Distribution Transformers
A.F. Picanço1*, C de Salles1, M.L.B. Martinez1, P.C. Rosa1, H.R.P.M. de Oliveira2
1
Federal University of Itajubá and 2AES Sul Utility Company
Rua Cel. Rennó, 05, Itajubá, MG, Brazil, CEP 37500-050
Keywords: Cost of Losses, Demand, Design, Distribution II. MANUFACTURING AND TOTAL COST
Transformer, Energy, Optimization. SURFACES
2
⎛ kVAi
24
⎞
TSMP = ∑ ⎜⎜ ⎟⎟ (3)
i =1 ⎝ kVAN ⎠
This case considered variations on the current density of This new case considered variations on the current
the HV windings, on the insulation thickness and on the density of the HV windings, on the insulation thickness and
gap between the LV and HV windings, a different solution on the gap between the LV and HV windings. Tables 5 and
compared with the previous one. Tables 3 and 4 show a 6 show a comparison between the technical and economical
comparison of the technical and economical characteristics characteristics presented by the efficient and standard
presented by the efficient and standard designs. The set of designs. The set of results presents one local and six global
results presents one local and seven global minimum minimum points.
points. The three studies presented have a different number of
global minimum points. This is a normal result and is
Table 3 – Transformer designs presenting losses lower than the standard related to the optimization process and to some technical
Reduction of Reduction of No- Reduction of Load restrictions.
k
Total Cost [%] Load Losses [%] Losses [%]
0 5,57 2,92 36,25 Table 5 – Transformer designs presenting losses lower than the standard
1 5,53 2,82 36,23
Reduction of Reduction of No- Reduction of
2 5,14 2,04 35,88 k
Total Cost [%] Load Losses [%] Load Losses [%]
3 5,13 3,18 23,47
0 3,14 3,18 23,47
4 4,97 2,77 23,88
1 2,98 2,77 23,38
5 4,43 1,86 22,58
2 2,46 1,86 22,58
6 4,15 0,31 29,12
3 2,24 2,92 36,25
7 3,35 0 20,98
4 2,20 2,82 36,23
5 1,81 2,04 35,88
Table 4 – Economic results of Table 3 6 1,44 0,31 29,12
Operational
Reduction of Pay-
Cost Reduction Energy Saved
k the Total back, Table 6 – Economic results of Table 5
per unit, [MWh/Year]
Cost [%] [Years] Operational
[US$/Year] Reduction
Pay- Cost
0 5,57 1,71 55,85 0,9329 of the Energy Saved
k back, Reduction
1 5,53 1,73 55,72 0,9308 Total Cost [MWh/Year]
[Years] per unit,
2 5,14 1,95 54,48 0,9100 [%]
[US$/Year]
3 5,13 0,09 37,39 0,6246 0 3,14 0,16 20,92 0,3495
4 4,97 0,18 36,87 0,6149 1 2,98 0,33 20,08 0,3417
5 4,43 0,50 34,83 0,5818 2 2,46 0,93 18,98 0,3171
6 4,15 1,85 42,93 0,7172 3 2,24 3,33 30,41 0,5080
7 3,35 1,28 30,75 0,5137 4 2,20 3,39 30,30 0,5061
5 1,81 3,91 29,29 0,4893
In this case, one recommended solution is design (k=2), 6 1,44 3,81 22,49 0,3757
which presents a reduction of 30% in the current density of
the HV winding, 10% of insulation thickness and 20% of Design 2 (k=2) presents a good solution, in that it
the gap between the LV and HV windings when compared presents a reduction of 10% on the current density of the
to the standard project of a distribution transformer. This HV winding, 10% of the insulation thickness, which must
can be attractive due to the fact that the technical and be verified by proper dielectric checking, and a rise of 20%
economical characteristics are quite close and that this of the gap between the LV and HV windings as compared
solution presents a lower manufacturing cost compared to to the standard values. In this case the amount of copper is
the local minimum point (k=0), reducing the investment. reduced and the solution presents an operational cost close
Figure 10 shows a daily load cycle with a TSMP of 4.5. to the minimum point. The payback is 0.93 years and there
is an energy savings of 0.3171 MWh per year.
Design 5 (k=5) is also a satisfactory solution when
energy savings is a priority in the utility policy. The
constructive parameters result in a reduction of 30% on the
current density of the HV winding, 10% of the insulation
thickness and 20% of the gap between the LV and HV
windings. The payback is 3.91 years and energy saved is [3] Blume, L.F., Boyajian, A., Camilli, G., Lennox, T.C.,
0.4893 MWh per year. Minneci, S., Montsinger, V.M. “Transformer Engineering:
Finally, the shape of the total cost surface for this case is A Treatise on the Theory, Operation, and Application of
shown in Figure 11. Transformers”. John Wiley&Sons, Inc., 1951.
[4] Bean, R.L., Chackan, N., Moore, H.R., Wentz, E.C.,
“Transformers for the Electric Power Industry”. McGraw-
Hill Book Company, Inc., 1959.
7800
[5] DelVecchio, R.M.,Poulin,B.,Feghali, P.T.,Shah,
7600
D.M., Ahuja, R. “Transformer Design Principles” CRC
7400 Press, 2001.
Total Cost
Alessandra Picanço acknowledges the financial support Credson de Salles was born in 1975 in Bueno Brandão, Minas Gerais
of CAPES, AES-Sul S.A. and PROCOBRE BRASIL. She State, Brazil. He received his B.Sc and M.Sc in electrical engineering in
from the Federal University of Itajubá where nowadays is a PhD Student.
also acknowledges the Prof. Dr. Estacio Tavares
Wanderley Neto for your support.
Hermes R. P. M. de Oliveira was born in 1960 in São Lourenço, Minas
Gerais State, Brazil. He received his B.Sc. and M.Sc. degrees in electrical
VIII. REFERENCES engineering from EFEI (UNIFEI). He has worked in AES Sul Company
since 1998.
[1] European Copper Institute. “The Scope for Energy
Saving in the EU through the Use of energy-Efficient Manuel L.B. Martinez was born in 1959 in Santos, São Paulo State,
Brazil. He received his B.Sc. and M.Sc degrees in electrical engineering
Electricity Distribution Transformers”. European
from the Federal University of Itajubá (UNIFEI) and Ph.D. degree from
Communities, 1999. PEA-USP. He has been responsible for the High Voltage Laboratory of
[2] U.S. Department of Energy. “Distribution UNIFEI since 1995.
Transformers Final Rule Technical Support Document –
TSD”. Washington, DC 20585, 2007.