -
#DIV/0! 178,760.00 196,636.00 -
#DIV/0! 178,760.00 196,636.00 -
#DIV/0! 178,760.00 196,636.00 -
#DIV/0! -
#DIV/0! -
#DIV/0! 135,000.00 148,500.00 -
#DIV/0! 125,000.00 137,500.00 -
#DIV/0! 10,000.00 11,000.00 -
#DIV/0! -
#DIV/0! 78,290.00 86,119.00 -
#DIV/0! -
#DIV/0! 48,000.00 52,800.00 -
#DIV/0! 50,000.00 55,000.00 -
#DIV/0! -
#DIV/0! -
#DIV/0! 40,000.00 44,000.00 -
#DIV/0! 48,000.00 52,800.00 -
#DIV/0! 56,360.00 61,996.00 -
#DIV/0! 117,100.00 128,810.00 -
#DIV/0! 147,520.00 162,272.00 -
#DIV/0! 186,520.00 205,172.00 -
#DIV/0! 216,940.00 238,634.00 -
#DIV/0! -
#DIV/0! 65,640.00 72,204.00 -
1.00 81,430.00 89,573.00 -
1.00 96,520.00 106,172.00 -
1.00 96,520.00 106,172.00 -
#DIV/0! -
#DIV/0! 142,800.00 157,080.00 -
1.00 188,300.00 207,130.00 -
#DIV/0! 288,280.00 317,108.00 -
#DIV/0! 254,770.00 280,247.00 -
#DIV/0! 75,000.00 82,500.00 -
#DIV/0! -
#DIV/0! -
#DIV/0! -
- 30,000.00 33,000.00 -
- 35,000.00 38,500.00 -
- 4,000.00 4,400.00 -
- 17,350.00 19,085.00 -
#DIV/0! 71,750.00 78,925.00 -
- 20,000.00 22,000.00 -
#DIV/0! 55,000.00 60,500.00 -
#DIV/0! -
#DIV/0! -
#DIV/0! 25,000.00 27,500.00 -
#DIV/0! 21,000.00 23,100.00 -
#DIV/0! 140,000.00 154,000.00 -
#DIV/0! 240,000.00 264,000.00 -
#DIV/0! -
#DIV/0! -
#DIV/0! 30,000.00 33,000.00 -
#DIV/0! 71,750.00 78,925.00 -
#DIV/0! 71,750.00 78,925.00 -
#DIV/0! 25,000.00 27,500.00 -
#DIV/0! 25,780.00 28,358.00 -
#DIV/0! 14,850.00 16,335.00 -
#DIV/0! 15,400.00 16,940.00 -
#DIV/0! 25,000.00 27,500.00 -
#DIV/0! -
HARGA HARGA
(Rp) (Rp)
#DIV/0! -
#DIV/0! 78,320.00 86,152.00 -
#DIV/0! 103,030.00 113,333.00 -
#DIV/0! -
#DIV/0! 107,810.00 118,591.00 -
#DIV/0! 114,290.00 125,719.00 -
#DIV/0! -
#DIV/0! 95,830.00 105,413.00 -
#DIV/0! 118,370.00 130,207.00 -
#DIV/0! -
#DIV/0! -
#DIV/0! -
#DIV/0! -
#DIV/0! 4,000.00 4,400.00 -
#DIV/0! 5,500.00 6,050.00 -
#DIV/0! 8,500.00 9,350.00 -
#DIV/0! 13,000.00 14,300.00 -
#DIV/0! 12,000.00 13,200.00 -
#DIV/0! 15,000.00 16,500.00 -
#DIV/0! -
#DIV/0! -
#DIV/0! 15,000.00 16,500.00 -
#DIV/0! 12,000.00 13,200.00 -
#DIV/0! 21,000.00 23,100.00 -
#DIV/0! 16,000.00 17,600.00 -
#DIV/0! -
#DIV/0! 12,000.00 13,200.00 -
#DIV/0! 6,000.00 6,600.00 -
#DIV/0! 36,000.00 39,600.00 -
#DIV/0! 11,000.00 12,100.00 -
#DIV/0! -
#DIV/0! 21,000.00 23,100.00 -
#DIV/0! -
#DIV/0! -
#DIV/0! 162,000.00 178,200.00 -
#DIV/0! 216,000.00 237,600.00 -
#DIV/0! 91,800.00 100,980.00 -
#DIV/0! 145,800.00 160,380.00 -
#DIV/0! 145,800.00 160,380.00 -
#DIV/0! -
#DIV/0! -
#DIV/0! 22,500.00 24,750.00 -
#DIV/0! 18,590.00 20,449.00 -
#DIV/0! 62,850.00 69,135.00 -
#DIV/0! 120,000.00 132,000.00 -
#DIV/0! 44,620.00 49,082.00 -
#DIV/0! 8,670.00 9,537.00 -
#DIV/0! 18,840.00 20,724.00 -
#DIV/0! 150,000.00 165,000.00 -
#DIV/0! -
#DIV/0! -
#DIV/0! 1,611,570.00 1,772,727.00 -
#DIV/0! 194,300.00 213,730.00 -
#DIV/0! 582,190.00 640,409.00 -
#DIV/0! 350,000.00 385,000.00 -
#DIV/0! 45,000.00 49,500.00 -
#DIV/0! 45,000.00 49,500.00 -
#DIV/0! -
#DIV/0! 42,640.00 46,904.00 -
#DIV/0! 4,950.00 5,445.00 -
#DIV/0! 22,310.00 24,541.00 -
#DIV/0! -
#DIV/0! 780,990.00 859,089.00 -
#DIV/0! 1,301,650.00 1,431,815.00 -
#DIV/0! -
HARGA HARGA
(Rp) (Rp)
#DIV/0! -
- 18,040.00 19,844.00 -
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0! 30,000.00 33,000.00 -
#DIV/0! 54,950.00 60,445.00 -
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0! - - -
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0! 19,000.00 20,900.00 -
#DIV/0! 19,000.00 20,900.00 -
#DIV/0! 17,350.00 19,085.00 -
#DIV/0! 41,320.00 45,452.00 -
#DIV/0! -
#DIV/0! -
#DIV/0! -
#DIV/0! 420,000.00 462,000.00 -
#DIV/0! - - -
#DIV/0! 425,000.00 467,500.00 -
#DIV/0! 400,000.00 440,000.00 -
#DIV/0! 1,200,000.00 1,320,000.00 -
#DIV/0! 1,500,000.00 1,650,000.00 -
#DIV/0! -
#DIV/0! -
#DIV/0! 60,000.00 66,000.00 -
#DIV/0! 70,000.00 77,000.00 -
#DIV/0! 86,000.00 94,600.00 -
#DIV/0!
