Anda di halaman 1dari 27

From:

Sent:
Subject:
Alan Schneider
Monday, July 19, 2010 2:42 PM
Julie Villa
FW: Report Draft Copy
Attachments: Rig Assessment Report-Combined (SS&Drill Ship) (2010 Jan).doc
Importance:
Follow Up Flag:
Flag Status:
Categories:
High
Follow up
Completed
Blue Category
From: Jerry Kilcrease [mailto:Jerry.Kilcrease@moduspec.com]
Sent: Tuesday, April 13, 2010 1:02 PM
To: Alan Schneider
Cc: jerome.levine@deepwater.com
Subject: Report Draft Copy
Importance: High
Let me know if I need to make any changes to the report. I went over it and hope all is ok.
nks and Regards,
. Kilcrease
ModuSpec, USA
Office: 281-398-3998
Cell: 334-470-1986
CONFIDENTIAL
EXHIBIT # . _ l ~ ] . . . _ , _ _
WIT:. _____ _
MODUSA 000201
file: / //CIIU sers/Bridget/Documents/Moduspec/Documents%20Produced/SEC.PROD. CMMN/FW%20Report%20Draft%20Copy .htm[9/ 16/201 0 6: 14:40 PM]
DRAFT COPY
RIG CONDITION ASSESSMENT
Rig Type RIG NAME
Prepared for
TRANSOCEAN USA, INC.
Houston, TX (USA)
Customer Reference:
ModuSpec Reference: USXXXX.X
By
MODUSPEC USA, INC.
Dates: XX- XX Month 2009
CONFIDENTIAL MODUSA 000202
1.0 TABLE OF CONTENTS
1.0
2.0
2.1
2.2
2.3
3.0
3.2
3.3
4.0
4.1
RST STRU
RST PIPE
WTD WTDR
RST STRU
RST STRU
4.2
VIINST
PROP
PROP THR
DPS
BLST
BLST CTRU
BILG
4.3
MOOR ANC
MOOR LINE
RSTTOW
MOOR LINE
4.4
DSRT HPU
DRHS DWKS
DRHS DWKS
DRHS ECBK
DRHS ECBK
DSRT ROT
DSRTTD
DSRTTDPH
DRHS DERK
(Rev Jan 2010)
Page
TABLE OF CONTENTS ................................................ 24
INTRODUCTION .......................... ... .............................. .
Rig Data ............. . ..................... . ........................... . ........ .
Survey Workscope .......................................................... .
Applicable Standards ................................. . ... .... . ............ .
EXECUTIVE SUMMARY ............................. ..... ............... .
Conclusion ............... . .. ................................ .. .. ............... .
End-of-Inspection Meeting Document ............................ . .. .
ASSESSMENT FINDINGS ....................... ....................... .
Hull and Structure ........... ........................... . .. . ............. .
Handrails/Walkways ............... . .............................. .... .. ... .
Vents Lines and Checks ........................................ ... ......... .
Manual Watertight Doors/Hatches .................................... .
Drill Floor ........................... . ...................... . .. ... .............. .
Cables/Cable Trays ......................................... . ............... .
Navigation/DP/Propulsion/Ballast/Bilge .................... .
Navigation Equipment .. ... .. ............................. . ........ ........ .
Propulsion Unit ................................... .. ......................... .
Thrusters ........ ................. .. .... . . ... ... ............................... .
DP System (A.S.K.) .... ......... . ....... .. .. . .............................. .
Ballast Piping and Valves ...... .. ... .. .................................... .
Ballast Control System ............ . ............................ ... ....... . .
Bilge System .. ............................................................... .
Mooring System .............. . ..... .. ........ .. .......................... .
Anchor Winches ............................................................. .
Mooring Chain ..................... ................. . ..... .................... .
Towing Lines and Equipment ............... . ........................... .
Mooring Wire ..................... .................................... . ....... .
Hoisting/ Rotating Equipment .......... ........................ . ... .
Top Drive Hydraulic Power Unit ........................................ .
Auxiliary Drawworks/Hoist ............................................. . . .
Drawworks Unit ............ . ................................................ .
Auxiliary Brake (Air, Hydraulic) ......... ... ........................... .
Electric Brake ................................................................ .
Rotary Table .............. . ................................................... .
Top Drive Unit ................... . ............................ .. ............. .
Top Drive Pipe Handler ................................................... .
Derrick ........... ... ............................ ... .. . ..... . .... .. ............. .
Rig Condition Assessment- RIG NAME
Reference: Order No. USXXXX.X
CONFIDENTIAL
Page 2 of 26
MODUSA 000203
DRHS DEAD
DRHS CROW
DRHS TRAV
DRHS MC
4.5
BMS TANK
BMS TANK
MDS
4.6
LPMS
LPMS
LPMS
HPMS MP
DRHS SWIV
CMT
HPMS
4.7
DIST INST
DIST INST
4.8
WCS CONN
WCS CONN
WCS FJRA
WCS RISE
WCS TJT
WCS RISA
RISH RHT
WCS TENR
RTS HCYL
RTS CTRU
WCS BOPR
WCS ANNU
WCS BOPS
WCS VLV
WCS CTRU
WCS PMP
WCS ACUM
WCS ACUM
WCS BOPU
WCS PMP
WCS SSHR
WCS BOPP
WCS UMB
WCS SSHR
BOPH
(Rev Jan 201 0)
Deadline Anchor ............................................................. .
Crown Block .................................................................. .
Traveling Block .............................................................. .
Motion Compensator ........................... . ........................... .
Mud/Cement Storage .................................................. .
Bulk Tank Storage .......................................................... .
Surge Tanks .................................................................. .
Mud Pit Agitators, Guns, Valves ...................................... ..
Mud Process ................................................................ .
Mud Mixing System ........... .. ........................................... .
Mud Handling System ..................................................... .
Mud Processing System ................ .. ............... .... ............. .
Mud Pumps ................................................................... .
Swivel ...... ... .................................................................. .
HP Cement System ......................................................... .
HP Mud System .............................................................. .
Drilling Instrumentation ............................................ ..
Drilling Instrumentation System ...................................... ..
Drilling Control/Monitoring Systems (VICIS, etc.) ............... .
Ri _ser/BOP & Well Control Equipment .......................... .
Connector: Riser ........................................................... .
Connector: Wellhead ...................................... . .............. .
Flex Joint ................................... ....... ........................... ..
