Anda di halaman 1dari 34

Proposed Construction of Shed

Bill Of Quantities
Item Description
Foundations (Provisional)
1 Excavate oversite to remove topsoil & spread & level on site
2 Excavate in pickable mat.for strip footings n.e 2 metres deep.
3 Scarify reduced surfaces and compact mechanically to 93% HCE<150mm
4 Cart away surplus excavated mat to a dump site to be located by Contractor
5 Backfilling to trenches wth approved excvated mat to 93% HCE,150mm dpth
6 150mm Hard core filling base course wth approved decomposed granite
7 Termite treatment
8 20 Mpa in footings
9 20 Mpa in surface beds
10 115 block wall in fdn
11 115 brickforce
12 Strike off & cure top surfces of concrete
13 Fabric reinforcement; Ref. S193
14 1 layer250 micron "Tarcon" polythene DPM laid on and including 50mm sand

Uom Qty

Rate

Amount

m2
m3
m2
m3
m3
m3
m2
m3
m3
m2
m
m2
m2
m2

1,728
192
1,728
30
161
1,728
30
173
1,728
1,728
1,728

17,370.94
43,427.34
39,084.61
41,255.97
43,427.34
49,024.91
53,927.40
1,021,225.25
1,021,225.25
140,611.43
19,700.00
5,046.00
157,200.00
30,125.00

30,016,977.41
8,338,049.28
67,538,199.17
1,237,679.19
6,991,801.74
93,186,548.93
30,636,757.50
176,671,968.25
8,719,488.00
271,641,600.00
52,056,000.00
747,035,069.46

Concrete, Formwork and Reinforcement


1
2
3
4
5
6
7
8
9
10
11
12
13

Blockwork
115 block wall in superstructure
115 brickforce
Half brick wall in common brickwork in beam filling
Bedding roof coverings
Set up in position cross brase & bldng in steel door frame n.e 5m2.
Set up in position cross brase & bldng in steel window frame n.e 5m2.
Brick-on- edge ext cill set slopping as described
Brick-on- edge lintol set horizontally as described
One layer of three ply DPC as described
One layer of three ply DPCto cills
One layer of three ply DPC to sprockets
230 x150 mm Air vents (EXT)
230 x150 mm Air vents (INT)

m2
m
m2
m
no
no
m
m
m2
m2
m2
no
no

801
2,355
10
32
7
7
14
24
8
2
2
14
14

140,611.43
19,700.00
84,366.86
75,930.17
39,150.00
39,150.00
102,122.53
102,122.53
120,325.00
120,325.00
120,325.00
25,365.00
25,365.00

112,629,755.43
46,393,500.00
843,668.58
2,429,765.51
274,050.00
274,050.00
1,429,715.35
2,450,940.60
956,583.75
193,723.25
235,235.38
355,110.00
355,110.00
9,797,952.42

1
2
3
4
5
6
7

Joinery & Ironmongery


44mm int.quality semi s/core flush panel door,concealed h/wood edging strip
44mm ext.quality semi s/core flush panel door,concealed h/wood edging strip
Union n CZ682-24-95CH two lever lockset
Union n CZ682-25-95CH three lever lockset
Chromium plated hat and coat hook
19mm chromium plated towel rail 500mm long incl end brackets
38mm Diameter rubber door stop screwed to plug in wall/floor

no
no
no
no
no
no
no

6
2
6
2
2
1
6

1,512,000.00
1,512,000.00
370,251.01
444,301.21
75,258.25
225,774.75
38,254.25

9,072,000.00
3,024,000.00
2,221,506.06
888,602.42
150,516.50
225,774.75
229,525.50
15,811,925.23

1
2
3
4
5
6

Plastering & Wall Linings


Two coats cement plaster to internal walls
Ditto in narrow width
Two coats cement plaster to external walls
Ditto in narrow width
180x180mm recesso Toilet roll holder iclu bldng into plastered wall
180x180x120mm single soap dish

m2
m2
m2
m2
no
no

91
3
66
9
2
2

65,690.70
65,690.70
65,690.70
65,690.70
55,254.85
55,254.85

5,977,853.70
197,072.10
4,335,586.20
591,216.30
110,509.70
110,509.70
11,322,747.70

1
2

SUMMARY
Foundations (Provisional)
Blockwork

747,035,069.46
9,797,952.42

1
2

Joinery & Ironmongery


Plastering & Wall Linings

15,811,925.23
11,322,747.70

Sub Total
13 Preliminaries & Generals

783,967,694.81
156,793,538.96
940,761,233.78
141,114,185.07

Sub Total
Add: 15% VAT
Total Cost of a Single Unit

Total Cost of 400Units

1,081,875,418.84

Units

400

1,081,875,418.84

432,750,167,537.00

Construction of Houses
Bill Of Quantities
Item Description
Foundations (Provisional)
1 Topsoil excavation
2 Excavate in pickable mat.for strip footings n.e 2 metres deep.
3 Scarify reduced surfaces and compact mechanically to 93% HCE<150mm
4 Cart away surplus excavated mat to a dump site to be located by Contractor
5 Backfilling to trenches wth approved excvated mat to 93% HCE,150mm dpth
6 150mm Hard core filling base course wth approved decomposed granite
7 Termite treatment
8 20 Mpa in footings
9 20 Mpa in surface beds
10 115 block wall in fdn
11 115 brickforce
12 Strike off & cure top surfces of concrete
13 Fabric reinforcement; Ref. S193
14 1 layer250 micron "Tarcon" polythene DPM laid on and including 50mm sand

Uom Qty

Rate

Amount

m2
m3
m2
m3
m3
m3
m2
m3
m3
m2
m
m2
m2
m2

66
22
26
8
12
13
54
4
5
45
90
54
54
54

20,845.12
52,112.81
31,267.68
37,130.38
49,941.44
73,537.37
64,712.88
1,123,347.78
1,123,347.78
154,672.57
29,550.00
8,073.60
194,928.00
32,390.40

1,375,778.13
1,146,481.78
812,959.80
297,043.01
599,297.29
955,985.75
3,494,495.58
4,108,082.81
5,953,743.21
6,967,999.41
2,662,455.00
435,974.40
10,526,112.00
1,749,081.60
41,085,489.77

154,672.57
154,672.57
29,550.00
92,803.54
83,523.19
35,235.00
38,367.00
112,334.78
112,334.78
122,731.50
122,731.50
122,731.50
26,125.95
26,125.95

461,190.60
261,163.00
130,581.50
50,895.00

20,880,797.36
41,761,594.71
295,500.00
2,969,713.40
584,662.33
246,645.00
537,138.00
2,696,034.66
893,061.48
197,597.72
239,940.08
1,718,241.00
365,763.30
10,744,296.97
4,150,715.40
522,326.00
2,089,304.00
6,762,345.40

1
2
3
4
5
6
7
8
9
10
11
12
13

Blockwork
115 block wall in superstructure
115 brickforce
Half brick wall in common brickwork in beam filling
Bedding roof coverings
Set up in position cross brase & bldng in steel door frame n.e 5m2.
Set up in position cross brase & bldng in steel window frame n.e 5m2.
Brick-on- edge ext cill set slopping as described
Brick-on- edge lintol set horizontally as described
One layer of three ply DPC as described
One layer of three ply DPCto cills
One layer of three ply DPC to sprockets
230 x150 mm Air vents (EXT)
230 x150 mm Air vents (INT)

m2
m
m2
m
no
no
m
m
m2
m2
m2
no
no

135
270
10
32
7
7
14
24
8
2
2
14
14

1
2
3
4

Roof Coverings
Asbestos sheeting to roof
Ridge
Stop ends
Rough raking and cutting to waste

m2
m
no
m

66
9
2
16

1
2
3

Carpentry
Supply and fix roof trusses
38x114mm sawn softwood wallplate
152x50mm wrot softwood purlins
12x225mm timber fascia as described

m
m
m

15
54
32

154,672.57
89,112.98
178,225.95
160,403.36

2,320,088.60
4,812,100.65
5,703,230.40
12,835,419.65

1
2
3
4
5
6
7

Joinery & Ironmongery


44mm int.quality semi s/core flush panel door,concealed h/wood edging strip
44mm ext.quality semi s/core flush panel door,concealed h/wood edging strip
Union n CZ682-24-95CH two lever lockset
Union n CZ682-25-95CH three lever lockset
Chromium plated hat and coat hook
19mm chromium plated towel rail 500mm long incl end brackets
38mm Diameter rubber door stop screwed to plug in wall/floor

no
no
no
no
no
no
no

6
2
6
2
2
1
6

1,461,190.60
1,360,800.00
470,254.00
564,304.80
78,592.00
112,545.00
39,258.00

1
2
3
4
5
6

Plastering & Wall Linings


Two coats cement plaster to internal walls
Ditto in narrow width
Two coats cement plaster to external walls
Ditto in narrow width
180x180mm recesso Toilet roll holder iclu bldng into plastered wall
180x180x120mm single soap dish