#DIV/0! 95,000.00 104,500.00 -
#DIV/0! 105,000.00 115,500.00 -
#DIV/0! 132,000.00 145,200.00 -
#DIV/0! 140,000.00 154,000.00 -
#DIV/0! 94,000.00 103,400.00 -
#DIV/0! 2,350.00 2,585.00 -
#DIV/0! -
#DIV/0! 16,000.00 17,600.00 -
#DIV/0! 26,000.00 -
#DIV/0! 32,000.00 -
#DIV/0! 38,000.00 -
#DIV/0!
HARGA HARGA
(Rp) (Rp)
#DIV/0! -
#DIV/0! 350,000.00 385,000.00 -
#DIV/0! 400,000.00 440,000.00 -
#DIV/0! 98,200.00 108,020.00 -
#DIV/0! 101,000.00 111,100.00 -
#DIV/0! 500,000.00 550,000.00 -
#DIV/0! -
#DIV/0! -
#DIV/0! 95,000.00 104,500.00 -
#DIV/0! -
#DIV/0! 161,000.00 177,100.00 -
#DIV/0! 185,000.00 203,500.00 -
#DIV/0! 231,000.00 254,100.00 -
#DIV/0! -
#DIV/0! 6,500.00 7,150.00 -
#DIV/0! 15,000.00 16,500.00 -
#DIV/0! 10,000.00 11,000.00 -
#DIV/0! 2,000.00 2,200.00 -
#DIV/0! 9,500.00 10,450.00 -
#DIV/0! 37,190.00 40,909.00 -
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0! Banjarnegara, Januari 2017 Banjarnegara, Januari 2017
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
HARGA HARGA
(Rp) (Rp)
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
HARGA HARGA
(Rp) (Rp)
#DIV/0! #DIV/0!
-
372,900.00
476,300.00
491,900.00
468,400.00
475,400.00
635,100.00
595,700.00
504,000.00
504,000.00
1,132.50
-
452,800.00
733,400.00
747,800.00
446,900.00
-
184,000.00
-
150,000.00
137,400.00
137,400.00
-
-
-
-
-
8,900.00
10,500.00
-
1,200.00
2,990.00
3,380.00
4,680.00
4,800.00
7,800.00
7,800.00
-
-
-
-
-
49,140.00
61,800.00
71,200.00
91,980.00
-
-
43,500.00
52,000.00
-
-
-
31,500.00
35,000.00
-
72,630.00
10,006,330.00
9,211,843.00
3,525,000.00
2,914,285.71
18,802,260.00
16,912,350.00
259,500.00
16,290.00
56,000.00
58,300.00
59,400.00
65,000.00
60,500.00
65,600.00
65,700.00
330,700.00
275,600.00
30,000.00
57,100.00
101,600.00
120,600.00
139,700.00
199,500.00
18,700.00
24,200.00
33,000.00
50,800.00
19,800.00
22,300.00
24,000.00
24,000.00
36,300.00
2,335,600.00
#REF!
#REF! 7,955.36
#REF! 7,995.46
27,300.00
38,900.00
#REF!
Banjarnegara, Januari 2017
XV PEKERJAAN PERP
Tenaga
1.00 m3 galian Tanah
36.00 oh Tukang
6.00 oh Kepala Tukang
3.00 oh Mandor
Tenaga
1.00 m' Galian Tanah
1.00 m' Urugan Pasir
1.00 m' Urugan Tanah Kemb
1.00 m' Ongkos Pemasanga
1.00 m' Pengetesan Pipa
Tenaga
1.00 m' Galian Tanah
1.00 m' Urugan Pasir
1.00 m' Urugan Tanah Kemb
1.00 m' Ongkos Pemasanga
1.00 m' Pengetesan Pipa
Tenaga
1.00 m' Galian Tanah
1.00 m' Urugan Pasir
1.00 m' Urugan Tanah Kemb
1.00 m' Ongkos Pemasanga
1.00 m' Pengetesan Pipa
Tenaga
1.00 m' Galian Tanah
1.00 m' Urugan Pasir
1.00 m' Urugan Tanah Kemb
1.00 m' Ongkos Pemasanga
1.00 m' Pengetesan Pipa
Tenaga
1.00 m' Galian Tanah
1.00 m' Urugan Pasir
1.00 m' Urugan Tanah Kemb
1.00 m' Ongkos Pemasanga
1.00 m' Pengetesan Pipa
Tenaga
1.00 m' Galian Tanah
1.00 m' Urugan Pasir
1.00 m' Urugan Tanah Kemb
1.00 m' Ongkos Pemasanga
1.00 m' Pengetesan Pipa
Tenaga
1.00 m' Galian Tanah
1.00 m' Urugan Pasir
1.00 m' Urugan Tanah Kemb
1.00 m' Ongkos Pemasanga
1.00 m' Pengetesan Pipa
Tenaga
1.00 m' Galian Tanah
1.00 m' Urugan Pasir
1.00 m' Urugan Tanah Kemb
1.00 m' Ongkos Pemasanga
1.00 m' Pengetesan Pipa
Tenaga
1.00 m' Galian Tanah
1.00 m' Urugan Pasir
1.00 m' Urugan Tanah Kemb
1.00 m' Ongkos Pemasanga
1.00 m' Pengetesan Pipa
Tenaga
1.00 m' Galian Tanah
1.00 m' Urugan Pasir
1.00 m' Urugan Tanah Kemb
1.00 m' Ongkos Pemasanga
1.00 m' Pengetesan Pipa
0.33
0.33
0.11
1.00
9.18
0.03
4.00
0.20
PEKERJAAN PERPIPAAN (Referensi PDAM)
#REF! #REF!
#REF! #REF! #REF! #REF!
Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509
#REF! #REF!
#REF! #REF! #REF! #REF! 48,000.00 55,488.00
12,306.20 #NAME? 12,306.20 #NAME?
Urugan Tanah Kembali 37,897.44 #NAME? 37,897.44 #NAME?
Ongkos Pemasangan Err:509 Err:509 Err:509 Err:509
#REF! #REF! #REF! #REF!
#REF! #REF!
#REF! #REF! #REF! #REF!