Riser ............................................................................. .
Telescopic (Slip) Joint .......................... . ......................... . .
Marine Riser Adapter ....................................... ........ ...... . .
Riser Gimbal I Spider ...................................... . ............... .
Tensioning Ring ............................................................. .
Riser Tensioners ........................................................... ..
Riser Recoil System ........... ................... .. ........................ .
BOP Rams (Various) ...................................................... ..
BOP Annulars ................................................................. .
BOP Stack Frame (General) ............................................ ..
Failsafe Valves ............................................................... .
BOP Control Panels .................................... . .. .. ........... . .... .
BOP Mixing Unit ............................................................. .
Accumulator Bottles, Stack Mounted ................ ... .............. .
Accumulator Bottles, Surface ........................................... .
BOP Control HPU (Koomey Unit) ..................................... ..
BOP Triplex Pumps ......................................................... .
Hose Reels (MUX & Hydraulic) ......................................... .
BOP Control Pods ........................................................... .
BOP MUX Cables ............................................................ .
BOP Pod Hoses (Hydraulic) ............................................. ..
BOP Cranes/Hoists/Handling/Transport ............................. .
Rig Condition Assessment - RIG NAME
Reference: Order No. USXXXX.X
CONFIDENTIAL
Page 3 of 26
MODUSA 000204
WCS DIVT
WCS CTRU
WCS MAN!
HOSE
WCS PIPE
4.9
HYD HPU
PH FGBD
PH PRS
PH PHM
PH PHM
PH PHM
PH PRS
PH DPF
PH DPF
PH PHM
PHL WPB
4.10
ELPG ENG
ELPG GEN
ELPD SWBD
ELPD SCR
ELPD TFMR
ELPD VFD
4.11
AIR COMP
AIR PIPE
AIR COMP
AIR PIPE
AIR COMP
AIR PIPE
4.12
SEA PIPE
TSF PIPE
DRLW PIPE
FUEL PIPE
LUBE PIPE
BILG SEP
4.13
MTHL CRN
MTHL OCRN
PHL MWIN
PH UWIN
(Rev Jan 201 0)
Diverter Assembly .......................................................... .
Diverter Control ...... ... ....................................... . .. .......... .
C&K Manifold and Piping ................................................ ..
Coflexip Type Hoses ....................................................... .
Connectors: Hydraulic Choke & Kill .................................. .
Tubular/Pipe Handling .......... .... ................................. ..
HPU's (Central or Stand-Alone) ........................................ .
Fingerboard .................................................... .. ............ . .
Varco PLS ...................................................................... .
Manipulator Arm ........................................................... ..
PFA (Pipe Feeding Arm) .................................................. .
PHM (Pipe Handling Machine) .......................................... .
Varco PRS/RHA .............................................................. .
Pipe Conveyor ........................................... ... .................. .
Pipe Skate .... . ....... ... ... . ... ...... .... .............. . ..... . .. . ............. .
Iron Roughneck ............................................................. .
Stabbing Board .............................................................. .
Power Generation ... ................ .. .... ...... ................... .. ... .
Main Engines .............. . ................................ ... .............. ..
Main AC Generators ......................... .. ............ . ......... ....... .
Switchboards .......................................................... . ... ... .
SCR Systems .......................... . .................................... .. .
Main Transformers ...... ..................... ........ ...................... .
VFD Systems .................. . ... .......... ............... .... ............. . .
Air Systems ... .................. .... ................... .... ................. .
Low Pressure Air Compressors (:540 PSI) ...... .. .................. .
Low Pressure Air Piping and Valves (:540 PSI) .................... .
High Pressure Air Compressors (>500 PSI) ........................ .
High Pressure Air Piping and Valves (>500 PSI) ................ ..
Medium Pressure Air Compressors (40-500 PSI) ................ .
Medium Pressure Air System Piping & Valves ( 40-500 PSI) .. .
Cooling Water/Fuel/Lube Oil/Oily Water .................... .
Salt Water Lines/Related Equipment.. .............................. ..
Fresh Water Lines/Related Equipment .............................. ..
Drill Water Lines/Related Equipment.. .............................. ..
Fuel Oil System Piping and Valves .................................... .
Lube Oil System Piping and Valves .......... .......... ...... ........ ..
Oily Water Treatment System .......................................... .
Lifting Equipment ......................... ........ .............. .. ....... .
Deck Cranes ................... . ... ......... . .... .......... . ........... ....... .
Gantry Cranes (Excluding BOP Cranes) ............................ ..
Air Hoists- Man Riding ........................ .. ................ ........ .. .
Air Hoists - Non Man Riding .... ........................................ ..
Rig Condition Assessment- RIG NAME
Reference: Order No. USXXXX.X
CONFIDENTIAL
Page 4 of 26
MODUSA 000205
' L
...
4.14
COMM REQT
COMM SCOM
COMM
VMS
4.15
ACOM GEQT
ACOM ACM
4.16
HVAC
LHTG LTE
POTW WTMK
POTW
EVNS
EVNS SWGE
LHTG LTE
HVAC
4.17
SURV RAFT
SURV BOAT
ELP GEN
WTD WTDR
FDS ALRM
FFS
FFS
FFS PMP
FFS PIPE
GDS ALRM
(Rev Jan 201 0)
Communications/Data Processing .............................. .
Radio Systems ...... . ........................................................ .
Satellite Communications ............. . ....... ....... .... .. .............. .
PA, PABX, Talk Back and Telephone Systems ......... ... ....... .. .
Data Management Monitoring & Control (VMS, PMS, DMS) .. .
Accommodations ............................ .................. . .......... .
Galley Refrigeration Equipment ........................................ .
Living Quarters/Rooms .. .. ............................................... .
Rig Utilities ................................................................. .
Ventilation Systems . .......................................... .... ......... .
Lighting System, non EX ................................................. .
Watermakers ................ .. .................. . ............................ .
Potable Water System ......................................... . .......... .
Sanitary Water System ....................... . ........................... .
Sewage Treatment Plant ................. ... ...... ...... ................ ..
Hazardous Area Electrical Equipment ................................ .
HVAC Systems ............................................................... .
Safety and Fire Fighting .............................................. .
Life Rafts ...................................................................... .
Lifeboats . ................................................. ..................... .
Emergency Generator System .......................................... .
Hyqraulically Operated Watertight Doors & Hatches ............ .
