Bill Of Quantities
Item Description
Foundations (Provisional)
1 Excavate oversite to remove topsoil & spread & level on site
2 Excavate in pickable mat.for strip footings n.e 2 metres deep.
3 Scarify reduced surfaces and compact mechanically to 93% HCE<150mm
4 Cart away surplus excavated mat to a dump site to be located by Contractor
5 Backfilling to trenches wth approved excvated mat to 93% HCE,150mm dpth
6 150mm Hard core filling base course wth approved decomposed granite
7 Termite treatment
8 20 Mpa in footings
9 20 Mpa in surface beds
10 115 block wall in fdn
11 115 brickforce
12 Strike off & cure top surfces of concrete
13 Fabric reinforcement; Ref. S193
14 1 layer250 micron "Tarcon" polythene DPM laid on and including 50mm sand
Uom Qty
Rate
Amount
m2
m3
m2
m3
m3
m3
m2
m3
m3
m2
m
m2
m2
m2
1,728
192
1,728
30
161
1,728
30
173
1,728
1,728
1,728
17,370.94
43,427.34
39,084.61
41,255.97
43,427.34
49,024.91
53,927.40
1,021,225.25
1,021,225.25
140,611.43
19,700.00
5,046.00
157,200.00
30,125.00
30,016,977.41
8,338,049.28
67,538,199.17
1,237,679.19
6,991,801.74
93,186,548.93
30,636,757.50
176,671,968.25
8,719,488.00
271,641,600.00
52,056,000.00
747,035,069.46
Blockwork
115 block wall in superstructure
115 brickforce
Half brick wall in common brickwork in beam filling
Bedding roof coverings
Set up in position cross brase & bldng in steel door frame n.e 5m2.
Set up in position cross brase & bldng in steel window frame n.e 5m2.
Brick-on- edge ext cill set slopping as described
Brick-on- edge lintol set horizontally as described
One layer of three ply DPC as described
One layer of three ply DPCto cills
One layer of three ply DPC to sprockets
230 x150 mm Air vents (EXT)
230 x150 mm Air vents (INT)
m2
m
m2
m
no
no
m
m
m2
m2
m2
no
no
801
2,355
10
32
7
7
14
24
8
2
2
14
14
140,611.43
19,700.00
84,366.86
75,930.17
39,150.00
39,150.00
102,122.53
102,122.53
120,325.00
120,325.00
120,325.00
25,365.00
25,365.00
112,629,755.43
46,393,500.00
843,668.58
2,429,765.51
274,050.00
274,050.00
1,429,715.35
2,450,940.60
956,583.75
193,723.25
235,235.38
355,110.00
355,110.00
9,797,952.42
1
2
3
4
5
6
7
no
no
no
no
no
no
no
6
2
6
2
2
1
6
1,512,000.00
1,512,000.00
370,251.01
444,301.21
75,258.25
225,774.75
38,254.25
9,072,000.00
3,024,000.00
2,221,506.06
888,602.42
150,516.50
225,774.75
229,525.50
15,811,925.23
1
2
3
4
5
6
m2
m2
m2
m2
no
no
91
3
66
9
2
2
65,690.70
65,690.70
65,690.70
65,690.70
55,254.85
55,254.85
5,977,853.70
197,072.10
4,335,586.20
591,216.30
110,509.70
110,509.70
11,322,747.70
1
2
SUMMARY
Foundations (Provisional)
Blockwork
747,035,069.46
9,797,952.42
1
2
15,811,925.23
11,322,747.70
Sub Total
13 Preliminaries & Generals
783,967,694.81
156,793,538.96
940,761,233.78
141,114,185.07
Sub Total
Add: 15% VAT
Total Cost of a Single Unit
1,081,875,418.84
Units
400
1,081,875,418.84
432,750,167,537.00
Construction of Houses
Bill Of Quantities
Item Description
Foundations (Provisional)
1 Topsoil excavation
2 Excavate in pickable mat.for strip footings n.e 2 metres deep.
3 Scarify reduced surfaces and compact mechanically to 93% HCE<150mm
4 Cart away surplus excavated mat to a dump site to be located by Contractor
5 Backfilling to trenches wth approved excvated mat to 93% HCE,150mm dpth
6 150mm Hard core filling base course wth approved decomposed granite
7 Termite treatment
8 20 Mpa in footings
9 20 Mpa in surface beds
10 115 block wall in fdn
11 115 brickforce
12 Strike off & cure top surfces of concrete
13 Fabric reinforcement; Ref. S193
14 1 layer250 micron "Tarcon" polythene DPM laid on and including 50mm sand
Uom Qty
Rate
Amount
m2
m3
m2
m3
m3
m3
m2
m3
m3
m2
m
m2
m2
m2
66
22
26
8
12
13
54
4
5
45
90
54
54
54
20,845.12
52,112.81
31,267.68
37,130.38
49,941.44
73,537.37
64,712.88
1,123,347.78
1,123,347.78
154,672.57
29,550.00
8,073.60
194,928.00
32,390.40
1,375,778.13
1,146,481.78
812,959.80
297,043.01
599,297.29
955,985.75
3,494,495.58
4,108,082.81
5,953,743.21
6,967,999.41
2,662,455.00
435,974.40
10,526,112.00
1,749,081.60
41,085,489.77
154,672.57
154,672.57
29,550.00
92,803.54
83,523.19
35,235.00
38,367.00
112,334.78
112,334.78
122,731.50
122,731.50
122,731.50
26,125.95
26,125.95
461,190.60
261,163.00
130,581.50
50,895.00
20,880,797.36
41,761,594.71
295,500.00
2,969,713.40
584,662.33
246,645.00
537,138.00
2,696,034.66
893,061.48
197,597.72
239,940.08
1,718,241.00
365,763.30
10,744,296.97
4,150,715.40
522,326.00
2,089,304.00
6,762,345.40
1
2
3
4
5
6
7
8
9
10
11
12
13
Blockwork
115 block wall in superstructure
115 brickforce
Half brick wall in common brickwork in beam filling
Bedding roof coverings
Set up in position cross brase & bldng in steel door frame n.e 5m2.