8,767,143.60
2,721,600.00
2,821,524.00
1,128,609.60
157,184.00
112,545.00
235,548.00
15,944,154.20
-

m2
m2
m2
m2
no
no

91
3
66
9
2
2

98,536.05
98,536.05
98,536.05
98,536.05
82,882.28
82,882.28

295,608.15
6,503,379.30
886,824.45
197,072.10
165,764.55
8,048,648.55

Metal Work
Window frames
ND4F
NC4F
NC5F
Door frames
813x2032x115 door frames

1
2

Pavings & Floor Coverings


40mm granolithic floor
75mm High granolithic skirting

m2
m

53
57

101,101.30
33,700.43

5,358,368.89
1,920,924.70
7,279,293.58

1
2
3
4
5
6
7
8

SheetMetalwork,Plumbing & Drainlaying(Provisional)


SOIL DRAINAGE
100mm PVC drain pipe as described under floors
100mm PVC y-junction
100mm PVC junction with inspection eye
110 mm Gully trap as described
Allow for testing
50mm pvc pipe
50mm pvc bend
50mm pvc tee

m
no
no
no
item
no
no
no

10
2
1
2
1
12
3
3

301,257.00
319,194.91
227,996.37
133,379.68
600,000.00
48,333.83
47,855.28
39,879.40

3,012,570.00
638,389.83
227,996.37
266,759.35
600,000.00
580,005.99
143,565.84
119,638.20

6
7
8
9
10
11
12

Cold Water Supply and Sanitary Fittings


Double sink
Wash hand basin
WC
Shower cap
22mm gi pipe
22mm tee
22mm bend

no
no
no
no
m
no
no

1
1
1
1
20
3
3

14,387,667.50
9,110,134.00
16,526,434.25
137,779.40
36,876.75
44,252.10
46,464.71

14,387,667.50
9,110,134.00
16,526,434.25
137,779.40
737,535.04
132,756.31
139,394.12
46,760,626.20

1
2
3

Glazing
3mm clear sheet glass and glazing in steel sash
3-4mm obscure ditto
Mirror size 600x450mm

m2
m2
m2

11
2
1

418,428.78
502,114.54
753,171.80

4,602,716.58
836,857.56
502,114.54
5,941,688.68

1
2
3
4
5
6
7

Painting
Prepare & apply 2 cts int. pva to int. walls
Prepare & apply 3 cts int. pva to ext. walls
2 cts high gloss enamel on general surfaces of doors
Ditto to steel window frames
Ditto to steel door frames
Bituminous paint to wall plates
Allow for touching up and cleaning

m2
m2
m2
m2
m2
m2
Sum

99
66
23
11
4
9
1

52,269.90
52,269.90
80,070.31
40,035.16
100,087.89
80,070.31
600,000.00

5,174,720.10
3,449,813.40
1,811,510.75
440,386.72
400,351.56
720,632.81
600,000.00
12,597,415.34

Provisional Sums
Electricity

sum

8,000,000.00

8,000,000.00
8,000,000.00

1
2
3

no
no
no

4
1
2

2,965,179.58
2,940,179.58
1,647,462.94

11,860,718.31
2,940,179.58
3,294,925.87

no

1,132,909.90

7,930,369.30
26,026,193.05

SUMMARY
Foundations (Provisional)
Blockwork
Roof Coverings
Carpentry
Joinery & Ironmongery
Plastering & Wall Linings
Metal Work
Pavings & Floor Coverings
SheetMetalwork,Plumbing & Drainlaying(Provisional)
Glazing
Painting
Sub Total
13 Preliminaries & Generals
14 Prime Costs & Provisional Sums
Sub Total
Add: 15% VAT
1
2
3
4
5
6
7
8
9
10
11

41,085,489.77
10,744,296.97
6,762,345.40
12,835,419.65
15,944,154.20
8,048,648.55
26,026,193.05
7,279,293.58
46,760,626.20
5,941,688.68
12,597,415.34
194,025,571.39
38,805,114.28
8,000,000.00
240,830,685.67
36,124,602.85

Total for one unit

Total Cost for 400Units

276,955,288.52

Units

400

276,955,288.52
-

110,782,115,406.95

Proposed Construction of 400no.Housing Units


Bill Of Quantities
Item Description
Foundations (Provisional)
1 Excavate oversite to remove topsoil & spread & level on site
2 Excavate in pickable mat.for strip footings n.e 2 metres deep.
3 Scarify reduced surfaces and compact mechanically to 93% HCE<150mm
4 Cart away surplus excavated mat to a dump site to be located by Contractor
5 Backfilling to trenches wth approved excvated mat to 93% HCE,150mm dpth
6 150mm Hard core filling base course wth approved decomposed granite
7 Termite treatment
8 20 Mpa in footings
9 20 Mpa in surface beds
10 115 block wall in fdn
11 115 brickforce
12 Strike off & cure top surfces of concrete
13 Fabric reinforcement; Ref. S193
14 1 layer250 micron "Tarcon" polythene DPM laid on and including 50mm sand

Uom Qty

Rate

Amount

m2
m3
m2
m3
m3
m3
m2
m3
m3
m2
m
m2
m2
m2

62
19
25
10
11
11
53
4
5
45
90
53
53
53

25,014.15
57,324.09
51,591.68
54,457.88
57,324.09
80,891.10
88,980.21
1,531,837.88
1,531,837.88
175,764.29
28,400.00
8,334.60
165,900.00
45,187.50

1,562,533.76
1,089,157.69
1,289,792.00
544,578.84
630,564.98
857,445.68
4,715,951.22
5,601,931.11
8,118,740.74
7,918,181.15
2,558,840.00
441,733.80
8,792,700.00
2,394,937.50
46,517,088.46

23,728,178.81
47,456,357.63
284,000.00
3,374,674.32
664,389.01
365,400.00
730,800.00
3,676,410.90
1,217,811.11
248,934.38
302,277.46
2,164,646.75
532,665.00
13,562,008.92
29,378,728.13
1,995,536.25
447,708.00
1,865,450.00
33,687,422.38

1
2
3
4
5
6
7
8
9
10
11
12
13

Blockwork
115 block wall in superstructure
115 brickforce
Half brick wall in common brickwork in beam filling
Bedding roof coverings
Set up in position cross brase & bldng in steel door frame n.e 5m2.
Set up in position cross brase & bldng in steel window frame n.e 5m2.
Brick-on- edge ext cill set slopping as described
Brick-on- edge lintol set horizontally as described
One layer of three ply DPC as described
One layer of three ply DPCto cills
One layer of three ply DPC to sprockets
230 x150 mm Air vents (EXT)
230 x150 mm Air vents (INT)

m2
m
m2
m
no
no
m
m
m2
m2
m2
no
no

135
270
10
32
7
7
14
24
8
2
2
14
14

175,764.29
175,764.29
28,400.00
105,458.57
94,912.72
52,200.00
52,200.00
153,183.79
153,183.79
154,617.63
154,617.63
154,617.63
38,047.50
38,047.50

1
2
3
4

Roof Coverings
Asbestos sheeting to roof
Ridge
Stop ends
Rough raking and cutting to waste

m2
m
no
m

66
9
2
16

443,452.50
221,726.25
223,854.00
116,590.63
48,937.50

1
2
3

Carpentry
Supply and fix roof trusses
38x114mm sawn softwood wallplate
152x50mm wrot softwood purlins
12x225mm timber fascia as described

m
m
m

15
54
32

443,452.50
74,260.81
148,521.63

6,651,787.50
4,010,083.88
4,752,692.00
15,414,563.38

1
2
3
4
5
6
7

Joinery & Ironmongery


44mm int.quality semi s/core flush panel door,concealed h/wood edging strip
44mm ext.quality semi s/core flush panel door,concealed h/wood edging strip
Union n CZ682-24-95CH two lever lockset
Union n CZ682-25-95CH three lever lockset
Chromium plated hat and coat hook
19mm chromium plated towel rail 500mm long incl end brackets
38mm Diameter rubber door stop screwed to plug in wall/floor

no
no
no
no
no
no
no

6
2
6
2
2
1
6

1,814,400.00
1,814,400.00
407,276.11
488,731.33
82,784.08
248,352.23
42,079.68

1
2
3
4
5
6

Plastering & Wall Linings


Two coats cement plaster to internal walls
Ditto in narrow width
Two coats cement plaster to external walls
Ditto in narrow width
180x180mm recesso Toilet roll holder iclu bldng into plastered wall
180x180x120mm single soap dish