Fire Detection System ..................................................... .
Fixed Fire Suppression System ........................................ ..
Fixed Foam Fire Fighting System ...................................... .
Fire Pumps ................................. . ................................... .
Fire Main Lines & Related Equipment ................................ .
Gas Detection System ................ ..................................... .
Rig Condition Assessment- RIG NAME
Reference: Order No. USXXXX.X
CONFIDENTIAL
Page 5 of 26
MODUSA 000206
2.0
2.1
Vessel:
Owner:
Type:
Built:
Class:
Classification:
Performance:
Location:
INTRODUCTION
Rig Data
Transocean USA, Inc.
Water depth ft.
Drilling depth ft.
Inspection dates:
ModuSpec References: XX/XX/xxjxx- USXXXX.X
2.2 Survey Workscope
In accordance with the instructions received, we attended on board the NAME OF RIG to
complete a condition assessment of the primary assets of the rig including drilling
equipment, mud system, well control equipment, marine equipment, hull, structure, power
plant, electrical equipment and safety equipment.
Additionally for these rigs utilizing the Transocean RMS system, this assessment was to
determine the present state of maintenance by reviewing tasks, histories and Operation
Event Reports (OER) on the assets inspected with particular emphasis on downtime risk
equipment.
The ultimate goal of the assessment was to determine the current condition of the rig's
assets. The audit was conducted in good faith, but the inspection of individual items of
equipment was subjected to time and operational constraints imposed by the time of the
assessment.
(Rev Jan 201 0)
Rig Condition Assessment- RIG NAME
Reference: Order No. USXXXX.X
CONFIDENTIAL
Page 6 of 26
MODUSA 000207
This report, prepared by ModuSpec, is confidential. It has been prepared on behalf of the client
mentioned on the cover page {"the client'') and is issued pursuant to an agreement between
ModuSpec and the client. It has been produced according to the scope of work and is only suitable
for use in connection therewith.
All measures and decisions based on this analysis and these findings are the sole responsibility of the
client.
ModuSpec does not accept:
any liability for the identification, indication or elimination of dangers and non-compliances
(in the broadest sense of the word), nor for any damage caused by any of these;
any obligation to report all facts or circumstances established during the visit. This obligation
comes completely under the authority and responsibility of the client
any liability for the client's obligations resulting from (legal) rules andjor statutes;
any liability or responsibility whatsoever in respect of or reliance upon this report by any
third party.
The execution of improvements recommended by ModuSpec does not indemnify the client against
any legal or contractual obligations and offers no safeguard against the elimination of dangers or
damages resulting from the client's products, services, company assets, etcetera.
No part of this publication may be reproduced, stored in a retrieval system or transmitted in any
form or by any means, electronic, mechanical, photocopying, recording, or otherwise without prior
permission, in writing, of ModuSpec, except for restricted use within the client's organization.
2.3 Applicable Standards
The criteria which have been used as reference during this assessment are internationally
recognized standards, local legislative requirements, customer's safety and operating
standards, the original equipment manufacturer's maintenance and operating specifications
and accepted oilfield operating and safety practices.
Rig Condition Assessment - RIG NAME
Reference: Order No. USXXXX.X
Page 7 of 26
(Rev Jan 201 0)
CONFIDENTIAL MODUSA 000208
- - - - - - ~
3.0 EXECUTIVE SUMMARY
3.2 Conclusion
In accordance with the instructions received, we attended on board the TransOcean Horizon
to complete a rig condition assessment of the primary drilling equipment, mud system, well
control equipment, marine equipment, hull, structure, power plant, electrical equipment and
safety equipment.
The rig was clean and the paint was in good condition.
The deck cranes were in bad condition . The main block on both cranes were worn and in
need of replacement. The whip line sheaves were worn and must be replaced. The gantry
crane was in fair condition. The walkway on the booms for both deck cranes, was only about
10 inches wide. The walk way at the boom tip had no platform around the sheaves and
causing a safety issue when performing the PM maintenance on the crane. The winch
located in the boom had no walkway or platform around the unit for maintenance. It was
recommended for a walkway to be installed in-side the boom for walking the boom when
performing maintenance on the winch located in the boom and for safe access to the boom
tip sheaves.
The salt water and fresh water piping was in bad condition due to age. The piping for the
cooling systems and the water makers were in bad condition. The piping was leaking around
the water makers and the cooling heat exchangers. The salt water service pumps in the
lower pump rooms were in bad condition. The pumps were leaking and in need of
replacements.
Number 2 thruster motor was out of service and must be replaced. All of the thruster were
having problems with water getting into the gear box due to the seals were in need of
replacement.
The ballast system was in fair condition. This was due to the hydraulic system for the ballast
valves were causing problems. The units were not closing the valves correctly due to the
solenoids on the 4 units in the columns were heating up to the point of burning out or
shutting off when using the system. Number 3 ballast pump was in bad condition, due to .
not staying primed and not pumping correctly when in use. The pump must be replaced if
repai rs cannot be make for the pump to work correctly.
The walkways on the lower sides of the columns were i n bad condition and must be
replaced.
The water makers were in fair condition; however, the units were not making the amount of
potable water needed to supply the rig . The units were making half of the amount of water
being used daily.
The water maker rooms located in front of each of the main engines did not have a
automatic bilge system. The crew members were pumping out the bilge in the areas with
diaphragm type pumps manually. With the fresh water and salt water piping in bad
condition, the rig was having issues with the pipes leaking often. This could cause a flooding
(Rev Jan 201 0)
Rig Condition Assessment - RIG NAME
Reference: Order No. USXXXX.X
CONFIDENTIAL
----------------- ----- -------------- ---
Page 8 of 26
MODUSA 000209
issue if the main water line burst in the water maker rooms. The bilge pumps located in the
lower pump rooms were having issues with not staying primed when in use.
The drill water pumps and piping was in fair condition. The drill water pumps were worn and
in need of replacements due to age.
12 Month 2010
J.R. Kilcrease
ModuSpec USA, Inc.
17171 Park Row, Suite 120
Houston, Texas 77084
Tel No.:
Fax No.:
E-mail:
Website:
281.398.3998
281.398.8694
qsa@moduspec.com
www.moduspec.com
Rig Condition Assessment- RIG NAME
Reference: Order No. USXXXX.X
(Rev Jan 201 0)
CONFIDENTIAL
. ---------- - - - - - - - ---
Page 9 of 26
MODUSA 000210
L
3.3 End-of-Inspection Meeting Document
Rig name:
Owner: Transocean USA Inc.