Set up in position cross brase & bldng in steel window frame n.e 5m2.
Brick-on- edge ext cill set slopping as described
Brick-on- edge lintol set horizontally as described
One layer of three ply DPC as described
One layer of three ply DPCto cills
One layer of three ply DPC to sprockets
230 x150 mm Air vents (EXT)
230 x150 mm Air vents (INT)
m2
m
m2
m
no
no
m
m
m2
m2
m2
no
no
135
270
10
32
7
7
14
24
8
2
2
14
14
1
2
3
4
Roof Coverings
Asbestos sheeting to roof
Ridge
Stop ends
Rough raking and cutting to waste
m2
m
no
m
66
9
2
16
1
2
3
Carpentry
Supply and fix roof trusses
38x114mm sawn softwood wallplate
152x50mm wrot softwood purlins
12x225mm timber fascia as described
m
m
m
15
54
32
154,672.57
89,112.98
178,225.95
160,403.36
2,320,088.60
4,812,100.65
5,703,230.40
12,835,419.65
1
2
3
4
5
6
7
no
no
no
no
no
no
no
6
2
6
2
2
1
6
1,461,190.60
1,360,800.00
470,254.00
564,304.80
78,592.00
112,545.00
39,258.00
1
2
3
4
5
6
8,767,143.60
2,721,600.00
2,821,524.00
1,128,609.60
157,184.00
112,545.00
235,548.00
15,944,154.20
-
m2
m2
m2
m2
no
no
91
3
66
9
2
2
98,536.05
98,536.05
98,536.05
98,536.05
82,882.28
82,882.28
295,608.15
6,503,379.30
886,824.45
197,072.10
165,764.55
8,048,648.55
Metal Work
Window frames
ND4F
NC4F
NC5F
Door frames
813x2032x115 door frames
1
2
m2
m
53
57
101,101.30
33,700.43
5,358,368.89
1,920,924.70
7,279,293.58
1
2
3
4
5
6
7
8
m
no
no
no
item
no
no
no
10
2
1
2
1
12
3
3
301,257.00
319,194.91
227,996.37
133,379.68
600,000.00
48,333.83
47,855.28
39,879.40
3,012,570.00
638,389.83
227,996.37
266,759.35
600,000.00
580,005.99
143,565.84
119,638.20
6
7
8
9
10
11
12
no
no
no
no
m
no
no
1
1
1
1
20
3
3
14,387,667.50
9,110,134.00
16,526,434.25
137,779.40
36,876.75
44,252.10
46,464.71
14,387,667.50
9,110,134.00
16,526,434.25
137,779.40
737,535.04
132,756.31
139,394.12
46,760,626.20
1
2
3
Glazing
3mm clear sheet glass and glazing in steel sash
3-4mm obscure ditto
Mirror size 600x450mm
m2
m2
m2
11
2
1
418,428.78
502,114.54
753,171.80
4,602,716.58
836,857.56
502,114.54
5,941,688.68
1
2
3
4
5
6
7
Painting
Prepare & apply 2 cts int. pva to int. walls
Prepare & apply 3 cts int. pva to ext. walls
2 cts high gloss enamel on general surfaces of doors
Ditto to steel window frames
Ditto to steel door frames
Bituminous paint to wall plates
Allow for touching up and cleaning
m2
m2
m2
m2
m2
m2
Sum
99
66
23
11
4
9
1
52,269.90
52,269.90
80,070.31
40,035.16
100,087.89
80,070.31
600,000.00
5,174,720.10
3,449,813.40
1,811,510.75
440,386.72
400,351.56
720,632.81
600,000.00
12,597,415.34
Provisional Sums
Electricity
sum
8,000,000.00
8,000,000.00
8,000,000.00
1
2
3
no
no
no
4
1
2
2,965,179.58
2,940,179.58
1,647,462.94
11,860,718.31
2,940,179.58
3,294,925.87
no
1,132,909.90
7,930,369.30
26,026,193.05
SUMMARY
Foundations (Provisional)
Blockwork
Roof Coverings
Carpentry
Joinery & Ironmongery
Plastering & Wall Linings
Metal Work
Pavings & Floor Coverings
SheetMetalwork,Plumbing & Drainlaying(Provisional)
Glazing
Painting
Sub Total
13 Preliminaries & Generals
14 Prime Costs & Provisional Sums
Sub Total
Add: 15% VAT
1
2
3
4
5
6
7
8
9
10
11
41,085,489.77
10,744,296.97
6,762,345.40
12,835,419.65
15,944,154.20
8,048,648.55
26,026,193.05
7,279,293.58
46,760,626.20
5,941,688.68
12,597,415.34
194,025,571.39
38,805,114.28
8,000,000.00
240,830,685.67
36,124,602.85
276,955,288.52
Units
400
276,955,288.52
-
110,782,115,406.95
Uom Qty
Rate
Amount
m2
m3
m2
m3
m3
m3
m2
m3
m3
m2
m
m2
m2
m2
62
19
25
10
11
11
53
4
5
45
90
53
53
53
25,014.15
57,324.09
51,591.68
54,457.88
57,324.09
80,891.10
88,980.21
1,531,837.88
1,531,837.88
175,764.29
28,400.00
8,334.60
165,900.00
45,187.50
1,562,533.76
1,089,157.69
1,289,792.00
544,578.84
630,564.98
857,445.68
4,715,951.22
5,601,931.11
8,118,740.74
7,918,181.15
2,558,840.00
441,733.80
8,792,700.00
2,394,937.50
46,517,088.46
23,728,178.81
47,456,357.63
284,000.00
3,374,674.32
664,389.01
365,400.00
730,800.00
3,676,410.90
1,217,811.11
248,934.38
302,277.46
2,164,646.75
532,665.00
13,562,008.92
29,378,728.13
1,995,536.25
447,708.00
1,865,450.00
33,687,422.38
1
2
3
4
5
6
7
8
9
10
11
12
13
Blockwork
115 block wall in superstructure
115 brickforce
Half brick wall in common brickwork in beam filling
Bedding roof coverings
Set up in position cross brase & bldng in steel door frame n.e 5m2.
