Shtokman project development: phase 1 Assets up to the challenges

SPV

Shtokman : A World class project


Huge IGIP : 3.7 Tcm equivalent to 1.3 years of world gas consumption today
760

Security through a worldwide market with diversified supply


+275 -140 -525 900 235 Europe FSU 760 1015 740

A need for Russia A need for European gas market

North America

-150 570 +270 +250 390 +20 Africa 140 Middle East 810 540 AsiaOceania 720

A need for US LNG markets

200 220 South America


Production Consumption Exports Imports

Production/Consumption (2020) = 4000 Bcm Trade = 815 Bcm

But also paving the way to develop the Oil and Gas reserves in Arctic

A world class Russian project under the spotlight of the World energy sector

SPV
2

A World class project


Huge IGIP : 3.7 Tcm equivalent to 1.3 years of world gas consumption today A need for Russia

Security through a worldwide market with diversified supply


+275 -140 -525 900 760 235 Europe FSU North America -150 570 +270 +250 390 140 Africa Middle East 810 540 AsiaOceania 720 760 1015 740

A need for European gas market A need for US LNG markets

+20 200 220 South America

Production Consumption

Exports Imports

Production/Consumption (2020) = 4000 Bcm Trade = 815 Bcm

But also paving the way to develop the Oil and Gas reserves in Arctic

A world class Russian project under the spotlight of the World energy sector

SPV
3

Brief field characteristics


The field was discovered in 1988 Seven exploratory/delineation wells have been drilled Extension of field 4836 km 4 producing formations J0, J1, J2 and J3 Offshore distance is about 600 km Sea depth in the field area is up to 350 m Gas in Place (C1+C2): 3,819 bn m3 Condensate in Place: 36,9 m metric tons Good petrophysical characteristics low CGR Low CO2 content No H2S
Top J0 depth map

SPV
4

Main principles of Shtokman Development

Floater

Onshore Installations

Offshore trunk line

SPV
5

North sea

LNG

Barents sea Teriberka

Shtokman field

Vyborg

Gas pipe Russia

Greisfald

SPV
6

Shtokman Field : A 3 phase development


Number of floaters: 3
Number of subsea production complexes , each for 8 wells: 7 Number of 42 600 Km trunk lines: 3

Phase 3 Phase 1

Template

Phase 2
Template Template Template Template

Template Template
7

SPV

Shtokman Field : A 3 phase development

Phase 1

Phase 2

Phase 3
8

SPV

The Shtokman Phase 1 Project Partners


SEVMORNEFTEGAZ Ltd

The Framework Agreement for Cooperation in the Development of the First Phase of the Shtokman Gas Condensate Field was signed with TOTAL Company on 13 June 2007

The Framework Agreement for Cooperation in the Development of the First Phase of the Shtokman Gas Condensate Field was signed with StatoilHydro Company on 25 October 2007

SPV
9

Framework for the phase 1 of the Shtokman development


Scope
Organize, design, finance, construct and operate the Shtokman phase 1 development Include: Offshore development, Offshore trunk line, Onshore receiving facilities, LNG plant (7.5Mty), and all associated facilities ( logistics etc..) including the ones necessary for the subsequent phases. Not including: LNG shipping, onshore pipe to Vyborg Production plateau of 23.7 Gm3/year ( i.e 70 MM cm/d # 400 000 bepd equivalent) ( 7,5Mty liquefied, 5 % gas for local market, the rest piped to North Stream network)

Creation of an Offshore Company with a branch in Russia (Special Purpose Vehicle (SPV))
Participating interests in SPV:

Gazprom 51% Total 25 % StatoilHydro 24%

North sea

LNG

Barents sea Teriberka

Shtokman field

Vyborg

Gas pipe Russia

Greisfald

SPV

10

Framework for the phase 1 of the Shtokman development

A single integrated dedicated Project Team Gazprom / Total / StatoilHydro Synergy of Russian and European cutting-edge skills and technologies
Sharing of knowledge and resources optimization

Key Dates for Phase 1:


FEED Contract award: November/December 2007 Final Investment Decision: 2009 Start gas export by pipeline: 2013 Start of LNG exports: 2014

