Paper published in Proceedings of the International Workshop on Advanced Design of Maritime Structures
in the 21st Century, March 5-7 2001 at the Port and Harbour Research Institute, Yokosuka, Japan
April 2001
1
Integral optimisation design techniques and neural networks
Jentsje van der Meer
Infram, PO Box 16, 8316 PT Marknesse, Netherlands, jentsje.vandermeer@infram.nl
Roy Stroeve and Rico Sies
Directorate-General of Public Works and Water Management, Utrecht, Netherlands
ABSTRACT: This paper deals with two advanced design methods in coastal engineering that will gain more
attention in the 21st century. An integral optimisation technique has been used for the design of a land recla-
mation in the North Sea for the future extension of the port of Rotterdam. The method was based on an inte-
gral economical optimisation taking into account all costs and risks related to the maritime structures simulta-
neously. Another innovative design tool is the development and application of a neural network. Neural
networks are used in many areas and some applications have already been developed for design of maritime
structures. A few applications are given and the advantages and disadvantages of such a system.
1
Figure 1. Considered layout of Maasvlakte II
Functional failure costs occur in case the structure Damage (repair and
fails to perform its function. Functional failure of functional failure)
2
1.4 System analysis of damage events 1.5 Failure costs
Damage to hydraulic structures is mainly caused by The failure events generate damage successively. In
extreme water levels and wave attacks during contrast with the construction costs, the damage is
storms. The analysis of the possible failure costs has taken into account every year during the life cycle of
been performed by tracing the waves from the North Maasvlakte II by calculating the yearly expected
Sea penetrating the harbour during storm conditions. damage and taking into account interest effects. A
Large waves may erode the dunes and displace the computation according to the principle “probability
concrete blocks of the breakwater. Wave transmis- times effect” yielded the yearly expected costs,
sion over and wave penetration along the front of the where the probability mainly depends on the unpre-
breakwater can cause wave heights that obstruct the dictable character of the hydraulic conditions. There-
shipping operations behind the breakwater. Tug- fore, the joint statistics of water heights and waves
boats, which are essential for large ships for entering heights have been determined probabilistically at the
into and manoeuvring in the harbour, are not able to boundary of Maasvlakte II. The wave propagation in
hook to the ships safely, because of the rough con- the harbour has been calculated with a wave
ditions. At the quay, waves can on the one hand transmission formulation for the breakwater and the
obstruct the transhipment, and on the other cause results of a wave penetration study for the entire
inundation by overtopping the quay. These events harbour layout.
contribute to the damage and will thereby influence For the sake of simplicity, in this study solely the
the optimal design. principal dimensions of the structures are varied.
The scheme in Figure 3 shows the existing rela- They also determine the total costs the most. These
tions between the structures of Maasvlakte II. The dimensions are the ‘tuning-scales’ of the optimisa-
crest height of the breakwater influences the optimal tion. Other, less important design parameters have
surface level of the industrial area, because the wave not been varied in the calculations. The principal
transmission over and through the breakwater influ- dimensions are given in Table 1 and Figure 4. The
ences the wave climate in the harbour. By conside- formulae used for the breakwater (stability and
ring the structures at Maasvlakte II as an interactive transmission) will be described in more detail.
system with coherence between the structures, the
calculations will result in a well balanced optimal
integral design.
Shoaling water
wave
penetration Hydraulic conditions
overtopping in harbour
and overflow
Wind
Hydraulic conditions
overtopping
and overflow in front of quay
obstruction trans-
geometrics and strengh shipment
Erosion sea defense
sea defence and industrial area Surface level of industrial area
Boundary of
project area
3
Table 1. Considered dimension of the hydraulic strutures B =
crest width
Hi =
incident significant wave height
Element Principal dimension ξ =
breaker parameter
industrial area surface level of industrial area Astr =
a coefficient depending on the type of struc-
breakwater crest height of breakwater, ture:
diameter concrete blocks rock slopes and concrete units: Astr = 0.64
sea defence width of dunes smooth impermeable dam (asphalt) Astr = 0.80
impermeable smooth block revetment Astr = 0.80
block mattresses Astr = 0.75
gabion matresses Astr = 0.70
sea harbour sea The standard deviation around the formula is
given by σCt = 0.06, resulting in a 90% confidence
dune band of Ct ± 0.10. For cubes the value of Astr = 0.64
breakwater Industrial
was used.