8,204.13 #NAME? 8,204.13 #NAME?
Urugan Tanah Kembali 21,655.68 #NAME? 21,655.68 #NAME? 51,000.00 58,956.00
Ongkos Pemasangan Err:509 Err:509 Err:509 Err:509
#REF! #REF! #REF! #REF!
#REF! #REF!
#REF! #REF! #REF! #REF!
6,563.30 #NAME? 6,563.30 #NAME?
Urugan Tanah Kembali 16,241.76 #NAME? 16,241.76 #NAME?
Ongkos Pemasangan Err:509 Err:509 Err:509 Err:509
#REF! #REF! #REF! #REF!
#REF! #REF!
#REF! #REF! #REF! #REF!
5,332.68 #NAME? 5,332.68 #NAME?
Urugan Tanah Kembali 10,827.84 #NAME? 10,827.84 #NAME?
Ongkos Pemasangan Err:509 Err:509 Err:509 Err:509
#REF! #REF! #REF! #REF!
#REF! #REF!
#REF! #REF! #REF! #REF!
4,922.48 #NAME? 4,922.48 #NAME?
Urugan Tanah Kembali 8,120.88 #NAME? 8,120.88 #NAME?
Ongkos Pemasangan Err:509 Err:509 Err:509 Err:509
#REF! #REF! #REF! #REF!
#REF! #REF!
#REF! #REF! #REF! #REF!
4,102.07 #NAME? 4,102.07 #NAME?
Urugan Tanah Kembali 5,413.92 #NAME? 5,413.92 #NAME?
Ongkos Pemasangan Err:509 Err:509 Err:509 Err:509
#REF! #REF! #REF! #REF!
#REF! #REF!
#REF! #REF! #REF! #REF!
8,204.13 #NAME? 8,204.13 #NAME?
Urugan Tanah Kembali 21,655.68 #NAME? 21,655.68 #NAME?
Ongkos Pemasangan Err:509 Err:509 Err:509 Err:509
#REF! #REF! #REF! #REF!
#REF! #REF!
#REF! #REF! #REF! #REF!
6,563.30 #NAME? 6,563.30 #NAME?
Urugan Tanah Kembali 16,241.76 #NAME? 16,241.76 #NAME?
Ongkos Pemasangan Err:509 Err:509 Err:509 Err:509
#REF! #REF! #REF! #REF!
#REF! #REF!
#REF! #REF! #REF! #REF!
4,102.07 #NAME? 4,102.07 #NAME?
Urugan Tanah Kembali 5,413.92 #NAME? 5,413.92 #NAME?
Ongkos Pemasangan Err:509 Err:509 Err:509 Err:509
#REF! #REF! #REF! #REF!
#REF! #REF!
#REF! #REF! #REF! #REF!
4,102.07 #NAME? 4,102.07 #NAME?
Urugan Tanah Kembali 5,413.92 #NAME? 5,413.92 #NAME?
Ongkos Pemasangan Err:509 Err:509 Err:509 Err:509
#REF! #REF! #REF! #REF!
50,000.00 57,800.00
40,000.00 46,240.00
50,000.00 57,800.00
50,000.00 57,800.00
2,500.00 2,890.00
45,000.00 52,020.00
0.02
1.00
41.67
190,000.00
180,000.00
49,000.00 56,644.00
25,000.00
Harga Satuan Upah
KABUPATEN BANJARNEGARA
Tahun 2023
Page 202
ANALISA HARGA SATUAN PEKERJAAN
PERMEN PU NO 1 TAHUN 2022
Assesoris
Ls 0.20 100,000.00 20,000.00
(perkuatan. Las. pengecatan dll)
Page 203
ANALISA HARGA SATUAN PEKERJAAN
PERMEN PU NO 1 TAHUN 2022
Dihitung.4.2.9 Meja Dapur (Spek & Ukuran disesuaikan dengan gambar) unit 10,287,236.40
Harga Satuan
No Uraian Satuan Koefisien Jumlah Harga (Rp)
(Rp)
1 m³ Beton mutu, f’c = 14,5 MPa
1 m3 0.30 1,069,362.45 320,808.73
(K175), Semi mekanis
Penulangan 1 kg dengan Besi
2 Kg 52.34 16,196.88 847,758.68
Polos atau Besi Sirip
Pemasangan 1 m2 Bekisting
3 untuk Plat lantai Beton m2 2.63 392,489.57 1,030,346.00
Bangunan Gedung
Pemasangan 1m2 Lantai
4 Keramik Ukuran 60x60 Motif m2 4.63 263,996.94 1,221,026.77
Halus
Page 204
RENCANA ANGGARAN BIAYA
( RAB )
Terbilang : " Seratus delapan puluh tiga juta lima ratus ribu rupiah "
Mengetahui, Menyetujui
Kepala Dinas Pekerjaan Umum dan Penataan Ruang Kepala Bidang Bangunan Gedung
Kabupaten Banjarnegara
HARGA KETERANGAN
URAIAN PEKERJAAN
Rp
1 2 3 4
Terbilang : " Seratus delapan puluh tiga juta lima ratus ribu rupiah "
Mengetahui, Menyetujui
Kepala Dinas Pekerjaan Umum dan Penataan Ruang Kepala Bidang Bangunan Gedung
Kabupaten Banjarnegara
A TENAGA
L.01 0.50 OH Pekerja 78,320.00
L.02 0.050 OH Mandor 91,000.00
B BAHAN
C PERALATAN
D Jumlah A + B + C
E Tenaga 10%
F Harga Satuan Pekerjaan (D+E)
A.4.6.1.16.a 1 m2 Pemasangan Rangka Atap Genteng plentong, Kayu Klas III (Kruing)
A Tenaga
L.01 0.1 OH Pekerja 78,320.00
L.02 0.1 OH Tukang Kayu 81,550.00
L.03 0.01 OH Kepala Tukang 91,000.00
L.04 0.005 OH Mandor 91,000.00
B Bahan
0.014 m3 Kayu Klas II (Kruing), Kaso-kaso (5x7) cm 7,500,000.00
0.0036 m3 Reng (2x3) cm 7,500,000.00
0.25 Kg Paku 5 dan 10 cm 20,000.00
C PERALATAN
Papan Kayu kelas
D
III
E Pemasangan Kusen Pintu Allu 10%
F Harga Satuan Pekerjaan (D+E)
A Tenaga
L.01 0.028 OH Pekerja 78,320.00
L.02 0.042 OH Tukang Cat 81,550.00
L.03 0.0042 OH Kepala Tukang 91,000.00
L.04 0.0030 OH Mandor 91,000.00
B Bahan
0.12 Kg Cat Dasar 27,400.00
0.18 Kg Cat Penutup 2 kali 27,400.00
C PERALATAN
D Jumlah A + B + C
E Pemasangan Pintu Kaca Rang 10%
