TECHNICAL STANDARD TS-085 TRENCHING AND CONDUIT STANDARD FOR UNDERGROUND DISTRIBUTION CABLE NETWORKS PUBLISHED: FEBRUARY 2012
TS-085
Date: 16/12/11
Page 1 of 73
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
REVISION NOTICE:
DATE
October 2006 December 2008
EXPLANATION
Modifications to clauses; 3, 4, 5, 7, 14 & added Appendix - B. Added clause 13 associated with Civil works specific to 66kV cables and minor updates and re-numbering. Restructured the document to current standards Removed Old Appendix B Added New Appendices: C, D, E, F, G, H, J and K Added New Clauses 7.2.4, 7.2.5, 9.5.1, 9.5.2, 9.8.2, 9.8.3, 9.9, 9.10, 9.14, 10.7, 10.8.1, 10.9.1 and 17.10. Updated all other clauses
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
February 2012
ETSA Utilities -
ETSA Utilities means Distribution Lessor Corporation subject to a two hundred year lease to the partnership of companies trading as ETSA Utilities or ETSA Utilities in its own right. ETSA Utilities, ABN 13 332 330 749, a partnership of:
CKI Utilities Development Limited, ABN 65 090 718 880. HEI Utilities Development Limited, ABN 82 090 718 951. each incorporated in The Bahamas. Spark Infrastructure SA (No.1) Pty Ltd, ABN 54 091 142 380. Spark Infrastructure SA (No.2) Pty Ltd, ABN 19 091 143 038. Spark Infrastructure SA (No.3) Pty Ltd, ABN 50 091 142 362. each incorporated in Australia.
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 2 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
Contents
1.0 2.0 3.0 4.0 5.0 6.0 7.0 PURPOSE ..............................................................................8 SCOPE..................................................................................8 GRACE PERIOD ...................................................................8 REFERENCES ........................................................................9 DEFINITIONS ......................................................................10 BACKGROUND ..................................................................13 CIVIL WORKS REQUIREMENTS ..........................................13
7.1 7.2 Customers Responsibilities .............................................. 13 Civil Contractors Responsibilities ..................................... 14
7.2.1 7.2.2 7.2.3 7.2.4 7.2.5 7.2.6 7.2.7 7.2.8 Access Permit Requirements ................................................. 14 Safe Edge Shovel Requirements ........................................... 14 Civil Works Notification Requirements .................................. 15 Civil Works Compliance Requirements ................................ 15 Civil Works Non-Compliance ................................................. 15 Requirements of Changes to Civil Works ............................. 16 Directional Bore Drawing Requirements .............................. 16 Site Conditions Requirements ................................................ 16
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
8.0
9.0
TRENCHING .......................................................................21
9.1 9.2 9.3 Cable/Conduit Requirements for ETSA Utilities Trench ... 21 Trench Requirements for Road Reserve/Crossing .......... 22 DPTI Requirements for DPTI Controlled Roads ................. 23
9.3.1 9.3.2 9.3.3 9.3.4 DPTI Open Shared Trenching Requirements ....................... 23 DPTI Trenchless Boring Requirements.................................... 24 DPTI Notification ....................................................................... 24 DPTI Traffic Control Notification Process .............................. 24
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 3 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
TS-085: Trenching & Conduit for Underground Distribution Cable Networks 9.3.5 9.3.6 DPTI Emergency Work Requirements ................................... 25 DPTI Maintenance Period Requirements ............................. 25
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
9.4 9.5
Public Road (Non DPTI Roads) Controlled by Council ... 25 Conduits within Railway Boundaries................................ 25
9.5.1 9.5.2 Telecommunications Pilot Cable Only................................. 26 Telecommunications Fibre Optic Only ................................ 26 Vertical Separation between Services ................................ 28 Horizontal Separation between Services ............................. 29
9.6
9.7 9.8
Reduced Cover Trenching ............................................... 33 Underground Cables on Bridge Crossings ...................... 33 Pit Installations ................................................................... 33 Cable Location Markers ................................................... 34 Trenchless/Directional Boring .......................................... 34
9.13.1 Requirements for Directional Boring ..................................... 35
Hydro Vacuum Excavation .............................................. 35 General .............................................................................. 36 Spare Conduit Provision ................................................... 36
10.2.1 Wherever an electrical cable is buried direct .................... 36 10.2.2 When a cable is installed in a conduit ................................. 37 10.2.3 Road Crossings......................................................................... 37
10.3 10.4
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 4 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
Conduit Sizes ..................................................................... 40 Conduit Cable Entry into Service Pillars .......................... 43 Conduits Compliance to AS/NZS Standards ................... 44
10.8.1 Identification of Conduit Sizes ............................................... 44 10.8.2 Colour of Conduits/Couplings ............................................... 44
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
10.9
11.0 TRENCHING ON PRIVATE PROPERTY ................................48 12.0 TRENCHING FOR SINGLE CUSTOMER ON VERGE ...........48 13.0 EXCAVATION FOR VAULTS AND PIERS ............................49 14.0 BEDDING SAND FOR LESS THAN 66kV ..........................49 15.0 POLYMERIC CABLE COVERS / MARKER TAPE .................50 16.0 BACKFILLING AND CONSOLIDATION .............................50 17.0 66kV UNDERGROUND CABLE INSTALLATION ..................51
17.1 17.2 Introduction ....................................................................... 51 66kV Design Information .................................................. 51
17.2.1 Extent of 66kV Civil Work ........................................................ 51 17.2.2 66kV Cable Route Design Changes ..................................... 52