area
1.7 Life cycle cost
Figure 4. Cross-section of the area with prinipal dimen-
sions The life cycle cost can be calculated as follows, as a
function of the dimensions of the structures:
4
Table 2. Comparison of optimal and actual dimensions Table 5. Probability of (functional) failure events opti-
of the hydraulic structures mal design
Optimal Actual dimensions Probability of failure events [yearly probability]
Parameter
design Maasvlakte I inundation depth > 0.1 m once every 97 year
surface level of NAP NAP + 5.0 m obstruction of transhipment 0.107 days / year
industrial area + 4.5 m Nod > 0.5 once every 79 year
crest height NAP NAP + 2.5 m
breakwater + 2.5 m Considering the preliminary design, the crest height
diameter concrete 2.1 m 2.55 m of the breakwater seems to low (NAP + 2.2 m) and
blocks breakwater provides the harbour relatively little protection to the
waves. The low breakwater leads to a higher
probability of obstruction for shipping than the
Table 3. Probability of damage events of actual optimal breakwater. Inundation occurs with higher
dimensions
frequency than in the optimum, which also is the
Probability of failure events [yearly probability] result of the lower surface level of the industrial
inundation depth > 0.1 m once every 432 year area. Although the construction costs of the optimal
obstruction of transhipment 0.076 days / year design are about 40 M€ higher than with the preli-
Nod > 0.5 never minary design, the failure costs however are 170 M€
lower. This leads to 130 M€ net of saving expenses
considering the life cycle. It is attractive to invest
1.9 Optimal design for Maasvlakte II more in construction costs, because later on this
When considering life cycle costs, it is optimal to investment will pay back by lower operational costs.
construct the industrial area fairly high above mean One of the reasons to raise the crest height of the
sea level (chart datum is called NAP). The optimum breakwater to the level NAP + 4.5 m in the reference
value became NAP + 6.5 m. The optimum width of design was the preliminary result of this study. The
the sea defence (dune) is 70 m. Economically it is final results of the optimisation study show that
preferable to design the crest height of the break- the crest height of the breakwater of the reference
water not only for protection of the shipping, but design is 1 meter higher than the optimum. The other
also to protect the industrial area to inundation by dimensions of the hydraulic structures are so near
overtopping. This twofold function leads to a crest the optimal value that the total life cycle costs of the
height of NAP + 3.5 m, which leads to obstruction of reference design are ‘only’ 15 M€ higher than the
transhipment with an average occurrence of 1 day optimum.
per year. Not only the optimum value of a parameter is
In the optimisation of the breakwater armour important, also the shape of the life cycle costs near
layer, besides the costs of complete failure of the the optimum may give valuable information. The
breakwater, also the maintenance costs for occur- global picture in Figure 2, for example, has a very
rences of initial damage has been taken into account. flat optimum. Without increasing costs significantly,
This is often called a ‘maintenance-aware’ design. it would be advisable, based on Figure 2, to chose a
Considering the life cycle, it appears to be optimal to larger “strength value” for design than the optimal
use concrete blocks of 2.8 m (50 tons). This leads to strength. A (much) lower failure probability would
initial damage on an average return period of 370 be reached without extra costs.
