PROVAST LIMITED

FACILITY COORDINATOR DAILY REPORT


Date; 24-052012 Project Title: FLB GATE HOUSE UPGRADE AND CONSTRUCTION OF SEPTIC TANK (Contractor: Godfearing ENT) INSTALLATION OF ELECTRCAL PANEL (Contractor: PSYECOM) Location Date of Mobilization KOLO CREEK FLB N/A

Date of completion

Nil

PTW USED PTW NO. 5934 and 72012 The PTW are still active Tool Box Talk; Hazards Associated with Excavation, Concrete casting, Block laying, Manual material Handling, make good all disturbed areas, housekeeping and most especially the cascade of 12 life saving Rules. Personnel on Site: N/A Visitors: Nil. Item Y N N/ Remarks A TOOL BOX MEETING Hazards Associated with Excavation, Concrete casting, Block laying, Manual material Handling, make good all disturbed areas, housekeeping and most especially the cascade of 12 life saving Rules. Incidentes U/A U/C N/M FAC FAT Full Report Reference NIL NIL NIL NIL.

GENERAL PROGRESS SUMMARY Standard Workmanship:


The standard of workmanship is on the average.

Action Taking:
In order to improve the standard of workmanship close supervision was adopted to ensure that works are carried out base on the specification as given in the contract.

Standard of Materials:
The quality of materials supplied so far are okay and as specified in the contract except for the door frames that the height were not up to the height of the respective doors.

Action Taken:

PROVAST LIMITED
FACILITY COORDINATOR DAILY REPORT Contractor was asked to removed the said door frames from site and replace it with a new one.

Delay:
The contractor had not being on site since Saturday 19-05-2012, when I contacted him he said that he lost somebody. He has promised to be on site since Monday the 21/05/2012 but as at the time of compiling this report he is still not on site.

Action Taken:
As requested, I have decided to do a reverse work programme to cover up for the outstanding activity. This work programme is expected to run for two weeks. The work programme is based on the assumption that there is no further amendment to the design provides information in the contract and no difficulties are encountered at this stage of the work.

LOWLIGHTS
The following are the major challenges 1. The PTW process here has pose a lot of delay to the progress of the jobs. 2. There is no site supervisor for the civil contractor to effectively drive the project and this is causing a lot of delayed.
WORK PLAN FOR NEXT DAY: 1. Installation of door frames and 2. Plumbing work

WORK PROGRESS NUN-RIVER FLB CIVIL UPGRADE MOBILIZATION

% Start 0%

% End 100%

Comments

Both contractors has fully mobilize to site and

since commence work. CIVIL WORKS


DEMOLISHING EXISTING BUILDING

0%

100%
The existing building and all the various components thereto that were mark for demolition has being completed

SUBSTRUCTURE SUPER-STRUCTURE ROOFING WORK

0%
0% 0%

100%
100% 95%

The sub structural activities have being completed. The super-structural activities have being completed. The roofing work has being completed but there is an area that needed to amend which was not properly done. The facia board

PROVAST LIMITED
FACILITY COORDINATOR DAILY REPORT flashing has not being installing. 0% 0% This activity is yet to commence
0% 0% 0% 0% 0% 0% 45% 0% 0% 70%

IRONMONGERY WORK PLUMBING WORK WALL AND FLOOR FINISHING WORK INSTALLATION OF AND ACCESSORIES PAINTING WORK

This activity is yet to commence This activity is yet to commence This activity is yet to commence This activity is yet to commence Excavation and block lying has being completed. The outstanding activities are; casting of column, beam and slab, internal rendering and plumbing work.

CONSTRUCTION OF SEPTIC TANK

OVERALL % OF CIVIL WORK COMPLETED TO DATE

0%

57%

ELECTRICAL WORKS
INSTALLATION OF ELECTRICAL PANEL 0% 80%

Excavation of cable trench has being completed Installation of panel shed is completed Installation of panel stand and installation of the panel casing and breakers has being completed Fixing of trucking is completed Drawing of cables from the panel to where the industrial socket is to be installed is about 90% completed The industrial socket is yet to be installed The power line are yet to terminate at both the feeder pillars and the panel. Testing and commissioning is outstanding

OVERALL % COMPLETED TO DATE

0%

80%

Reported by Review By

Engr. NGBAA, DORNU SIMEON ENGR. AYENOR NYERO