10,886,400.00
3,628,800.00
10,886,400.00
814,552.22
977,462.67
82,784.08
1,490,113.35
28,766,512.31
-

m2
m2
m2
m2
no
no

91
3
66
9
2
2

72,259.77
72,259.77
72,259.77
72,259.77
60,780.34
60,780.34

6,575,639.07
216,779.31
4,769,144.82
650,337.93
144,519.54
121,560.67
12,477,981.34

Metal Work
Window frames
ND4F
NC4F
NC5F
Door frames
813x2032x115 door frames

1
2

Pavings & Floor Coverings


40mm granolithic floor
75mm High granolithic skirting

m2
m

53
57

137,865.41
45,955.14

7,306,866.66
2,619,442.77
9,926,309.43

1
2
3
4
5
6
7
8

SheetMetalwork,Plumbing & Drainlaying(Provisional)


SOIL DRAINAGE
100mm PVC drain pipe as described under floors
100mm PVC y-junction
100mm PVC junction with inspection eye
110 mm Gully trap as described
Allow for testing
50mm pvc pipe
50mm pvc bend
50mm pvc tee

m
no
no
no
item
no
no
no

10
2
1
2
1
12
3
3

221,290.59
304,889.26
245,878.44
133,379.68
750,000.00
48,333.83
47,855.28
39,879.40

2,212,905.92
442,581.18
304,889.26
491,756.87
133,379.68
9,000,000.00
145,001.50
143,565.84

6
7
8
9
10
11
12

Cold Water Supply and Sanitary Fittings


Double sink
Wash hand basin
WC
Shower cap
22mm gi pipe
22mm tee
22mm bend

no
no
no
no
m
no
no

1
1
1
1
20
3
3

15,528,637.50
12,422,910.00
17,081,501.25
145,294.64
34,194.81
41,033.77
43,085.46

15,528,637.50
12,422,910.00
17,081,501.25
2,905,892.80
102,584.42
123,101.30
61,038,707.51

1
2
3

Glazing
3mm clear sheet glass and glazing in steel sash
3-4mm obscure ditto
Mirror size 600x450mm

m2
m2
m2

11
2
1

418,428.78
512,156.83
768,235.24

4,602,716.58
836,857.56
512,156.83
5,951,730.97

1
2
3
4
5
6
7

Painting
Prepare & apply 2 cts int. pva to int. walls
Prepare & apply 3 cts int. pva to ext. walls
2 cts high gloss enamel on general surfaces of doors
Ditto to steel window frames
Ditto to steel door frames
Bituminous paint to wall plates
Allow for touching up and cleaning

m2
m2
m2
m2
m2
m2
Sum

99
66
23
11
4
9
1

56,369.50
56,369.50
64,056.25
32,028.13
88,077.34
70,461.88
750,000.00

5,580,580.50
3,720,387.00
1,275,303.57
704,618.75
128,112.50
792,696.09
70,461.88
12,272,160.29

Provisional Sums
Electricity

sum

6,500,000.00

6,500,000.00
6,500,000.00

1
2
3

no
no
no

4
1
2

2,626,265.67
1,459,036.48
1,224,366.28

10,505,062.67
2,626,265.67
2,918,072.96

no

1,259,887.38

8,819,211.63
24,868,612.92

SUMMARY
Foundations (Provisional)
Blockwork
Roof Coverings
Carpentry
Joinery & Ironmongery
Plastering & Wall Linings
Metal Work
Pavings & Floor Coverings
SheetMetalwork,Plumbing & Drainlaying(Provisional)
Glazing
Painting
Sub Total
13 Preliminaries & Generals
14 Prime Costs & Provisional Sums
Sub Total
Add: 15% VAT
1
2
3
4
5
6
7
8
9
10
11

46,517,088.46
13,562,008.92
33,687,422.38
15,414,563.38
28,766,512.31
12,477,981.34
24,868,612.92
9,926,309.43
61,038,707.51
5,951,730.97
12,272,160.29
264,483,097.90
52,896,619.58
6,500,000.00
323,879,717.48
48,581,957.62

Total cost of a house

Total Cost for 400Units

372,461,675.10

Units

400

372,461,675.10

148,984,670,041.32

Bill Of Quantities
Description

Item

Unit

Foundations (Provisional)
1

Clear site of all rubbish,debri etc

m2

Excavate oversite to remove topsoil & spread & level on site

m2

Excavate in pickable mat.for strip footings n.e 2 metres deep.

m3

Scarify reduced surfaces and compact mechanically to 93% HCE<150mm dpth

m2

Allow for risk of collapse to sides of excavation

m2

Cart away surplus excavated mat to a dump site to be located by Contractor

m3

Backfilling to trenches wth approved excvated mat to 93% HCE,150mm dpth

m3

150mm Hard core filling base course wth approved decomposed granite

m3

Termite treatment

m2

10

20 Mpa in footings

m3

11

20 Mpa in surface beds

m3

12

One block wall in foundation

m2

13

115 brickforce

14

Strike off & cure top surfces of concrete

m2

15

Fabric reinforcement; Ref. S193

m2

16

1 layer250 micron "Tarcon" polythene DPM laid on and including 50mm sand blinding

m2

Brickwork
1

One block wall in superstructure

m2

Half brick wall in concrete brickwork in beam filling

m2

75mm Brickforce to suit 115mm brick wall

Half brick shower kerb

Bedding roof coverings

Set up in position cross brase & bldng in steel door frame n.e 5m2.

no

Set up in position cross brase & bldng in steel door frame exc. 5m2.

no

Set up in position cross brase & bldng in steel window frame n.e 5m2.

no

Brick-on- edge ext cill set slopping as described

10

Brick-on- edge lintol set horizontally as described

11

Rough raking and cutting

m2

12

Rake out joints of brickwork for turning in of metal flashing

13

One layer of three ply DPC as described

m2

14

10mm Kaylite joint filler material in expansion joints as described

m2

15

230 x150 mm Air vents (EXT)

no

16

230 x150 mm Air vents (INT)

no

17

Built in jet master

no

Qty

Roof Coverings
1

Marley major concrete interlocking roof tiles

m2

Ridge

Valley

Stop ends

no

Underfelt to roof tiles

m2

Rough raking and cutting to waste

Carpentry
Supply and fix roof trusses

sum

38 x 38mm Fascia runners

38 x 38mm timber butterns

m2

38x114mm sawn softwood wallplate

152x50mm wrot softwood purlins

12x225mm flat asbestos cement fascia as described

Joinery & Ironmongery


1

12mm "Gypsum Industries" plasterboard sheeting as described

Cornice

Extra over for trimming for & forming trap door 610x610 as described

no

19x75mm W/hardwood angle rounded skirting wth & inclu 19mm Quadrant
44mm int.quality semi s/core flush panel door,concealed h/wood edging strip size
813x2032mm
44mm ext.quality semi s/core flush panel door,concealed h/wood edging strip size
813x2032mm
22x145mm pelmets, Commercial grade blockboard top, end or front secured to sw bearer

Ditto stop ends

38x50mm Wrot softwood bearer

10

Union n CZ682-24-95CH two lever lockset

no

11

Union n CZ682-25-95CH three lever lockset

no

12

Chromium plated hat and coat hook

no

13

19mm chromium plated towel rail 900mm long incl end brackets

no

14

20mm chromium shower curtain rail 900mm long incl end brackets

no

15

Approved chromium plated shower rose and arm

no

16

Approved 15mm chromium plated shower mixer

no

17

Approved 15mm sink mixer wth swivel arm

no

18

38mm Diameter rubber door stop screwed to plug in wall/floor

no

19

Approved plastic nylon shower curtain size 1200x2200mm long

no

20

Union 8095 indictor bolt

21

Supply and fix BICs

5
6

m2

m
no
no
m
no

no
sum

Plastering & Wall Linings


1

One coat cement plaster with steel float and set in Rhinoset internal

m2

Ditto in narrow width

m2

One coat wood float plaster to walls externally

m2

One coat wood float plaster to walls in n. w.