F Harga Satuan Pekerjaan (D+E)
A Tenaga
L.01 0.2 OH Pekerja 78,320.00
L.02 0.3 OH Tukang Kayu 81,550.00
L.03 0.03 OH Kepala Tukang 91,000.00
L.04 0.01 OH Mandor 91,000.00
B Bahan
0.0163 m3 kayu tahun, balok 2,400,000.00
Paku 7 cm – 10
0.25 Kg 20,000.00
cm
C PERALATAN
D Kepala Tukang
E Mandor 10%
F Harga Satuan Pekerjaan (D+E)
67,116.50
61,015.00
58,740.00
2,275.00
61,015.00
6,101.50
67,116.50
290,846.60
24,406.00
23,496.00
910.00
240,000.00
240,000.00
264,406.00
26,440.60
290,846.60
70,072.20
17,352.00
7,832.00
8,155.00
910.00
455.00
46,350.00
28,800.00
400.00
17,150.00
63,702.00
6,370.20
70,072.20
16,027.00
43,710.00
39,160.00
4,550.00
43,710.00
4,371.00
48,081.00
865,749.89
192,292.50
117,480.00
61,162.50
6,825.00
6,825.00
594,752.86
295,714.29
161,460.00
137,578.57
787,045.36
78,704.54
865,749.89
55,832.53
38,458.50
23,496.00
12,232.50
1,365.00
1,365.00
12,298.35
5,431.68
6,866.67
50,756.85
5,075.68
55,832.53
33,136.40
25,639.00
15,664.00
8,155.00
910.00
910.00
4,485.00
4,485.00
30,124.00
3,012.40
33,136.40
1,064,992.74
161,755.25
129,228.00
22,426.25
2,548.00
7,553.00
806,419.96
449,880.00
138,059.96
218,050.00
430.00
968,175.21
96,817.52
1,064,992.74
161,968.84
12,191.90
5,482.40
5,708.50
637.00
364.00
135,052.50
132,300.00
2,752.50
147,244.40
14,724.44
161,968.84
201,092.54
66,661.40
40,726.40
21,203.00
2,366.00
2,366.00
116,150.00
110,250.00
5,250.00
650.00
182,811.40
18,281.14
201,092.54
326,489.57
84,608.70
51,691.20
26,911.50
3,003.00
3,003.00
212,200.00
98,000.00
7,000.00
1,300.00
36,000.00
39,900.00
30,000.00
296,808.70
29,680.87
326,489.57
334,409.57
84,608.70
51,691.20
26,911.50
3,003.00
3,003.00
219,400.00
98,000.00
7,000.00
1,300.00
43,200.00
39,900.00
30,000.00
304,008.70
30,400.87
334,409.57
193,133.07
30,766.80
18,796.80
9,786.00
1,092.00
1,092.00
144,808.71
116,250.00
13,248.00
11,035.71
4,275.00
175,575.51
17,557.55
193,133.07
113,241.66
32,139.75
19,580.00
10,193.75
1,183.00
1,183.00
70,807.21
42,542.50
13,524.00
3,705.00
11,035.71
102,946.96
10,294.70
113,241.66
228,838.32
89,736.50
54,824.00
28,542.50
3,185.00
3,185.00
118,298.33
93,500.00
16,215.00
8,583.33
208,034.83
20,803.48
228,838.32
41,942.45
12,819.50
7,832.00
4,077.50
455.00
455.00
25,310.00
23,660.00
1,650.00
38,129.50
3,812.95
41,942.45
89,952.23
19,274.75
11,748.00
6,116.25
682.50
728.00
62,500.00
62,500.00
81,774.75
8,177.48
89,952.23
102,880.38
49,640.00
31,328.00
16,310.00
1,820.00
182.00
43,887.62
25,000.00
11,040.00
7,847.62
93,527.62
9,352.76
102,880.38
11,056,408.00
1,419,280.00
313,280.00
978,600.00
109,200.00
18,200.00
8,632,000.00
8,250,000.00
270,000.00
112,000.00
10,051,280.00
1,005,128.00
11,056,408.00
169,787.20
17,352.00
7,832.00
8,155.00
910.00
455.00
137,000.00
105,000.00
27,000.00
5,000.00
154,352.00
15,435.20
169,787.20
111,272.49
7,456.81
3,367.76
3,506.65
391.30
191.10
93,700.00
88,000.00
1,500.00
4,200.00
101,156.81
10,115.68
111,272.49
683,664.25
14,862.95
6,657.20
6,931.75
819.00
455.00
606,650.00
352,000.00
130,000.00
112,500.00
12,150.00
621,512.95
62,151.30
683,664.25
24,750.33
15,500.30
1,174.80
12,232.50
1,365.00
728.00
7,000.00
7,000.00
22,500.30
2,250.03
24,750.33
50,050.33
15,500.30
1,174.80
12,232.50
1,365.00
728.00
30,000.00
30,000.00
45,500.30
4,550.03
50,050.33
15,942.59
6,273.26
2,192.96
3,425.10
382.20
273.00
8,220.00
3,288.00
4,932.00
14,493.26
1,449.33
15,942.59
113,241.66
32,139.75
19,580.00
10,193.75
1,183.00
1,183.00
70,807.21
42,542.50
13,524.00
3,705.00
11,035.71
102,946.96
10,294.70
113,241.66
96,677.90
43,769.00
15,664.00
24,465.00
2,730.00
910.00
44,120.00
39,120.00
5,000.00
87,889.00
8,788.90
96,677.90
DAFTAR ANALISA PEKERJAAN
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
I A.1.1.1. HARGA SATUAN PEKERJAAN PERSIAPAN
1 1.1.a 1 m' Pembuatan 1 m' Pagar Sementara dari Kayu Tinggi 2 m 297,301.61
A TENAGA 51,278.00
L.01 0.4 OH Pekerja 78,320.00 31,328.00
L.02 0.2 OH Tukang Kayu 81,550.00 16,310.00
L.03 0.02 OH Kepala Tukang 91,000.00 1,820.00
L.04 0.02 OH Mandor 91,000.00 1,820.00
B BAHAN 218,996.19
1.25 Btg Bambu diameter 8 - 10 / 400 cm 15,000.00 18,750.00