Set up in position cross brase & bldng in steel window frame n.e 5m2.
Brick-on- edge ext cill set slopping as described
Brick-on- edge lintol set horizontally as described
One layer of three ply DPC as described
One layer of three ply DPCto cills
One layer of three ply DPC to sprockets
230 x150 mm Air vents (EXT)
230 x150 mm Air vents (INT)
m2
m
m2
m
no
no
m
m
m2
m2
m2
no
no
135
270
10
32
7
7
14
24
8
2
2
14
14
175,764.29
175,764.29
28,400.00
105,458.57
94,912.72
52,200.00
52,200.00
153,183.79
153,183.79
154,617.63
154,617.63
154,617.63
38,047.50
38,047.50
1
2
3
4
Roof Coverings
Asbestos sheeting to roof
Ridge
Stop ends
Rough raking and cutting to waste
m2
m
no
m
66
9
2
16
443,452.50
221,726.25
223,854.00
116,590.63
48,937.50
1
2
3
Carpentry
Supply and fix roof trusses
38x114mm sawn softwood wallplate
152x50mm wrot softwood purlins
12x225mm timber fascia as described
m
m
m
15
54
32
443,452.50
74,260.81
148,521.63
6,651,787.50
4,010,083.88
4,752,692.00
15,414,563.38
1
2
3
4
5
6
7
no
no
no
no
no
no
no
6
2
6
2
2
1
6
1,814,400.00
1,814,400.00
407,276.11
488,731.33
82,784.08
248,352.23
42,079.68
1
2
3
4
5
6
10,886,400.00
3,628,800.00
10,886,400.00
814,552.22
977,462.67
82,784.08
1,490,113.35
28,766,512.31
-
m2
m2
m2
m2
no
no
91
3
66
9
2
2
72,259.77
72,259.77
72,259.77
72,259.77
60,780.34
60,780.34
6,575,639.07
216,779.31
4,769,144.82
650,337.93
144,519.54
121,560.67
12,477,981.34
Metal Work
Window frames
ND4F
NC4F
NC5F
Door frames
813x2032x115 door frames
1
2
m2
m
53
57
137,865.41
45,955.14
7,306,866.66
2,619,442.77
9,926,309.43
1
2
3
4
5
6
7
8
m
no
no
no
item
no
no
no
10
2
1
2
1
12
3
3
221,290.59
304,889.26
245,878.44
133,379.68
750,000.00
48,333.83
47,855.28
39,879.40
2,212,905.92
442,581.18
304,889.26
491,756.87
133,379.68
9,000,000.00
145,001.50
143,565.84
6
7
8
9
10
11
12
no
no
no
no
m
no
no
1
1
1
1
20
3
3
15,528,637.50
12,422,910.00
17,081,501.25
145,294.64
34,194.81
41,033.77
43,085.46
15,528,637.50
12,422,910.00
17,081,501.25
2,905,892.80
102,584.42
123,101.30
61,038,707.51
1
2
3
Glazing
3mm clear sheet glass and glazing in steel sash
3-4mm obscure ditto
Mirror size 600x450mm
m2
m2
m2
11
2
1
418,428.78
512,156.83
768,235.24
4,602,716.58
836,857.56
512,156.83
5,951,730.97
1
2
3
4
5
6
7
Painting
Prepare & apply 2 cts int. pva to int. walls
Prepare & apply 3 cts int. pva to ext. walls
2 cts high gloss enamel on general surfaces of doors
Ditto to steel window frames
Ditto to steel door frames
Bituminous paint to wall plates
Allow for touching up and cleaning
m2
m2
m2
m2
m2
m2
Sum
99
66
23
11
4
9
1
56,369.50
56,369.50
64,056.25
32,028.13
88,077.34
70,461.88
750,000.00
5,580,580.50
3,720,387.00
1,275,303.57
704,618.75
128,112.50
792,696.09
70,461.88
12,272,160.29
Provisional Sums
Electricity
sum
6,500,000.00
6,500,000.00
6,500,000.00
1
2
3
no
no
no
4
1
2
2,626,265.67
1,459,036.48
1,224,366.28
10,505,062.67
2,626,265.67
2,918,072.96
no
1,259,887.38
8,819,211.63
24,868,612.92
SUMMARY
Foundations (Provisional)
Blockwork
Roof Coverings
Carpentry
Joinery & Ironmongery
Plastering & Wall Linings
Metal Work
Pavings & Floor Coverings
SheetMetalwork,Plumbing & Drainlaying(Provisional)
Glazing
Painting
Sub Total
13 Preliminaries & Generals
14 Prime Costs & Provisional Sums
Sub Total
Add: 15% VAT
1
2
3
4
5
6
7
8
9
10
11
46,517,088.46
13,562,008.92
33,687,422.38
15,414,563.38
28,766,512.31
12,477,981.34
24,868,612.92
9,926,309.43
61,038,707.51
5,951,730.97
12,272,160.29
264,483,097.90
52,896,619.58
6,500,000.00
323,879,717.48
48,581,957.62
372,461,675.10
Units
400
372,461,675.10
148,984,670,041.32
Bill Of Quantities
Description
Item
Unit
Foundations (Provisional)
1
m2
m2
m3
m2
m2
m3
m3
150mm Hard core filling base course wth approved decomposed granite
m3
Termite treatment
m2
10
20 Mpa in footings
m3
11
m3
12
m2
13
115 brickforce
14
m2
15
m2
16
1 layer250 micron "Tarcon" polythene DPM laid on and including 50mm sand blinding
m2
Brickwork
1
m2
m2
Set up in position cross brase & bldng in steel door frame n.e 5m2.
