S.No
1 1.1 1.2 2 2.1 2.2 2.3 2.4 2.5 2.6 3 3.1 3.2 3.3 3.4 3.5
Process Description
Installation Verification Check Check framework,mounting/ anchor bolt Location/ leveling Completeness off assy/ sub.assy to erect Installation Equipment Installation/ Lifting procedure if heavy lifting is required Rigging & lifting of the equipment Verification of location ( Dimensional Check) Levelling/Shimming/Grouting Bolting / torque of securing bolts Check securing of equipment by welding Mechanical Completion Alignment of rotating equipment after hook up Erect Coupling guard Fill up mechanical completion check sheet Final check on completion Final documention
Acceptance Criteria
Verifying Doc
Manufacture's installation procedure/ criteria as per specification & tolrances As per Manufacture's drawing
H W
H W
H W
H W
Vendor's procedure & equipment drawing Vendor's procedure & equipment drawing Project drawing,equipment drawing & manufacturing's recommendation Project drawing,equipment drawing & manufacturing's recommendation As per drawing/ Engg.Specification As per drawing.
Vendor Installation procedure Vendor Installation procedure Vendor Installation procedure Vendor Installation procedure As per design calculation and ASME standards As per drawing
Doc. Doc. Inspection Report Inspection Report Inspection Report Inspection Report
M M H H H H
M M H W W W
M M H W W W
M M H H H H
Pjt drawing,Equip.drg. Manuf's recomm. Also As per specification & manufacter's criteria before & after piping fix up. As per drawing Project Procedure Project Procedure Contract doc. Drawing & site condition Insp.records & all project drawing Insp.records & all project drawing Contract doc.
Inspection Report Inspection Report Mech.completion & commsission check sheet. Mech.completion & commsission check sheet. Final documentation & punch list
M H R+A
W H R+A
W H R+A
W H R+A
Legends
W - Witness ( Formal written notification one day ahead from agency concerned) H - Hold point ( Formal written notification one day ahead from agency concerned) M - Random/ spot check of activites ( No formal notification required) R - Review ( of certificates, record & documentation) A - Approve ( A document or an activity for which a document will be required by the indicated authority & approval obtained)
Owner
H W
A A H H H H
W H R+A
Check point
Transportation to site unloading storage before erection
Yes
No
Lifting arrangment
Saftey Points
At Height => Height pass, Harness, life line, fall arrester, net etc,
ii
iii
iv
vi
Inspection Format Equipment Erection Equipment Name : S.No Inspection Point Drawing Tag No : Actual Remarks
Dimension
Hole Center/dia
Finish
Verification of Location
10