66kV Cable Trench Dimensions ....................................... 52 66kV Cable Separation from Other Services .................. 52 66kV Directional Boring .................................................... 52 Installation of (66kV) Conduits in Open Trench .............. 53 Lubrication Points -66kV ................................................... 53 Laying 66kV Cables .......................................................... 53
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 5 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
17.9
Thermocouples - 66kV...................................................... 53
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
17.11 Bentonite Mixture in Conduits - 66kV .............................. 56 17.12 Protective Cover Slabs - 66kV ......................................... 56 17.13 66kV Sand Backfilling Requirements ............................... 56
17.13.1 Sand Backfill - 66kV ................................................................. 56
17.14 Cable Marker Tapes - 66kV ............................................. 57 17.15 Cable Markers - 66kV....................................................... 57 17.16 Pits - 66kV .......................................................................... 57 17.17 Joint Bays - 66kV ............................................................... 57
18.0 CONTAMINATED SOIL ......................................................58 APPENDICES: ..............................................................................59 A: Civil Works Notification & Compliance ..............................59 B: Cable Location Marking Drawings ......................................60 C: Example of Directional Bore Drawing ................................61 D: Typical Shared Trench Arrangements ................................62
D-1: Cables Buried Direct (Shared Trench) ............................. 62
(In Footpath for Non DPTI Roads) ....................................................... 62
F: Typical Reduced Cover Trenching ......................................66 G: Typical ETSA Utilities Telecomm Trench (Only) ..................67
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 6 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 7 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
1.0
PURPOSE
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
This Technical Standard specifies the standard trench, conduit, retaining walls and Civil works requirements for a new or upgraded installation that will be a component of ETSA Utilities distribution network. Once the scope for a trench, conduits, retaining walls and Civil works is determined then this technical standard will assist the Customer in the Civil component of electrical works/network extension. The construction could encompass a network extension, PLEC projects, ETSA Utilities capital works, specific arrangements or customer works. These works could be on private property or on a public road verge. This standard will assist in clarifying the responsibilities of customers regarding agreements, approvals, construction requirements and the ETSA Utilities requirements for Civil Works Compliance
2.0
SCOPE
The specification in this technical standard is applicable (but not limited) to all parties involved in the activities of trenching, conduit installation, retaining walls and Civil works associated with the underground installation or alteration of distribution cable networks. This technical standard is to cover all underground trenching and conduit installations; however, section 17.0 is an additional requirement for applications to 66kV underground networks. The appendices at the end of this document provides more detailed information on trench arrangements, Civil works notification and Civil works compliance and cable location markers. The Electricity (General) Regulations 1997, other statutory authority requirements, AS/NZS standards and the Building Code of Australia (BCA) are the basis of TS-085. For any situation that is not covered in this standard, the requirement of AS/NZS 3000 applies. There may be additional requirements and specifications that are project specific. For further assistance/information concerning this technical standard, please contact the relevant ETSA Utilities Manager. This technical standard is available at the ETSA Utilities websites below: Intranet website (Internal) Internet website (External)
3.0
GRACE PERIOD
The maximum grace period acceptable by ETSA Utilities for implementing this Standard is 3 months from the date of publication. All projects that are not in receipt of Specification Compliance at the revised date of issue for this technical standard will need to incorporate the latest requirements. This is applicable to both the design and construction phases of the project. The validity period for a Specification Compliance is 60 days. On the expiry of a Specification Compliance, any specification change without a documented exemption must be incorporated into the design and construction of ETSA Utilities infrastructure.
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 8 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
4.0
REFERENCES
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
The following listed documents are for additional information. It is advisable to refer to the current publications before implementing them. Other documentation may be required on a project specific basis. For the Civil Contractors conducting regular Civil works for any ETSA Utilities installations, there is a Civil Construction Manual40 available on request. This manual details many project specific aspects of Civil works that may not be detailed in this standard.
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 9 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
5.0
DEFINITIONS
AS/NZS stands for Australia and New Zealand Standards published by Standards Australia. Authorised Person - the person in charge of the premises, or the registered electrical worker or licensed electrical Contractor or other person appointed or selected by the person in charge of the premises, to perform specific duties associated with the electrical installation on the premises. Boring - refers to activities of directional drilling (typically horizontal or vertical). Cable/s - a wire, conductor or form of material designed for carrying electric current or communications signals, installed underground. Customer - has the meaning given to that term in the Electricity Act 1996, namely a person who has a supply of electricity available from a transmission or distribution network for consumption by that person and includes: (a) The occupier for the time being of a place to which electricity is supplied; (b) Where the context requires, a person seeking an electricity supply; (c) A person of a class declared by regulation to be customers; and (d) Customer may or may not necessarily be the landowner.
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 10 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
NSP - stands for ETSA Utilities Network Standards and Performance Group.