Location:
Customer: Transocean USA Inc.
Inspection dates:
Date of meeting:
Order No.:
Name Title Signature
Customer
Representative( s):
Rig Staff:
ModuSpec
Surveyor(s):
Note: The original signed end-of-inspection meeting document is kept on file in the
ModuSpec office and a copy can be provided upon request .
(Rev Jan 2010)
Rig Condition Assessment - RIG NAME
Reference : Order No. USXXXX.X
CONFIDENTIAL
Page 10 of 26
MODUSA 000211
- - - - ~ - - - - - - - - -- ----------- ..
DRAFT COPY
4.0 ASSESSMENT FINDINGS
4.1 Hull and Structure
Marine Integrity
The client would like a brief summary of the condition of hull/pontoon/structure
RST STRU Handrails/Walkways
Upon assessment of the handrails and walkways around the rig, they were in good
condition. The rig crew members have kept them repaired and painted. The walkways going
down the forward and aft columns of the rig were in bad condition due to being in the water
most of the time when on location. One walkway in the moon pool, located near the BOP
Crane was in need of repair to the under-side. The platform was corroded and in need of
protective coating. Two of the under-side braces were corroded and in need of being
replaced.
The walkways and handrails were in good condition.
Recommendations:
Replace the ladders and walkways on the lower part of all 4 columns of the rig as
needed.
Repair the platform walkway in the moon pool as needed and apply protective
coating/paint.
RST PIPE Vent Lines and Checks
Upon inspection of the vents and checks, they were in good condition, however it was noted
one vent for the sludge oil tank did not have a containment area around the vent. Oil was
accumulating around the top part of the vent, and therefore starting to drip off of the vent .
The vent was located on the Port Forward side of the rig and on the outside of the handrail.
The fuel vents all were installed with containment areas around them, and all were in good
condition. In review of the history on the vents and checks, it was noted the PMs were
preformed on regular bases.
The vents and checks were in good condition.
Recommendations:
Install a containment area around the sludge tank vent (located on the Port Forward
side of the rig) as needed.
WTDWTDR Manual Watertight Doors/Hatches
The manual watertight doors were in good condition and operated well. The gaskets were in
good condition, as well as the dogs (locks) being in good order and adjusted as needed.
(Rev Jan 201 0)
Rig Condition Assessment- RIG NAME
Reference: Order No. USXXXX.X
CONFIDENTIAL
Page 11 of 26
MODUSA 000212
In review of the history, the PMs were showing to be completed on regular bases and up to
date.
The manual watertight hatches were in fair condition. The main hatch for the welding area,
needs the gasket replaced due to age and the gasket was hard, this would not let the
gasket seal correct when closed. The hand winch for raising the hatch cover was in bad
condition. The safety cover that goes over the teeth of the winch was missing and the teeth
on the gears were worn severely. The teeth on the winch for sack room hatch cover were
worn to the point of needing to be replaced as well.
The watertight hatch covers for the vents on the Port and STBD side of the rig, located
behind the cranes, was in bad condition. The gaskets were dry and cracked due to age. The
hatch covers were corroded and would not let the hatch cover seal when closed.
The manual watertight doors and hatches were in fair condition.
Recommendations:

4.2 Navigation /DP /Propulsion /Ballast/Bilge
PROP THR Thrusters
The rig was equipped with 8 thrusters, information on the units are as follows.
Thruster/Type (azimuth/in line)
Quantity
Location (aft, opposite corners, 4 corners)
Driven by Electric Motor (yes/No)
Make/Type
Power Output (HP EA.)
Propeller Type(Fixed I Variable Pitch)
Nozzled (yes/no)
Thruster Power (HP Total)
Azimuth - Full 360
8
4 Corners
Yes- Variable Speed Drive
Kamewa
7375 hp (5500 kw)
Fixed
Yes (w/5o down tilt)
59,000 (44 MN)
Number 2 thruster was out of service due to motor was bad and in need of replacement.
All of the thrusters were getting water into the oil of the gear units, due to the seals were
leaking. This has been going on for some time now and will continue to get worse in time.
Number 8 thruster was leaking hydraulic oil around the inside shaft. The unit had the oil
seal rubber out of place and was raised up on the shaft. The hoses for all of the thrusters
were showing signs of age and beginning to get dry cracked and hard. In review of the
history, it was noted the oil samples were showing water in the gear oil. Number 3 thruster
was showing to have more water in the sample then the others. The PMs were up to date on
the units, however, number 2 was out of service and the PMs were delayed due to this
nature. On interviews with crew members, it was noted, the thruster has been performing
well and the rig had no major issues other then number 2 thruster motor going out .
The units were showing signs of wear and in need to being overhauled in the near future.
The cooling heat exchanger units were in bad condition due to age and have to be cleaned
more often then normal. The water pipes of the cooling units were leaking at the flange
(Rev Jan 201 0)
Rig Condition Assessment- RIG NAME
Reference: Order No. USXXXX.X
CONFIDENTIAL
Page 12 of 26
MODUSA 000213
connections on all of the units. The cooling pumps were in good condition and were running
normal.
The thrusters were in fair condition.
Recommendations:
Replace the hydraulic seal on the shaft for number 8 thruster.
Replace all cracked and hard hydraulic hoses on the thruster as needed.
Replace the motor on number 2 thruster.
Replace all shaft seals on all 8 thrusters at nearest opportunity.
DPS DP System (A.S.K.)
Information on DP system as follows:
DP System
Class Ill Kongsberg-Simrad Dynamic Positioning
System in accordance with ABS DPS-3
requirements and recommendations. System
consists of a triple redundant dynamic positioning
system and shall accept inputs from Hipap
Acoustic Positioning System, four (4) different
GPS (DGPS) based on correction signal inputs
. from different sources, (3) three gyrocompass,
(3) three vertical reference units, and (3) three
wind sensors, as well as operator friput. Power
Management System is interfaced with the
Integrated Alarm & Control System.
Position Reference
Kongsberg-Simrad Hipap & DGPS
Integrated Alarm & Control System
Kongsberg-Simrad lACS will operate as the
System Control & Data acquisition system for the
MODU. The lACS will perform several different
functions including: Power Management System,
Machinery Monitoring & Control, Manual Thruster
control and Autopilot, Dynamic Positioning
Control, Ballast & Bunker Monitoring & Control,
Bulk Storage Sys. Monitoring & Control, Safety
Sys. (Fire, Gas, WT Doors, HVAC Control, etc.)