m2

150x150x6mm White glazed wall tiles as described

m2

Ditto in narrow width

m2

Ditto in splashbacks

m2

180x180mm recesso Toilet roll holder iclu bldng into plastered wall

no

180x180x120mm single soap dish

no

Metal Work
Aluminium sliding door
1

PD12xx

no

PD15xx

no

PD240xxo

no

Window frames
4

ND7-NG8

no

ND4-NG4

no

ND1-NG5

no

NE2

no

ND4

no

NE4

no

10

NDV22-NG22

no

11

NC4

no

12

NE1

no

13

813x2032x115 door frames

no

14

Roller shutter doors

no

15

Jetmaster

no

Pavings & Floor Coverings


1

40mm granolithic floor

75mm High granolithic skirting

300x300x8mm Non slip Ceramic floor tiles finished with two coats of wax polish

6x40mm Aluminium dividing strip

30mm screed

m2

Carpert floor

m2

m2
m
m2
m

SheetMetalwork,Plumbing & Drainlaying(Provisional)


1

0.6 mm Galvanised sht metal flashing as described

m2

Gutter
2

125x100x125 ogee type eaves gutter

Eo stop end

no

Ditto bend

no

Down pipe 100mm

EO shoe

no

Ditto bend

no

Ditto neck

no

Shower tray

no

WC Complete with 14 ltr fibreglasscisten as described.

no

Bath 1825x745mm as described

no

Fibre vanity basin size 550x460mm as described.

no

Double sink

no

50mm PVC pipe as described

50mm PVC pipe as described under surface beds

100mm PVC ventilating pipe as described fixed to walls

Extra over items


10

50mm PVC bend

no

11

50mm PVC bend with inspection eye

no

12

50mm PVC junction with inspection eye

no

13

100mm PVC junction with inspection eye

no

14

100mm PVC bend with inspection eye

no

15

100mm PVC straight connector

no

16

Air vent valve

no

17

32 mm chromium plated ''botle'' trap

no

18

75mm Glass - enamelled spigot socket ''P'' trap as described

no

19

40 mm chromium plated ''botle'' trap

no

20

50mm copper deep seal ''P'' & ''S'' trap as described

no

21

40 mm copper deep seal as described

no

22

40 mm copper deep seal as described shower waste pipe

23

Allow for testing

no
item

SOIL DRAINAGE
24

100mm PVC drain pipe as described under floors

25

100mm PVC bend

no

26

100mm PVC bend with inspection eye

no

27

100mm PVC junction with inspection eye

no

28

110 mm Gully trap as described

no

29

Encase 100mm pipe as described

30

Allow for testing

m
item

HOT & COLD WATER INSTALLATION


COPPER PIPING
31

15mm service connector as described

no

31

15mm service pipe as described

32

15mm service pipe as described in chase

33

15mm service pipe as described in roof space

34

22mm service pipe as described

35

22mm service pipe as described in chase

36

22mm service pipe as described in roof space

37

22mm bend

no

38

22mm tee

no

39

22x15mm Tee

no

Galvanised Mild steel Pipes


40

20mm pipe in ground as described

Geysers
41

100 ltr roof gyser as described

no

42

15mm stop cocks & jointing to pipe

no

43

22mm stop cocks & jointing to pipe

no

44

Approved water metre connected to 20mm dai. Pipe.

no

45

Leave hole for small pipe throu. 115 wall.

no

46

100mm cast iron ''ABC''c/r eye as described

no

47

Excavate in pickable mat.for 150mm pipe as described

48

Backfilling imported fill haul distance n.e. 1.5km

m3

Glazing
1

3mm clear sheet glass and glazing in steel sash

m2

3-4mm obscure ditto

m2

Mirror size 600x450mm

m2

Painting
1

Prepare & apply 2 cts int. pva to steel float walls

m2

Prepare & apply 3 cts int. pva to wood float walls

m2

Prepare & apply 3 cts int. pva on ceilings

m2

Metal primer,undercoat,2 cts high gloss enamel on general surfaces of doors

m2

Ditto to steel window frames

m2

Clear polyurethane varnish on skirtings

m2

Metal primer,undercoat,2 cts high gloss enamel on steel door frames

m2

Ditto roller shutter doors

m2

Gloss enamel to pelmets

m2

10

Bituminous paint to wall plates

m2

11

Allow for touching up and cleaning

Sum

Provisional Sums
1

Electricity

sum

Supply and fix shower cubicles

sum

Extenal works, landscaping and boundary fence

sum

SUMMARY
1

Foundations (Provisional)

Brickwork

Roof Coverings

Carpentry

Joinery & Ironmongery

Plastering & Wall Linings

Metal Work

Pavings & Floor Coverings

SheetMetalwork,Plumbing & Drainlaying(Provisional)

10

Glazing

11

Painting
Sub Total

13

Preliminaries & Generals

14

Prime Costs & Provisional Sums


Sub Total
Add: 15% VAT
Total Carried to Form of Tender

BRIAN COLOQUHOUN AND PARTNERS CONSULTING ENGINEERS

EXCAVATIONS
DATA
Excavation Gang
WX
Gang Boss
WG1
Labourer

2.02 p day x 9hrs x 1


1.58 p day x 9hrs x 10

18.18
142.20
160.38

Excavation Gang
WX
Gang Boss
WG1
Labourer

2.02 p day x 9hrs x 1


1.58 p day x 9hrs x 8

18.18
113.76
131.94

Tractor & Trailer


Diesel
Operator WG3

(hire charge)

Plate compactor
Petrol
Operator WG3

per day
p Lt x 10Lt p hr x 9 hrs
9hrs p day

27.00 per day x1


1.20 p Lt x 0.90 x 8hrs worked
1.59 p hrx9hrs p day

27.00
8.64
14.31
49.95

Bomag 90 Roller
Diesel
Operator WG3

0.00 p day x 1
p lt x1.25ltr p hr x9 hrs spd
p hrx9hrs p day

Bomag 90 Roller
Diesel
Operator WG3

0.00 p day x 1
0.00 p lt x1.25ltr p hr x9 hrs spd
0.00 p hrx9hrs p day

350 c.f.m - compressor


350 c.f.m - compressor
Breaker
Air hose
Diesel
Jack hammer
Operator WG3

99.00 per day


78.00
100 p day
1.05 per ltr x 10ltrs per hr x9 hrs a day
per hr x 2 x 9hts /1.25 cm
0.00 p hrx9hrs p day

99.00
78.00
94.50
100.00
371.50

Sand cost per m3

Pit sand cost per m3

Gravel cost per m3

Decomposed granite

RATE BUILD UP

Excavate in pickable mat.to reduced levels n.e 2m deep


Excavation Gang G.B & 10
160.38 p day / 22 cu m p day
L

7.29

8.75

10.69

12.83

13.37

16.04

0.53
0.53

0.64

1.07
0.40
1.47

1.76

0.80
0.32
0.09
1.21

1.46

2.92
2.92

3.50

64.15
64.15

76.98

7.29

Excavate in pickable mat.for ground beams, strip footings n.e 2 metres deep.
Excavation Gang G.B & 10

160.38 p day / 15 cu m p day

L 10.69

Excavate in pickable mat. for column bases n.e 2 metres deep.


Excavation Gang G.B & 10

160.38 p day / 12 cu m p day

L 13.37

Scarify reduced surfaces and compact mechanically to 93% HCE<150mm dpth as described.
Excavation Gang G.B & 10
Bomag
L

160.38 p day / 300 sq m p day


0.00 p day x 2 No / 300 m2 p day

0.53

0.00

Hand or power ram bottoms of bases to 93% HEC density, 150mm depth as described
Excavation Gang G.B & 10
160.38 p day /150 m2 p day
Plate compactor
49.95 p day x 2 / 250 m2 p day
L

1.07

0.40

Allow for risk of collapse to sides of excavation


Excavation Gang G.B & 10
Excavation Gang G.B & 10
Plate compactor
L

160.38 p day / 10 cu m p day


160.38 p day / 25 cu m p day
49.95 p day x 2 / 55 cu m p day
= applied Factor
x 0.05
P
0.09

1.12

Cart away surplus excavated mat to a dump site to be located by Contractor


Excavation Gang G.B & 10
Tractor and trailer
L

160.38 p day / 55 cu m p day load


0.00 per day / 55 cu m p day x 1.30 Bulking

2.92

Extra over for excavation in soft rock.