no
Set up in position cross brase & bldng in steel door frame exc. 5m2.
no
Set up in position cross brase & bldng in steel window frame n.e 5m2.
no
10
11
m2
12
13
m2
14
m2
15
no
16
no
17
no
Qty
Roof Coverings
1
m2
Ridge
Valley
Stop ends
no
m2
Carpentry
Supply and fix roof trusses
sum
m2
Cornice
Extra over for trimming for & forming trap door 610x610 as described
no
19x75mm W/hardwood angle rounded skirting wth & inclu 19mm Quadrant
44mm int.quality semi s/core flush panel door,concealed h/wood edging strip size
813x2032mm
44mm ext.quality semi s/core flush panel door,concealed h/wood edging strip size
813x2032mm
22x145mm pelmets, Commercial grade blockboard top, end or front secured to sw bearer
10
no
11
no
12
no
13
19mm chromium plated towel rail 900mm long incl end brackets
no
14
20mm chromium shower curtain rail 900mm long incl end brackets
no
15
no
16
no
17
no
18
no
19
no
20
21
5
6
m2
m
no
no
m
no
no
sum
One coat cement plaster with steel float and set in Rhinoset internal
m2
m2
m2
m2
m2
m2
Ditto in splashbacks
m2
180x180mm recesso Toilet roll holder iclu bldng into plastered wall
no
no
Metal Work
Aluminium sliding door
1
PD12xx
no
PD15xx
no
PD240xxo
no
Window frames
4
ND7-NG8
no
ND4-NG4
no
ND1-NG5
no
NE2
no
ND4
no
NE4
no
10
NDV22-NG22
no
11
NC4
no
12
NE1
no
13
no
14
no
15
Jetmaster
no
300x300x8mm Non slip Ceramic floor tiles finished with two coats of wax polish
30mm screed
m2
Carpert floor
m2
m2
m
m2
m
m2
Gutter
2
Eo stop end
no
Ditto bend
no
EO shoe
no
Ditto bend
no
Ditto neck
no
Shower tray
no
no
no
no
Double sink
no
no
11
no
12
no
13
no
14
no
15
no
16
no
17
no
18
no
19
no
20
no
21
no
22
23
no
item
SOIL DRAINAGE
24
25
no
26
no
27
no
28
no
29
30
m
item
no
31
32
33
34
35
36
37
22mm bend
no
38
22mm tee
no
39
22x15mm Tee
no
Geysers
41
no
42
no
43
no
44
no
45
no
46
no
47
48
m3
Glazing
1
m2
m2
m2
Painting
1
m2
m2
m2
m2
m2
m2
m2
m2
m2
10
m2
11
Sum
Provisional Sums
1
Electricity
sum
sum
sum
SUMMARY
1
Foundations (Provisional)
Brickwork
Roof Coverings
Carpentry
Metal Work
10
Glazing
11
Painting
Sub Total
13
14
EXCAVATIONS
DATA
Excavation Gang
WX
Gang Boss
WG1
Labourer
18.18
142.20
160.38
Excavation Gang
WX
Gang Boss
WG1
Labourer
18.18
113.76
131.94
(hire charge)
Plate compactor
Petrol
Operator WG3
per day
p Lt x 10Lt p hr x 9 hrs
9hrs p day
27.00
8.64
14.31
49.95
Bomag 90 Roller
Diesel
Operator WG3
0.00 p day x 1
p lt x1.25ltr p hr x9 hrs spd
p hrx9hrs p day
Bomag 90 Roller
Diesel
Operator WG3
0.00 p day x 1
0.00 p lt x1.25ltr p hr x9 hrs spd
0.00 p hrx9hrs p day
99.00
78.00
94.50
100.00
371.50
Decomposed granite
RATE BUILD UP
7.29
8.75
10.69
12.83
13.37
16.04
0.53
0.53
0.64
1.07
0.40
1.47
1.76
0.80
0.32
0.09
1.21
1.46
2.92
2.92
3.50
64.15
64.15
76.98
7.29
Excavate in pickable mat.for ground beams, strip footings n.e 2 metres deep.
Excavation Gang G.B & 10
L 10.69
L 13.37
Scarify reduced surfaces and compact mechanically to 93% HCE<150mm dpth as described.