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 12 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
6.0
BACKGROUND
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
The responsibility for the installation of a trench for the installation of ETSA Utilities infrastructure can be: The Customer for a network extensions which includes land developments, Network Extensions or Customer alterations to the ETSA Utilities electrical network; Council for Power Line Environment Committee (PLEC) projects; and ETSA Utilities for capital works and, under specific arrangements, some customer works. The Electricity (General) Regulations 1997 (Part 6, Section 39A), requires a separation between a building or a structure and underground powerlines: At a voltage of 33kV or less shall be within 2.0 m; and At a voltage greater than of 33kV shall be within 3.0 m. Any trench installation not meeting these requirements will be non-compliant without exemption from the OTR. The Designer/Contractor will need to supply OTR exemption as a component of Civil Works Compliance Form. There are other separation requirements documented in section 9.6 in this document that are requirements of other service providers. A trench containing ETSA Utilities cables and the associated conduits are to be positioned in the straightest possible alignment to accommodate future cable installations. ETSA Utilities may agree to provide a quotation for the installation of a trench on behalf of a customer. For access to the list of Civil Contractors utilised by ETSA Utilities refer to NICC-203 which is available on our Internet website. Undertaking of trenching shall be in a workman-like manner and shall meet the requirements of TS-085 and any other relevant specification. The trench containing the electrical works is a component of the asset inspection process and it is the responsibility of the customer/land owner to ensure that the trench meets the specification. An ETSA Utilities Asset Compliance Officer may inspect the trench at any time. A non-compliance notice will be issued for any civil works, where remedial work to a trench is required to meet this Technical Standard including any other associated specifications requirements. If there is any query relating to the requirements of this Technical Standard (TS-085), please contact the Network Project Officer (NPO) responsible for the project.
7.0
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 13 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
7.2
7.2.2
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 14 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
7.2.3
7.2.4
7.2.5
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 15 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
7.2.6
7.2.7
7.2.8
8.0
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 16 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
Ensures the easement for the electrical design drawing and the subsequent transfer to a deposited plan is appropriate in size to fit the padmount transformer and the retaining wall.
8.2
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 17 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
If above stated requirements are not met, then non-compliance will be issued. Refer to the TS-102: Easement Standard, Appendix-B for fill and cut scenarios of retaining wall details; A retaining wall construction needs to be of a quality that will ensure the long-term stability and safety of the ETSA Utilities asset; The retaining wall and backfill shall be designed to drain the area behind the wall and continue to do so indefinitely without blockage, so that hydrostatic pressure is not exerted on the wall at any time; A more effective system of drainage consists of a continuous agricultural pipe located at the base of all retaining walls and be surrounded by gravel or crushed stone with a continuous vertical layer of granule material at least 300mm thick covering the rear face of the wall area; Retaining walls shall be constructed of concrete masonry materials; For vertical block type retaining walls, a suitable concrete/steel reinforced foundation shall be constructed; If interlocking style blocks are utilised, they shall be of a pinned or socket and nib type. The two top courses shall be pinned and glued with an epoxy style resin and the top course shall consist of a glued top capping; Any brick style retaining wall construction will not be approved unless the number of courses is a minimum 5. Open style interlocking blocks may be acceptable provided the soil is retained. The use of Geo cloth type material may also be acceptable. Ensure that the material to be utilised for a retaining wall will be acceptable to ETSA Utilities; This style of retaining wall construction has the potential to require an easement larger than standard in order to provide the required retaining wall strength. Please contact your ETSA Utilities Network Project Officer prior to installation. ETSA Utilities reserves the right to request engineering calculations for any retaining wall. ETSA Utilities will consider a submission from a Certified Structural/Civil Engineer to a variation to the construction material utilised for a retaining wall as described in this clause; Material to be retained shall be classified in one of the 3 types listed below: 1. Coarse-grained soil without admixture of fine soil particles; Very permeable (clean sand or gravel); 2. Coarse-grained soil of low permeability due to admixture of particles of silt size; and 3. Residual soil with stones, fine silty sand and granular materials with conspicuous clay content. Materials not acceptable include very soft or soft clay, organic silt or silty clays, and medium or stiff clay;
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 18 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
Dispensation for the installation of a retaining wall can be granted by the relevant regional Network Manager when the following can be verified: 1. The short and long term stability of a padmount transformer will not be compromised. 2. The easement site and adjacent properties will not be impacted by erosion run off. I.e. It can be demonstrated that the site adjacent to the easement is well consolidated and/or there is other means of retainment or removal of any run off material.
8.2.1
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 19 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
Retaining Wall
Easement to be extended to include the area occupied by the retaining wall if required.
ETSA Utilities Transformer/ Switching Cubicle Ground Level Suitable Retaining Fill Continuous agricultural pipe the length all retaining wall sections plus external weep holes on the lowest section of the retaining walls
Note Retaining wall to be built up to the height of the base Granulated material behind all retaining wall sections * 1.0m * ETSA Utilities extended easement requirement for a Fill situation. Weep hole Ground level Retaining Wall
300mm min.
Ground Level
Continuous Agricultural Pipe The Length of all Retaining Wall Sections. Agricultural Pipe to Drain to The Front of Equipment.
Ground Level Easement Boundary Ag pipe to exit at the Front of the Retaining wall 300mm
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 20 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
9.0
When installing conduits/cables in a trench, consider the following Design Requirements: The trench shall be as straight as possible with a firm and smooth base; The installation of multiple conduits requires a minimum separation of 25mm in all directions (or as otherwise specified) between ETSA Utilities conduits. This is to ensure the bedding sand fully encompasses the conduit at the time of back filling. This will reduce future compaction issues. (Refer to figure-4 below); There shall be a minimum separation of 50mm in all directions (or as otherwise specified) between direct laid ETSA Utilities cable circuits. The greater the cable circuit separation, the greater the current carrying capacity of the electrical cable. (Refer to figure 4 below): Note: If the trench width allows for greater than 50mm separation, the preferred installation method is to increase cable separation to maximise the spacing. From time to time, there may be a requirement for a specific separation that is greater than the minimum. (Refer to figure-4 below). Separation from a trench wall to any ETSA Utilities infrastructure will normally be a minimum of 50mm. This is to reduce the likelihood of any damage to electrical infrastructure from sharp edges, stones, etc. Note: Under some circumstances, ETSA Utilities may approve a lesser dimension if it can be verified the trench edge is such that it will not damage the installed cables or if the installed conduit is medium or heavy duty. (Refer to figure-4 below). Conduit 50mm 25mm Cable circuit separation 50mm minimum (Refer section 9.1 & 9.2) Cables 25mm 50mm Bedding Sand Bottom of trench FIGURE 4 TRENCHING Dimensions for ETSA Utilities infrastructure in this standard are the minimum except where shown; The maximum depth of any length of open trench should not be greater than 1.2m without ETSA Utilities approval; Any trench, which has depth/cover over 1.5 m, requires additional construction requirements. For trenching and shoring examples, refer to the OHS&W Regulations 1995. Locate the trench, where practicable, in accordance with the publication A Code for the Placement of Infrastructure Services in New and Existing Streets (Services in Streets Code).