Excavation Gang G.B & 10
Excavation Gang G.B & 10

0.00

160.38 p day / 2.5 cu m p day


0.00 p day / 15 cu m p day [+]

64.15

Extra over for excavation in hard rock


Excavation Gang G.B & 10
Excavation Gang G.B & 10
350 c.f.m - compressor {DIESEL }
Excavation Gang G.B & 10

112.27

160.38
160.38
371.50
160.38

p day /2.0 cu m p day Breaking


p day / 3.75 cu m p day Bulking
p day /40.00 cu m p day
p day / 15 cu m p day

80.19
42.77
9.29
10.69
121.55

145.86

2.92
1.82
4.73

5.68

9.29

Backfilling to trenches wth approved excvated mat to 93% HCE,150mm dpth


Excavation Gang G.B & 10
Plate compactor

2.92

160.38 p day / 55 cu m p day


49.95 p day x 2 / 55 cu m p day

1.82

Approved non- expansive mat wth gravel infill , level and compact as described
Excavation Gang G.B & 10
Bomag Roller
Gravel

160.38 p day / 75 cu m p day


0.00 p day / 75m3 p day x 2
p m3 x 1.33 bulk

2.14

0.00

0.32

0.00

0.32
0.32

0.38

0.64

0.77

0.27
0.27

0.32

M 0.00

Clear site of all vegetation incl removal and dis posal of bushes as described
Excavation Gang G.B & 10
160.38 p day / 250 m2 p day
L

2.57

M 0.00

150mm Hard core filling base course wth approved decomposed granite
to 93% HCE density
Excavation Gang G.B & 10
160.38 p day / 75 cu m p day
Bomag Roller
0.00 p day / 75m3 p day x 2
Decomposed granite
p m3 x 1.33 bulk
Applied Factor x 0.15
L

2.14
2.14

0.64

600x600x50mm Paving slabs laid on 50mm sand bed


Excavation Gang G.B & 10
B/layer & Team
Bomag
Slabs
Sand

160.38 p day / 600m2 p day spreading


p day / 30m2 p day spreading
0.00 p day x 2 No / 300 m2 p day
pm2x1.025 wst
0.00 p m3 x.050x 1.33 bulk

0.27

0.00

M 0.00

100mm Thick plain concrete(15Mpa) appron including shallow excavations


Concrete
Excavations

(1.0x1.0x0.1m) @ 8526.04
(1.0x1.0x0.1m) @ 631.22

852.60

Strip vegetable soil 150mm deep


Excavation Gang G.B & 10
L

852.60
63.12
915.73

0.80

63.12

160.38 p day / 200 m2 p day

0.80

0.96

Use This table together with the concrete data above for the calculation of the rates.
DATA FOR THE RATES
NET RATES
RESOURCE WASTAGE
PLANT

1.00

WAGES

1.00

CEMENT

1.1

STONE

GRADE
40

GRADE OF CONCRETE
GRADE
25

GRADE
30

961.28*1.00 waste

961.28*1.00 waste

GRADE
20

961.28*1.00 waste

GRADE
15

961.28*1.00 waste

GRADE
10 mass

961.28*1.00 waste

GRADE
10 blinding

961.28*1.00 waste

961.28*1.00 waste

648300.73x9.6bgs pm3x1.10 waste

648300.73x8.58bgs pm3x1.10 waste

648300.73x7.6bgs pm3x1.10 waste

648300.73x6.46bgs pm3x1.10 waste

648300.73x5.32bgs pm3x1.10 waste

648300.73x4.18bgs pm3x1.10 waste

648300.73x4.6bgs pm3x1.10 waste

1.075

5214915x0.86m3 p m3x1.075 wst

5214915x0.781m3 p m3x1.075 wst

5214915x0.781m3 p m3x1.075 wst

5214915x0.781m3 p m3x1.075 wst

5214915x0.764m3 p m3x1.075 wst

5214915x0.781m3 p m3x1.075 wst

5214915x0.75m3 p m3x1.075 wst

SAND

1.2

1317788x0.58m3 p m3 x1.20 wst

1317788x0.598m3 p m3 x1.20wst

1317788x0.64m3 p m3 x1.20wst

1317788x0.676m3 p m3 x1.20 wst

1317788x0.671m3 p m3 x1.20 wst

1317788x0.75m3 p m3 x1.20 wst

1317788x0.80m3 p m3 x1.20 wst

WASTAGE
ON MAT.

0.00

VIBRATION

1.00

TOTAL COST

0.00

0.00

0.00

0.00

0.00

0.00

0.00

50.16p m3 x 1.00 waste

50.16p m3 x 1.00 waste

50.16p m3 x 1.00 waste

50.16p m3 x 1.00 waste

50.16p m3 x 1.00 waste

50.16p m3 x 1.00 waste

50.16p m3 x 1.00 waste

TOTAL COST

TOTAL COST

TOTAL COST

TOTAL COST

TOTAL COST

TOTAL COST

TOTAL COST

CONCRETE RATES
1) PLANT
DATA
A. Concrete volume per day
B. Mixer (14/10 Electrical) & Weigh batcher Hire Rate per day
C. Diesel price per litre
D. Oil price per litre
E. Diesel used per day
F. Oil used per month

15 m3
400,000.00
400,000.00
35 Litres
10 Litres

COST
Mixer & Weigh batcher Hire
Diesel
Oil
Total cost
Unit Allow

34,181,818.18 p day /15 cu m p day

2) WAGES
DATA
A. Concrete Volume per day
B. WG1 Rate per day
C. WG3 Rate per day
D. WG4 Rate per day

125775.920 p hr x 9 hrs p day


127938.740 p hr x 9 hrs p day
132270.660 p hr x 9 hrs p day

20000000.00 x 1
400,000.00 p Ltr x 20 Ltrs p day
400,000.00 p Ltr x 5 Ltrs p day/22

20000000.00
14,000,000.00
181,818.18
34,181,818.18
2,278,787.88

15 m3
1131983.28
1151448.66
1190435.94

3) Total Volume of Concrete

m3
p day m3

>>>>>
Approximately

15 m3 p day

WG.1
2N on stone
2N on sand
2N on cement
1N on top of mixer
5N on wheel barrows
3N on placing
1N on curing
16
N TOTAL

WG 3
1N Mixer operator
1N Vibrator operator
2N Screeder
4
N TOTAL
WG 4
1N Gang Boss
1
COST
WG1
WG3
WG4
Total Cost
Unit Allow

(In P & G)

N TOTAL

125775.920 p day x 16
127938.74 p day x 4
132270.66 x 1
23907963.06 / 15 cu m p day

18,111,732.48
4,605,794.64
1,190,435.94
23,907,963.06
1,593,864.20

4. CEMENT
DATA
A. WG1 Rate per hour
B Price delivery
C Transport per bag
COST
Cement
Loading
Offloading
Transport
Total cost
Add waste 1%

125775.920
2500000.00

5) STONE
DATA
A. WG1 Rate per hour
B. Price ex works per m3
C. Transport per m3
COST
Stone
Loading
Offloading
Transport
Total Cost
6) RIVER SAND
DATA
A. WG1 Rate per hour
B. Price ex works per m3
C. Transport per m3
COST
Sand
Loading
Offloading
Transport
Total cost
7) VIBRATION
DATA
A 48mm Poker
B. 63mm Poker
C. Petrol Vibrator
D. Petrol price per litre
E, Petrol used per day
F. Concrete volume per day
COST
Pokers
Vibrator
Petrol
Total Cost

2500000.00 p bg x 1

2500000.00

2500000.00 x 1.01 waste

0.00 per bag


2500000.00
2525000.00

125775.920
5214915.00

10000000.00
0.00
0.00

10000000.00
0.00
0.00
0.00
10000000.00

125775.920
1317788.00
0.00
3500000.00
0.00
0.00
0.00

1800000.00
0.00
0.00
0.00
1800000.00

150,000.00
150,000.00
150,000.00
400,000.00
2.00 Litre
15.00 m3
500000.00/2000
500000/2000
400000 p Lt x 2Lts pdy / 15 cu m pdy

100.00
250.00
53333.33
53683.33

MURRAY AND ROBERTS CONSTRUCTION ZIMBABWE


NET RATES
RESOURCE

WASTAGE

GRADE
40

GRADE
30

WAGES

1.00

1,593,864.20

1,593,864.20

1,593,864.20

1,593,864.20

1,593,864.20

1,593,864.20

1,593,864.20

1,593,864.20

CEMENT

1.10

26,664,000.00

23,830,950.00

21,109,000.00

17,942,650.00

14,776,300.00

14,776,300.00

11,609,950.00

12,776,500.00

STONE

1.075

9,245,000.00

8,395,750.00

8,395,750.00

8,395,750.00

8,213,000.00

8,213,000.00

8,395,750.00

8,062,500.00

SAND

1.20

1,252,800.00

1,291,680.00

1,382,400.00

1,460,160.00

1,449,360.00

1,449,360.00

1,620,000.00

1,728,000.00

0.00
1.00

TOTAL COST

2,278,787.88

GRADE
10 blinding
2,278,787.88

1.00

VIBRATION

2,278,787.88

GRADE
GRADE
15 blinding
10 mass
2,278,787.88

PLANT

WASTAGE
ON MAT.