Excavation Gang G.B & 10
Bomag
L
0.53
0.00
Hand or power ram bottoms of bases to 93% HEC density, 150mm depth as described
Excavation Gang G.B & 10
160.38 p day /150 m2 p day
Plate compactor
49.95 p day x 2 / 250 m2 p day
L
1.07
0.40
1.12
2.92
0.00
64.15
112.27
160.38
160.38
371.50
160.38
80.19
42.77
9.29
10.69
121.55
145.86
2.92
1.82
4.73
5.68
9.29
2.92
1.82
Approved non- expansive mat wth gravel infill , level and compact as described
Excavation Gang G.B & 10
Bomag Roller
Gravel
2.14
0.00
0.32
0.00
0.32
0.32
0.38
0.64
0.77
0.27
0.27
0.32
M 0.00
Clear site of all vegetation incl removal and dis posal of bushes as described
Excavation Gang G.B & 10
160.38 p day / 250 m2 p day
L
2.57
M 0.00
150mm Hard core filling base course wth approved decomposed granite
to 93% HCE density
Excavation Gang G.B & 10
160.38 p day / 75 cu m p day
Bomag Roller
0.00 p day / 75m3 p day x 2
Decomposed granite
p m3 x 1.33 bulk
Applied Factor x 0.15
L
2.14
2.14
0.64
0.27
0.00
M 0.00
(1.0x1.0x0.1m) @ 8526.04
(1.0x1.0x0.1m) @ 631.22
852.60
852.60
63.12
915.73
0.80
63.12
0.80
0.96
Use This table together with the concrete data above for the calculation of the rates.
DATA FOR THE RATES
NET RATES
RESOURCE WASTAGE
PLANT
1.00
WAGES
1.00
CEMENT
1.1
STONE
GRADE
40
GRADE OF CONCRETE
GRADE
25
GRADE
30
961.28*1.00 waste
961.28*1.00 waste
GRADE
20
961.28*1.00 waste
GRADE
15
961.28*1.00 waste
GRADE
10 mass
961.28*1.00 waste
GRADE
10 blinding
961.28*1.00 waste
961.28*1.00 waste
1.075
SAND
1.2
1317788x0.598m3 p m3 x1.20wst
1317788x0.64m3 p m3 x1.20wst
WASTAGE
ON MAT.
0.00
VIBRATION
1.00
TOTAL COST
0.00
0.00
0.00
0.00
0.00
0.00
0.00
TOTAL COST
TOTAL COST
TOTAL COST
TOTAL COST
TOTAL COST
TOTAL COST
TOTAL COST
CONCRETE RATES
1) PLANT
DATA
A. Concrete volume per day
B. Mixer (14/10 Electrical) & Weigh batcher Hire Rate per day
C. Diesel price per litre
D. Oil price per litre
E. Diesel used per day
F. Oil used per month
15 m3
400,000.00
400,000.00
35 Litres
10 Litres
COST
Mixer & Weigh batcher Hire
Diesel
Oil
Total cost
Unit Allow
2) WAGES
DATA
A. Concrete Volume per day
B. WG1 Rate per day
C. WG3 Rate per day
D. WG4 Rate per day
20000000.00 x 1
400,000.00 p Ltr x 20 Ltrs p day
400,000.00 p Ltr x 5 Ltrs p day/22
20000000.00
14,000,000.00
181,818.18
34,181,818.18
2,278,787.88
15 m3
1131983.28
1151448.66
1190435.94
m3
p day m3
>>>>>
Approximately
15 m3 p day
WG.1
2N on stone
2N on sand
2N on cement
1N on top of mixer
5N on wheel barrows
3N on placing
1N on curing
16
N TOTAL
WG 3
1N Mixer operator
1N Vibrator operator
2N Screeder
4
N TOTAL
WG 4
1N Gang Boss
1
COST
WG1
WG3
WG4
Total Cost
Unit Allow
(In P & G)
N TOTAL
125775.920 p day x 16
127938.74 p day x 4
132270.66 x 1
23907963.06 / 15 cu m p day
18,111,732.48
4,605,794.64
1,190,435.94
23,907,963.06
1,593,864.20
4. CEMENT
DATA
A. WG1 Rate per hour
B Price delivery
C Transport per bag
COST
Cement
Loading
Offloading
Transport
Total cost
Add waste 1%
125775.920
2500000.00
5) STONE
DATA
A. WG1 Rate per hour
B. Price ex works per m3
C. Transport per m3
COST
Stone
Loading
Offloading
Transport
Total Cost
6) RIVER SAND
DATA
A. WG1 Rate per hour
B. Price ex works per m3
C. Transport per m3
COST
Sand
Loading
Offloading
Transport
Total cost
7) VIBRATION
DATA
A 48mm Poker
B. 63mm Poker
C. Petrol Vibrator
D. Petrol price per litre
E, Petrol used per day
F. Concrete volume per day
COST
Pokers
Vibrator
Petrol
Total Cost
2500000.00 p bg x 1
2500000.00
125775.920
5214915.00
10000000.00
0.00
0.00
10000000.00
0.00
0.00
0.00
10000000.00
125775.920
1317788.00
0.00
3500000.00
0.00
0.00
0.00
1800000.00
0.00
0.00
0.00
1800000.00
150,000.00
150,000.00
150,000.00
400,000.00
2.00 Litre
15.00 m3
500000.00/2000
500000/2000
400000 p Lt x 2Lts pdy / 15 cu m pdy
100.00
250.00
53333.33
53683.33
WASTAGE
GRADE
40
GRADE
30
WAGES
1.00
1,593,864.20
1,593,864.20
1,593,864.20
1,593,864.20
1,593,864.20
1,593,864.20
1,593,864.20
1,593,864.20
CEMENT
1.10
26,664,000.00
23,830,950.00
21,109,000.00
17,942,650.00
14,776,300.00
14,776,300.00
11,609,950.00
12,776,500.00
STONE
1.075
9,245,000.00
8,395,750.00
8,395,750.00
8,395,750.00
8,213,000.00
8,213,000.00
8,395,750.00
8,062,500.00
SAND
1.20
1,252,800.00
1,291,680.00
1,382,400.00
1,460,160.00
1,449,360.00
1,449,360.00
1,620,000.00
1,728,000.00
0.00
1.00
TOTAL COST
2,278,787.88
GRADE
10 blinding
2,278,787.88
1.00
VIBRATION
2,278,787.88
GRADE
GRADE
15 blinding
10 mass
2,278,787.88
PLANT
WASTAGE
ON MAT.