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 21 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
The installer shall submit all variations to the construction drawing for inclusion on the As Constructed ETSA Utilities drawing; It is the Civil and Electrical Contractors responsibility to forward hand written mark-ups of hard copy drawings detailing all changes and necessary installations information are returned to the designer within 30 days of completion to ensure that the final As Constructed drawings are correct. For the specific requirements relating to the submission of As Constructed drawings, refer to TS-100 - clauses 6.3 and 6.5 which is applicable to all Civil installations.
9.2
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 22 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
9.3
DPTI requirements can impact both a designer and a constructor. In country regions, DPTI have highlighted most DPTI controlled roadside sites with a distinctive but discreet marker. Information on Transport SA Guide to Matters of National Environmental Significance and a List of Roadside Significant Sites visit Transport SA website.
9.3.1
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 23 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
TS-085: Trenching & Conduit for Underground Distribution Cable Networks 9.3.2 DPTI Trenchless Boring Requirements
Multiple conduits can be passed through a single bore or tunnel. It is required that there be a minimum spacing of 10D between single bores where there are multiple bores where D is the diameter of the largest conduit. Refer to figure-6 below. The minimum depth of a trenchless bore will generally be 1.5m to minimise ground swell. The final depth is to be determined in conjunction with the boring Contractor, with the minimum depth to be achieved wherever possible. Refer to figure-6 below. Ground Level Bore 1 Min.1.5m Bore 2
100mm conduit
125mm conduit
9.3.3
DPTI Notification
The electrical designer shall submit any design to DPTI for comment where any ETSA Utilities infrastructure, i.e., poles, cable or conduit, will be running parallel to the kerb for some distance. This is to ensure any installation takes into account any future road widening. The Constructor: An electrical or Civil Contractor shall submit a Notification Form, which is available to download from DPTI website, 5 working days prior to the commencement of works. Any Civil works that will be undertaken on a DPTI road over a period greater than one day requires 4 weeks notice. The notice is required for the following: Any work that requires traffic management, this may also include work on overhead mains; An open trench or trenchless boring; and Any cable pulling through installed conduits.
9.3.4
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 24 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
TS-085: Trenching & Conduit for Underground Distribution Cable Networks 9.3.5 DPTI Emergency Work Requirements
DPTI requires verbal notification to the appropriate DPTI representative at the earliest opportunity. This shall be followed by submission of a Notification Form within 24 hours of the emergency.
9.3.6
9.4
9.5
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 25 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
An electrical conduit should be installed a minimum of 2.0m deep under any rail line for a 3.0m distance beyond the outer rails. Refer to figure 7 below; Conduits in other locations within railway property shall have 1.0m minimum cover; and A railway authority may approve a lesser depth, but the depth shall not be less than the ETSA Utilities standard. For more details, refer to Guidelines for ETSA Utilities Crossings of the Electrified DPTI Railway Network
ETSA Utilities access point(s) to cables to be located outside of the rail corridor and the depth of the cables outside of rail corrider to be the requirements of TS-085 and TS-100 Rail corridor boundary fence 3m minimum to AS 4799 ETSA Utilities cable in conduit Depth to the Requirements of AS 4799
9.5.1
9.5.2
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 26 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
9.6
For normal trenching and trenchless technology installation, clearance from ETSA Utilities assets to other service utility assets shall not be less than (and preferably exceed) the minimum vertical and horizontal clearances as shown in the Table 1 (Vertical Separation) and Table 2 (Horizontal Separation) below. Written agreement on reduced clearances shall be obtained from the relevant ETSA Utilities Manager and the relevant Service Owner. Refer to Appendix F below and for clearance in shared trench arrangements, refer to Appendix D, E, G, H and K below. The following notes apply to Table 1 and Table 2 below: 1. For any other authorities infrastructure, crossing ETSA Utilities cables (and associated conduits), which are less than 66kV, a minimum separation if not specified as greater by other authority is 150mm. 2. For any other authorities infrastructure, running parallel to ETSA Utilities cables (and associated conduits), which are less than 66kV, a minimum separation if not specified as greater by another authority is 600mm. For any other authorities infrastructure, crossing ETSA Utilities 66kV cables (and associated conduits), refer to Section 17.4. For any other authorities infrastructure, running parallel to ETSA Utilities 66kV cables (and associated conduits), refer to Section 17.4. Any authority that is unable to achieve these specified minimum separations needs to contact ETSA Utilities for approval. As per AS/NZS 3500.3, the minimum separation between any underground stormwater drain and an electrical supply cable shall be at least a. 100mm provided the electrical supply cable is indicated along its length with orange marker tape complying with AS/NZS 2648.1 and is mechanically protected; or b. 600mm, where the electrical supply cable neither indicated nor mechanically protected. Refer to AS 2885.1, for clearances to the high-pressure gas mains. As per AS/NZS 3500.3, the minimum separation between any underground stormwater drain crossing another service shall a. cross at angle 90 if practicable, but not less than 45; b. have a vertical separation of not less than 100mm; and c. be marked along its length for 1m either side of the centreline of the service with marker tape complying with AS/NZS 2648.1, laid 150mm above the installed service. Refer to AS/NZS 4645.3, which states that: a. where a plastic main or service is laid parallel to other utility assets, a minimum separation distance is required in order to affect repairs. The minimum separation distance shall be 250mm; and
3. 4. 5. 6.