2,278,787.88

GRADE OF CONCRETE
GRADE
GRADE
GRADE
25
20
15
2,278,787.88
2,278,787.88
2,278,787.88

53,683.33

53,683.33

53,683.33

53,683.33

53,683.33

41,088,135.42

37,444,715.42

34,813,485.42

31,724,895.42

28,364,995.42

28,311,312.08

25,552,035.42

26,439,652.08

44,933,658.50

41,776,182.50

38,069,874.50

34,037,994.50

33,973,574.50

30,662,442.50

31,727,582.50

UNIT ALLOWABLES
RESOURCE
PLANT

GRADE OF CONCRETE
=APPLD FCTRx0.075x1.10
=APPLD FCTRx0.05x1.10
GRADE
GRADE
GRADE
GRADE
GRADE
GRADE
GRADE
GRADE
40
30
25
20
15
15 blinding
10 mass
10 blinding
2,332,471.21
2,332,471.21
2,332,471.21
2,332,471.21
2,278,787.88
192,428.88
2,332,471.21
125,333.33

LABOUR
MATERIAL

1,593,864.20

1,593,864.20

1,593,864.20

1,593,864.20

1,593,864.20

131,493.80

1,593,864.20

87,662.53

37,161,800.00

33,518,380.00

30,887,150.00

27,798,560.00

24,438,660.00

2,016,189.45

21,625,700.00

1,241,185.00

FORMWORK

SUBS

TOTAL COST
Tsuro's Net
Tsuro's Gross

41,088,135.42
6252.13
49305762.5
49,305,762.50

53,683.33

37,444,715.42
5653.36

34,813,485.42
5475.45

31,724,895.42
5252.99

44,933,658.50

41,776,182.50

38,069,874.50

28,311,312.08
5050.44
5555.484
33,973,574.50

2,340,112.12
416.66
458.326
2,808,134.55

25,552,035.42
4648.08
5112.888
30,662,442.50

1,454,180.86
232.4
255.64
1,745,017.04

REINFORCEMENT
DATA
SKILLED WORKER ONE
SKILLED WORKER TWO
SKILLED WORKER THREE
SKILLED WORKER FOUR
WORKER EXEMPTED
WORKER GRADE FOUR
WORKER GRADE THREE
WORKER GRADE TWO
WORKER GRADE ONE

Steel Fixer and Team


Steel Fixer
SW1
48186.23
SW2
45892.41
SW3
44426.92
SW4
41584.26

48,186.23
45,892.41
44,426.92
41,584.26
41,584.26
41,244.80
39,818.73
39,106.63
39,106.63

p hr x 9 hrs x 1
p hr x 9 hrs x 2
p hr x 9 hrs x 3
p hr x 9 hrs x 3
= applied Factor / 9

Steel handling team (GB&10)


Steel handling team
Assistants

48,186.23
91,784.82
133,280.76
124,752.78
398,004.59

398,004.59 p day x 1
39,106.63 p hr x9 hrs p day x 10

398,004.59
3,519,596.70
3,917,601.29

MATERIALS
Fabric reinforcement; Ref. S193

10,094,500.00 psheet

RATE BUILD UP

4/2/2/G Fabric reinforcement; Ref. S193

Steel hangling team (GB&10)


Mesh reinforcement S193
L

15670.41

3,917,601.29 p day / 250m2 p day


701,006.94 p m2x0.925x1.20 waste & laps
M

778,117.71

15,670.41
778,117.71
793,788.11

952,545.74

Joinery & Ironmongery


DATA
SKILLED WORKER ONE
SKILLED WORKER TWO
SKILLED WORKER THREE
SKILLED WORKER FOUR
WORKER EXEMPTED
WORKER GRADE FOUR
WORKER GRADE THREE
WORKER GRADE TWO
WORKER GRADE ONE

234,474.00
212,292.00
195,259.00
177,464.00
177,464.00
132,271.00
127,939.00
125,776.00
125,776.00

Carpentry Team
Capenter
SW1
234,474.00 p hr x 9 hrs x 1
SW2
212,292.00 p hr x 9 hrs x 2
SW3
195,259.00 p hr x 9 hrs x 3
SW4
177,464.00 p hr x 9 hrs x 3
= applied Factor / 9

234,474.00
424,584.00
585,777.00
532,392.00
1,777,227.00

Carpenter &Team (C + 1)
Carpenter
1,777,227.00
Assistant
125,776.00

per day
x 9 hrs per day

1,777,227.00
1,131,984.00
2,909,211.00

Carpenter &Team (C + 2)
Carpenter
1,777,227.00
Assistants
125,776.00

per day
x 9 hrs per day x 2 No

1,777,227.00
2,263,968.00
4,041,195.00

40mm Wood Screws


Nails
RATE BUILD UP
4/6/2/B
F4

44mm internal quality semi solidcore flush panels doors wth concealed
hardwood edge strip as described
Size 813x 2032 mm
Carpenter and team
2,909,211.00 / 2.5 No per day
Door
15,000,000.00 each x 1.01
40mm wood csrews
150,000.00 eachx8n x1.05
.
L
1,163,684.40
m

per kg

25,000.00
250,000.00

1,163,684.40
15,150,000.00
1,260,000.00
17,573,684.40
16,410,000.00

PLASTERING & WALL LINING


DATA

234,474.00
212,292.00
195,259.00
177,464.00
177,464.00
132,271.00
127,939.00
125,776.00
125,776.00

SKILLED WORKER ONE


SKILLED WORKER TWO
SKILLED WORKER THREE
SKILLED WORKER FOUR
WORKER EXEMPTED
WORKER GRADE FOUR
WORKER GRADE THREE
WORKER GRADE TWO
WORKER GRADE ONE
Plasterer and Team
Plasterer
SW1
234474.00
SW2
212292.00
SW3
195259.00
SW4
177464

p hr x 9 hrs x 1
p hr x 9 hrs x 2
p hr x 9 hrs x 3
p hr x 9 hrs x 3

= applied Factor / 9
Plasterer and Team
Plasterer
Assitant

Rate per day


125,776.00 x9

234,474.00
424,584.00
585,777.00
532,392.00
1,777,227.00

1,777,227.00
1,131,984.00
2,909,211.00

Cement per 50kg bag


Price delivered to site
Loading
Offloading
Transport

2,500,000.00
-

Total cost

2,500,000.00

Sand
Price
Loading
Offloading
Transport

3,500,000.00
-

Total cost

3,500,000.00

1:4 Cement and Sand morta


Labourer
Cement 50kg
River Sand

1,131,984.00 /120bags per day x8.9m3 handle


2,500,000.00 x8.9bgsx1.01 waste
3,500,000.00 pm3x1.50m3x1.15 waste

83,955.48
22,472,500.00
6,037,500.00
28,593,955.48

1:3 Cement morta Build up


Labourer
1131984.00 /120bagsx10.60
Cement
2500000.00 pbagx10.60x1.01waste
Sand
3500000.00 pm3x1.30x1.15 waste

99,991.92
26,765,000.00
5,232,500.00
32,097,491.92

1:6 Cement morta Build up


Labourer
1131984.00 /120bagsx6.40
Cement
2500000.00 pbagx6.4x1.01waste
Sand
3500000.00 pm3x1.69x1.15 waste

60,372.48
16,160,000.00
6,802,250.00
23,022,622.48

1:5Cement morta Build up


Labourer
1131984.00 /120bagsx7.5
Cement
2500000.00 pbagx7.5x1.01waste
Sand
3500000.00 pm3x1.69x1.15 waste

70,749.00
18,937,500.00
6,802,250.00
25,810,499.00

RATE BUILD UP

4/8/1/E
I1

One coat wood float plaster to walls externally


Plastering and gang
2,909,211.00 / 18 m2 pday first ct
1:4 cement morta
28,593,955.48 x.020m3pm2x1.25

161,622.83
714,848.89
876,471.72

L
4/8/1/F
12

161,622.83

One coat wood float plaster to walls in n. w.