CAPEX about 15 G$

SPV
11

Phase 1 development: General arrangement summary


Upstream
3 sub sea templates (20 wells) and associated flow lines and risers Floating processing & ice-resistant platform (FPU, SPAR or similar): gas & condensate dehydration, compression, utilities, living quarter (Disconnectable?) One 42, dry 2 phase transport to shore via 550 km subsea pipeline Ice and Iceberg management

Onshore plant near Murmansk - Teriberka


Receiving facilities, Gas treatment facilities LNG plant : Gas liquefaction (7.5 Mt/year) LNG Gas & condensate storage Harbor & export facilities (LNG & Condensate) All others facilities required to operate the Offshore and onshore installations

SPV
12

Shtokman phase 1 development: Main Challenges

A world class project with extraordinary challenges in a frontier environmental context Technical challenges Planning and costs challenges Organization and human challenges
SPV
13

A challenging environmental context


Arctic conditions, Barents sea with extreme weather conditions:
Design impact Operating conditions Construction windows limited

At the eve of a huge development in Murmansk area . The project shall be integrated in the local context

Essential to preserve the environment in a


sensitive ecosystem

SPV
14

Technical Challenges : Offshore Facilities


Topsides operating weight up to 45 000 tons ( production is 400 000 Bepd equivalent !) Two (2) main concepts - to be ice resistant and disconnectable - under preliminary design and evaluation HSE and Operational aspects

15
Sail Consolidated Layer

Ridge elevation (m)

- 15 Keel Keel

- 30 0
15

50

100 Ridge width (m)

150

200 SPV

Technical challenges : Export pipeline to shore


The Dry 2 Phase transport challenges:
Offshore riser arrangement (high flow rates) Large diameter and high design pressure pipeline Liquid Hold-up in the range 30 70 MSm3/d to be managed in operations Size of the 2 phase slug catcher onshore to be optimized . Constructability and shore approach difficulties Optimization between pipe diameter / Inlet & outlet pressure / maximum liquid hold-up / operating conditions (minimum maximum flow-rates)

SPV
16

Technical challenges : LNG plant: specific site conditions


Design capacity = 7.5 Mt/year Main aspects for optimization and design:
Arctic climate Winterisation Construction constraints (stick built / modular) Appropriate design: number of trains, driver selection, cooling media, reservation for next phases..

SPV
17

Technical challenges : Associated facilities - Logistics


600 Km offshore from Murmansk Supporting facilities for onshore and offshore installation Thousands of construction workers during the construction peak activities

SPV
18

Planning and Costs Challenges

Tight schedule
FEED in 2007 FID in 2009 ( based on EPC tenders analysis) First pipe gas in 2013, First LNG in 2014

Budget: Keep budget under control and always maintain a high level of competitiveness

Need Innovative and robust solutions in Planning and Cost optimization

SPV
19

Organization and Human Challenges

An efficient project organization with proper delegation of authorities already set up An organization with a strongly motivated team, success oriented 3 different but complementary cultures being one of the project asset

One of our most important challenge

SPV
20

Assets up to Challenges for a new frontier project


The Shtokman project has some considerable assets to balance its challenges
Gazprom strong leadership The project partners - all have a strong expertise Benefit of Russian, French and Norwegian culture Expertise already developed within Russian institutes High level of education allowing access to locally qualified resources A Russian project benefiting of Russian industrial network, local content and Regional expertise and experience. International contractors eager to join this new frontier project

Project assets balance the project challenges


21

SPV

The Shtokman Project phase 1 , in brief .. One of the top world class project with exciting challenges balanced by robust assets A challenging project to be developed with a Russian, Regional and International cooperation A Russian project with a world class partnership to :
Increase gas delivery and Improve the energy security to the world market by 2013. Pave the way for an efficient development of the Arctic Shelf with

the highest standards in terms of Safety Heath and Environment.

SPV

22

Shtokman project development: phase 1 A project with assets up to the challenges

Thank you

SPV

Technical challenges
Ice conditions & Iceberg Management
In 2003, more than 15 icebergs have been observed close to Shtokman, 2 of them weighting more than 3 millions tons

=> Disconnectable floating support ?

Ice conditions => Offshore Facilities have to be ice resistant

SPV
24