The DP system was in good condition and in good working order. Upon interviews with crew
members, it was noted; they have not had any issues with the system and has been
working normal in the past. In review of the history, it was noted no major issues were on
record. The system was under operation during the assessment and was performing normal.
No problems or issues noted.
(Rev Jan 2010)
Rig Condition Assessment - RIG NAME
Reference: Order No. USXXXX.X
CONFIDENTIAL
Page 13 of 26
MODUSA 000214
No recommendations were noted.
The DP System was in good condition.
Recommendations:
BLST Ballast Piping and Valves
The ballast piping and valves were in fair condition. The HPU units for the system valves
was causing some problems. The sensor relays in all 4 units were heating up and the relays
were burning. The crew members stated this has been giving them problems for some time
now. The HPU units had some small leaks around the hose connections and the pumps.
The piping was in fair condition. In number 8 thruster room the salt water pipes were
leaking at the pumps and the rig crew had replaced some of the pipes. The ballast pumps
were showing signs of wear due to age and the seals were leaking on the pumps in number
8 thruster room. On review of the history, the PMs were up to date and being completed on
regular bases.
The ballast piping and valves were in fair condition.
Recommendations:
Replace the ballast pumps in #8 thruster room.
Replace all worn and leaking ballast pipes as needed.
BLST CTRU Ballast Control System
The ballast control system on the bridge was in good condition and working well.
The HPU units, located in each column, were in fair condition. The relays for the HPU unit
valve controls were heating up and causing issues. The relay panels on all 4 HPU ballast
control unit were having the same issues. On interviews with crew members, it was noted,
the system was using a 12o Volt current and they stated the system should be using a 24
volt system. The major concern of the relays going out, would be a flooding problem or
safety issues of the watertight integrity of the rig.
The ballast system was in fair condition.
Recommendations:
Replace all 4 HPU relay panels and all relays for the system.
Replace the ballast pumps in #8 thruster room as needed.
Repair all hydraulic leaks on the 4 HPU units as needed.
BILG Bilge System
The bilge system was in fair condition. The system had some issues with priming. The
pumps were not holding the prime at times and they crew would use the priming units that
were on the rig to re-prime the pumps. The alarms for the system was in good working
order and all tested during the assessment. The relays in the same panel of the ballast
(Rev Jan 201 0)
Rig Condition Assessment - RIG NAME
Reference: Order No. USXXXX.X
CONFIDENTIAL
Page 14 of 26
MODUSA 000215
- ------ ------- --- ---- -- - --- - --
system were heating up and causing the same issues as the ballast system. On review of
the history, it was noted, all PMs were up to date and being completed on regular bases. On
interviews with crew members, it was noted, the problems they were having was with the
relays on the control units. In the bilge of the thrusters rooms, the system would not pull all
of the water at times and they would have to prime the pumps.
The bilge system was in fair condition.
Recommendations:
Repair the problem of the pumps losing prime. Check and replace the pump
impellers or replace the pumps.
Replace the relays and panel as needed for the bilge system.
4.3 Mooring System
Recommendations:

MOORANC Anchor Winches
The rig was not equipped with anchor winches.
Recommendations:

MOOR LINE Mooring Chain
The rig was not equipped with mooring chain.
Recommendations:

RSTTOW Towing Lines and Equipment
The towing Lines and equipment had been removed for the rig. In an interview with the
crew members, and review of documents, it was noted the rig was not required to have the
equipment on board due to the D.P. class of the rig.
Recommendations:

MOOR LINE Mooring Wire
The rig was not equipped with mooring wire.
Recommendations:

(Rev Jan 201 0)
Rig Condition Assessment- RIG NAME
Reference: Order No. USXXXX.X
CONFIDENTIAL
Page 15 of 26
MODUSA 000216
4.10 Power Generation
ELPG ENG Main Engines
The rig was equipped with 6 Wartsila engines, as follows.
Make/Type Wartsila I 18V32
Maximum Continuous Power hp: 7290 KW 9775 HP
At Rotation Speed of rpm: 720
Equipped w/Spark Arrestors yes/no: Yes
Mufflers Installed yes/no: Yes
The engines were in good condition. In review of the history that the hams were being
Preformed on regular basis and were up to date.
On interviews with crew members, it was noted, the engines must have the injectors
changed. This was due to the injectors installed in the engines do not meet EPA regulations.
They have ordered the correct injectors or making the changes.
During the assessment, we tested all shut downs on 5 of the engines, number 3 engine was
out of service at the time. It was noted during the shutdown testing, several of the water
jacket cooling sensors were disconnected and not working. Due to the main water piping
was shut off to the engine. This was due to a spool was in bad condition and had to be
changed out. They had to shut off the water supply to the port side of the rig to make the
repairs needed for the water line. During the testing of the engine shut downs, (High temp,
low oil pressure, and over speed) all of the shut down systems were normal. The engines
were not due for an overhaul due to the hours on the engines at the time of assessment.
The engines were in good condition.
The hours on the engines are as follows. As of April 6, 2010.
(Rev Jan 201 0)
Rig Condition Assessment - RIG NAME
Reference: Order No. USXXXX.X
CONFIDENTIAL
Page 16 of 26
MODUSA 000217
1 26267
2 39805
3 34789
4 29864
5 35841
6 34980
Recommendations:
Replace the injectors as required when they are received on rig.
Repair the main cooling water piping for #3 engines.
Repair or replace all water jacket sensors on all 6 engines as needed.
4.11 Air Systems
AIR COMP Medium Pressure Air Compressors ( 40-500 PSI)
The rig was equipped with 4 Gardner Denver air compressors. The information on the units
were as follows.
Air Compressors - Medium Pressure (rig air):
Quantity
Make
Model
Rated Capacity
Working Pressure
Prime Mover (electric/diesel)
Continuous Power
Air Dryers
Quantity
Make/Type
Rated Capacity
Air Compressors - Lower Pressure (bulk air):
Quantity
Make
no. : 4
scfm:
PSI:
Gardner Denver
EBQ99F Rotary Screw
750
125
Electric
HP: 200
no.: 4
scfm:
Desiccant Dominick Hunter I DX 11 0 Heatless
1089
no.: 3
Kim ray -4 each reduicing wave/back pressure
valves
Model Series G Regulator 318 FGT-BP & FGT-PR
Rated Capacity cu.ft./hr. : 10,600 each
Working Pressure PSI: 60
The compressors and systems were in good condition. The hours on the compressors were
as follows.