5.0 Kg Semen Portlan (SP) 1,380.00 6,900.00
0.005 m3 Pasir Beton 245,238.10 1,226.19
0.009 m3 Koral Beton 296,666.67 2,670.00
0.072 m3 Kayu 5/7X4m Kayu Kruing 2,400,000.00 172,800.00
0.06 Kg Paku Biasa 2" - 5" 17,500.00 1,050.00
0.40 Liter Residu 39,000.00 15,600.00
C PERALATAN
D Jumlah A + B + C 270,274.19
E Overhead & Profit 10% 10% 27,027.42
F Harga Satuan Pekerjaan (D+E) 297,301.61
2 1.1.b 1 m' Pagar Sementara dari Seng Gelombang Tinggi 2,00 m 798,886.21
A TENAGA 51,924.00
L.01 0.2 OH Pekerja 78,320.00 15,664.00
L.02 0.4 OH Tukang Kayu 81,550.00 32,620.00
L.03 0.02 OH Kepala Tukang 91,000.00 1,820.00
L.04 0.02 OH Mandor 91,000.00 1,820.00
B BAHAN 674,336.19
1.25 Btg Bambu diameter 8 - 10 / 400 cm 15,000.00 18,750.00
2.5 Kg Semen Portlan (SP) 1,380.00 3,450.00
1.2 Lbr Seng Gelombang 75,900.00 91,080.00
0.005 m3 Pasir Beton 245,238.10 1,226.19
0.009 m3 Koral Beton 296,666.67 2,670.00
0.072 m3 Kayu 5/7X4m Kayu Kruing 7,500,000.00 540,000.00
0.06 Kg Paku Biasa 2" - 5" 17,500.00 1,050.00
0.45 Kg Meni Besi 35,800.00 16,110.00
C PERALATAN
D Jumlah A + B + C 726,260.19
E Overhead & Profit 10% 10% 72,626.02
F Harga Satuan Pekerjaan (D+E) 798,886.21
Overhead & Profit 10%
3 1.1.c 1 m' Pagar Sementara dari kawat duri Tinggi 1.80 m 81,207.71
A TENAGA 43,769.00
L.01 0.2 OH Pekerja 78,320.00 15,664.00
L.02 0.3 OH Tukang Kayu 81,550.00 24,465.00
L.03 0.02 OH Kepala Tukang 91,000.00 1,820.00
737989325.xlsx Persiapan-222
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
L.04 0.02 OH Mandor 91,000.00 1,820.00
B BAHAN 30,056.19
1.25 Btg Bambu diameter 8 - 10 / 400 cm 15,000.00 18,750.00
2.0 Kg Semen Portlan (SP) 1,380.00 2,760.00
1.2 m1 Kawat duri 3,000.00 3,600.00
0.005 m3 Pasir Beton 245,238.10 1,226.19
0.009 m3 Koral Beton 296,666.67 2,670.00
0.06 Kg Paku Biasa 2" - 5" 17,500.00 1,050.00
C PERALATAN
D Jumlah A + B + C 73,825.19
E Overhead & Profit 10% 10% 7,382.52
F Harga Satuan Pekerjaan (D+E) 81,207.71
Overhead & Profit 10%
4 1.1.d 1 m' Pengukuran dan Pemasangan Bouwplank 70,017.20
A Tenaga 17,352.00
L.01 0.1 OH Pekerja 78,320.00 7,832.00
L.02 0.1 OH Tukang Kayu 81,550.00 8,155.00
L.03 0.01 OH Kepala Tukang 91,000.00 910.00
L.04 0.005 OH Mandor 91,000.00 455.00
B Bahan 46,300.00
0.012 m3 Kayu 5/7x 4m Kayu Tahun 2,400,000.00 28,800.00
0.02 Kg Paku Biasa 2" - 5" 17,500.00 350.00
0.007 m3 Kayu Papan 3/20 Tahun 2,450,000.00 17,150.00
C PERALATAN
D Jumlah A + B + C 63,652.00
E Overhead & Profit 10% 10% 6,365.20
F Harga Satuan Pekerjaan (D+E) 70,017.20
737989325.xlsx Persiapan-223
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
B Bahan 1,004,744.52
1.25 Btg Bambu Ø 8 - 10 / 4 m 15,000.00 18,750.00
0.18 m3 Kayu 2,400,000.00 432,000.00
0.85 Kg Paku Biasa 2" - 5" 17,500.00 14,875.00
1.1 Kg Besi Strip 18,000.00 19,800.00
35 Kg Semen Portlan (SP) 1,380.00 48,300.00
0.15 m3 Pasir pasang 245,238.10 36,785.71
0.1 m3 Pasir Beton 245,238.10 24,523.81
0.15 m3 Koral Beton 296,666.67 44,500.00
30 buah Batu bata Merah 900.00 27,000.00
0.25 Lbr Seng Plat 15,000.00 3,750.00
2 buah Jendela Naco 150,000.00 300,000.00
0.08 m2 Kaca Polos 82,000.00 6,560.00
0.15 buah Kunci Tanam 162,000.00 24,300.00
0.06 Lbr Plywood 4 mm 60,000.00 3,600.00
C PERALATAN
D Jumlah A + B + C 1,437,884.52
E Overhead & Profit 10% 10% 143,788.45
F Harga Satuan Pekerjaan (D+E) 1,581,672.98
8 1.3.1.1.1.a.(a) 1 m' Pengeboran Sumur Air tanah Dangkal ∅ 1"- 1,25" pada tanah biasa -
B Tenaga -
L.01 0.150 OH Pekerja 0.00 -
L.14 0.050 OH Juru bor 0.00 -
L.04 0.015 OH Mandor 0.00 -
B Bahan
C PERALATAN 0
0.05 Hari Stang bor, batang bor dan mata bor ∅ 1,25" 0
737989325.xlsx Persiapan-224
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
D Jumlah A + B + C -
E Overhead & Profit 10% 10% -
F Harga Satuan Pekerjaan (D+E) -
737989325.xlsx Persiapan-225
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
10 A.4.4.3.13 1 m2 Pemasangan 1m2 Lantai Ubin Teralux Marmer Ukuran 60cm x60cm
A Tenaga
L.01 0.240 OH Pekerja
L.02 0.120 OH Tukang Batu
L.03 0.012 OH Kepala Tukang
L.04 0.012 OH Mandor
B Bahan
3.10 Buah Keramik Homogen 40x40 cm 0.4
9.6 Kg Portland Semen 0.16
1.500 Kg Semen warna 6.25
