Anda di halaman 1dari 12

ABSTRACT

Construction of bridges, especially construction of deepwater pile caps, on major rivers is a challenging task when water depth and water velocity are high. Traditional cofferdams approach of pile cap construction is not suitable under such circumstances. At Sungai Kerian Bridge our group is proposing a new solution by replacing the existing 2 lanes bridge with 4 Lanes Bridge to increase the traffic volume capacity by successfully implementing the pile cap lowering technique for the construction of deep-water pile caps and piers of the old existing Sungai Kerian Bridge which is located in Parit Buntar. This method involves casting of a pile cap above water on temporary soffit shutter, lowering it to the desired level under water through precise synchronized operation of hydraulic jacks, and finally connecting the pile cap with the piles deep under water. This is an important milestone for local Contractors involved in bridge construction in Parit Buntar. The experience gained through the construction of 4 Lanes Bridge in Sungai Kerian Bridge could be successfully utilized in the construction of bridges over any major river, using solely local expertise.

ACKNOWLEDGEMENTS

Thankful to god for his graciousness, that the authors can complete the Group Project for Construction Technology with success.

The authors deeply acknowledge and thanks to Dr Izwan Johari on mentoring and for his guidance throughout this project. Thanks are also due to all the staff of Universiti Sains Malaysia Engineering Campus who has directly or indirectly involved with this Project.

Lastly we wish to thank our family and friends in Universiti Sains Malaysia Engineering Campus which have given us a lot of support and encouragement to complete this report.

INTRODUCTION
Construction of bridges on major rivers is a challenging task. This is particularly true for construction of bridges in deep waters, which is common for many rivers in Malaysia where water-depth remains very high, even during the dry season. Among the bridge components, construction of pile cap and pier is particularly challenging in deep water. Traditionally, cofferdams are used for construction of pile caps and piers in relatively shallow water. However, this traditional approach suffers from major drawbacks, both from technical and cost considerations, in situations where water depth is high and there is high difference between water levels at high tide and low tide. This approach is therefore not suitable for construction of pile caps and piers in deep waters. Among the state of the art construction of techniques used for construction of pile cap and pier in deep water, the pile cap lowering technique or the jack-down method has been successfully used for bridge construction in many countries. Recently, contractor company in Malaysia were successfully implemented the pile cap lowering technique for the construction of deep-water pile caps and piers in deep waters. This report describes the lift slab technique propose 4 lanes Sg Kerian Bridge for the construction of pile caps and piers in the bridge.

LITERATURE REVIEW

ISSUES
POTENTIAL HEAT ISSUES. For the construction process of the pile cap which will support the bridge piers, some issues occur. The some of the issue is potential heat which influence with concretes using in pile cap construction process. All concretes generate heat as the cementitious materials hydrate. Most of this heat generation occurs in the first days after placement. For thin items such as pavements, heat dissipates almost as quickly as it is generated. For thicker concrete sections (mass concrete), heat dissipates more slowly than it is generated. The net result is that mass concrete can get hot. Management of these temperatures is necessary to prevent damage, minimize delays, and meet project specifications. Method Of Heat(Temperature) Control. Methods of controlling mass concrete temperatures range from relatively simple to complex and from inexpensive too costly. Depending on a particular situation, it may be advantageous to use one or more methods over another.

Low-Heat Material. Different types of cement (and cements within each type) generate varying amounts of heat. Figure 2 presents the typical heats of hydration of different cement types. Type IV cements is not shown because it is rarely available. Low-heat generating concrete mixtures is always a wise choice for mass concrete to minimize potential thermal problems. Low-heat generating concrete mixes use the maximum allowable level of low-heat pozzolans such as Class F fly ash or slagas cement replacements, and the minimum amount of total cementitious materials that achieves the project requirements. Class F fly ash generates about half as much heat as the cement that it replaces and is often used at a replacement rate of 15 to 25%. Ground granulated blast-furnace slag is often used at a replacement rate of 65 to 80% to reduce heat. The reduction in heat generation achieved depends on the concrete temperature, and should be evaluated on a case-by-case basis. Figure 3 illustrates the effect of Class F fly ash and different cement types on the adiabatic temperature rise of concrete. This is the theoretical increase in temperature of the concrete above the placement temperature, if the concrete is not allowed to cool. In Fig. 3, the total quantity of cementitious materials for all mixes is 525 lb/yd3 (311 kg/m3) of concrete.

