DESIGN
ENGINEERING
Products
Products
PROVIDE ON-TIME DELIVERY REDUCE LEADTIME MINIMIZE INVENTORY REDUCE CUSTOMER PRICES
Increasing Cost
Optimal Range
Set up costs
Inventory costs
Week 1
Week 2
Week 3
Week 4
1000 units ship
Problem:
The present demand is met but the lead time is too long. I want shorter lead times for 1000 units.
Problem:
I want to reduce the amount of inventory in the system.
Batch Build with Simple Stocking Solution: Step 1. Reduce cycle time by reducing lot sizes.
Order Placed for 1000 units
Work Center A
Work Center C
The smaller the order size, the less time a job spends at each work center and the less time it takes to move through the plant.
Batch Build with Simple Stocking Step 2. Deliver smaller quantities, more frequently.
500 unit order placed A Inv. = 500 B Week 1 500 units inventory ship Week 2 500 units ship C 500 unit order placed A B Week 3 Week 4 C 500 Units Inventory Replenished
Near zero lead time Inventory cut to 500 units Twice as many orders placed
Batch Build with Simple Stocking Solution: Step 1. Reduce cycle time by reducing lot sizes Step 2. Reduce inventory
250 unit order placed A B Inv. = 250 Week 1 250 units inventory ship Week 2 250 units ship 250 units ship Week 3 Week 4 250 unit order placed C A B 250 unit order placed C A B 250 unit order placed C A B C 250 Units Inventory Replenished
Inventory cut to 250 units Near zero lead time Four times as many orders placed
Shorter Turns =
order order order order order order order order order order order order ship
Lower Inventory
Week 1
ship ship ship ship
Week 2
ship ship ship
Week 3
ship ship
Week 4
ship ship
With no stock in the system our stocking program turns into a CONTINUOUS FLOW system.
OBJECTIVE: IMPLEMENT QUICK FIX TO MEET LEAD TIMES METHOD: USE FORECAST TO ANTICIPATE DEMAND
Forecast in paper form - too tough to manage Develop software to receive forecast electronically Merge forecast with our own MRP data Generate reports that show us what to build eliminate process of manual discovery
The Solution - Step 2 OBJECTIVE: DETERMINE IF A CONTINUOUS FLOW MODEL CAN BE ADAPTED TO THIS CUSTOMER METHOD: ANALYZE ACTUAL PART DEMAND RESULT:
TYPICAL PART DEMAND OVER TIME PROCESS DEMAND OVER TIME
Time
Process Demand
Part Demand
Time
The Solution - Step 3 OBJECTIVE: REDUCE TIME IN THE PROCESS METHOD: ANALYZE AVERAGE CYCLE TIME FOR ALL PARTS RESULT:
2 Days
8 Days
4 Days
4 Days
6 Days
2 Days
SHEAR Engineering Review Order material/pre-sheared blanks (3 to 7 days) Queued at shear Shear < 1hr DATA ENTRY Queue order Put order in system Stuff shop router packet
FORMING PAINT Queue 3+days Queue at Brake = 3.7hr painter, 4+days Return to warehouse, 1day SHIP Re-pack parts Load truck
METHOD: USE LEAN MANUFACTURING TECHNIQUES, KAIZEN PRINCIPLES (5S, ETC.). START AT THE END OF THE PROCESS
# of Tools
Turret / Tooling
The Solution - Step 4 ADDITIONAL RESULTS: Developed press brake tooling identification scheme. Tools documented by their I.D. on setup sheets. Standardized blank sizes from >100 unique blanks to 20. Our supplier agreed to maintain these sizes for us on their floor - reducing raw material lead time down to 1 day. Cross trained (2) additional people to perform order entry function.
2 Days
2 Days
2 Days
4 Days
1 Day
PAINT - 2 days
SHIP - 1 day
INVENTORY: REDUCED 78% FROM $500K TO $110K PRICE: REDUCED 21% TO CUSTOMER
DATA ENTRY & SHEAR PUNCH GOAL: 5 DAY CYCLE TIME FORM PAINT & SHIP
DELIVERY: 100% QUALITY: 0 REJECTS INVENTORY: REDUCE TO $0. ELIMINATE BUILDING TO FORECAST,
ALL PRODUCT - BUILD TO ORDER.
With our success in Lean, we commit to do the following for our customers:
Experts in administration of On- & Off-Site programs. Lean / Continuous Flow Fabrication KANBAN Consignment Pull Systems Build to Forecast Landed-Cost Estimating & Delivery
Kanban
Internal
Optimizes batch sizing of component parts Ensures long-leadtime purchased parts stock Accommodates short notice pull-ins
External
Compresses leadtime Eliminates large blanket POs Liability covers more WIP than FG Pull system has built-in redundancy for complex assemblies
Consignment
VMI / SMI
Hybridization
Most Contract manufacturer (job shop) VMI schemes employ a mixture of Kanban, Consignment, Build-toForecast, or other pull type programs. These systems are flexible and can be combined or adapted to meet the specific needs of the customer and the product.
Soft Tooled
DELIVERY
INVENTORY MANAGEMENT
Mixed Tooling
DESIGN RELEASE FOR PRODUCTION. QTI QUOTES TOOLING LEVEL and PART COST
Hard Tooled
Bottom Line
Bottom Line
Bottom Line
True Synergy
The combination of Lean Manufacturing and Managed Inventory Systems enhances the effectiveness and value of each. Implemented together, these practices significantly reduce costs, while improving service levels to customers.
MANUFACTURING
DESIGN
ENGINEERING