7. 8.
9.
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 27 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
12.
13.
9.6.1
Types
Non-ETSA Utilities Telecomm. Pipe Non-ETSA Utilities Telecomm. Pits Low Pressure Gas Non-Metallic Pipes
(Refer to notes 9 & 10)
100 100 250 225 (for sewer main pipe diam. 300) 300 (for other sewer mains) (Refer to note 1) 600 225 600 (Refer to note 6a) 100 600 (Refer to note 6b) 100 (Refer to note 8)
300 100 250 225 (for sewer main pipe diam. 300) 300 (for other sewer mains) (Refer to note 1) 600 225 600 (Refer to note 6a) 100 600 (Refer to note 6b) 100 (Refer to note 8) Approval Required from ETSAs MNP Refer to: Notes 3 & 4. and Section 17.4
SA Water - Sewer
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 28 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
9.6.1
Horizontal separation will be dependent on the extent that the external plant is parallel with the ETSA Utilities infrastructure. To ensure compliance with the NICC-404 only hand digging is permissible for any excavation within 1.0m of any ETSA Utilities assets. Refer to notes (above) and Table 2 (below) for the minimum horizontal separation between services. TABLE 2 - Horizontal Separation between Services Types ETSA Utilities LV Mains ETSA Utilities HV < 66kV Mains ETSA Utilities 66kV Cables
Non-ETSA Utilities Telecomm. Pipe Non-ETSA Utilities Telecomm. Pits Low Pressure Gas Non-Metallic Pipes
(Refer to notes 9 & 10)
100 100 250 500 (for sewer main pipe diam. 300) 1000 (for other sewer mains) (Refer to note 1) 600 500 (for water main pipe diam. 200) 1000 (for other water mains) 600 (Refer to note 6a) 100 600 (Refer to note 6b) 100 (Refer to note 8)
300 100 250 500 (for sewer main pipe diam. 300) 1000 (for other sewer mains) (Refer to note 1) 600 500 (for water main pipe diam. 200) 1000 (for other water mains) 600 (Refer to note 6a) 100 600 (Refer to note 6b) 100 (Refer to note 8)
SA Water - Sewer
Private Sewer
Approval Required from ETSAs MNP Refer to: Notes 3 & 4. and Section 17.4
SA Water - Water
9.7
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 29 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
PREFERRED G.L.
Alternative Conduit route
Coupling location is not appropriate if there is any tension. This creates a lip which can damage cables
Preferred gradient rise/fall of conduit 100mm per 1metre For primary run.
9.8
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 30 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
9.8.1
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 31 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
10. 11.
9.8.2
9.8.3
9.8.4 9.8.5
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 32 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
9.9
9.10 9.11
Pit Installations
There are number of pits available in various sizes. The Installed pit shall be of a size appropriate for the purpose. The designer also needs to be mindfull of clearances to the other services and note that clearance to water pipe lines infrastructure (e.g. SA Water) from ETSA Utilities LV pit shall be 1.0m. Also, refer to clause 9.6 and figure 9 below. Where conduits are installed into the body of a pit, the conduit needs to be 25 to 50mm inside the pits body. All conduit edges shall have no sharp edges. The Contractor shall cap all conduit entries, to stop the entry of foreign material between the time of the conduit installation and the installation of ETSA Utilities cables. Refer to clause 10.10.4 below and refer to TS100 for design information on service pillar and pit. Expanding foam or silicon should be utilised as a sealer at the conduit entry point into the wall of a service pillar if the conduit is not a tight fit.
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 33 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
Preferred 0 40mm to pit bottom for low voltage cable entry to ensure appropriate room for cable cones
9.12
9.13
Trenchless/Directional Boring
Some trenching scenarios need to undertake the installation of conduit using trenchless boring technique. Directional Drilling should only be considered in situations where Open Trenching is not an option. Good examples of this would be - but not limited to under rivers, under tram or train lines, in CBD areas where the road is full of services and does not provide an alignment for an open trench. Trenchless/directional boring technology is utilised where: Open trenching is not suitable (or not an option) to the local conditions. The minimum depth needs to be 1.5m to ensure there is no groundswell above the conduit installation. The most suitable boring technique for a particular site will be dependent on the following considerations: Number and size of cables to be installed; Length required; Type of soil and condition; Location accuracy required; Straight or curved profile/route required; and Restraints on size of equipment used and/or work site access. When required, Install nylon draw ropes and seal the conduit ends, using suitable tapered push-in polystyrene plugs.