0.045 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 10% 10%
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 10% 10%
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 10% 10%
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 10% 10%
32 A.4.4.3.64 1 m2 Pemasangan 1 m2 Paving Block Mutu K-225 (Blok Beton) Natural tebal 8 c
Tenaga
L.01 0.5 OH Pekerja
L.02 0.5 OH Tukang Batu
L.03 0.05 OH Kepala Tukang
L.04 0.0013 OH Mandor
Bahan
1.01 m3 Pavingblock 8 cm natural
0.05 m3 Pasir Urug
C PERALATAN
0.1 Ls 10 % dari bahan
D Jumlah A + B + C
E Overhead & Profit 10% 10%
an DINDING
40cm x40cm 35,353.73
32,139.75
78,320.00 19,580.00
81,550.00 10,193.75
91,000.00 1,183.00
91,000.00 1,183.00
-
-
-
-
32,139.75
3,213.98
35,353.73
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- -
- -
- -
- -
-
-
-
-
-
-
-
-
-
-
- -
- -
- -
- -
-
-
-
-
-
-
-
-
-
-
- -
- -
- -
- -
-
-
-
-
-
-
-
-
-
-
- 6.25
-
-
-
-
-
-
-
-
-
-
-
-
-
- 6.25
-
-
-
-
-
-
0 s.d. <30 cm -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - 50
- -
- -
- -
-
-
-
0 s.d. <30 cm -
-
-
-
-
-
-
- -
- -
- -
- -
-
-
-
166,866.94
89,736.50
78,320.00 54,824.00
81,550.00 28,542.50
91,000.00 3,185.00
91,000.00 3,185.00
61,960.71
34,000.00 35,700.00 9.18273646
1,380.00 13,800.00
245,238.10 11,035.71
2,850.00 1,425.00
151,697.21
15,169.72
166,866.94
58,567.69
18,028.30
78,320.00 7,048.80
81,550.00 7,339.50
91,000.00 3,185.00
91,000.00 455.00
35,215.05
3,090.91 32,763.64 11.1111111
1,380.00 1,573.20
245,238.10 735.71
2,850.00 142.50
53,243.35
5,324.34
58,567.69
-
-
0.00 -
0.00 -
0.00 -
0.00 -
-
0.00 -
0.00 -
0.00 -
0.00 -
-
-
-
-
-
0.00 -
0.00 -
0.00 -
0.00 -
-
0.00 -
0.00 -
-
-
-
-
-
0.00 -
0.00 -
0.00 -
0.00 -
-
0.00 -
0.00 -
-
-
-
-
-
0.00 -
0.00 -
0.00 -
0.00 -
-
0.00 -
0.00 -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
0.00 -
0.00 -
0.00 -
0.00 -
-
0.00 -
0.00 -
0.00 -
0.00 -
-
-
-
249,208.06
115,375.50
78,320.00 70,488.00
81,550.00 36,697.50
91,000.00 4,095.00
91,000.00 4,095.00
111,177.29
3,400.00 88,400.00 25
1,380.00 12,834.00
245,238.10 4,414.29
2,850.00 5,529.00
226,552.79
22,655.28
249,208.06
231,333.06
115,375.50
78,320.00 70,488.00
81,550.00 36,697.50
91,000.00 4,095.00
91,000.00 4,095.00
94,927.29
65,000.00 72,150.00 25
1,380.00 12,834.00
245,238.10 4,414.29
2,850.00 5,529.00
210,302.79
21,030.28
231,333.06
263,996.94
89,736.50
78,320.00 54,824.00
81,550.00 28,542.50
91,000.00 3,185.00
91,000.00 3,185.00
150,260.71
40,000.00 124,000.00 25
1,380.00 13,800.00
245,238.10 11,035.71
2,850.00 1,425.00
239,997.21
23,999.72
263,996.94
238,421.94
89,736.50
78,320.00 54,824.00
81,550.00 28,542.50
91,000.00 3,185.00
91,000.00 3,185.00
127,010.71
32,500.00 100,750.00 25
1,380.00 13,800.00
245,238.10 11,035.71
2,850.00 1,425.00
216,747.21
21,674.72
238,421.94
69,277.69
18,028.30
78,320.00 7,048.80
81,550.00 7,339.50
91,000.00 3,185.00
91,000.00 455.00
44,951.41
25,000.00 42,500.00 25
1,380.00 1,573.20
245,238.10 735.71
2,850.00 142.50
62,979.71
6,297.97
69,277.69
-
-
0.00 -
0.00 -
0.00 -
0.00 -
-
0.00 -
- -
0.00 -
0.00 -
0.00 -
-
-
-
277,238.32
89,736.50
78,320.00 54,824.00
81,550.00 28,542.50
91,000.00 3,185.00
91,000.00 3,185.00
162,298.33
125,000.00 137,500.00
1,380.00 16,215.00
245,238.10 8,583.33
252,034.83
25,203.48
277,238.32
307,488.32
89,736.50
78,320.00 54,824.00
81,550.00 28,542.50
91,000.00 3,185.00
91,000.00 3,185.00
189,798.33
150,000.00 165,000.00
1,380.00 16,215.00
245,238.10 8,583.33
279,534.83
27,953.48
307,488.32
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
78,179.64
20,822.40
78,320.00 9,398.40
81,550.00 9,786.00
91,000.00 1,092.00
91,000.00 546.00
50,250.00
16,500,000.00 49,500.00
15,000.00 750.00
71,072.40
7,107.24
78,179.64
87,770.00 8,777.00
152,793.30
15,279.33
168,072.63
108,980.00 10,898.00
193,583.30
19,358.33
212,941.63
- Dihitung.44 1 m2 Pemasangan 1 m2 Atap UPVC Double Layer 241,759.10
A Tenaga 7,281.00
L.01 0.053 OH Pekerja 78,320.00 4,150.96
L.02 0.025 OH Tukang Kayu 81,550.00 2,038.75
L.03 0.006 OH Kepala Tukang 91,000.00 546.00
L.04 0.006 OH Mandor 91,000.00 545.29
B Bahan 212,500.00
