NICMAR
PGPM 24
Assignment
Enhancing the level of the energy consumption, particularly in less developed and developing countries, is a global challenge. 20 % of world population living in industrialized countries consumes 60 % of energy and remaining 80% of population has to manage within 40% of total energy. This has obliviously resulted in wide disparities between the standard of living and quality of life of high energy consuming countries on the one hand and those who dont have the opportunities of adequate access to energy on the other. It is precisely for these reasons that development of different sources of energy and increase in its consumption has become a priority agenda of all the developing countries.
In the light of the above, prepare an assignment on how to solve the problem of energy deficiency in India by alternate sources of energy.
The assignment should cover the following: 1. Indias Energy Sector 2. Power Sector present scenario 3. Growth of Power sector 4. Investment in power sector 5. Current problems in Power Sector 6. Demand Supply Gap 7. Strategies in achieving Power for all
NICMAR
PGPM 24
NICMAR
PGPM 24
2. Power sector present scenario In past our growth rates of gross domestic product (GDP) have been such as to double our per capita income over the period of 20 years. The changing world scenario Political, economical, social and cultural has proven to all of us that such a growth rate will reduce Indias stature in the world and put it in the receiving end of the game. Indias Power sector can be classified by the generation of electricity using different fuels such as Thermal, Hydro, Nuclear and Renewable Energy Sources (RES).
Fuel Total Thermal Coal Gas Oil Hydro Nuclear Renewable Energy Sources (RES) MW 118695.98 99753.38 17742.85 1199.75 38706.40 4780 20162. 24 %age 65.09 54.70 9.73 0.65 21.22 2.62 11.05
NICMAR
PGPM 24
Power VS Overall
NICMAR
PGPM 24
Plan wise Outlay 2448 7294 19265 15902 39287 95700 15.39 18.57 20.13
Power VS Overall
Plan wise Expenditure 2932 7399 18299 15779 39426 109291 18.58 18.77 16.74
NICMAR
PGPM 24
The investment in power sector over the 10th plan (actual), 11th plan (proposed) and 12th plan (projected) is depicted below,
Figures in US $ Billion
In INR total investment in power sector in Xth plan was Rs 291,850 Cr or US$ 60 billion. For the XIth plan the INR figure is Rs 666,525 Cr out of which Rs 185,512 Cr is private sector share.
NICMAR
PGPM 24
Though the investment targets by the government has been kept at around US$ 133 billion, the actual investment is however, expected to be around US$ 86 billion primarily on account of slippage in the target achievement by central sector. A power project implementation period is around 36 to 48 months from the date of award of the mandate and hence only those projects which have been cleared up to march 2008would be in position meets the target date. One can keep un awarded central projects out of the purview of the target achievement figures and on that account alone, a total of over US$ 15 billion will remain un-realized. Similarly there could be slippages in the already awarded projects and therefore a shortage of around US$ 20 to 25 billion is expected during the XIth plan period.
NICMAR
PGPM 24
consumers is heavily subsidized. Only a part of this subsidy is recovered by SEBs through cross subsidization of tariff from commercial and industrial consumers. The SEBs in the process, have been incurring heavy losses. If the SEBs were to continue to operate on the same lines, their internal resources generation during next ten years will be negative, being of the order of 77,000 crore. This raises serious doubts about the ability of the states to contribute their share to capacity addition during the ninth plan and thereafter. The highlights the importance of initiating power sector reforms at the earliest and the need for tariff rationalization. Other problems in power sector of India are: A. Inadequate power generation capacity. B. Lack of optimum utilization of existing generation capacity. C. Inadequate inter transmission links. D. Inadequate and aging sub-transmission & Distribution network leading to power cuts and local failure. E. Large scale theft and skewed tariff structure. F. Slow pace of rural electrification.