years. The mean time between significant damage Two of these life cycle cost pictures are presented
events is about 70,000 year. in Figures 5 and 6, one for the surface level of the
industrial area and one for the crest height of the
breakwater. In Figure 5 the optimal height of the
Table 4. Comparison of optimal dimensions of the industrial area is found for NAP + 6.5 m. A lower
hydraulic structures with the reference design and the value will increase damage costs (flooding), a little
preliminary design higher value to NAP + 7 m would not increase (con-
Optimal Reference Preliminary
struction) costs significantly. A higher value than
Parameter this NAP + 7 m would indeed increase construction
design design design
surface level of NAP NAP NAP costs, and therefore, total life cycle costs. A level
industrial area + 6.5 m + 5.8 m + 5.6 m between NAP + 6.5 and + 7 m would be a good
crest height NAP NAP NAP choice.
breakwater + 3.5 m + 4.5 m + 2.2 m Figure 6 shows the total life cycle costs for the
diameter concrete 2.8 m 2.7 m 2.7 m crest height of the breakwater. The minimum is
blocks breakwater found for NAP + 3.5 m, but there is hardly any diffe-
width of dunes 70 m 100 m rence in costs for crest heights between NAP + 3.5
and + 5 m. A crest height lower than NAP + 3.5 m
5
would increase the damage costs and is not recom- 1.10 Dealing with uncertainties
mended. But actually the designer has some freedom
The method to determine the optimal dimensions of
between above given values, despite the fact that the
the structures is subject to many uncertainties, al-
exact optimum is found for NAP + 3.5 m.
though they do not play an equally important role.
Every parameter used in the calculations is a source
of uncertainty. An extensive sensitivity analysis has
shown the significant parameters that influence the
optimum. Attention should be paid to these parame-
ters. The optimum is sensible especially for uncer-
tainties concerning wave statistics, wave propaga-
tion in and outside the harbour and the determination
of the inundation depth on the industrial area. More-
over, an expectation of future interest rates and eco-
nomic growth is very important, since these parame-
ters influence the optimum quite strongly.
2.1 Introduction
Table 6. Costs over the life time of the area in millions of Another innovative design tool is the development
euro (close to US$) in the optimal design situation and application of a neural network. Neural net-
Description costs (M€) works are used in many areas and some applications
have already been developed for design of maritime
Damage to industrial area 42 structures. Mase et al. (1995) used the extensive data
Damage to breakwater 2 of Van der Meer (1988) to develop a neural network
Damage to dunes 2 for stability of rock slopes. Van Gent and Van den
Damage by obstruction of transhipment 20 Bogaard (1998) describe a neural network for wave
Total damage costs 66 forces on a vertical structure, which can be com-
pared with the Goda formula. Medina (1999) devel-
Construction costs breakwater 250 oped a neural network for wave run-up and overtop-
Construction costs quay walls 605 ping on breakwaters.
Construction costs industrial area 589 This section of the paper will discuss criteria for
Construction costs dunes 311 development and application of a neural network.
Total construction costs 1755 The paper will describe the differences between the
stability formula and the neural network and the ad-
Total life cycle costs 1821 vantages and disadvantages of both methods. It will
also show the possibility for developing a new neu-
6
ral network for wave overtopping, based on a large (training set). After the training, or learning proce-
database, mainly developed in ten years of coopera- dure, the neural network needs to be validated by us-
tive European research. ing the remaining part of the data set.
7
Figure 9. Comparison between measured and predicted
stability numbers by neural network prediction (Mase et
al., 1995) Figure 11. Comparison between measured and predicted
damage levels by neural network prediction (Mase et al.,
Both figures show a similar behaviour and the 1995)
neural network does not predict better than the fom-
ula or vice versa. In figures 10 en 11 similar graphs Comparison of the two figures leads to a few con-
are given, but now for the damage level S. The dam- clusions. In the actual area of application (no dam-
age level in design of rock layers varies between 2- age up to underlayer visible, S=2-12 or 17) there is
12 for steep slopes and 3-17 for gentle slopes. The hardly difference between both methods. Beyond the
range considered in figures 10 and 11 shows values high damage levels the neural network predicts
of S up to 40. These values mean large reshaping of much better, due to the fact that the network was
the structure and were not considered in the predic- trained for such values, where too extreme values
tion formulae of Van der Meer (1988). were ignored in the stability formulae. One conclu-
sion is the neural network predicts better, the oppo-
site site is that the neural network predicts values
with hardly any physical meaning.