2,278,787.88
GRADE OF CONCRETE
GRADE
GRADE
GRADE
25
20
15
2,278,787.88
2,278,787.88
2,278,787.88
53,683.33
53,683.33
53,683.33
53,683.33
53,683.33
41,088,135.42
37,444,715.42
34,813,485.42
31,724,895.42
28,364,995.42
28,311,312.08
25,552,035.42
26,439,652.08
44,933,658.50
41,776,182.50
38,069,874.50
34,037,994.50
33,973,574.50
30,662,442.50
31,727,582.50
UNIT ALLOWABLES
RESOURCE
PLANT
GRADE OF CONCRETE
=APPLD FCTRx0.075x1.10
=APPLD FCTRx0.05x1.10
GRADE
GRADE
GRADE
GRADE
GRADE
GRADE
GRADE
GRADE
40
30
25
20
15
15 blinding
10 mass
10 blinding
2,332,471.21
2,332,471.21
2,332,471.21
2,332,471.21
2,278,787.88
192,428.88
2,332,471.21
125,333.33
LABOUR
MATERIAL
1,593,864.20
1,593,864.20
1,593,864.20
1,593,864.20
1,593,864.20
131,493.80
1,593,864.20
87,662.53
37,161,800.00
33,518,380.00
30,887,150.00
27,798,560.00
24,438,660.00
2,016,189.45
21,625,700.00
1,241,185.00
FORMWORK
SUBS
TOTAL COST
Tsuro's Net
Tsuro's Gross
41,088,135.42
6252.13
49305762.5
49,305,762.50
53,683.33
37,444,715.42
5653.36
34,813,485.42
5475.45
31,724,895.42
5252.99
44,933,658.50
41,776,182.50
38,069,874.50
28,311,312.08
5050.44
5555.484
33,973,574.50
2,340,112.12
416.66
458.326
2,808,134.55
25,552,035.42
4648.08
5112.888
30,662,442.50
1,454,180.86
232.4
255.64
1,745,017.04
REINFORCEMENT
DATA
SKILLED WORKER ONE
SKILLED WORKER TWO
SKILLED WORKER THREE
SKILLED WORKER FOUR
WORKER EXEMPTED
WORKER GRADE FOUR
WORKER GRADE THREE
WORKER GRADE TWO
WORKER GRADE ONE
48,186.23
45,892.41
44,426.92
41,584.26
41,584.26
41,244.80
39,818.73
39,106.63
39,106.63
p hr x 9 hrs x 1
p hr x 9 hrs x 2
p hr x 9 hrs x 3
p hr x 9 hrs x 3
= applied Factor / 9
48,186.23
91,784.82
133,280.76
124,752.78
398,004.59
398,004.59 p day x 1
39,106.63 p hr x9 hrs p day x 10
398,004.59
3,519,596.70
3,917,601.29
MATERIALS
Fabric reinforcement; Ref. S193
10,094,500.00 psheet
RATE BUILD UP
15670.41
778,117.71
15,670.41
778,117.71
793,788.11
952,545.74
234,474.00
212,292.00
195,259.00
177,464.00
177,464.00
132,271.00
127,939.00
125,776.00
125,776.00
Carpentry Team
Capenter
SW1
234,474.00 p hr x 9 hrs x 1
SW2
212,292.00 p hr x 9 hrs x 2
SW3
195,259.00 p hr x 9 hrs x 3
SW4
177,464.00 p hr x 9 hrs x 3
= applied Factor / 9
234,474.00
424,584.00
585,777.00
532,392.00
1,777,227.00
Carpenter &Team (C + 1)
Carpenter
1,777,227.00
Assistant
125,776.00
per day
x 9 hrs per day
1,777,227.00
1,131,984.00
2,909,211.00
Carpenter &Team (C + 2)
Carpenter
1,777,227.00
Assistants
125,776.00
per day
x 9 hrs per day x 2 No
1,777,227.00
2,263,968.00
4,041,195.00
44mm internal quality semi solidcore flush panels doors wth concealed
hardwood edge strip as described
Size 813x 2032 mm
Carpenter and team
2,909,211.00 / 2.5 No per day
Door
15,000,000.00 each x 1.01
40mm wood csrews
150,000.00 eachx8n x1.05
.
L
1,163,684.40
m
per kg
25,000.00
250,000.00
1,163,684.40
15,150,000.00
1,260,000.00
17,573,684.40
16,410,000.00
234,474.00
212,292.00
195,259.00
177,464.00
177,464.00
132,271.00
127,939.00
125,776.00
125,776.00
p hr x 9 hrs x 1
p hr x 9 hrs x 2
p hr x 9 hrs x 3
p hr x 9 hrs x 3
= applied Factor / 9
Plasterer and Team
Plasterer
Assitant
234,474.00
424,584.00
585,777.00
532,392.00
1,777,227.00
1,777,227.00
1,131,984.00
2,909,211.00
2,500,000.00
-
Total cost
2,500,000.00
Sand
Price
Loading
Offloading
Transport
3,500,000.00
-
Total cost
3,500,000.00
83,955.48
22,472,500.00
6,037,500.00
28,593,955.48
99,991.92
26,765,000.00
5,232,500.00
32,097,491.92
60,372.48
16,160,000.00
6,802,250.00
23,022,622.48
70,749.00
18,937,500.00
6,802,250.00
25,810,499.00
RATE BUILD UP
4/8/1/E
I1
161,622.83
714,848.89
876,471.72
L
4/8/1/F
12
161,622.83
581,842.20
714,848.89
1,296,691.09
L
5/8/1/E
581,842.20
161,622.83
645,262.48
806,885.31
5/8/1/F
161,622.83
645262.48
581,842.20
645,262.48
1,227,104.68
581,842.20
1,556,029.30
714848.89
1,051,766.06
714848.89
645262.48
968,262.37
Description
Uom
Qty
Lab Rate
Lab Amt
Foundations
Clear site of all rubbish,debri etc
m2
330
0.64
Excavate oversite to remove topsoil & spread & level on site
m2
330
0.80
Excavate in pickable material to reduced levels n.e 300mm
m3deep
99
7.29
Excavate in pickable mat.for strip footings n.e 2 metres deep.