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 34 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
Note 1. Refer to E1921 sht 2.1 for standard arrangements 2. Refer to E1921 sht 6.1 to 6.4 for assembly details 3. A P7 pit is preferred for LV cable junctions and service arrangements for approved below ground connections 4. The preference is for all conduits to enter at the ends of a pit
TS-085: Trenching & Conduit for Underground Distribution Cable Networks 9.13.1 Requirements for Directional Boring
When utilising trenchless/directional boring technology consideration shall be given to the following requirements: When installing more than one conduit in the bored hole, or the hole exceeds the outer diameter of the conduit by more than 25mm, then fill the resulting voids with a suitable approved slurry. When installing banks of conduits in a bore, install conduits in such a way when practicable that the conduit profile is the same at the entry and exit. The design and construction of a bore means polyethylene pipe is required as per Table 9 and Table 10 in this document. Also, consider the potential for cable de-rating for the deeper burial of cables and the minimum allowable depth can be preferable. For ETSA Utilities Telecommunications conduits that will only have Optic Fibre Cables installed, marker tape with tracer wires shall be required. Any trenchless bore installation requires a bore log of the final depths and locations to be included on the As Constructed drawing as a permanent record of the installation. Refer to TS-100 for the directional bore drawing preparation detail. Also, refer to Appendix-C for Example of Directional Bore Drawing in this document. Further clarification can be obtained from the Facilities Records Coordinator through the ETSA Utilities Project Manager.
9.14
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 35 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
10.0
10.2
Note: Where one LV circuit consists of two or more parallel bundles of cables, a spare conduit must be provided for each bundle of cables.
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 36 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
10.2.2.1
10.2.2.2
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 37 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
10.3
The requirement for bends will need to be assessed at the time of installation as well as at the time of trench design layout. Where spare conduits are required, refer to clause 10.2 above, the extent of the installation shall satisfy the minimum conduit bend requirements as per the following tables 4, 5, 6, 7, 8, 9, 10 and 11: TABLE 4 - Conduit Bend Requirements Situation Common Trench T Intersections Trench Direction Changes Greater than 90 Deg Transformer Vaults - General Transformer Vault for a Future Stage Trench Direction Changes less than 90 Deg Road Crossing - Primary Cable Run Road Crossing Tee Off/Non Continuous Requirement No Bend Requirement No Bend Requirement Bend Requirement Bends Required Bends Required Continuous Nil
TABLE 5 - For/and up to 33kV Projects Rigid, Straight Lengths - Electrical Orange Conduits with Belled End
Nom. Size (mm) 32 (OD) 100 (ID) 100 (ID) ETSA Utilities Class Type HD LD LD ETSA Utilities Minimum Conduit Bend Requirement (mm) 312 Radius (HDPE or HD rigid PVC to match the conduit) 1800 Radius (HDPE or HD rigid PVC to match the conduit) IPLEX CT73109 or Equivalent
TABLE 6 - For the CBD Applications - for/and up to 33kV Projects Rigid, Straight Lengths - Electrical Orange Conduits with Belled End
Nom. Size (mm) 125 (ID) 100 (ID) ETSA Utilities Class Type LD LD ETSA Utilities Minimum Conduit Bend Requirement (mm) 1800 Radius (HDPE or HD rigid PVC to match the conduit) IPLEX CT73109 or Equivalent
TABLE 7 - ALTERNATIVE Conduit Sizes - For 300mm2 Size Cables For/and up to 33kV Projects Rigid, Straight Lengths - Electrical Orange Conduits with Belled End
Nom. Size (mm) 150 (ID) ETSA Utilities Class Type LD ETSA Utilities Minimum Conduit Bend Requirement (mm) 1800 Radius (HDPE or HD rigid PVC to match the conduit)
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 38 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
TABLE 11 - GUIDE ONLY Generally for 66kV Projects For Horizontal Directional Boring/Drilling Installations Polyethylene Conduit - Straight Lengths HDPE Electrical Orange
Nom. Size (mm) HDPE 225 (OD) HDPE 125 (OD) ETSA Utilities Class Type HD Iplex SDR13.6 Class 10 or Equivalent HD Vinidex or HD Iplex SDR11 Class 9 or Equivalent ETSA Utilities Minimum Conduit Bend Requirement (mm) 1800 Radius (HDPE or HD rigid PVC to match the conduit) 1800 Radius (HDPE or HD rigid PVC to match the conduit)
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 39 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
10.4
Conduit Reinforcement
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
Encasing conduit bends in concrete, is not recommended for open trenching. Conduit bends encased in concrete can create issues at the time of the cable installation. Concerns are: Concrete has a much higher coefficient of friction than PVC and will increase any pulling tension if the conduit is compromised; and There is the potential to cause serious damage to the cable by the potentially rough surface finish of the concrete if a conduit wall is worn through. A cable pull over anything but a very short distance (i.e. a low voltage pull from pillar/pit to pillar/pit), shall undergo a full assessment that is not limited but shall consider the following: Ensure the cable pulling tension is known and specified; For a long cable pull, where there are number of corners/slopes, the designer shall be vigilant and apply the appropriate cable pulling tension; Ensure enough lubrication injection points are made available; Apply appropriate lubrication to both the cable and the draw wire Ensure the cable pull through a conduit is slow.
10.5
Conduit Sizes
The following tables from 12 to 18 (below) specify the minimum conduit sizes for various cables sizes and rated voltage. Installation of a larger/higher conduit classification is acceptable on the provisos that the conduit is continuous with any existing and/or future continuous conduit installation. The use of standard 200mm white PVC pressure pipe, as an alternative to the orange type is not permitted without MNSPs written approval. Telecommunications conduit is to be White and shall be marked as Telecommunications. Selection of conduit classification should be based on consideration of all factors, which may affect the operation of the conduit, such as: Temperature of operation Future development, extension requirements and external loading Care shall be taken in joining conduits. Different grades have different internal diameters and the resultant raised internal edge has the potential to damage the outer layer of cable during cable pulling.