(Rev Jan 2010)
Rig Condition Assessment- RIG NAME
Reference: Order No. USXXXX.X
CONFIDENTIAL
Page 17 of 26
MODUSA 000218
-- _,;;,
No. 1 28416.5
No. 2 55472.1
No. 3 50733.3
No.4 53412.5
The units were under operation at the time of assessment. All 4 compressors were
operating normal and the air PSI was 125. The temp. on the units were normal, reading
from 178 F to 190 F on the units. On review of the history, all PMs were up to date and
being completed on regular bases. It was noted, number 4 and number 2 compressor end
on the units had been replaced in Jan. 2010. On interviews with crew members, ity was
noted the compressors, dryers, and the Kim-ray reducer valves have been working well and
not causing any major issues.
The air compressor system was in good condition and no recommendations were made
upon assessment.
Recommendations:

AIR PIPE
PSI)
Medium Pressure Air System Piping &. Valves ( 40-500
Upon inspection of the air piping and valves, they were found to be in good condition. The
valves were working properly and easy to open and close. The history documents reviled no
problems with the pipe or valves: The PMs were all up to date and being performed on
regular bases. The pipes were labeled and painted in all locations.
No recommendations were made during assessment.
Recommendations:

4.12 Cooling Water/Fuel/Lube Oil/Oily Water
SEA PIPE Salt Water Lines/Related Equipment
The salt water piping was in bad condition. The lines going to the water makers were
leaking in several places and on all six water makers. The flanges were leaking around the
spools at all six water makers. The main line going to the water makers was severely
corroded. Number 1 water maker cooler unit was leaking around the weld of the flange
where it connects to the unit. The main salt water line going to number three engine had
been shut down for repairs to the piping. The main spool in the pipe had been pulled out
and the pipe was blanked off. The spool was severely corroded and leaking around the
flange connections of the spool. The main valves would not close completely, this was due
to age and the valve seals, and gates were not sealing off when closed. Therefore the water
for the port side of the rig had to be shut off completely in order to install a new spool. In
review of the history, it was noted, the rig has been having problems with the salt water
lines for some time. This was due to the piping being in bad condition due to age and
wearing thin. The rig crew had installed temporary soft patches on some of the piping until
the pipes can be replaced.
(Rev Jan 201 0)
Rig Condition Assessment- RIG NAME
Reference: Order No. USXXXX.X
CONFIDENTIAL
Page 18 of 26
MODUSA 000219
~ '
The salt water piping in the Thruster rooms located in the lower columns were in bad
condition. On interviews with crew members, it was noted, they have been working to
replace short pipes as needed due to leaks. Some of the pipes had been temporary welded
places around the flanges due to leaks.
The salt water lines and system were in bad condition.
Recommendations:
Replace all corroded salt water piping as needed.
Replace all flanges on the water makers as needed.
TSF PIPE Fresh Water Lines/Related Equipment
The fresh water piping was in bad condition. This was due to the corroded piping through
out the rig. The main fresh water piping for the water makers was in bad condition. The
pipes were severely corroded and in need of being replaced. The piping for the main cooling
heat exchanges was corroded severely and in need of being replaced. The valves at both
main cooling heat exchangers located on the STBD and Port side of the rig in the engine
rooms were hard to operate and stiff. In interviews with crew members, it was noted, the
valves would not close and completely shut of the water supply in the main water lines.
Therefore, when replacing any of the pipes or valve spools in the system, they had to shut
down the main water supply to the port or STBD side of the rig. This may cause safety
issues at times.
In review of the history, the PMs for the fresh water cooling systems and valves were up to
date and being performed on regular bases. The cooling heat exchangers were in fair
condition. The flanges were leaking due to the piping was thin around the flanges at the
connections.
The fresh water piping was in bad condition.
Recommendations:
Replace all fresh water piping and valves as needed.
Install a shut off valve for each fresh water line going to each engine. This would
help on being able to make repairs to the line and valves without shutting down the
entire water supply to each side of the rig when making repairs.
DRLW PIPE Drill Water Lines/Related Equipment
The drill water piping was in good condition. The drill water pumps in the lower pump room
on the STBD and Port side of the rig were in fair condition. The drill water pumps on the
Port side of the rig were worn and leaking due to age of the pumps. In review of the history,
it was noted the PMs were being performed on regular bases and were up to date in the
system. On interviews with crew members, it was noted some of the drill water valves in
the mud pit room were leaking by when closed.
The drill water system was in fair condition.
Recommendations:
Replace drill water pumps as needed.
Replace the drill water valves in the mud pit room as needed.
(Rev Jan 201 0)
Rig Condition Assessment- RIG NAME
Reference: Order No. USXXXX.X
CONFIDENTIAL
Page 19 of 26
MODUSA 000220
FUEL PIPE Fuel Oil System Piping and Valves
The fuel oil system and pumps were in good condition. The fuel transfer pumps located in
the lower pump rooms, had some small leaks on the piping for the relief valves. The relief
valves were tagged with out of dates for being tested. The PMs were up to date on the fuel
oil system and PMs were being done on regular bases. On interviews with crew members, it
was noted the fuel oil system has been working well in the past and no major issues were
noted.
In the fuel purifier rooms, the fuel and oil tank sight glass gauges were held open with tie
wraps. This was a safety issue due to the auto shut off valves could not work properly when
tied off in the open position.
The fuel oil system was in good condition.
Recommendations:
Remove the tie warps on the sight glass gauge valves. (NOTE. This was taken care of
by crew members before the assessment was completed.)
Retest or recertify all pressure relief valves on the fuel transfer pumps.
Repair the small leaks on the piping for the pressure relief valves.
LUBE PIPE Lube Oil System Piping and Valves
The lube oil piping and system was in good condition. The pumps were in operating normal
and no leaks were visible. The oil coolers were cleaned on regular bases and required in the
PM system. In review of the history the PMs were up to date and no major issues were on
record. On interviews with crew members, it was noted the system had not had any
problems in the past. On number 2 oil cooler, on of the lines had a small leak and was
repaired by crew members during the assessment.