Plastering and gang
2,909,211.00 / 5 m2 pday first ct
1:4 cement morta
28,593,955.48 x.020m3pm2x1.25

581,842.20
714,848.89
1,296,691.09

L
5/8/1/E

581,842.20

161,622.83
645,262.48
806,885.31

5/8/1/F

161,622.83

645262.48

One coat wood float plaster to walls in n. w.


Plastering and gang
2,909,211.00 / 5 m2 pday first ct
1:5 cement morta
25,810,499.00 x.020m3pm2x1.25

581,842.20
645,262.48
1,227,104.68

581,842.20

1,556,029.30

714848.89

One coat wood float plaster to walls externally


Plastering and gang
2,909,211.00 / 18 m2 pday first ct
1:5 cement morta
25,810,499.00 x.020m3pm2x1.25
L

1,051,766.06

714848.89

645262.48

968,262.37

Proposed Construction of House at


17 a Rotfontein
Item

Description
Uom
Qty
Lab Rate
Lab Amt
Foundations
Clear site of all rubbish,debri etc
m2
330
0.64
Excavate oversite to remove topsoil & spread & level on site
m2
330
0.80
Excavate in pickable material to reduced levels n.e 300mm
m3deep
99
7.29
Excavate in pickable mat.for strip footings n.e 2 metres deep.
m3
115
10.69
Scarify reduced surfaces and compact mechanically to 93%
m2HCE<150mm 330
dpth
0.53
Allow for risk of collapse to sides of excavation
m2
324
1.12
Cart away surplus excavated mat to a dump site to be located
m3 by Contractor45
2.92
Extra over for excavation in soft rock.
m3
5
64.15
Extra over for excavation in hard rock
m3
2
112.27
Backfilling to trenches wth approved excvated mat to 93%m3
HCE,150mm dpth28
2.92
Approved non- expansive mat wth gravel infill , level and compact
m3
as described
40
2.14
150mm Hard core filling base course wth approved decomposed
m3
granite 40
0.32
15 Mpa in footings
m3
26
1,593,864.20
20 Mpa in surface beds
m3
27
1,593,864.20
Half brick wall in loadbearings in foundation brickwork m2
24
#REF!
One brick wall in loadbearings foundation brickwork
m2
108
#REF!

Mat Rate
211.70
264.63
721.71
1,229.58
176.42
363.74
131.22
320.76
224.53
81.65
85.54
12.83
41,440,469.30
43,034,333.51
#REF!
#REF!

24,438,660.00
27,798,560.00
#REF!
#REF!

#REF!
Concrete,Formwork & Reinforcement
20 Mpa in stairs
20 Mpa in gutters
20 Mpa in slabs
Strike off & cure top surfces of concrete
Mild steel rods not exceeding 8mm diameter
Fabric reinforcement; Ref. S193
Spacer blocks

m3
m3
m3
m2
kg
m2
item

1
6
47
345
800
15,670
1

Brickwork
Half brick wall in commom brickwork
m2
339
One brick wall in common brickwork
m2
607
75mm Brickforce to suit 115mm brick wall
m
93
150mm Brickforce to suit 230mm brick wall
m
423
Half brick shower kerb in commom brickwork
m
5
Bedding roof coverings
m
123
Set up in position cross brase & bldng in steel frame n.e 5m2.
no
84
Brick-on- edge ext cill set slopping as described
m
46
Brick-on- edge lintol set horizontally as described
m
46
raking and cutting
m2
30
Rake out joints of brickwork for turning in of metal flashingm
92
One layer of three ply DPC as described
m2
34
Two layers DPC vertically betwwen RC concrete slab and m2
brick walls
55
1 layer250 micron "Tarcon" polythene DPM laid on and including
m2
50mm sand
277blinding
Under concrete surface beds
m2
45
10mm Kaylite joint filler material in expansion joints as described
m2
160
230 x150 mm Air vents (EXT)
no
54
230 x150 mm Air vents (INT)
no
54

1,593,864.20
1,593,864.20
1,593,864.20
1,650.00
#REF!
778,117.71
300,000.00

17
30
#REF!
0.25
#REF!
#REF!
16.92
#REF!
#REF!
#REF!
18,594.24
#REF!
#REF!
#REF!
#REF!
10.58
#REF!
#REF!

1,593,864.20
9,563,185.22
74,911,617.59
569,250.00
#REF!
12,193,419,751.75
300,000.00
#REF!
5,701.38
17,977.52
#REF!
107.47
#REF!
#REF!
1,421.62
#REF!
#REF!
#REF!
1,710,670.08
#REF!
#REF!
#REF!
#REF!
1,692.40
#REF!
#REF!
#REF!

27,798,560.00
27,798,560.00
27,798,560.00
#REF!

78
227
#REF!
1.16
#REF!
#REF!
15.04
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
674,492.57
#REF!
#REF!

Roof Coverings
Marley major concrete interlocking roof tiles
152x50mm wrot softwood purlins
38x38mm Bargeboard runners to foot of roof members
12x225mm flat asbestos cement fascia as described
Ditto asbestos cement bargeboard as before

m2
m
m
m
m

Carpentry
38 x 38mm Fascia runners
m
38x114mm sawn softwood wallplate
m
50x150mm rafters
m
75mm pergola gumpoles
m
12mm "Gypsum Industries" plasterboard sheeting as described
m2
Extra over for trimming for & forming trap door 610x610 as no
described

345
1,265
123
123
123

129,156.79
#REF!
#REF!
#REF!
#REF!

123
123
1,900
25
313
4

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

Joinery & Ironmongery


75mm hardwood meranti coved cornice fixed to wall incl angles
m and mitres 390
#REF!
19x75mm W/hardwood angle rounded skirting wth & inclu 19mm
m
Quadrant390
#REF!
44mm int.quality semi s/core flush panel door,concealed h/wood
no edging strip28size 813x2032mm
522,534.21
44mm ext.quality semi s/core flush panel door,concealed h/wood
no
edging strip2size 813x2032mm
528,534.21
22x145mm Commercial grade blockboard top, end or frontm2
secured to sw bearer
190
#REF!
38x50mm Wrot softwood bearer
m
190
#REF!
Union n CZ682-24-95CH two lever lockset
no
30
110,390.00
Union n CZ682-25-95CH three lever lockset
no
4
128,390.00
Chromium plated cabin hook & eye
no
8
#REF!
Chromium plated hat and coat hook
no
12
#REF!
19mm chromium plated towel rail 900mm long incl end brackets
no
5
#REF!
20mm chromium shower curtain rail 900mm long incl end no
brackets
5
#REF!
Approved chromium plated shower rose and arm
no
5
#REF!
Approved 15mm chromium plated shower mixer
no
5
#REF!
Approved 15mm sink mixer wth swivel arm
no
5
#REF!
38mm Diameter rubber door stop screwed to plug in wall/floor
no
34
#REF!
Approved plastic nylon shower curtain size 1200x2200mm no
long
5
#REF!
Union 8095 indictor bolt
no
5
#REF!
Plastering & Wall Linings
One coat cement plaster with steel float and set in Rhinoset
m2internal
Ditto in narrow width
m2
One coat wood float plaster to walls externally
m2
One coat wood float plaster to walls in n. w.
m2
150x150x6mm White glazed wall tiles as described
m2
Ditto in narrow width
m2
180x180mm recesso Toilet roll holder iclu bldng into plastered
no wall
180x180x120mm single soap dish
no
340x340x120mm double soap dish
no
150x150x6mm Terra-coat red quary tiles on cills in n.w m

1,140
34
920
15
15
6
5
5
5
15

#REF!
#REF!
161,622.83
581,842.20
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