Fig. 2: Heat of hydration for typical cements

Fig. 3: Concrete temperatures of mixes with 525 lb/yd3 of cementitious materials

Pre-cooling Of Concrete The concrete temperature at the time of placement has a great impact on the maximum concrete temperature. Typically, for every 1 F (0.6 C) reduction or increase in the initial concrete temperature, the maximum concrete temperature is changed by approximately 1 F (0.6 C). As an example, to reduce the maximum concrete temperature by approximately 10 F (6 C), the concrete temperature at the time of placement should generally be reduced by 10 F (6 C). Methods to precool concrete include shading and sprinkling of aggregate piles (as appropriate), use of chilled mix water, and replacement of mix water by ice. Efforts to cool aggregates have the most pronounced effects on the concrete temperature because they represent 70 to 85% of the weight of the concrete. Liquid nitrogen can also be used to precool concrete or concrete constituents. This option can significantly increase the cost of concrete; however, it has been used to successfully precool concrete to 34 F (1 C) for highly specialized mass concrete placements.

Fig. 4: Effects of internal cooling pipes

Post-cooling Of Concrete Cooling pipes in mass concrete are sometimes used to reduce maximum concrete temperatures and to quickly reduce interior temperatures. This method can have high initial and operating costs, but benefits can often outweigh these costs if cooling pipe size, spacing, and temperatures are optimized properly. Figure 4 illustrates the reduction in the average temperature of a mass concrete pour with and without internal cooling pipes. Note the reduction in the maximum concrete temperature and the increased rate of cooling. It is important to emphasize again that significant internal and surface thermal cracking can result if post-cooling is improperly designed or performed. However, if properly designed, a post-cooling system can significantly reduce concrete temperatures and the amount of time required for cooling. Surface Insulation Insulation or insulated formwork is often used to warm the concrete surface and reduce the temperature difference, which in turn minimizes the potential for thermal cracking. For most mass pours, surface insulation does not appreciably increase the maximum concrete temperature, but it can significantly decrease the rate of cooling. Insulation is inexpensive, but resulting delays from the reduced cooling rate can be costly. Insulation often has to remain in place for several weeks or longer. Removing it too soon can cause the surface to cool quickly and crack. Many types of insulation materials are available, and insulation levels can be optimized to meet required temperature differences and maximize the rate of cooling. Aggregate Thermal properties of the coarse aggregate can have a significant effect on mass concrete. Concretes containing low-thermal-expansion aggregates such as granite and limestone generally permit higher maximum allowable temperature differences than concretes made using highthermal-expansion aggregates, as shown in Fig. 5 (Fig. 5 is similar to Fig. 1, except a second calculated maximum allowable temperature difference is added for concrete with a high thermal-expansion aggregate). This means that selecting an aggregate with a low thermal expansion will reduce the potential for thermal cracking.

Fig. 5: Effect of aggregate on the maximum allowable temperature difference

SITE VISITS

PROJECT PLANNING

Two(2) lane bridge Cast in Situ Bored Pile bridge construction services. The bridge foundation

Four(4) lane bridge

Cast in Situ Bored Pile bridge construction services.

SUMMARY
For the conclusion of this project is to ensure the desirable strength, appearance, and durability qualities of concrete are achieved in the constructions process and mass concrete elements of the Sungai Kerian Bridge, attention needs to be directed to the buildup of heat during curing. The exothermic reaction of cement requires the dissipation of heat if the heat is to be kept from affecting the designers anticipated quality of the concrete element. Practices for coping with excess heat were first developed during construction of large concrete dams requiring relatively low concrete strengths. Recent bridge designing practices now mean the concerns regarding heat in the construction of dams are now also concerns for the construction of bridges. The designs for the new bridges incorporate large volume concrete piles, piers, pier columns, pier tables, and footings. The pier tables and columns also require a high compressive strength. For normal strength concrete a more or less passive approach can be used. The dissipation of heat can be controlled by slowing the rate of strength gain by replacing cement with normal quality mineral admixture (fly ash); having low initial temperatures so the rock, sand and water can absorb heat; and lowering the cement content to reduce the amount of heat produced. For high strength concrete, as demonstrated by the high strength mass concrete footing at Bent 18 of the 580/680 Interchange, a more active practice such as an internal pipe cooling system during curing appears to be needed.

Anda mungkin juga menyukai