Van Gent and Van den Boogaard (1998) used
various data sets from various laboratories, all de-
scribing the horizontal force on a vertical structure
(with or without inclination of the top, with or with-
out a berm). The comparison of the neural network
with measured values is given in the left graph of
Figure 12. The right graph of this figure gives the
prediction with the Goda formula.
Also here a few conclusions can be drawn. First
of all the neural network gives a better prediction
than the Goda formula. But one should consider the
fact that the Goda formula was not calibrated or
trained on the data set used, where the neural net-
work was. This is different with the neural network
of Mase et al. (1995) and the Van der Meer formula,
where both were based on exactly the same data set.
The right graph in Figure 12 shows in fact how the
Goda formula behaves for all kind of vertical struc-
tures in all kind of situations, and a direct compari-
son with the neural network is in fact not completely
Figure 10. Comparison between measured and predicted fair.
damage levels by Van der Meer’s formula (Mase et al.,
1995)
8
Figure 12. Comparison of measured and predicted horizontal forces on vertical structures. Left the neural network pre-
diction, right the Goda formula. From Van Gent and Van den Bogaard (1998).
Medina (1999) developed a neural network for quired, the programme gives directly the answer
wave run-up and overtopping. They used only one needed.
data set and only a limited amount of tests. A con-
ventionally determined formula would also have fit-
ted to the data. The main conclusion on Medina’s References
work is that it is indeed possible to develop a neural Mase, H., M. Sakamoto and T. Sakai, 1995. Neural net-
network for wave run-up and overtopping. work for stability analysis of rubble mound break-
waters. ASCE, J. of WPC&OE, 121(6): 294-299.
Medina, J.R., 1998. Neural network modeling of runup
2.5 Future applications and overtopping. Proc. Coastal Structures ’99, San-
Of course many applications are possible, as long tander, Spain. Balkema, Rotterdam, ed. Losada.
as the phenomenon is complex and data is available. Van der Meer, J.W., 1988. Rock slopes and gravel
Two possible future applications will be described. beaches under random wave attack. PhD thesis Delft
Many data sets are available on wave overtopping University of Technology, The Netherlands.
at all kind of coastal structures, such as dikes, rubble Van der Meer, J.W., 1998. Geometrical design of coastal
mound coastal protections and (nearly) vertical sea- structures. In “Dikes and revetments”, chapter 9. Ed.
walls. Very often a formula was derived for each set K.W. Pilarczyk, Balkema, Rotterdam.
of data or each set of tests. No general prediction Van der Meer, J.W., 1999. Design of concrete armour
formula is available which covers all kind of coastal layers. Proc. Coastal Structures 99, Santander Spain.
structures. This is also hardly or not possible. Van Gent, M.R.A. and H.F.P. van den Bogaard, 1998.
Neural network and numerical modelling of forces on
And, therefore, this is the ideal situation for de-
vertical structures. ASCE, Proc. ICCE ’98, Copen-
velopment of a generic prediction method on wave
hagen, Denmark.
overtopping by means of a neural network. The ex-
tensive testing in Europe over the last decade, very
often in co-operative research for the European
Community, contains about 3000 – 5000 tests on
wave overtopping at all kind of coastal structures.
Another possible application has correlation with
the work of Van Gent and Van den Bogaard (1998).
It is not possible to predict the horizontal wave force
on a vertical structure, there are enough data sets to
develop a neural network for vertical uplift forces
underneath such structures.
Although the development of a neural network
may be fairly complicated, the application of a
trained neural network is very easy. It is comparable
to a spreadsheet calculation: input parameters are re-