No recommendations were made at the time of assessment.
The lube oil system was in good condition.
Recommendations:
BILG SEP Oily Water Treatment System
The oily water separators were in bad condition. The tanks were severely corroded and in
need of being replaced. The piping for the drain on the relief valves was not connected
correct and was leaking. The relief valves were out of date on the tags and were leaking.
The pumps on both units were corroded. The piping connections going into the units was
corroded and in need of being replaced/repaired.
In review of the history, it was noted, the PMs were up to date and being performed on
regular bases. On interviews with crew members, it was noted, the units were in bad
condition according to the interviews. During the testing of the units, it was noted the relief
valves were leaking and the pumps were loud while running.
(Rev Jan 201 0)
Rig Condition Assessment- RIG NAME
Reference: Order No. USXXXX.X
'
CONFIDENTIAL
- - ~ - - - - - - - - - - - - - -- - ~ ~ -- - ~ ---
Page 20 of 26
MODUSA 000221
The oily water separators were in bad condition.
Recommendations:
Replace the relief valves on both units as needed.
Repair the piping connections on the units.
Replace both oily separator units as needed. The tanks were severely corroded.
4.13
MTHL CRN
STBD
Port
Knuckle
Boom
Lifting Equipment
Deck Cranes
22294 N/A 22294
17371 N/A 17371
N/A N/A N/A
The rig was equipped with 2 Liebherr Pedestal type cranes; located one on the port side of
the rig, and one on the STBD side of the rig on the main deck. Each crane had a 150 ft.
Boom, with 1,893 ft. of boom cable. The main block rated for 92 metric tons with 1,920 ft.
Of cable, and the whip line hook rated for 15 metric tons with 475 ft. of cable.
The information on the knuckle boom crane was has follows.
Make Outreach
Type Knuckle boom
Location (stbd., port, aft, fwd.) Forward
Maximum Rated Capacity (main hook) lt.: 3.57
Maximum Rated Capacity (whip hook) lt.: N/A
Boom Length ft.: 68
Port Crane
The sheaves at the boom tip had cable prints in the sheaves and showing signs of wear.
The sewing bolts were in bad condition and severely corroded. The radiator housing was
corroded around the fan guard. The housing bolt holes were severely corroded around the
bolts. The hoses for the oil cooler mounted in the radiator system were hard and cracked
due to age. In review of the history, it was noted most of the hydraulic hoses had not been
(Rev Jan 201 0)
Rig Condition Assessment- RIG NAME
Reference: Order No. USXXXX.X
CONFIDENTIAL
Page 21 of 26
MODUSA 000222
replaced during the life of the crane. The hydraulic hoses going to all of the winches have
not been replaced as well. It was noted the winches have not been reworked or replaced for
the life of the crane. No records were provided show the hydraulic motors or the pumps
were reworked or replaced on the winches as well. The main block was in bad condition due
to the sheaves were worn severely. The main block only had one grease point, it was for the
swivel. The sheaves had no grease point for lubrication of the sheaves or pin. The whip line
sheaves at the boom tip were worn and in need of being replaced. In review of the history
and in interviews of crew members, it was noted; the engine had not been reworked or
replaced during the life of the crane. It was also noted the rig has a new engine on order for
the crane. This was to be installed at nearest opportunity. All limits switches were in good
working order during the testing and assessment of the crane ..
STBD C;ane
On the STBD crane, the boom section bolts were severely corroded at each section of the
boom where they join together.
The sheaves at the boom tip had cable prints in the sheaves and showing signs of wear.
The sewing bolts were in bad condition and severely corroded. The radiator housing was
corroded around the fan guard. The housing bolt holes were severely corroded around the
bolts. The hoses for the oil cooler mounted in the radiator system were hard and cracked
due to age. In review of the history, it was noted most of the hydraulic hoses had not been
replaced during the life of the crane. The hydraulic hoses going to all of the winches have
not been replaced as well. It was noted the winches have not been reworked or replaced for
the life of the crane. No records were provided show the hydraulic motors or the pumps
' were reworked or replaced on the winches as well. The main block was in bad condition due
to the sheaves were worn severely. The main block only had one grease point, it was for the
swivel. The sheaves had no grease point for lubrication of the sheaves or pin. The whip line
sheaves at the boom tip were worn and in need of being replaced. In review of the history
and in interviews of crew members, it was noted; the engine had not been reworked or
replaced during the life of the crane. It was also noted the rig has a new engine on order for
the crane. This was to be installed at nearest opportunity. The crane has had major issues
for some time now, according to the history and interviews of crew members. The STBD
crane had a fire around 2005 and was repaired by crew members; however, this has cause
issues with the crane performing correct at times, according to the interviews.
All limits switches were in good working order during the testing and assessment of the
crane.
Knuckle Boom Crane
The knuckle boom crane was in fair condition. In review of the history, the PMs were being
performed on regular bases and were up to date. On interviews, it was noted the crane had
not been reworked (overhauled) during the life of the crane. No records were on hand as
well. The hydraulic motors had not been overhauled or replaced. The hydraulic hoses were
(Rev Jan 201 0)
Rig Condition Assessment - RIG NAME
Reference: Order No. USXXXX.X
CONFIDENTIAL
Page 22 of 26
MODUSA 000223
hard and stiff due to age. The walkway platform was in bad condition due to correction.
However, during the assessment the walkway platform was removed and repaired. The
walkway was reinstalled and painted as well. The crane performed normal during the testing
of the unit and no abnormal noises were noted. The grabs on the unit were in good working
order; however, the hose connections had some small leaks at the connections.
The cranes were in bad condition.
Recommendations:
Replace all three whip line sheaves located at boom tip on both cranes.
Replace or rework the main block on both cranes and have recertified.
Replace all main block sheaves in boom on both cranes as needed.
Install new walkway on boom. Recommended to install the new walkway on the
inside of the boom and add a small platform around the winch mounted in the boom.
Rework or replace all winches on both cranes as needed and required. No records of
any of the winches being replaced during the life of the cranes.
Rework/overhaul the knuckle boom crane.
Replace all aged hydraulic hoses as needed.
Replace or rework all hydraulic motors and pumps on the unit.
MTHL OCRN Gantry Cranes (Excluding BOP Cranes)
The rig was equipped with a overhead gantry crane. The information of the crane was as
follows.