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 40 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
*32 (OD)
HD
1 1 1
*32 (OD)
2.7
32
EA8045
100 (ID)
LD
100 (ID)
3.0
114
102
NC2505
3 LD (White)
630mm2 HV
(1 cable per conduit per phase)
100 (ID)
Optic Fibre
100 (ID)
N/A
114
N/A
N/A
Notes for Table 12: 1. * = Refer to Clause 10.8.1 for conduit OD & ID sizing. 2. N/A = (Data) Not Available; LD = Light Duty (Orange, except for Telecommunications which shall be White); E.g. Series 1 Pipes > class PN4 and class PN6.3; HD = Heavy Duty (Orange); E.g. Series 1 Pipes > class PN9 and class PN12.5.
TABLE 13 - ALTERNATIVE Conduit Sizes for 300mm2 Size Cables (For/and up to 33kV Projects) Rigid, Straight Lengths - Electrical Orange Conduits with Belled End
Nom. Size (mm) ETSA Utilities Class Type Technical Conduit Data No. of Conduits Required Application Mean Diam. (mm) Alternative 300mm2 HV 3 150 (ID) LD 1
(1 cable per conduit per phase)
Alternative 300mm2 HV
(1 cable per conduit per phase)
150 (ID)
4.2
160
127
NC2518
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 41 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
Class Type
1 1 125 (ID)
LD
3.7
140
127
NC2509
630mm2 HV 3
(1 cable per conduit per phase)
100 (ID)
LD (White)
Optic Fibre
100 (ID)
TABLE 15 - For 66kV Projects Rigid, Straight Lengths - Electrical Orange Conduits with Belled End
Nom. Size (mm) ETSA Utilities Class Type Technical Conduit Data No. of Conduits Required Application Mean Diam. (mm) 66kV 3
(1 cable per conduit per phase)
150 (ID)
LD (Class PN6)
160 (OD) & 150 (ID) 225 (OD) & 200 (ID) 100 (ID) 100 (ID) 3.0 114 6 6.1 N/A 6 4.8 N/A 6
Non-Stock
200 (ID)
LD (Class PN6)
66kV 3
(1 cable per conduit per phase)
LD LD (White)
NC2505
N/A
114
N/A
Non-Stock
Notes for Table 15: 1. # = as per AS/NZS 1477, Class PN6, Table 4.2 (A), Colour Orange 2. ## = Manufactured by special order, Orange 200mm conduits with minimum 90m lengths with sufficient lead time. 3. * = Refer to Clause 10.8.1 for conduit OD & ID sizing.
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 42 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
ETSA Utilities
ETSA Utilities
66kV
(1 cable per conduit per phase)
10.4 Vinidex or 11 Iplex or Equivalent 125 75 Vinidex or 100 Iplex or Equivalent 23007 Vinidex or EMCX9125100 Iplex or Equivalent
NonStock
10.6
10.7
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 43 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
10.8
Conduits and couplings shall be UPVC material and meet the requirements of AS/NZS 2053 Parts 1 and 2 for Rigid Plain designation; The conduit will be marked with the word Electrical, the conduit size and class, e.g. Electrical Ducting 100 mm 6.0 Class; No lower grade form of rigid conduit is permitted without the approval of MNSP; Conduits shall also meet the requirements of AS/NZS 1477 for the Test for Impact at 20 degrees C; and Conduits colour Orange (excluding Telecommunications conduits, which shall be White). Notes: ETSA Utilities requires that the installation and handling rigid LD PVC conduit be in accordance with: 1. PIPA website, which provides information on Solvent Cement Jointing of PVC Pipe. 2. AS/NZS 2032: Clause 5.3.11 - Bending of PVC Pipes that recommends a minimum radius of 150 x OD for non-pressure (electrical) pipes.
10.9
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 44 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
Floor of trench /opening for bore FIGURE 10 - SECURING THE END OF DIRECTIONAL BORING CONDUIT
226
12
* (Special Order)
NonStock
NonStock
Notes for Table 18: 1. * = GUIDE ONLY, Orange, as per AS/NZS 4130, Class PN10, manufactured by special order, minimum 90m length order with sufficient lead time; 2. 225mm diameter white PVC Series 1 Pressure Pipes as an alternative to Orange type is not permitted without MNSP approval.
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 45 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
Design Information shall detail via cross sections that detail network requirements along the route. When installing conduit consider the following general factors: Conduit designs shall be prepared to ensure that pulling tensions do not exceed the maximum permissible as required by the Construction Standard TS-087; Installation details and techniques for cable pulling through conduits should be as stated in E drawing E1906; and Lube injection points need to be considered by the designer for long pulls with multiple bends. In some situations lube Injection point are not possible and Front End Lubrication is the best method.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
TABLE 19 - GUIDE ONLY - Cap Size Guide for Conduits with No Cables
Description Cap, Push on 40mm for Consumers Conduit Cap, Push on 50mm for Consumers Conduit Cap, Push on 80mm Cap, Push on 100mm Stock Item No NC 6462 NC 6470 NC 6501
11.0
12.0
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 48 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
13.0
14.0
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 49 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
AS 1141.11-1996
AS 1289. 3.3.1-1995
15.0
16.0
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 50 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
17.0
17.2
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 51 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
17.3
17.4
17.5
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 52 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
17.6
The Contractor shall install conduits for the cables at locations as specified, and as shown on the cable route drawings. Refer to Appendix-J for typical trench arrangements - 66kV Projects. At locations other than specified in the cable route drawings, consideration will be given to any proposal to install the cables in ducts to simplify the cable installation provided the cable system will remain adequate to meet the service conditions specified. ETSA Utilities approval is required for such variations.
17.7
17.8
17.9
Thermocouples - 66kV
Thermocouples, where specified, shall be fitted to the outer serving of the power cables in accordance with the cable manufacturer's instructions. Thermocouple leads shall be taken to suitable terminals in pits or terminal boxes supplied and installed by the Contractor. Earthing link box pits may be used where appropriate.
