Import and Export of Electrical Energy

By:- NK BHATI Yadav Measurements , Udaipur.

A specifically designed programme for Da Afghanistan Breshna Sherkat (DABS) Afghanistan


1

Areas Covered Under this Module Power flow principles Import and export of power Metering point and energy flow Power flow quadrants and power factor Reactive and apparent energy flow Various energy registers in energy measurement

6/3/2010

copyright YMPL Udaipur

Power Flow

Electricity

Power System

Power System

6/3/2010

copyright YMPL Udaipur

Measurement Reference

Utility A A B

Utility B

Current transformer connection polarity


6/3/2010 copyright YMPL Udaipur 4

EHV BUS

HV BUS

P1

P2

P2

P1

Power flow to Voltage bus is taken positive (import) Current transformer connection polarity (p2 to bus side)

6/3/2010

copyright YMPL Udaipur

Example of small tie line


-20 MW 4 MVR 20 MW -4 MVR

Load with green Arrows indicating Amount of MW flow

Bus 2
204 MW 102 MVR

Bus 1
1.00 PU

1.00 PU 106 MW 0 MVR -14 MW 4 MVR 14 MW -4 MVR 1.00 PU 102 MW 51 MVR 150 MW AGC ON 37 MVR AVR ON 100 MW

150 MW AGC ON -34 MW 116 MVR AVR ON 10 MVR 34 MW -10 MVR

Note the power balance at each bus

Home Area
Used to control output of generator

Bus 3

Direction of arrow is used to indicate direction of real power (MW) flow


copyright YMPL Udaipur 6

6/3/2010

Power Flow Quadrants: IEC62053-23


V

Q4
PF: Leading /capacitive Export Reactive Power

Import Active Power

Q1
PF: lagging/ Inductive

Q3
PF: lagging /Inductive Export Active Power Import Reactive Power

Q2
copyright YMPL Udaipur
PF: Leading / capacitive

6/3/2010

Power Components
V 00

900 2700 I Quadrature component

In phase component 1800


6/3/2010 copyright YMPL Udaipur 8

Power Flow Quadrants


Voltage vector Quadrant 4 kW Import kVAr (capacitive) Export kW kVAr kW + - - Quadrant 1 kW Import kVAr (Inductive) Import kW + kVAr + kVAr + kW export kVAr (capacitive) Import Quadrant 2 kW -

kVAr - kW export kVAr (Inductive) export Quadrant 3

6/3/2010

copyright YMPL Udaipur

Energy Flow conditions- case 1

A Gen

B Gen

Load Load

Q1: meter B
6/3/2010

KW +, KVAr +
copyright YMPL Udaipur 10

Energy Flow conditions- case 2

A Gen

B Gen

Load Load

Q2: meter B KW -, KVAr +


6/3/2010 copyright YMPL Udaipur 11

Energy Flow conditions- case 3

A Gen

B Gen

Load Load

Q3: meter B KW -, KVAr 6/3/2010 copyright YMPL Udaipur 12

Energy Flow conditions- case 4

A Gen

B Gen

Load Load

Q4: meter B KW +, KVAr 6/3/2010 copyright YMPL Udaipur 13

Wheeling of Energy
A B

Gen

Gen

Load C Load

Gen
6/3/2010 copyright YMPL Udaipur 14

Energy Registers

Active energy register


Active Import Active Export

Reactive Energy register


Reactive import Reactive export

6/3/2010

copyright YMPL Udaipur

15

Energy Registers

Apparent energy register


Apparent Import Apparent Export Pythagoras Sum with Reactive energy
Lag only lag+lead

6/3/2010

copyright YMPL Udaipur

16

Metering errors

CT/ PT ratio errors CT/PT phase error Connected burden, rating, connections errors Meter errors
Class 0.5 or Class 0.2 meter

Dynamic compensation of external errors


6/3/2010 copyright YMPL Udaipur 17

In electric power transmission, wheeling is a term used to describe either of the following:
the act of transporting electric power (megawatts or megavoltamperes) over transmission lines, or; the act of providing the service of transporting electric power over transmission lines.

Tie line : A connection between systems, such as electrical power

6/3/2010

copyright YMPL Udaipur

18

Any Question?

6/3/2010

copyright YMPL Udaipur

19

THANK YOU!