Make Hydralift
Type Gantry Type
Rated Capacity mt: 37 (18.5x2)
Location Aft Riser Deck
The crane was in fair condition. During the testing of the crane no abnormal vibrations or
noises were noted. All limit switches were in good working order. On interviews with crew
members, it was noted the crane was grabbing during the travel of the unit on the tracks.
They had to adjust the travel limits on the unit to fix this problem. During the testing of the
unit no grabbing as noted while the cranes was moved up and down the tracks. In review
of the history, it was noted the issues of the grabbing during travel was recorded and the
repairs were recorded as well. The PMs were being performed on regular bases and were up
to date in the system. The unit was having some issues with the hoist units speed being out
of sink with each other. During travel of the hoist back and forth #1 hoist would move more
slower the #2 hoist. The limit sensors were out of sink and should be replaced if the speed
of the hoist cannot be set the same on both hoists. Before moving the crane to the Port
Side, the operator was having to move the unit to the STBD side first (for about a foot) if
not the unit would not travel to the Port.
(Rev Jan 201 0)
Rig Condition Assessment - RIG NAME
Reference: Order No. USXXXX.X
CONFIDENTIAL
Page 23 of 26
MODUSA 000224
The gantry crane was in fair condition.
Recommendations:
Replace/repair the limit sensors for the hoist travel speed.
Repair the problem with the crane not moving to the Port without moving the unit to
the STBD first . The crane should travel both ways with out problems.
4.16 Rig Utilities
Ventilation Systems
The ventilation fans and duct work was in fair condition. This was due to the (VMSA) supply
fans for the machinery area on the port and STBD side of the rig. Both units were located
next to the cranes. They were corroded severely and the gaskets were in bad condition. The
supply duct for the fans on the port side of the rig had gaskets pieced together in the
corners of the hatch covers, leaving gaps in the gasket. This will not let the hatch cover seal
when the hatch is closed. The lip on the duct vent was corroded on the lip as well
preventing the hatch from sealing when closed. The hatch covers were corroded around the
lip where the gasket fits on the cover, therefore the hatch covers must be replaced or
repaired. The louvers were corroded and must be replaced. The ventilation fans and duct for
the rest of the rig was in good condition. For example, the pit room, shaker room, shack
room and other areas all were in good condition. Upon review of the history on the
ventilation system, the PM's were being completed on regular bases. On interviews with
crew members it was noted they had replaced some of the vent duct work and no major
problems were noted with the system. However, it was noted that none of the mushroom
vents on the main deck had screen on them. The ventilation ducts on the main deck were
not labelled clearly for identifying the units as to what area/room the vent went too.
The ventilation system was in fair condition.
Recommendations:
Repair or replace (VMSA) supply ventilation ducts and hatch covers on the port and
STBD side of the rig as needed.
Label all ventilation ducts clearly as needed.
Replace all bad or pieced together vent cover gaskets on vent ducts as needed .

POTW WTMK Wat ermakers
The rig was equipped with 6 Alfa-Laval, water makers. They were in fair condition. The flange
connections were showing signs of wear, due to the flanges often leaking. The piping was in bad
condition for the units. Therefore the flanges were changed out often. This was causing the flange
connections to wear around the seal and starting to leak at the seal. In interviews with crew members, it
was noted, the water makers were only making about half of the amount of potable water used on the rig.
The rig had to get potable water from the supply boats. They were having problems with the cooling
exchangers leaking and making repairs to the piping on weekly bases. In reviewing of the history, it was
(Rev Jan 201 0)
Rig Condition Assessment- RIG NAME
Reference: Order No. USXXXX.X
CONFIDENTIAL
Page 24 of 26
MODUSA 000225
noted the PMs for the units were up to date and were completed on a regular bases. The crew members
were cleaning the units often due to age.
The water makers were in fair condition.
Recommendations:
Install a new water maker for being able to supply the amount of potable water
needed for the rig.
Replace the corroded flange connections on all 6 water makers as needed.
Replace the fresh water and salt water piping on the water makers as needed.
4.17 Safety and Fire Fighting
ELP GEN Emergency Generator System
The emergency generator information installed on the rig was as follows.
Make/Type Caterpillar 3408 DITA
Maximum Output kw: 400 cont. power output
At Rotation Speed rpm: 1200
Starting Methods (Automatic, Manual, Automatic Electric I Hydraulic
Air/Hydraulic)
Maximum Angle of Operation degrees: 22.5 Per ABS
The unit was in good condition. In review of the history, the PMs were up to date and being
completed on regular bases. In interviews with crew members, it was noted, the engine had
not given any problems in the past. We test ran the engine and checked all of the
shutdowns for the engine. All of the shutdowns preformed normal and were in good
condition. The low oil pressure, high temperature shut down, and the over speed test were
preformed with no problems. The engine had 2 means of starting, one with batteries and
could be started with a hydraulic starter as well. We tested both starting system on the
engine. No problems were found and the unit started with both systems.
The emergency generator was in good condition.
Recommendations:
The C02 fire Suppression System lines in the emergency generator room were
painted white. The lines must be painted red and labelled.
WTDWTDR Hydraulic Watertight Doors & Hatches
The hydraulic watertight doors were in fair condition. The rig had 2 of the hydraulic doors
not working correct at the time of assessment. The doors had to be manually opened with
(Rev Jan 2010)
Rig Condition Assessment- RIG NAME
Reference: Order No. USXXXX.X
CONFIDENTIAL
Page 25 of 26
MODUSA 000226
the hand pump. One of the doors was located on the 28 and half meter deck level and one
located on the 24 meter deck level on the STBD side of the rig in the column. In review of
the history, it was noted the crew had been working on some of the doors and repairing the
tracks for the doors as needed. It was also noted the PMs for the doors were being
completed on regular bases and they were up to dated in the system. On interviews with
the crew members, no major problems with the doors were noted.
During the assessment, it was noted 3 of the hydraulic doors in the port aft column were in
need of being adjusted due to the doors dragging on the track at the bottom.
The hydraulic doors and hatches were in fair condition.
Recommendations:
Adjust the hydraulic doors in the port aft column as needed.
Repair or replace the hydraulic cylinders for the two doors that were being opened
manually. Repair the doors as needed .

(Rev Jan 201 0)
Rig Condition Assessment- RIG NAME
Reference: Order No. USXXXX.X
CONFIDENTIAL
Page 26 of 26
MODUSA 000227
L

Anda mungkin juga menyukai