1.000 lbr Atap UPVC Double Layer 212,500.00 212,500.00
C PERALATAN
D PERALATAN 219,781.00
E JUMLAH A + B + C 10% 21,978.10
F Harga Satuan Pekerjaan (D+E) 241,759.10
HARGA JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
JUMLAH A + B + C
3 A.4.5.2.3 1 m2 Pemasangan Atap Genteng Morando 57,552.28
A Tenaga 19,320.25
L.01 0.15 OH Pekerja 78,320.00 11,748.00
L.02 0.075 OH Tukang Kayu 81,550.00 6,116.25
L.03 0.008 OH Kepala Tukang 91,000.00 728.00
L.04 0.008 OH Mandor 91,000.00 728.00
B Bahan 33,000.00
12 Buah Genteng Morando 2,750.00 33,000.00
C PERALATAN
D JUMLAH A + B + C 52,320.25
E Overhead & Profit 10% 10% 5,232.03
F Harga Satuan Pekerjaan (D+E) 57,552.28
8 A.4.5.2.8 1 m' Pemasangan 1 m2 Atap Serat Semen Gelombang 92cm x 250cm x 5mm 21,645.80
A Tenaga 19,678.00
L.01 0.140 OH Pekerja 0.00 -
L.02 0.075 OH Tukang Kayu 78,320.00 5,874.00
L.03 0.080 OH Kepala Tukang 81,550.00 6,524.00
L.04 0.080 OH Mandor 91,000.00 7,280.00
B
Bahan -
Serat semen gel
0.500 Lbr 0.00 -
92x250
0.120 Kg Paku pancing 6x23 0.00 -
C PERALATAN
D JUMLAH A + B + C 19,678.00
E Overhead & Profit 10% 10% 1,967.80
F Harga Satuan Pekerjaan (D+E) 21,645.80
10 A.4.5.2.10 1 m2 Pemasangan1 m2 Atap Serat Semen Gelombang 92cm x 200cm x 5mm 49,178.03
A Tenaga 17,947.30
L.01 0.14 OH Pekerja 78,320.00 10,964.80
L.02 0.07 OH Tukang Kayu 81,550.00 5,708.50
L.03 0.007 OH Kepala Tukang 91,000.00 637.00
L.04 0.007 OH Mandor 91,000.00 637.00
B Bahan 26,760.00
Serat semen gel
0.6 Lbr 41,500.00 24,900.00
92x200
0.12 Kg Paku Pancing 60 x 230 15,500.00 1,860.00
C PERALATAN
D JUMLAH A + B + C 44,707.30
E Overhead & Profit 10% 10% 4,470.73
F Harga Satuan Pekerjaan (D+E) 49,178.03
5 A.4.5.1.5 1 m2 Memasang Langit-langit Tripleks Uk (120x240) cm, Tebal 3 mm, 4 mm & 6 mm 43,837.20
A Tenaga 17,352.00
L.01 0.10 OH Pekerja 78,320.00 7,832.00
L.02 0.10 OH Tukang Kayu 81,550.00 8,155.00
L.03 0.01 OH Kepala Tukang 91,000.00 910.00
L.04 0.005 OH Mandor 91,000.00 455.00
B Bahan 22,500.00
0.375 Lbr Tripleks (4 mm) 60,000.00 22,500.00
0.03 Kg Paku Tripleks 0.00 -
C PERALATAN
D JUMLAH A + B + C 39,852.00
E Overhead & Profit (contoh 10%) 10% 3,985.20
F Harga Satuan Pekerjaan (D+E) 43,837.20
A Tenaga 86,760.00
L.01 0.50 OH Pekerja 78,320.00 39,160.00
L.02 0.50 OH Tukang Kayu 81,550.00 40,775.00
L.03 0.050 OH Kepala Tukang 91,000.00 4,550.00
L.04 0.025 OH Mandor 91,000.00 2,275.00
B Bahan 1,314,000.00
3.60 m1 Profil Alum”T” 365,000.00 1,314,000.00
0.15 Kg Kawat Ø4 mm 0.00 -
1.05 buah Ramset 0.00 -
1.50 lbr Akustik 60 x 120 0.00 -
C PERALATAN
D JUMLAH A + B + C 1,400,760.00
E Overhead & Profit (contoh 10%) 10% 140,076.00
F Harga Satuan Pekerjaan (D+E) 1,540,836.00
4 Dihitung.6 1 unit Pemasangan 1 Buah Wastafel + Pedestal + Asesories + Kran Air Stainless s
A Tenaga
L.01 - OH Pekerja
L.02 1.200 OH Tukang Batu
L.03 - OH Kepala Tukang
L.04 - OH Mandor
B Bahan
1.00 Bh Wastafel
1.0 bh Pedestal
1 ls Kran Stainless + Assesoris lainnya
C PERALATAN
D Overhead & Profit (contoh 10%)
E Harga Satuan Pekerjaan (D+E)
F Harga Satuan Pekerjaan (D+E)
C PERALATAN
D Overhead & Profit (contoh 10%)
E Harga Satuan Pekerjaan (D+E)
F Harga Satuan Pekerjaan (D+E)
C PERALATAN
D JUMLAH A + B +C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
C PERALATAN
D JUMLAH A + B +C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
30 A.5.1.1.38 1 m' Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 15 cm
A Tenaga
L.01 0.060 OH Pekerja
L.02 0.030 OH Tukang Batu
L.03 0.003 OH Kepala Tukang
L.04 0.003 OH Mandor
B Bahan
1.60 bh pipa tanah
6.80 kg Semen Portlan
0.013 m3 Pasir Pasang
0.011 m3 Pasir Urug
C PERALATAN
D JUMLAH A + B +C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
2,810,235.00
10% 281,023.50
3,091,258.50
449,753.72
228,855.00
78,320.00 78,320.00
81,550.00 122,325.00
91,000.00 13,650.00
91,000.00 14,560.00
180,012.02
175,000.00 175,000.00
139,222.74 5,012.02
408,867.02
10% 40,886.70
449,753.72
1,497,439.68
173,520.00
78,320.00 78,320.00
81,550.00 81,550.00
91,000.00 9,100.00
91,000.00 4,550.00
1,187,788.80
350,000.00 350,000.00
139,222.74 835,336.42
245,238.10 2,452.38
1,361,308.80
10% 136,130.88
1,497,439.68