m3
115
10.69
Scarify reduced surfaces and compact mechanically to 93%
m2HCE<150mm 330
dpth
0.53
Allow for risk of collapse to sides of excavation
m2
324
1.12
Cart away surplus excavated mat to a dump site to be located
m3 by Contractor45
2.92
Extra over for excavation in soft rock.
m3
5
64.15
Extra over for excavation in hard rock
m3
2
112.27
Backfilling to trenches wth approved excvated mat to 93%m3
HCE,150mm dpth28
2.92
Approved non- expansive mat wth gravel infill , level and compact
m3
as described
40
2.14
150mm Hard core filling base course wth approved decomposed
m3
granite 40
0.32
15 Mpa in footings
m3
26
1,593,864.20
20 Mpa in surface beds
m3
27
1,593,864.20
Half brick wall in loadbearings in foundation brickwork m2
24
#REF!
One brick wall in loadbearings foundation brickwork
m2
108
#REF!
Mat Rate
211.70
264.63
721.71
1,229.58
176.42
363.74
131.22
320.76
224.53
81.65
85.54
12.83
41,440,469.30
43,034,333.51
#REF!
#REF!
24,438,660.00
27,798,560.00
#REF!
#REF!
#REF!
Concrete,Formwork & Reinforcement
20 Mpa in stairs
20 Mpa in gutters
20 Mpa in slabs
Strike off & cure top surfces of concrete
Mild steel rods not exceeding 8mm diameter
Fabric reinforcement; Ref. S193
Spacer blocks
m3
m3
m3
m2
kg
m2
item
1
6
47
345
800
15,670
1
Brickwork
Half brick wall in commom brickwork
m2
339
One brick wall in common brickwork
m2
607
75mm Brickforce to suit 115mm brick wall
m
93
150mm Brickforce to suit 230mm brick wall
m
423
Half brick shower kerb in commom brickwork
m
5
Bedding roof coverings
m
123
Set up in position cross brase & bldng in steel frame n.e 5m2.
no
84
Brick-on- edge ext cill set slopping as described
m
46
Brick-on- edge lintol set horizontally as described
m
46
raking and cutting
m2
30
Rake out joints of brickwork for turning in of metal flashingm
92
One layer of three ply DPC as described
m2
34
Two layers DPC vertically betwwen RC concrete slab and m2
brick walls
55
1 layer250 micron "Tarcon" polythene DPM laid on and including
m2
50mm sand
277blinding
Under concrete surface beds
m2
45
10mm Kaylite joint filler material in expansion joints as described
m2
160
230 x150 mm Air vents (EXT)
no
54
230 x150 mm Air vents (INT)
no
54
1,593,864.20
1,593,864.20
1,593,864.20
1,650.00
#REF!
778,117.71
300,000.00
17
30
#REF!
0.25
#REF!
#REF!
16.92
#REF!
#REF!
#REF!
18,594.24
#REF!
#REF!
#REF!
#REF!
10.58
#REF!
#REF!
1,593,864.20
9,563,185.22
74,911,617.59
569,250.00
#REF!
12,193,419,751.75
300,000.00
#REF!
5,701.38
17,977.52
#REF!
107.47
#REF!
#REF!
1,421.62
#REF!
#REF!
#REF!
1,710,670.08
#REF!
#REF!
#REF!
#REF!
1,692.40
#REF!
#REF!
#REF!
27,798,560.00
27,798,560.00
27,798,560.00
#REF!
78
227
#REF!
1.16
#REF!
#REF!
15.04
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
674,492.57
#REF!
#REF!
Roof Coverings
Marley major concrete interlocking roof tiles
152x50mm wrot softwood purlins
38x38mm Bargeboard runners to foot of roof members
12x225mm flat asbestos cement fascia as described
Ditto asbestos cement bargeboard as before
m2
m
m
m
m
Carpentry
38 x 38mm Fascia runners
m
38x114mm sawn softwood wallplate
m
50x150mm rafters
m
75mm pergola gumpoles
m
12mm "Gypsum Industries" plasterboard sheeting as described
m2
Extra over for trimming for & forming trap door 610x610 as no
described
345
1,265
123
123
123
129,156.79
#REF!
#REF!
#REF!
#REF!
123
123
1,900
25
313
4
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
1,140
34
920
15
15
6
5
5
5
15
#REF!
#REF!
161,622.83
581,842.20
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
44,559,092.55
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
14,630,957.88
1,057,068.42
#REF!
#REF!