44,559,092.55
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
14,630,957.88
1,057,068.42
#REF!
#REF!
3,311,700.00
513,560.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
148,693,006.67
8,727,633.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
714,848.89
714,848.89
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

Metal Work
Balustrades,910mm high,40mm dia m.s. tube
XO A luminium sliding door
Window frame type NE22 size 2000x653mm
Ditto ND4F
Ditto NE4
Ditto ND11F
Ditto NE2
Ditto NC2F
Ditto NC11F
Ditto ND12F
Ditto ND1
Ditto ND2
Ditto NE7

item
no
no
no
no
no
no
no
no
no
no
no
no

1
3
3
1
5
5
2
3
2
3
20
4
2

Pavings & Floor Coverings


40mm screed to floors to receive ceramic floor tiles.
m2
577
75mm High skirting with cove at junction as described. m2
580
300x300x8mm Non slip Ceramic floor tiles finished with two
m2coats of wax polish
245
20mm x 300mm skirting as described
m
74
Raking cutting and waste on ceramic tiles
m2
44
Raking cutting and waste on ceramic tiles
m
22
6x40mm Aluminium dividing strip
m
23
40mm granolithic paving steel trowelled laid on cills.
m2
96
100mm High skirting with cove at junction as described. m
96
Cut and fill around shower trap
no
5
Cut and fill around wc pan
no
5

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
2,500.00
2,500.00

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!

12,500.00
12,500.00
#REF!

SheetMetalwork,Plumbing & Drainlaying


0.6 mm Galvanised sht metal flashing as described
WC Complete with 14 ltr fibreglasscisten as described.
Fibre vanity basin size 780x560mm as described.
Bath 1825x745mm as described
Fibre vanity basin size 550x460mm as described.
50mm PVC pipe as described
50mm PVC pipe as described under surface beds
100mm PVC ventilating pipe as described fixed to walls
100mm PVC waste pipe as described fixed to walls

m2
no
no
no
no
m
m
m
m

Extra over items


50mm PVC bend
no
50mm PVC bend with inspection eye
no
50mm PVC junction with inspection eye
no
100mm PVC junction with inspection eye
no
100mm PVC bend with inspection eye
no
100mm PVC straight connector
no
Air vent valve
no
32 mm chromium plated ''botle'' trap
no
75mm Glass - enamelled spigot socket ''P'' trap as described
no
40 mm chromium plated ''botle'' trap
no
50mm copper deep seal ''P'' & ''S'' trap as described
no
40 mm copper deep seal as described
no
40 mm copper deep seal as described shower waste pipe no
Allow for testing
item

20
5
5
5
5
19
91
50
50

#REF!
483,106.95
342,115.79
1,141,528.97
442,115.79
31,754.32
31,754.32
31,754.32
31,754.32

12
10
3
5
8
7
12
5
5
2
9
7
9
2

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
200,000.00

5,000,000.00
2,500,000.00
342,156.98
315,249.50
308,159.89
458,129.37
297,297.64
387,039.41
432,891.28
529,876.31
207,238.45
316,219.87
305,419.87

#REF!
2,415,534.75
1,710,578.95
5,707,644.85
2,210,578.95
603,332.08
2,889,643.12
1,587,716.00
1,587,716.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
400,000.00
-

#REF!
#REF!
#REF!
2,500.00
2,500.00

SOIL DRAINAGE

100mm PVC drain pipe as described under floors


100mm PVC bend
100mm PVC bend with inspection eye
100mm PVC junction with inspection eye
110 mm Gully trap as described
Encase 100mm pipe as described
Encase 100mm pipe as described
Allow for testing

m
no
no
no
no
m
m
item

15
14
29
29
5
46
75
2

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
200,000.00

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

HOT & COLD WATER INSTALLATION


COPPER PIPING
15mm service connector as described
15mm service pipe as described
15mm service pipe as described in chase
15mm service pipe as described in roof space
22mm service pipe as described
22mm service pipe as described in chase
22mm service pipe as described in roof space
22mm bend
22mm tee
22x15mm Tee

no
m
m
m
m
m
m
no
no
no

2
19
33
85
33
45
24
15
15
17

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

400,000.00
-

Galvanised Mild steel Pipes


20mm pipe in ground as described

99

Geysers
100 ltr roof gyser as described
no
3
15mm stop cocks & jointing to pipe
no
21
22mm stop cocks & jointing to pipe
no
25
Approved water metre connected to 20mm dai. Pipe.
no
1
Leave hole for small pipe throu. 115 wall.
no
15
Leave hole for small pipe throu. 230 wall.
no
15
Chase wall for 50mm pipe as described
m
380
150mm pipe as described
m
5
150mm pipe as described
m
58
150mm bend
no
61
150mm junction
no
18
150x100mm junction
no
16
150mm cast iron ''ABC''c/r eye as described
no
17
Excavate in pickable mat.for 75mm pipe as described
m
19
Excavate in pickable mat.for 150mm pipe as described m
15
E.O. excavate in soft rockfor 75mm pipe as described
m3
18
E.O. excavate in soft rockfor 75mm pipe as described with m3
15 Mpa
10
150mm concrete sorround (15Mpa) as described
no
16
E.O. excavate inhard rock.for 75mm pipe as described m3
56
Backfilling imported fill haul distance n.e. 1.5km
m3
56
Backfilling imported fill haul distance within site
m3
51
Cart away surplus excavated mat to a dump site to be located
m3 by Contractor45
Glazing
3mm clear sheet glass and glazing in steel sash
3-4mm obscure ditto
Mirror size 400x400mm

m2
m2
no

75
6
5

Painting
Prepare & apply 2 cts int. pva to steel float walls
m2
1,140
Ditto in narrow widths
m2
34
Prepare & apply 3 cts int. pva to wood float walls
m2
920
Ditto in narrow widths
m2
34
Prepare & apply 3 cts int. pva on ceilings
m2
577
Metal primer,undercoat,2 cts high gloss enamel on generalm2
surfaces of doors46
Ditto to steel window frames
m2
56
Clear polyurethane varnish on skirtings
m2
28
Metal primer,undercoat,2 cts high gloss enamel on steel door
m2 frames
56

#REF!

1,468,984.79
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

8478.231
8478.231
1356.52

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
4,406,954.37
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
635,867.33
50,869.39
6,782.58
693,519.30
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

74,321.84
45,156.79
250,000.00

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

1
2
3
4
5
6
7
8
9
10
11
12

SUMMARY
Foundations
Concrete,Formwork & Reinforcement
Brickwork
Roof Coverings
Carpentry
Joinery & Ironmongery
Plastering & Wall Linings
Metal Work
Pavings & Floor Coverings
SheetMetalwork,Plumbing & Drainlaying
Glazing
Painting

Sub Total
Preliminaries & Generals
13
Prime Costs & Provisional Sums
Total Carried to Form of Tender

Labour Total
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
693,519.30
#REF!

#REF!
#REF!
#REF!

Material Amt
635,405,160.00
750,561,120.00
#REF!
#REF!

Plant Rate Plant Amt

0.09
9.29
1.82
2,278,787.88
2,332,471.21

#REF!
27,798,560.00
166,791,360.00
1,306,532,320.00
#REF!
#REF!
26,572.78
138,009.38
#REF!
490.21
#REF!
#REF!
1,263.52
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
107,918,811.52
#REF!
#REF!
#REF!

2,332,471.21
2,332,471.21
2,332,471.21

29.43
18.58
50.86
59,248,484.85
62,976,722.73
122,225,306.43
2,332,471.21
13,994,827.27
109,626,146.97
125,953,445.45
-

#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
657,660,976.04
10,722,733.31
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

5,000,000.00
7,500,000.00
1,026,470.94
315,249.50
1,540,799.45
2,290,646.85
594,595.28
1,161,118.23
865,782.56
1,589,628.93
4,144,769.00
1,264,879.48
610,839.74
27,904,779.96
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
12,500.00
12,500.00
#REF!
-

5,574,138.00
270,940.74
1,250,000.00
7,095,078.74
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

Material Total
#REF!
#REF!
#REF!
#REF!

Plant Total

Total

#REF!
27,904,779.96
#REF!
7,095,078.74
#REF!

122,225,306.43
125,953,445.45
-

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
27,904,779.96
#REF!
#REF!
7,788,598.04
#REF!

#REF!
#REF!

248,178,751.89
37,226,812.78

#REF!
#REF!

#REF!

285,405,564.67

#REF!

Anda mungkin juga menyukai