NICMAR
PGPM 24
since 2002-03, reflecting buoyant industrial demand. Industrial consumers are the largest group of electricity consumers, followed by the domestic, agricultural and commercial consumers, in that order. Indias per capita electricity consumption increased from 178 kWh in 1985-86 to 704.4 kWh in 2007-08. Over the period, 2001-08, per capita consumption has increased at an average rate of 4.45 per cent. It is still much lower compared to the international standards. Electricity Demand and Supply FY Energy (MU) Demand Availability Shortage 2002-03 545,983 497,890 48,093 2003-04 559,264 519,398 39,866 2004-05 591,373 548,115 43,258 2005-06 631,024 578,511 52,513 2006-07 693,057 624,716 68,341 2007-08 737,052 664,660 72,392 2008-09 777,039 691,038 86,001 2009-10 830,594 746,644 83,950 Electricity Requirement % 8.8 7.1 7.3 8.3 9.9 9.8 11.1 10.1 Peak Demand (MW) Demand Met Shortage 81,492 71,547 9,945 84,574 75,066 9,508 87,906 77,652 10,254 93,214 81,792 11,422 100,715 86,818 13,897 108,866 90,793 18,073 109,809 96,785 13,024 118,472 102,725 15,747 % 12.2 11.2 11.7 12.3 13.8 16.6 11.9 13.3
The demand for power is expected to increase to 975 billion kWh by 2011-12. However, at an average GDP growth rate of 8 per cent, the overall demand is expected to increase to about 1,097 billion kWh in 2011-12, including the demand from non-utilities. The 17th Electric Power Survey (EPS) has forecast a peak demand of 152,746 MW for 2010-11. That means a capacity addition requirement of about 72,000 MW during the Eleventh Plan period. Though the target set for capacity addition during the Eleventh Plan period is 78,700 MW, only 62,000 MW is expected to be added by the end of the period.
10
NICMAR
PGPM 24
Projected Requirement of Electricity Energy Requirement (Billion kWh) GDP growth at 2003-04 2006-07 2011-12 2016-17 2021-22 2026-27 2031-32 8.0% 633 761 1,097 1,524 2,118 2,866 3,880 9.0% 633 774 1,167 1,687 2,438 3,423 4,806 8.0% 89 107 158 226 323 437 592 Peak Demand (GW) 9.0% 89 109 168 250 372 522 733 8.0% 131 153 220 306 425 575 778 Installed Capacity Required (GW) 9.0% 131 155 233 337 488 685 960
Capacity Addition Plan The following table provides the Eleventh Plan targets for adding generation capacity. In a reversal of the trend witnessed during the 1990s, a substantial contribution is expected from the hydropower sector. Also, the private sector is expected to account for 15 GW of the planned capacity addition of 78.7 GW during this period. Installed Capacity Addition Plan (MW)
Sector 11thPlan Total Central State Private Thermal 59,693 24,840 23,301 11,552 Hydro 15,627 8,654 3,482 3,491 Nuclear 3,380 3,380 Grand Total 78,700 36,874 26,783 15,043
Recognizing the large potential of coal reserves in the country as an economic and readily available resource, a significant proportion of the future capacity additions is expected to be based on coal. Further, to reduce the environmental impact and to increase efficiency, the strategies proposed by the power ministry include introduction of large-sized units (660-800
11
NICMAR
PGPM 24
MW) employing the super-critical technology. The source-wise capacity addition as envisaged under Eleventh Plan period is as given below: Additional generation capacity would require commensurate investments in transmission infrastructure as well. Huge transmission capacity enhancement is required under Phase-III of National Grid Programme, which targets an inter-regional exchange capacity of 37,700 MW by 2012. With rapid industrialization and growing power requirements, many states have decided to set up high-capacity intra-state power transmission systems. PPP model is being adopted by many utilities to attract private investment in transmission sector. The future capacity addition plan envisaged is as given in the table below: Projected Transmission Line Length (Ckm)
12
NICMAR
PGPM 24
(100,000 MW), Transmission systems and distribution networks. The government role is revolving around following tasks: 1. Reliability of Power 2. Quality of power 3. Tariffs 4. Commercial viability of power industry Strategies to achieve Power for all Power generation Strategy with focus on low cost generation, optimization of capacity utilization, controlling the input cost, optimization of fuel mix, technology up gradation and utilization of non conventional energy sources. Transmission Strategy focus on development of national grid including interstates connections, technology up gradation and optimization of transmission coast. Distribution Strategy to achieve distribution reforms with focus on system up gradation loss reduction, theft control, consumer service orientation, quality power supply commercialization, Decentralized distributed generation and supply for rural areas. Regulation Strategy aimed at protecting consumer interest and making the sector commercially viable. Financing Strategy to generate resources for required growth of the power sector, conservation strategy to optimize the utilization of electricity with focus on demand side management, load management and technology up gradation to provide energy efficient gadgets. Communication Strategy for political consensus with media support to enhance the genera, public awareness.
13
NICMAR Bibliography:-
PGPM 24
1. NICMAR lesson book Power Plant Engineering (PGPM 24 ) 2. Position Paper on The power Sector in INDIA Dec 2009 3. Industry Insight Indian Power Sector 4. CEA, IMaCS Research 5. Website: www.powermin.nic.in
14