3,311,700.00
513,560.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
148,693,006.67
8,727,633.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
714,848.89
714,848.89
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
Metal Work
Balustrades,910mm high,40mm dia m.s. tube
XO A luminium sliding door
Window frame type NE22 size 2000x653mm
Ditto ND4F
Ditto NE4
Ditto ND11F
Ditto NE2
Ditto NC2F
Ditto NC11F
Ditto ND12F
Ditto ND1
Ditto ND2
Ditto NE7
item
no
no
no
no
no
no
no
no
no
no
no
no
1
3
3
1
5
5
2
3
2
3
20
4
2
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
2,500.00
2,500.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
12,500.00
12,500.00
#REF!
m2
no
no
no
no
m
m
m
m
20
5
5
5
5
19
91
50
50
#REF!
483,106.95
342,115.79
1,141,528.97
442,115.79
31,754.32
31,754.32
31,754.32
31,754.32
12
10
3
5
8
7
12
5
5
2
9
7
9
2
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
200,000.00
5,000,000.00
2,500,000.00
342,156.98
315,249.50
308,159.89
458,129.37
297,297.64
387,039.41
432,891.28
529,876.31
207,238.45
316,219.87
305,419.87
#REF!
2,415,534.75
1,710,578.95
5,707,644.85
2,210,578.95
603,332.08
2,889,643.12
1,587,716.00
1,587,716.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
400,000.00
-
#REF!
#REF!
#REF!
2,500.00
2,500.00
SOIL DRAINAGE
m
no
no
no
no
m
m
item
15
14
29
29
5
46
75
2
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
200,000.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
no
m
m
m
m
m
m
no
no
no
2
19
33
85
33
45
24
15
15
17
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
400,000.00
-
99
Geysers
100 ltr roof gyser as described
no
3
15mm stop cocks & jointing to pipe
no
21
22mm stop cocks & jointing to pipe
no
25
Approved water metre connected to 20mm dai. Pipe.
no
1
Leave hole for small pipe throu. 115 wall.
no
15
Leave hole for small pipe throu. 230 wall.
no
15
Chase wall for 50mm pipe as described
m
380
150mm pipe as described
m
5
150mm pipe as described
m
58
150mm bend
no
61
150mm junction
no
18
150x100mm junction
no
16
150mm cast iron ''ABC''c/r eye as described
no
17
Excavate in pickable mat.for 75mm pipe as described
m
19
Excavate in pickable mat.for 150mm pipe as described m
15
E.O. excavate in soft rockfor 75mm pipe as described
m3
18
E.O. excavate in soft rockfor 75mm pipe as described with m3
15 Mpa
10
150mm concrete sorround (15Mpa) as described
no
16
E.O. excavate inhard rock.for 75mm pipe as described m3
56
Backfilling imported fill haul distance n.e. 1.5km
m3
56
Backfilling imported fill haul distance within site
m3
51
Cart away surplus excavated mat to a dump site to be located
m3 by Contractor45
Glazing
3mm clear sheet glass and glazing in steel sash
3-4mm obscure ditto
Mirror size 400x400mm
m2
m2
no
75
6
5
Painting
Prepare & apply 2 cts int. pva to steel float walls
m2
1,140
Ditto in narrow widths
m2
34
Prepare & apply 3 cts int. pva to wood float walls
m2
920
Ditto in narrow widths
m2
34
Prepare & apply 3 cts int. pva on ceilings
m2
577
Metal primer,undercoat,2 cts high gloss enamel on generalm2
surfaces of doors46
Ditto to steel window frames
m2
56
Clear polyurethane varnish on skirtings
m2
28
Metal primer,undercoat,2 cts high gloss enamel on steel door
m2 frames
56
#REF!
1,468,984.79
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
8478.231
8478.231
1356.52
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
4,406,954.37
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
635,867.33
50,869.39
6,782.58
693,519.30
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
74,321.84
45,156.79
250,000.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
1
2
3
4
5
6
7
8
9
10
11
12
SUMMARY
Foundations
Concrete,Formwork & Reinforcement
Brickwork
Roof Coverings
Carpentry
Joinery & Ironmongery
Plastering & Wall Linings
Metal Work
Pavings & Floor Coverings
SheetMetalwork,Plumbing & Drainlaying
Glazing
Painting
Sub Total
Preliminaries & Generals
13
Prime Costs & Provisional Sums
Total Carried to Form of Tender
Labour Total
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
693,519.30
#REF!
#REF!
#REF!
#REF!
Material Amt
635,405,160.00
750,561,120.00
#REF!
#REF!
0.09
9.29
1.82
2,278,787.88
2,332,471.21
#REF!
27,798,560.00
166,791,360.00
1,306,532,320.00
#REF!
#REF!
26,572.78
138,009.38
#REF!
490.21
#REF!
#REF!
1,263.52
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
107,918,811.52
#REF!
#REF!
#REF!
2,332,471.21
2,332,471.21
2,332,471.21
29.43
18.58
50.86
59,248,484.85
62,976,722.73
122,225,306.43
2,332,471.21
13,994,827.27
109,626,146.97
125,953,445.45
-
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
657,660,976.04
10,722,733.31
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
5,000,000.00
7,500,000.00
1,026,470.94
315,249.50
1,540,799.45
2,290,646.85
594,595.28
1,161,118.23
865,782.56
1,589,628.93
4,144,769.00
1,264,879.48
610,839.74
27,904,779.96
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
12,500.00
12,500.00
#REF!
-
5,574,138.00
270,940.74
1,250,000.00
7,095,078.74
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
Material Total
#REF!
#REF!
#REF!
#REF!
Plant Total
Total
#REF!
27,904,779.96
#REF!
7,095,078.74
#REF!
122,225,306.43
125,953,445.45
-
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
27,904,779.96
#REF!
#REF!
7,788,598.04
#REF!
#REF!
#REF!
248,178,751.89
37,226,812.78
#REF!
#REF!
#REF!
285,405,564.67
#REF!