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 53 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
Flowable Thermal Backfill (FTB) is a self-levelling, self-compacting and low strength cementation material. It is characterised in its plastic state by its flowable consistency. In many backfilling applications, FTB is a better alternative to the conventional compacted granular fill method where it eliminates the need for the conventional placement and compaction equipment. This material is typically a mixture of cement, fly ash, fine aggregate and water and has a consistency Equivalent to that of a thick slurry or grout, which may also include Slag/Silica fume in the mixture. To enhance the performance properties and variations to the proportioning of the typical FTB mixture, additional chemical admixtures/additives may improve the versatility in design of the FTB material. In contrast to concrete, FTB does not require curing. However, some protection may be necessary during very cold weather applications or wet conditions. FTB works well particularly around pipes and culverts.
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 54 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 55 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
The use of Bentonite is not permitted under normal circumstances and shall be avoided, unless ETSA Utilities approves its use. Please seek further advice before considering or using this product.
K m/W
0.9 1.0
Special precaution shall be taken to install sand backfill with optimal compaction to ensure that the required thermal resistivity is achieved. The Contractor shall provide a construction Work Method statement describing how this will be achieved to the relevant ETSA Utilities Manager for approval.
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 56 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
Note for Table 22: When underground conduit system has optical fibre (Telecommunications) cables ONLY, then the marker tape installed will require tracer wire.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
18.0
CONTAMINATED SOIL
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
The Customer is responsible to ensure that the soil is free from any contaminants that may be a risk to the health of ETSA Utilities distribution workers; this is imperative where ETSA Utilities performs the works. Written assurance may be required to demonstrate that the soil is free from contamination and if necessary a report detailing known contamination and steps taken to alleviate the health risks. Test results may be required to be submitted to ETSA Utilities before ETSA Utilities agrees to work on the site.
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 58 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
TS-085: Trenching & Conduit for Underground Distribution Cable Networks App-A: Civil Works Notification & Compliance Responsibility
Civil Works Notification Form NICC - 453 available on Intranet and on Internet websites. 1. Insert point of Contact: Compliance CoOrd 2. Issue to Customer as part of Information Pack 1. Fill in B: Contract Supervisor/TSW8 2. Issue to Civil Contractor Civil Works Compliance Form NICC - 452 available on Intranet and on Internet websites. 1. Insert name of Contract Supervisor/TSW8 2. Issue to Customer 1. Fill in ETSA Utilities Contract Supervisor/TSW8 2. Issue to Civil Contractor 1. Highlight point of contact as Electrical Contractor 2. Issue as part of Information Pack 1. Customer to insert Electrical Contractor details 2. Forward form to Civil Contractor
Return Form to: 1. For a Contestable Project 2. For all other Projects (Contract Supervisor /TSW8)
TS-085
Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
Page 59 of 73
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version
TS-085: Trenching & Conduit for Underground Distribution Cable Networks App-B: Cable Location Marking Drawings
TS-085
Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
Page 61 of 73
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version
TS-085: Trenching & Conduit for Underground Distribution Cable Networks App-D1: Typical Shared Trench Arrangements Cables Buried Direct
D: Typical Shared Trench Arrangements D-1: Cables Buried Direct (Shared Trench)
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
TS-085: Trenching & Conduit for Underground Distribution Cable Networks App-D-2: Typical Shared Trench Arrangements Cables in Conduits
D-2: Cables in Conduits (Shared Trench) (In Footpath or Road Crossing for Non DPTI Roads)
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
TS-085: Trenching & Conduit for Underground Distribution Cable Networks App-E-2: Typical ETSA Utilities Trench Only Cables in Conduits
E: Typical ETSA Utilities Trench Only E-1: Cables Buried Direct - (ETSA Utilities Only) (In Footpath for Non DPTI Roads)
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 64 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
TS-085: Trenching & Conduit for Underground Distribution Cable Networks App-E-2: Typical ETSA Utilities Trench Only Cables in Conduits
E-2: Cables in Conduits - (ETSA Utilities Only) (In Footpath or Road Crossing for Non DPTI Roads)
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
TS-085: Trenching & Conduit for Underground Distribution Cable Networks App-F: Typical Reduced Cover Trenching
TS-085: Trenching & Conduit for Underground Distribution Cable Networks App-G-1: Typical ETSA Utilities Telecommunication Trench Only
G: Typical ETSA Utilities Telecomm Trench (Only) G-1: Cables in Conduit (ETSA Utilities Telecomm Only)
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 67 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
TS-085: Trenching & Conduit for Underground Distribution Cable Networks App-H: Trenching on Private Property
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 68 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
TS-085: Trenching & Conduit for Underground Distribution Cable Networks App-H: Trenching on Private Property
TS-085 Issue: FEB 2012 Authorised: Jehad Ali Date: 24/02/12 Page 69 of 73 The use of this Technical Standard is subject to the conditions stated in ETSA Utilities Disclaimer.
TS-085: Trenching & Conduit for Underground Distribution Cable Networks App-J-1: Typical Flat Arrangement - 66kV Cables
J: Typical Trench Arrangements for 66kV J-1: Typical Flat Arrangement 66kV - Roadway
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version
TS-085: Trenching & Conduit for Underground Distribution Cable Networks App-J-2: Typical Trefoil Arrangement - 66kV Cables
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version
TS-085: Trenching & Conduit for Underground Distribution Cable Networks App-J-3: Typical Under Bore Arrangement - 66kV Cables
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version