413,216.24
124,918.75
78,320.00 93,984.00
81,550.00 11,824.75
91,000.00 13,650.00
91,000.00 5,460.00
250,732.38
200,000.00 240,000.00
1,380.00 8,280.00
245,238.10 2,452.38
375,651.13
10% 37,565.11
413,216.24
2,097,860.00
10% 209,786.00
2,307,646.00
315,000.00
10% 31,500.00
346,500.00
1,528,385.00
10% 152,838.50
1,681,223.50
996,385.00
10% 99,638.50
1,096,023.50
-
-
0.00 -
0.00 -
0.00 -
0.00 -
-
0.00 -
0.11 0.00 -
82.644628099 0.00 -
0.0121 - 4.356
-
10% -
-
-
-
0.00 -
0.00 -
0.00 -
0.00 -
-
0.00 -
-
10% -
-
-
-
0.00 -
0.00 -
0.00 -
0.00 -
-
0.00 -
0.00 -
0.00 -
0.00 -
-
10% -
-
385,066.97
10% 38,506.70
423,573.67
576,268.36
10% 57,626.84
633,895.20
690,221.43
10% 69,022.14
759,243.57
-
-
-
-
-
-
-
- -
- -
-
10% -
-
-
-
-
-
-
-
-
- -
- -
-
10% -
-
-
-
-
-
-
-
-
- -
- -
-
10% -
-
-
-
-
-
-
-
-
- -
- -
-
10% -
-
-
-
-
-
-
-
-
- -
- -
-
10% -
-
-
-
-
-
-
-
-
- -
- -
-
10% -
-
21,432.70
8,440.52
78,320.00 2,819.52
81,550.00 4,893.00
91,000.00 546.00
91,000.00 182.00
11,043.75
7,125.00 8,550.00
7,125.00 2,493.75
19,484.27
10% 1,948.43
21,432.70
25,695.20
8,440.52
78,320.00 2,819.52
81,550.00 4,893.00
91,000.00 546.00
91,000.00 182.00
14,918.75
9,625.00 11,550.00
9,625.00 3,368.75
23,359.27
10% 2,335.93
25,695.20
31,662.70
8,440.52
78,320.00 2,819.52
81,550.00 4,893.00
91,000.00 546.00
91,000.00 182.00
20,343.75
13,125.00 15,750.00
13,125.00 4,593.75
28,784.27
10% 2,878.43
31,662.70
37,370.61
12,660.78
78,320.00 4,229.28
81,550.00 7,339.50
91,000.00 819.00
91,000.00 273.00
21,312.50
13,750.00 16,500.00
13,750.00 4,812.50
33,973.28
10% 3,397.33
37,370.61
44,190.61
12,660.78
78,320.00 4,229.28
81,550.00 7,339.50
91,000.00 819.00
91,000.00 273.00
27,512.50
17,750.00 21,300.00
17,750.00 6,212.50
40,173.28
10% 4,017.33
44,190.61
74,973.99
18,945.67
78,320.00 6,343.92
81,550.00 11,009.25
91,000.00 1,228.50
91,000.00 364.00
49,212.50
31,750.00 38,100.00
31,750.00 11,112.50
68,158.17
10% 6,815.82
74,973.99
94,534.57
8,440.52
78,320.00 2,819.52
81,550.00 4,893.00
91,000.00 546.00
91,000.00 182.00
77,500.00
50,000.00 60,000.00
50,000.00 17,500.00
85,940.52
10% 8,594.05
94,534.57
Stainlessteel 34,000.56
30,909.60
78,320.00 2,349.60
81,550.00 24,465.00
91,000.00 2,730.00
91,000.00 1,365.00
-
- -
- -
30,909.60
10% 3,090.96
34,000.56
56,667.60
51,516.00
78,320.00 3,916.00
81,550.00 40,775.00
91,000.00 4,550.00
91,000.00 2,275.00
-
- -
- -
- -
- -
51,516.00
10% 5,151.60
56,667.60
72,213.02
37,498.20
78,320.00 783.20
81,550.00 32,620.00
91,000.00 3,640.00
91,000.00 455.00
28,150.00
28,000.00 28,000.00
6,000.00 150.00
65,648.20
10% 6,564.82
72,213.02
41,033.52
10,303.20
78,320.00 783.20
81,550.00 8,155.00
91,000.00 910.00
91,000.00 455.00
27,000.00
27,000.00 27,000.00
37,303.20
10% 3,730.32
41,033.52
80,788.93
10% 8,078.89
88,867.83
Pipa Tanah Ø 15 cm 38,790.17
7,691.70
78,320.00 4,699.20
81,550.00 2,446.50
91,000.00 273.00
91,000.00 273.00
27,572.10
8,000.00 12,800.00
1,380.00 9,384.00
245,238.10 3,188.10
200,000.00 2,200.00
,
35,263.80
10% 3,526.38
38,790.17
123,226.66
17,947.30
78,320.00 10,964.80
81,550.00 5,708.50
91,000.00 637.00
91,000.00 637.00
94,076.93
47,190.00 51,909.00
675,000.00 18,225.00
1,380.00 5,409.60
245,238.10 13,733.33
200,000.00 4,800.00
112,024.23
10% 11,202.42
123,226.66
675,551.39
48,714.10
78,320.00 29,761.60
81,550.00 15,494.50
91,000.00 1,729.00
91,000.00 1,729.00
565,423.52
150,000.00 165,000.00
675,000.00 371,250.00
1,380.00 14,214.00
245,238.10 14,959.52
200,000.00 13,800.00
614,137.62
10% 61,413.76
675,551.39
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
18 A.4.2.1.19 1 m' Pemasangan 1 m Talang ½ Lingkaran D-15 cm, Seng Pelat bjls 30 86,945.10
A Tenaga 39,671.00
L.01 0.15 OH Pekerja 78,320.00 11,748.00
L.02 0.3 OH Tukang Kayu 81,550.00 24,465.00
L.03 0.03 OH Kepala Tukang 91,000.00 2,730.00
L.04 0.008 OH Mandor 91,000.00 728.00
B Bahan 39,370.00
1.05 Lbr Seng Plaat 29,000.00 30,450.00
0.01 Kg Paku Biasa 1 - 2,5 cm 17,000.00 170.00
0.5 Kg Besi strip 17,500.00 8,750.00
C PERALATAN
D JUMLAH A + B +C 79,041.00
E Overhead & Profit (contoh 10%) 10% 7,904.10
F Harga Satuan Pekerjaan (D+E) 86,945.10